Council Rock School District
Facilities Committee Meeting Minutes
Meeting Date: October 25, 2012
Meeting Time: Start-6:00pm Finish-7:15pm
Next Meeting Date: November 14, 2012 Location: Chancellor Center
Page 1 of 2
ATTENDEES
Board of Director Attendees: Kyle McKessy, Bernadette Heenan, Bill Foster, Wendi Thomas
CRSD Administration Attendees: Mark Klein, Bob Reinhart, Doug Taylor, Andy Sanko, Nicole Crawford, Joe MacClay
CRSD School District Attendees: Gail Klohe
Public Attendees: Nancy Carroll, Paul Cohen, Joanne Hinton, Alison Rapine, Diana Bilyk
Professional Consultants Attendees:
David Schrader- Schradergroup, Arif Fazil- D’Huy Engineering
SUMMARY OF MEETING
Energy Procurement Update:
1. Deferred to November meeting
Facility Improvement Project Updates:
Holland Elementary School
2. Deferred to November meeting
Goodnoe Elementary School
1. Please see memo titled Facility Improvement Project Updates for an outline of the discussion
regarding Goodnoe Elementary School project.
2. A PowerPoint including an update on the Project Budget and Milestone Schedule was presented.
A copy of the PowerPoint is attached to this meeting memorandum. Questions relative to the
PowerPoint should be directed to Doug Taylor.
3. The CRSD met with the Newtown Township Board of Supervisors on Wednesday, October 24,
2012 seeking a waiver from Frost Lane Improvements, Traffic Impact Fees and a Traffic Study.
The Board of Supervisors rendered no decision relative to the Frost Lane Improvements but
required the following by the CRSD:
a. Perform a Traffic Impact Study for submission to the Township.
Council Rock School District
Facilities Committee Meeting Minutes
Meeting Date: October 25, 2012
Meeting Time: Start-6:00pm Finish-7:15pm
Next Meeting Date: November 14, 2012 Location: Chancellor Center
Page 2 of 2
b. Establish the Traffic Impact Fees for further consideration of a waiver by the Township.
Miscellaneous Items Update:
No comments
Facility Upgrade Donations:
No comments
Public Comments:
1. Questions relative to the PowerPoint were addressed during the presentation.
The meeting adjourned at 7:15 pm.
Anyone taking exception to the statements in these minutes, including omissions, shall notify the CRSD in
writing within three (3) business days of receipt.
Respectfully Submitted,
Council Rock School District
Douglas Taylor
Doug Taylor, Assoc. AIA, AVS
Supervisor of Operational Services
Attachments: PowerPoint of Goodnoe ES Presentation
Distribution: Post to CRSD website
C:\+Doug Folders\+Facilities Committee\FACCOM 2012-13\FACCOM minutes 2012-13
Council Rock School District
SCHRADERGROUP architecture, LLC programming I planning I architecture
GOODNOE
ELEMENTARY
SCHOOL
proposed additions and
renovations
October 25, 2012 Facilities Committee Meeting
Council Rock School District
Goodnoe Elementary School
discussion budget update
building conditions
milestone schedule update
miscellaneous items
questions/comments
Council Rock School District
Scope and Budget Developed in 2009
(nearly 4 years ago)
Detailed Cost Analysis
Timing of Act 34 Hearing and Holland ES Bid
Process
Keeping Board Informed and In Control of
Project is Key
Scope of Work in Alignment with
Churchville and Holland ES’s
Economic Conditions and Escalation
budget update
Council Rock School District
Goodnoe Elementary School
Additions and Alterations Budget Summary October 25, 2012
Previous
Act 34
Budget
Current
Cost
Estimate
Discrepancy Items Included in Cost Estimate and Comments
General Const. $ 6,542,692
$ 7,152,909 Includes $1.6M – Site (Org. budget had no input from NT & was
approx. $1M less)
Potential site cost reduction of $400,000 (Frost Lane)
Includes $1.1M for roof replacement (Not part of org. budget)
Includes $200,000 for ceiling replacement
Includes $72,000 to clean and repair exterior brick veneer
Includes $140,000 to cover EIFS with new metal panel system
Includes $23,500 to repair existing retaining wall
Scope preserves parity between Churchville and Holland ES
Includes 11 Classroom addition
Plumbing Const. $ 773,913 $ 1,079,226 Infrastructure improvements similar to Churchville & Holland
Mechanical Const. $ 1,944,318 $ 3,982,252 Infrastructure improvements similar to Churchville & Holland
Electrical Const. $ 1,246,622 $ 3,478,332 Infrastructure improvements similar to Churchville & Holland
Asbestos Abatement $ 60,000 $ 100,000 Infrastructure improvements similar to Churchville & Holland
Sub-Total
Construction Costs
$ 10,567,545 $ 15,792,719
Soft Costs $ 2,534,372 $ 2,823,199 Fees - $1,397,199:
A/E - $775,099 (less site & asbestos); CM $416,000;
Asbestos $40,000; IAQ $10,000; Civil 1 $48,300, Civil 2 $62,800
Misc. $45,000
Permits/Approvals/Inspections - $176,000
Builder’s Risk insurance - $25,000
Contingency - $710,000 (4.5%)
Council Rock School District
Goodnoe Elementary School
Additions and Alterations Budget Summary October 25, 2012
Previous
Act 34
Budget
Current
Cost
Estimate
Discrepancy Items Included in Cost Estimate and Comments
Soft Costs
(Continued)
FFE & Technology - $425,000
Construction Testing & TAB - $90,000
Financing and Reimbursement – Not Included
Total Project Costs $ 13,101,917 $ 18,615,918 $ 5,514,001 Discrepancy Items Summary
$1.1 M Roof replacement (Not part of original budget)
$1.0 M Site scope & requirements (Orig. did not have NT input)
$0.2 M Ceiling replacement in existing building (not part of
original budget.)
$0.5 M For scope of items such as infrastructure, exterior,
finishes & program for consistency with Churchville & Holland
$0.3 M soft cost – increased A/E fees and Civil fees
$2.4 M economic conditions and escalation
Alternate Scope
Items for Cost Control
($ 493,210) Deduct 2 Classrooms from building addition (2 CR’s in total)
($ 493,210) Deduct 2 Classrooms from building addition (Total of 4 CR’s when
combined with above)
$ 65,000 Add 2 folding partitions, new doors, HVAC controls, switches, etc.
at Classrooms C02 and C05
$ 225,000 Add new casework at existing CR’s. Wall cabinets in all CR’s.
$ TBD Add Gymnasium flooring (This alternate may not be applicable
since existing floor is being removed due to environmental
abatement)
Council Rock School District
Goodnoe Elementary School
Additions and Alterations Budget Summary October 25, 2012
Previous
Act 34
Budget
Current
Cost
Estimate
Discrepancy Items Included in Cost Estimate and Comments
Alternate Scope
Items for Cost Control
(Continued)
$ 15,000 Add Tackboards/Tackstrips
$ 32,000 Add Rollershades
$ TBD Deduct telecommunication at existing classrooms
$ TBD Add/Deduct Siemens controls/ChangeAire
$ TBD Add 2 year warranty ILO 1 year
$ TBD Add stone building pad for additions
$ TBD Provide Alternate HVAC equipment
$ TBD Electrical Alternates: equip. manufactures, lighting, etc.
$ TBD Plumbing Alternates: flex at heads, ProPress fittings, etc.
Sub-Total ($ 649,420) All Deduct Items
Total with All
Deduct Items
$ 17,966,498 Reduces Classroom addition from 11 to 7
Budget Approved by
School Board
$ 13,101,917 $ 4,864,581 Discrepancy
Council Rock School District
Representative photos of some of the existing conditions &
items not originally budgeted for
existing building conditions
Council Rock School District
Council Rock School District
Council Rock School District
Council Rock School District
Council Rock School District
Council Rock School District
Council Rock School District
Design Team End User meetings Complete
D’Huy Engineering hired as Construction Manager April 2012
CRSD hired TEI as new Civil Engineer June 2012
CRSD and TEI review revised Site Plan with NT August 2012
Project Approvals (PlanCon, Township, BCCD, etc.) Sept 2012-March 2013
NT Board of Supervisors Mtg – Traffic Issues October 24, 2012
Budget Update Reviewed at Facilities Committee Mtg October 25, 2012
Terraform meeting with Township Engineer (CKS) November 2012
NT Planning Commission Resubmission November 16, 2012
BCCD Technical Review November 26, 2012
PlanCon Part A/B Approval
(Project Justification & Schematic Design) Complete
Design Team meetings, Construction Documents, Specs. 95% Complete
NT Planning Commission Mtg (Final Approval) December 4, 2012
NT Board of Supervisors (Final Approval) January 9, 2012
project milestone schedule
Council Rock School District
PlanCon Act 34 Hearing (Initial Hearing)
(Presentation of Project to Public) December 2011
PlanCon Act 34 Hearing (Second Hearing, Revised Budget)
(Presentation of Project to Public) January 2013
Plan Part D/E Approval
(Project Accounting Based on Estimates/Design Dev.) February 2013
BCCD/NPDES Approvals February 2013
Board Approval of bid docs (PlanCon Part F)
(Construction Documents) February 2013
Bidding Phase March-April 2013
Board Approval (PlanCon Part G) Award of Contracts
(Project Accounting Based on Bids) April 18, 2013
Construction Activities May 2013- Aug 2015
project milestone schedule
Council Rock School District
Goodnoe Elementary School
miscellaneous items lot consolidation (july 2001)
rezoning R-1 (residential) sail house &
POS (park & open space) parking
adjacent to sail house to EIR
(educational-institutional-recreational)
frost lane impact to project
traffic study + $8,800
impact to construction budget + $400,000
impact to professional fees? (possible
resubmission to the BCCD)
impact to schedule (fall 2013 start?)
separate bid – PDE challenge
Council Rock School District
Questions?