Upload
satin
View
47
Download
3
Tags:
Embed Size (px)
DESCRIPTION
Critical Chain Project Management. Case Study Application and Lessons Learned. Prepared for PMI Montgomery Chapter February Chapter dinner February 6, 2013 Mike Hannan, VP, Public Sector Services Hilbert Robinson, Senior Program Manager. Objectives. - PowerPoint PPT Presentation
Citation preview
Critical Chain Project ManagementCase Study Application and Lessons Learned
Prepared for PMI Montgomery ChapterFebruary Chapter dinner
February 6, 2013
Mike Hannan, VP, Public Sector ServicesHilbert Robinson, Senior Program Manager
Objectives
2
1. Use Actual Case Studies to address typical questions about the applicability of CCPM to real life project/program management challenges
2. Stimulate thinking about how you might apply this yourselves
Agenda
3
1. Brief Review of “The Three New Rules” of CCPM2. Case Study # 1 : Redesign of Commercial Jetliner3. Case Study # 2 : Nuclear Submarine Maintenance4. Q & A
New Rules
4
1
New Rule Advantage
Buffer Projects, Not Tasks
Faster project and a more reliable
project commitment.
Old RuleProblem
Plan each task as a highly reliable commitment.
Task variability preventsreliable project commitments.
2Assign staff to multiple
tasks, and start all projectsas early as possible.
Focusing staff on 1 taskat a time results in low resource utilization, andholds up other projects.
Stagger ProjectsMaximize project completion rate
and resource utilization.
3 Each PM lobbies the PMOfor critical resources.
Priorities across projectsshift, resulting in persistent conflicts over resources.
Protect ProjectBuffers ThatNeed It Most
Clarity, commonly agreedpriorities, stronger
cooperation among PMs
Change the rules, change the game, change results, close the gap
Case Study Format
5
Background, Performance Gap Implementation Challenges Approach / Application of the New Rules Results Lessons Learned
6
Case Study # 1 – New Product Development
The Application of CCPM to the Re-design of Commercial Jet Liner
Background / Performance Gap
Program budget is lowest ever – dictated by promises to investors Program schedule is shortest ever – dictated by promises to the market Program delivery date is set and not negotiable Executive in charge of only part of the program Only half the staff located at main site, 25% are overseas Must implement EVM and other “Best Practices”
Program Launch
Conceptual Design Fabrication Assembly Test DeliveryPreliminary
DesignDetail
Design
• Mechanical Engineering Only• Several hundred scientists, designers, analysts and technicians involved• Budget in the high 9 figures• Sub-contractors not involved
Additional Challenges and Special Considerations
How to draw boundaries around the resource poolsWhat do we define as a projectWhat work statement to include or ignoreHow much of the value stream to includeShould we do a pilotHow to integrate with other best practices / avoid
turf warsShould we also consider:
– Budget buffers– Scope / performance buffers
8
Approach / application of the rules
Independent cross functional product teams by airplane sections Program management specialist does both EVM and CCPM Build CCPM team plan first then convert to EVM baseline Standardize the design and drawing release process Each drawing is a project, hundreds of projects per team Use common template library for ease of planning and integration of
reporting across multiple teams Build comprehensive load to capacity model for each team Initially, no staggering – dates already set Instead, analyze staffing requirements and adjust staffing plans Renegotiate supplier commitments where necessary
9
Team
Team
Team
Te
am
Team
Team
70
135
0 0000000
106106
135
113113
0
100
150
124
100
8080
128
137
102107
149
73 737581
59
146
79
0
114
0
10
60
0 0
4045
99
0
30
150
0
135
109
43
73
8381
72
8989
120
63
16
29
110
0 00
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
0 10 20 30 40 50 60 70 80 90 100
% Critical Chain Complete
% B
uffe
r Inc
ursi
on
Example Multi-Project DashboardDifferent shaped dots for different types of deliverables
Approaching the end of the program
Approach / Application of Rules
Status by estimating
duration remaining,
not % complete
NO multi-tasking
Finish when you’re
done, not when it’s due
Plan using 50% probabilities for task durations, not 80%
Team members share
responsibility for project
deliverables
All team members work to the same priorities
Start only when ALL the prerequisites are complete
Poster Used to Communicate Desired Behavior
Critical Chain Execution Run
Rules
Seek out, identify and resolve issues quickly
Results
0.8
0.9
1.0
1.1
1.2
1.3
2001MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2002JAN FEB
Contractor2 1 CPAF RDTEElement: LR777.01 Name: AFITCPI and SPI
Index of Dollars
CPI 1.0051.0031.0071.0091.0300.9820.9600.9620.9640.9600.9651.001SPI 0.9931.0181.0141.0050.9980.8990.9040.9230.9490.9440.9400.972
Performance to PUSH system—late and over budget
Cost Performance Index (CPI) Schedule Performance Index (SPI)
Earned Value Reports-Before
Question: Please predict how the chart looks from this point to the end of the program.
Business as usual
Crisis
0.8
0.9
1.0
1.1
1.2
1.3
2001MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2002JAN FEB
Contractor2 1 CPAF RDTEElement: LR777.01 Name: AFITCPI and SPI
Index of Dollars
CPI 1.0051.0031.0071.0091.0300.9820.9600.9620.9640.9600.9651.001SPI 0.9931.0181.0141.0050.9980.8990.9040.9230.9490.9440.9400.972
Radically and rapidly increased system performance
Earned Value Reports-After
Cost Performance Index (CPI) Schedule Performance Index (SPI)
Results
Did you guess correctly? Be honest
Business as usual
Crisis New mode of
operations
Results
Engineering thought that
this was a VERY aggressive schedule
Working to flow events and NOT to due dates
3 weeks ahead
4 weeks ahead
8 weeks ahead
12 weeks ahead
Second Airplane Program
Two weeks of xmas break
Even shorter schedule yet finished 3 months early!!
Lessons Learned
Trust the data or, fix the data then, trust the data
No compelling need or reason to get better, no compelling results
Buffer Watching is not the same as Buffer Management
EVM and CCPM works together just fine, if you want them to
CCPM Scales up just fine
Benefits grow with increased alignment over a larger span of control
Quality improves with improved focus
Some people will have a hard time making the switch
100% compliance is not a pre-requisite
It is not just about scheduling. Focus on behaviors
It is not about the software
Trust the data or, fix the data then, …15
Case Study # 2
16
Navy – Pearl HarborThe Application of CCPM to the Repair of Nuclear Submarines
Find picture of fast attack submarine
Case Study Format
17
Background / Performance Gap Implementation challenges Approach / Application of the rules (deviations) Results Lessons Learned
18
Background / Performance Gap
Pearl Harbor Naval Shipyards employ about 4,000 peopleMaintain and modernize submarinesProjects start and end at a pre-determined timeMuch of the work is identified after project startsTasks completed using 81 specific trade skills
19
Expect high attrition – must refresh workforce - maintain critical skills
972 6681027
2182
3799
5248 5065
2066
493
735
383
144
88
100
63
279
0
1000
2000
3000
4000
5000
6000
18 - 25 26 - 30 31 - 35 36 - 40 41 - 45 46 - 50 51 - 55 56 - 60 61 - 65 66+
Total ES w/o Apprentices Apprentices Total ES
33%over 50
1707
10511306
2326
3887
5311 5065
2066
493 100
Nav
al S
hipy
ard
End
Stre
ngth
2002 DataTotal Workforce 23,530Attrition 1,129
Background / Performance Gap
Workforce Age Profile
20
Background / Performance Gap
Uncertainty• Neither the scope nor the work content is clear upfront, but we
need to make firm commitments before the projects begin
Not enough capacity• Our people (and equipment) resources are already overloaded,
but we keep accepting more projects
Aggressive schedules• It already takes heroic efforts to meet due-dates, yet we are being
asked to deliver more scope in lesser time
Complexity• Fixing Hundreds of components, in dozens of integrated systems • Severe space constraints – space is a limited resource• Highly dependent on specialized skills in short supply
21
Background / Performance Gap
Constraining Business Rules/Practices• Managing the money got in the way of managing the work
• Bad measures driving people to behave badly– Poor planning (confusion between work breakdown and workflow logic)
– Multi-tasking – staying busy but not making progress
– Parkinson's Law – Keep jobs open until all money has been spent
22
Background / Performance Gap
Customers disillusioned with late projects
Multiple scheduling tools and work lists
Job timelines inconsistent
Multiple priority lists across the organization
Difficulty in correctly prioritizing jobs
Increasing management complexity with contractors
No appropriate tool for balancing resources
No means for evaluating impact of new work
No means to validate necessity of overtime
23
Background / Performance Gap
Add to this picture:
1. Six months post 9/11
2. There is an X-fold increase in the need for secret missions
Proud tradition and impressive accomplishments, but…There still existed a substantial gap.
Measure Before After
Percent of on-time delivery < 60%
Amount of overtime charges Too high
Work not completed at end of project > 6%
Staffing requirements Too high
Implementation Challenges
How to deal with the nuclear culture – all changes increase safety risk How to plan when 30% of the work has not yet been identified How to integrate work being done by shipboard personnel How to integrate work being done by contractors How to integrate work being done in the many production shops How to handle a single CCPM project in a multi-project environment How to deal with fixed start AND finish dates How do deal with high volume of non-project work Getting permission to ignore / modify business rules / practices
24
Approach / Application of the Rules
Used templates and place holders to complete planning quickly Joint planning sessions with contractors and crew Modeled physical space as resources Separate “misc work” file reduced schedule clutter Free standing Local Area Network to address IT/security concerns Use schedule to determined and renegotiate due dates Not able to officially implement pipelining / (pseudo stagger) Full load to capacity picture for the first time
– Identified pockets of hidden resources– Identified urgent cross training needs – shifted manpower around
All over time decisions made based on buffer recovery expectations
25
26
Approach / Application of the Rules
Task # Task Name
1 Initiate Work Request2 Screen work to FMB3 Review work for acceptance4 Perform ship check5 Identify work scope6 Identify material requirements7 Write work package and provide to Zone Manager8 Review work package content for completeness9 Submit work package to work control10 Write work authorization form (WAF) and submit to ship11 Hang Tags, open WAF and notify Zone Manager WAF is open12 Remove Miscelleaneous interference as necessary13 Remove major inteference where required14 Perform authorized work15 Review completed work16 Grant testing authority to ship17 Clear tags and revise WAF18 Verify that all work related to the affected system is complete19 Establish required system conditions in preparation for testing20 Test system to verify integrity and performance requirments21 Document test results22 Re-install all interference23 Close WAF24 Sign AWR (Ship and QA)25 Review TGI and submit to Work Package Control26 Close All TGIs27 Sign Pre-requisit List28 Sign Certification Letter29 Issue Certification Letter
This step does the work
Summarized to seven schedulable steps and replicate for each component
Typical process to repair a single component
28
Focused Use of Overtime
29.8%
27.7%
17.4%
13.0%
14.6%
12.5%
14.9%
10.1%
$2,489,450
$2,015,968
$2,220,402
$1,981,335
$2,187,398
$1,398,487
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
2000 2001 1Q02 2Q02 3Q02 4Q02 1Q03 2Q03
% O
vert
ime
-$250,000
$250,000
$750,000
$1,250,000
$1,750,000
$2,250,000
$2,750,000
Ove
rtim
e C
ost p
er Q
uart
er
May 2003
29
On Time Completion
(5)(4)(3)(2)(1)
-123456789
101112131415161718192021222324
11/1
6/01
11/1
9/01
12/0
3/01
12/0
5/01
02/0
4/02
02/0
4/02
02/2
1/02
02/2
5/02
02/2
5/02
03/1
8/02
03/1
9/02
04/0
1/02
04/0
8/02
04/1
8/02
04/2
9/02
05/3
1/02
05/3
1/02
06/0
6/02
06/2
4/02
07/1
9/02
07/2
3/02
07/3
1/02
09/0
9/02
08/2
1/02
09/1
6/02
09/2
7/02
09/2
2/02
09/3
0/02
10/1
4/02
11/0
4/02
11/1
2/02
11/1
3/02
12/1
6/02
01/1
8/03
02/0
3/03
Avail Start Date
Day
s Ea
rly (-
) Lat
e (+
)
This chart displays the "On Time Completion" metric for the last 35 availabilities. It also superimposes a 10 Availability moving average line. The small tick marks at the axis indicate on time completion. Numbers above the line indicate late, numbers below the line indicate early.
May 2003
30
Improved Schedule Adherence
0.00
0.20
0.40
0.60
0.80
1.00
1.20
2000 2001 1Q02 2Q02 3Q02 4Q02 1Q03 2Q03
Quarter
% O
n Ti
me
This chart displays the "On Time Completion" metric. The ratio is the total number "On Time" versus the total completed. (This is
the equivalent of the Schedule Indicator in the DMOIs.)The Goal
May 2003
31
Background / Performance Gap
Performance Gap significantly reduced!!!
Proud tradition and impressive accomplishments, but…There still existed a substantial gap.
Measure Before After
Percent of on-time delivery < 60% >95%
Amount of overtime charges Too high Cut in half
Work not completed at end of project > 6% <2%
Staffing requirements Too high Cut by 25%
32
Critical Success Factors
1. Project schedules buffered, with aggressive task estimates2. Modeling is not too granular, and does not require too
much data 3. Pipeline is level-loaded at the constraints only, with
adequate protective capacity for all resources4. Task priorities are followed and tasks are regularly updated5. Buffer recovery is planned and managed6. Resource requirements are proactively managed7. Write new planning and execution process guides8. Use CCPM to focus other initiatives9. Revise performance metrics and accounting process10. Conduct CCPM expert training for stabilization
33
Transformation Challenges
1. System (holistic) versus functional (silo) perspective2. Multiple initiatives / change overload3. Frequent changes in military and civilian leadership4. Difficult to change large project midstream5. Full benefits not visible for single projects in the multi-project,
multi-shipyard environment
A Few Key Takeaways
34
CCPM is simple in concept—it turns common sense into common practice.
Introducing CCPM will help any project right away, regardless of how sophisticated and disciplined your project-management practices are (or aren’t).
Some “high-discipline” PM organizations take longer to realize CCPM benefits, because they have a harder time letting go of the “Old Rules.”
Many “low-discipline” PM organizations have an easier time adopting CCPM, because the “Old Rules” are not as deeply embedded.
Questions???
35
Documented Benefits of Critical Chain
36
Sample Results
18 months vs. 60 months,
IT department first then drug development – CEO: “100% due date performance”
Warner Robbins – Iraq War – Expanded C-5 air lift capacity by 8 million ton-miles
Iraq War – One extra submarine in steaming days
Satellite Division – Turned around the business
Engine Division – partially funded Northwest acquisition
Software delivered 5 months early, 33% cost reduction
37
Sometimes Speed and Reliability Are Mission Critical.