Upload
judah
View
21
Download
0
Tags:
Embed Size (px)
DESCRIPTION
CTF3 schedule following the fire incident. Fire in MKS13 Faraday Cage. Thu 4 Mar, lunch time …. Faraday Cage. MKS 13. Modulator in Gallery. Pulse Forming Network in Faraday Cage. Pulse Forming Network after fire. Events and actions. Modulator turned on around 12h00 - PowerPoint PPT Presentation
Citation preview
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
CTF3 schedule following the fire incident
CTF3 schedule following the fire incident
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
• Thu 4 Mar, lunch time …
Modulator in Gallery
Faraday Cage
Pulse Forming Networkin Faraday Cage
Pulse Forming Networkafter fire
Fire in MKS13 Faraday Cage
DRIVE BEAM LINAC
CLEXCLIC Experimental Area
DELAY LOOP
COMBINERRING
CTF3 – Layout
10 m
4 A – 1.2 ms150 Mev
30 A – 140 ns150 Mev
MKS 13
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Events and actions
• Modulator turned on around 12h00
• Smoke alarm level 3 at fire service 12h33
• Fire Service in place at 12h42Smoke from MKS 13General emergency stop activated
• All electricity (including MKS13) cutapart from lift and smoke extraction system
• CO2 , powder, then water and eventually foam applied => corrosive!!!
• Fire extinguished around 16h00
• Building access refused to everyone apart from fire service and safety commission
• Cleaning company BELFOR contacted for swab testing to check contamination of zone
• Safety commission enquiry started Surveillance camera image
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Clean up
• Gallery partitioned initially into 2 zones (contaminated area + “clean area”)
• Clean up of contaminated area, initial estimation > 4 weeks
• New swab test on equipment in “clean area”, contamination of ventilation ducts
• Clean up scheduled for 6 weeks• cleaning finished 27 April (most of it even before)
• All electrical systems locked off• gallery classified as non controlled area (cleaning firm didn’t need film badges)
=> no beam or RF possible
Contaminated area from MKS13
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Components from each rack dismounted and identified
Dust removal from sub components
Chemical cleaning
Ovens for drying after chemical cleaning
Vacuum ovens for 2nd stageCleaned components waiting for reinstallation in gallery
Cleaning procedure
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Some images from gallery
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Damaged cables
• >300 cables and ~40 HV vacuum cables in front of PFN damaged• All cables will be repaired – 4 ½ weeks estimated => until 26 May
• complete replacement (vacuum)• replace damaged section with connectors at both ends
• consequence:• all power still disconnected in the klystron gallery => until 20 May • vacuum pumps off in Delay Loop, Combiner Ring + part of linac
• Main worry: testing of connections (plus cleaned electronic racks…) => bumpy start-up?
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Restart planning
• Meeting on Wednesday 24th March with groups and departments who have equipment in the area to define an action plan for recovery after the clean up
• meeting three days ago about detailed planning
• Fire detection system gets repaired this week=> fire detection tests after re-establishing general power
• visual inspection by equipment experts
• gradually power on the equipments when powering possible=> hardware + controls tests
• modify klystrons for increased safety
• restart klystron interlock system for access => safety chain tests
• 3-4 weeks after end of cable repair
=> restart RF mid june
Other activities in the shadow:
• Remove two accelerating structures(as late as possible, when vacuum pumps are powered again)
• Realign beam lines in CLEX• Repair leaks in TBL PETS• Repair high power attenuator for RF deflectors• Maintenance of local cooling towers
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Optics improvements (DL dispersion)Full transport to CLEX
Bunch length control (first tests)
PETS conditioned to nominal power/pulse length
Accelerating structure conditioned to nominal power/pulse length
PETS breakdown rate measurements?
Test of new PETS on-off scheme
Two-Beam test power & energy gain,
100MV/m
Beam Loading compensation experiment
Measurement of breakdown kicks
Measurement of effect of beam loading on breakdown rate
1st TBL PETS installation
Operating scenario for 2010
(from CTF3 Committee of 11th February)
2nd TBL PETS installation
TBL studies
• Stability studies & improvements• PETS no recirculation• Phase stability• Operation at 5 Hz (or more)• Control of beam losses• Coherent Diffraction Radiation …
2nd run PHIN
TBL studies 30% deceleration
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Bunch length control < 1 mm rms (end of linac)
Full beam loading (95% transfer) high current acceleration (up to 5 A)
Ring isochronicity ap < 10-4
Sub-Harmonic bunching with fast (< 6ns) 180 phase switch(8.5% satellites)
Control of ring length to better than 0.5 mm
Factor 2 combination in Delay Loop (from 3.5 to 7 A)
Bunch train recombination factor 4 in Combiner Ring (from 3 to 12 A)
Beam current stability ~ 0.1 % end-of-linac,~ 0.2 % combiner ring
Transverse rms emittance 100 p mm mrad (end of linac)
Bunch train recombination 2 x 4 in DL and CR (from 3.5 to 28 A)
Transverse rms emittance < 150 p mm mrad (combined beam)
Bunch length control < 1 mm rms (combined beam)
Beam current stability ~ 0.1 % for combined beam
CTF3 Achievements – What is still missing for feasibility – Drive Beam Generation
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Beam-powered test of a PETS with external recirculation to 170 MW, <200 ns - ~10 A beam currentPower & drive beam energy loss measurements.
CTF3 Achievements – What is still missing for feasibility – TBL / TBTS / CALIFES
Beam-powered test of a PETS to nominal parameters (135 MW, 240 ns) with external recirculation (10 A) and without (20 A) – including probe beamImproved power & drive beam energy loss measurements(Break-down kick measurement).
8 PETS + spectrometer installed to verify transport of a 28 A beam with up to 30% of energy extracted.
Nominal probe beam to end of line (no accelerating structure)
Probe beam acceleration to 100 MV/m.
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Optics improvements (DL dispersion)Full transport to CLEXBunch length control (first tests)TBTS initial PETS testsCALIFES setupnew setup when MKS13 available?
PETS conditioned to nominal power/pulse lengthTBL PETS tests
Accelerating structure conditioned to nominal power/pulse length
PETS breakdown rate measurements???
Test of new PETS on-off scheme
Two-Beam test power & energy gain, 100MV/m
Beam Loading compensation
experiment
Measurement of breakdown kicks
Measurement of effect of beam loading on breakdown rate
1st TBL PETS
installation
PHIN possible
<-------->
2nd TBL PETS installation
6 weeks PHINphase-coding
Laser preparation
TBL studies(limited)
• Stability studies & improvements• PETS no recirculation• Phase stability• Operation at 5 Hz (or more)• Control of beam losses• Coherent Diffraction Radiation …
TBL studies 30% deceleration ?
1
1
2
2
3
3
4
5
6
8
7
4 5 67
8
1
4
2 3
65
7 8
CTF3 schedule following the fire incidentCTF3 schedule following the fire incidentR. Corsini – CLIC/CTF3 Coll. Board – 7 May 2010
Conclusions
• 17 weeks delay with respect to nominal program (42 weeks initially planned operation time)
=> >40% of the beam time lost!
• klystron MKS13 not available, acc. structures are removed
=> lower energy than before => complete new machine setup
• repair of MKS13 man-power limited, will happen late in the year (possibly back to nominal energy only in 2011)
• difficult start-up with additional HW checks
=> only less than half of useful beam time this year=> compromises on the program 2010 have to be made
• plan to have minimum winter shutdown and continue operation early in 2011
=> the items planned for up to end 2010 extend to mid 2011