Upload
brett-payne
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
CTR PerformanceWSDOT Nisqually Board Room
December 4, 2015
Lynn PetersonSecretary of Transportation
2013/2014 Cycle
Additional CTR Performance
Paul MasonPerformance Analyst
The Employer Survey in conjunction with the Aggregate Report
2
Employer Survey:
535 Responses for 2013/2014 sites
Available fields to answer: 221
For surveys received: Average fields with a response: 77.1% Five sites responded to fewer than 30%
of the fields, with these five ignored
Provides additional worksite information not captured in the aggregate report
Aggregate Report
966 Worksites counting towards goal for 2013/2014
VMT reduced by 33 million miles
Worksite sizes vary from 1 to well over 20,000 employees
Median size: 243 employees
3
Percentage of Questions Answeredper Employer Survey
4
5 of 535 Surveys Answered less than 50% of questions
Min: 28.1%Max: 92.8%Average: 77.1%
Number of Worksites by Industry Type
5
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Number of Employees by Industry Type
6
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Non-Drive Alone Travel Rates by Industry TypeWeighted by total number of employees
7
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Count of Sites, by Employer SizeAll Employees
8
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Non-Drive Alone Travel Rate and Employer SizeAll Employees
9
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Non-Drive Alone Travel Rate and Employer SizeAll Employees
10
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Non-Drive Alone Travel Rate and Proximity of Site to Bus Stop
11
Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.
Private Investment and Performance?
• The annual employer survey asks about different funding amounts• Challenges:
– The existing Employer survey responses to financial questions represent less than half of the 966 worksites in this cycle
– In looking at the provided data, some worksites within the same company have identical numbers reported, suggesting that some financial data may be double-reported
– There are privacy concerns around this information being collected and analyzed
• With the private financial information being incomplete, we cannot draw conclusions based on our current data
12
CTR Benefit Versus Traditional Construction?
13
VMT reduction of 33 million miles in 2014
This translates to an approximate VMT reduction of 36,000 miles per peak hour
Average throughput during peak period = 1,800 single occupancy vehicles per lane per hour
Per WSDOT 2015 Corridor Capacity Report, averaging SOV throughput per lane on I-5, I-405, SR-520, and I-90 during the peak periods
http://wsdot.wa.gov/publications/fulltext/graynotebook/CCR15.pdf
This is the equivalent capacity of adding a single lane that is 40.3 miles long
Since the program is administered in multiple areas throughout the state, the simple addition of 40.3 lane-miles would not yield the same results achieved by the program.
CTR Benefit Versus Traditional Construction?
14
Theoretical Cost of a 40.3 mile long lane added to the existing freeway
Costs for adding an additional lane to an existing freeway+
$4.1 to $14.7 million per lane-mile in 2015 dollars, small urban area Low estimate of $7.5 million per lane-mile in 2015 dollars, large urbanized area
Cost of adding 40.3 miles From $166 million to $591 million, small urbanized environment A low estimate of $304 million, large urbanized environment
+Per-mile cost of adding a lane is outlined below, per FHWA’s Table 6-1. Elemental Capital Improvement Costs, in 2002 dollars
https://www.fhwa.dot.gov/asset/hersst/pubs/tech/tech06.cfm
*The following calculator was used to convert from 2002 to 2015 dollars. This calculator is tied to the consumer price index (CPI) http://www.usinflationcalculator.com/
Since the program is administered in multiple areas throughout the state, the simple addition of 40.3 lane-miles would not yield the same results achieved by the program.
Right of way acquisition costs vary widely depending on the area. The above estimates may be high for rural areas and low for large urban areas.
Question for the Board
15
Now is a good time to discuss assumptions and methodologies
Additional methods and analyses can be applied to existing program data
Calculations can be simplified, where appropriate
Can the performance committee convene to discuss the above items and more?