NUMBER OF TURBINES Maximum of 20 LOCATION South West of Dunoon ESTIMATED PROJECT TIMELINE The construction of the Cowal and Trossachs Forest District Wind Farm-Bachan Burn requires consent from the Scottish Government as current designs indicate the proposal will have an approximate maximum installed capacity of over 50MW. Should our proposals fall below 50MW they will be determined by Argyll and Bute Council. The Council will remain a statutory consultee throughout the process. If permission were to be granted, an estimated timeline of the development is given below. Keep informed of any significant changes to these timescales via the project website www.bachanburnwindfarm.co.uk PNE WIND UK (PNE) and Forestry Commission Scotland (FCS) are working in close partnership to develop the Cowal and Trossachs Forest District Wind Farm - Bachan Burn. PNE wishes to apply for permission under section 36 of the Electricity Act 1989 to develop the Cowal and Trossachs Forest District Wind Farm - Bachan Burn, located South West of Dunoon. If consent is granted Autumn 2013 Project scoping October 2013 Pre-application consultation commenced 26 & 27 March 2014 First round of public consultation exhibitions Autumn 2014 Second round of public consultation exhibitions Winter 2014 Application to be submitted to the Scottish Government 2018 Operational wind farm Estimated 2017 Construction starts If consent is granted These dates are approximate and may change as the project progresses. 207000 208000 209000 210000 211000 212000 213000 214000 215000 216000 217000 218000 219000 667000 668000 669000 670000 671000 672000 673000 674000 675000 676000 677000 SIZE: A3 TITLE: KEY: Site Location Map Reproduced from Ordnance Survey data, HMSO © Crown Copyright Reserved. License number 100049943. PROJECT NAME: Cowal and Trossachs Forest District Wind Farm - Bachan Burn . DATE: 12/02/2014 Site boundary Proposed development area 1:40,000 SCALE: 0 1,000 Metres COWAL AND TROSSACHS FOREST DISTRICT WIND FARM - BACHAN BURN PROPOSAL 2 October 2013 Drop in session held TOTAL INSTALLED CAPACITY Greater than 50MW MAXIMUM LIFE SPAN 25 years

COWAL AND TROSSACHS FOREST DISTRICT WIND …61a796d943f5dfb8c579-989379e08401d41d7a4c568a2c7cfe43.r39.cf3.rackcd…develop the Cowal and Trossachs Forest District Wind Farm - Bachan

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: COWAL AND TROSSACHS FOREST DISTRICT WIND …61a796d943f5dfb8c579-989379e08401d41d7a4c568a2c7cfe43.r39.cf3.rackcd…develop the Cowal and Trossachs Forest District Wind Farm - Bachan

NUMBER OF TURBINESMaximum of 20

LOCATIONSouth West of Dunoon

ESTIMATED PROJECT TIMELINEThe construction of the Cowal and Trossachs Forest District Wind Farm-Bachan Burn requires consent from the Scottish Government as current designs indicate the proposal will have an approximate maximum installed capacity of over 50MW. Should our proposals fall below 50MW they will be determined by Argyll and Bute Council. The Council will remain a statutory consultee throughout the process. If permission were to be granted, an estimated timeline of the development is given below.

Keep informed of any significant changes to these timescales via the project website www.bachanburnwindfarm.co.uk

PNE WIND UK (PNE) and Forestry Commission Scotland (FCS) are working in close partnership to develop the Cowal and Trossachs Forest District Wind Farm - Bachan Burn.

PNE wishes to apply for permission under section 36 of the Electricity Act 1989 to develop the Cowal and Trossachs Forest District Wind Farm - Bachan Burn, located South West of Dunoon.

If consent is granted

Autumn 2013 Project scoping

October 2013Pre-application consultation commenced

26 & 27 March 2014First round of public consultation exhibitions

Autumn 2014Second round of public consultation exhibitions

Winter 2014Application to be submitted to the Scottish Government

2018 Operational wind farm

Estimated 2017Construction starts

If consent is granted

These dates are approximate and may change as the project progresses.

207000 208000 209000 210000 211000 212000 213000 214000 215000 216000 217000 218000 219000

6670

0066

8000

6690

0067

0000

6710

0067

2000

6730

0067

4000

6750

0067

6000

6770

00

SIZE: A3

TITLE:

KEY:

Site Location Map

Reproduced from Ordnance Survey data, HMSO © Crown Copyright Reserved. License number 100049943.

PROJECT NAME:

Cowal and Trossachs Forest District Wind Farm - Bachan Burn

.DATE: 12/02/2014

Site boundaryProposed development area

1:40,000SCALE:

0 1,000

Metres

COWAL AND TROSSACHS FOREST DISTRICT WIND FARM - BACHAN BURN PROPOSAL

2 October 2013Drop in session held

TOTAL INSTALLED CAPACITY

Greater than 50MW

MAXIMUM LIFE SPAN

25 years

Page 2: COWAL AND TROSSACHS FOREST DISTRICT WIND …61a796d943f5dfb8c579-989379e08401d41d7a4c568a2c7cfe43.r39.cf3.rackcd…develop the Cowal and Trossachs Forest District Wind Farm - Bachan

PNE is currently exploring two initial design options for the Cowal and Trossachs Forest District Wind Farm - Bachan Burn. We would welcome your thoughts on both plans.

>

>

>

>

>

>

>

>

>

>

>

>

>

>

>

>

>

>

> >

°

Key:

> Wind Turbine Positions

Forestry Commission Boundary

Crane Pad

Water Crossing

Site Access Tracks

Cowal and Trossachs Forest District Wind Farm - Bachan Burn

20 wind turbines at 110m blade tip heightMarch 2014

Reproduced from Ordnance Survey data, HMSO © Crown Copyright Reserved 2014. License number 0100031673.

Features on these drawings (such as turbine positions, site access tracks and crane pads) may change between now and the submission of a planning application. Additional infrastructure such as substation and site compounds has not been shown at this stage.

0 1,000

Meters

Scoping Proposal Wind Turbine Layout Ver.1

>

>

>

>

>

>

>

>

>

>

>

>

>

>>

°

Key:

> Wind Turbine Positions

Forestry Commission Boundary

Crane Pad

Water Crossing

Site Access Tracks

Cowal and Trossachs Forest District Wind Farm - Bachan Burn

15 wind turbines at 145m blade tip heightMarch 2014

Reproduced from Ordnance Survey data, HMSO © Crown Copyright Reserved 2014. License number 0100031673.

Features on these drawings (such as turbine positions, site access tracks and crane pads) may change between now and the submission of a planning application. Additional infrastructure such as substation and site compounds has not been shown at this stage.

0 1,000

Meters

Scoping Proposal Wind Turbine Layout Ver.2

The second proposed layout consists of 15 turbines with a maximum tip height of 145m.

Both of these initial design options have an estimated installed capacity of over 50MW. Turbine numbers and dimensions may reduce and the layout may change as a result of ongoing site assessments.

The first of these design options consists of 20 turbines with tip heights of 110m. This is the maximum number of turbines that can be developed on this site.

Page 3: COWAL AND TROSSACHS FOREST DISTRICT WIND …61a796d943f5dfb8c579-989379e08401d41d7a4c568a2c7cfe43.r39.cf3.rackcd…develop the Cowal and Trossachs Forest District Wind Farm - Bachan

Landscape and visual assessment is a key part of the development process, and is used to inform the design of the proposals.

Preliminary Zone of Theoretical Visibility (ZTV) diagrams have been produced for the Cowal and Trossachs Forest District Wind Farm - Bachan Burn initial layout options. These diagrams indicate the number of turbines theoretically visible from the surrounding area.

!!!!!!!!!

!!!!!!!!

!! !

5km

35km

30km

25km

20km

15km

10km

Reproduced from Ordnance Survey digital map data © Crown copyright 2013. All rights reserved. Licence numbers 100047514, 0100031673.

0 5 10 15 20 km

LUC GLA FIG05-02a_5754-004_20TL_ZTV 25/09/2013

Map Scale @ A3:1:275,000

I

Zone of Theoretical Visibility(20 Turbines)

Site Boundary

! Turbine Location

35km study area

5km interval from outer turbines

Theoretical Visibility

1 - 4 turbines visible

5 - 8 turbines visible

9 - 12 turbines visible

13 - 16 turbines visible

17 - 20 turbines visible

Notes

The ZTV is calculated to turbine tip height (110m)from a viewing height of 2m above ground level.

The terrain model assumes bare ground and is derived from OS Terrain 50 height data.

Earth curvature and atmospheric refraction have been taken into account.

Cowal and TrossachsForest District Wind Farm -Bachan Burn

!!

!

!

!!!

!

!!

!

!

!

! !

5km

35km

30km

25km

20km

15km

10km

Reproduced from Ordnance Survey digital map data © Crown copyright 2013. All rights reserved. Licence numbers 100047514, 0100031673.

0 5 10 15 20 km

LUC GLA FIG05-02b_5754-004_15TL_ZTV 25/09/2013

Map Scale @ A3:1:275,000

I

Zone of Theoretical Visibility(15 Turbines)

Site Boundary

! Turbine Location

35km study area

5km interval from outer turbines

Theoretical Visibility

1 - 3 turbines visible

4 - 7 turbines visible

7 - 9 turbines visible

10 - 12 turbines visible

13 - 15 turbines visible

Notes

The ZTV is calculated to turbine tip height (145m)from a viewing height of 2m above ground level.

The terrain model assumes bare ground and is derived from OS Terrain 50 height data.

Earth curvature and atmospheric refraction have been taken into account.

Cowal and TrossachsForest District Wind Farm -Bachan Burn

For further information on the visibility of the proposed wind farm please speak to one of the PNE WIND UK team who will be able to talk you through our interactive 3D computer visualisation.

This ZTV indicates the theoretical visibility of 20 turbines with tip heights of 110m.

This ZTV indicates the theoretical visibility of 15 turbines with tip heights of 145m.

Page 4: COWAL AND TROSSACHS FOREST DISTRICT WIND …61a796d943f5dfb8c579-989379e08401d41d7a4c568a2c7cfe43.r39.cf3.rackcd…develop the Cowal and Trossachs Forest District Wind Farm - Bachan

As part of the Environmental Impact Assessment (EIA) process, the wind farm and all associated infrastructure will be assessed in terms of potential impacts to each aspect of the environment, and all findings will be reported in an Environmental Statement which will form part of the future planning application.

°

Key:

Wind Turbine Development Area

Forestry Commission Boundary

March 2014

Reproduced from Ordnance Survey data, HMSO © Crown Copyright Reserved 2014. License number 0100031673.

0 1,000

Meters

Constraints:

" Dwellings

Dwellings 1000m buffer

Watercourses 70m buffer

Telecoms links 100m buffer

Roads 150m buffer

Terrain slope class:

<14%

14-18%

>18%

Cowal and Trossachs Forest District Wind Farm - Bachan BurnSite Development Constraints

°

Key:

Wind Turbine Development Area

Forestry Commission Boundary

March 2014

Reproduced from Ordnance Survey data, HMSO © Crown Copyright Reserved 2014. License number 0100031673.

0 1,000

Meters

Cowal and Trossachs Forest District Wind Farm - Bachan BurnPredicted Wind Speeds

Predicted Average Annual Wind Speedat 80m Height (metres per second):

6.5 - 7.0

7.0 - 7.5

7.5 - 8.0

8.0 - 8.5

8.5 - 9.0

9.0 - 9.5

9.5 - 10.0

10.0 - 10.5

10.5 - 11.0

Note: 1m/s = 2.24 mph

The Cowal and Trossachs Forest District Wind Farm - Bachan Burn provides an excellent wind resource as highlighted by the figure to the left. The red shading indicates the highest wind speeds.

Extensive onsite assessments are undertaken to ensure that the wind farm will feature a design that is sensitive to the natural features of the site and presents the most practical environmental option for a wind farm at this location.

The map to the left shows the development constraints that are present onsite.