15
CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason Performance Analyst

CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Embed Size (px)

Citation preview

Page 1: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

CTR PerformanceWSDOT Nisqually Board Room

December 4, 2015

Lynn PetersonSecretary of Transportation

2013/2014 Cycle

Additional CTR Performance

Paul MasonPerformance Analyst

Page 2: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

The Employer Survey in conjunction with the Aggregate Report

2

Employer Survey:

535 Responses for 2013/2014 sites

Available fields to answer: 221

For surveys received: Average fields with a response: 77.1% Five sites responded to fewer than 30%

of the fields, with these five ignored

Provides additional worksite information not captured in the aggregate report

Aggregate Report

966 Worksites counting towards goal for 2013/2014

VMT reduced by 33 million miles

Worksite sizes vary from 1 to well over 20,000 employees

Median size: 243 employees

Page 3: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

3

Page 4: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Percentage of Questions Answeredper Employer Survey

4

5 of 535 Surveys Answered less than 50% of questions

Min: 28.1%Max: 92.8%Average: 77.1%

Page 5: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Number of Worksites by Industry Type

5

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 6: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Number of Employees by Industry Type

6

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 7: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Non-Drive Alone Travel Rates by Industry TypeWeighted by total number of employees

7

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 8: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Count of Sites, by Employer SizeAll Employees

8

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 9: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Non-Drive Alone Travel Rate and Employer SizeAll Employees

9

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 10: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Non-Drive Alone Travel Rate and Employer SizeAll Employees

10

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 11: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Non-Drive Alone Travel Rate and Proximity of Site to Bus Stop

11

Note: These only reflect the 530 sites with Employer survey responses. The remaining 436 sites (of 966) are not represented here.

Page 12: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Private Investment and Performance?

• The annual employer survey asks about different funding amounts• Challenges:

– The existing Employer survey responses to financial questions represent less than half of the 966 worksites in this cycle

– In looking at the provided data, some worksites within the same company have identical numbers reported, suggesting that some financial data may be double-reported

– There are privacy concerns around this information being collected and analyzed

• With the private financial information being incomplete, we cannot draw conclusions based on our current data

12

Page 13: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

CTR Benefit Versus Traditional Construction?

13

VMT reduction of 33 million miles in 2014

This translates to an approximate VMT reduction of 36,000 miles per peak hour

Average throughput during peak period = 1,800 single occupancy vehicles per lane per hour

Per WSDOT 2015 Corridor Capacity Report, averaging SOV throughput per lane on I-5, I-405, SR-520, and I-90 during the peak periods

http://wsdot.wa.gov/publications/fulltext/graynotebook/CCR15.pdf

This is the equivalent capacity of adding a single lane that is 40.3 miles long

Since the program is administered in multiple areas throughout the state, the simple addition of 40.3 lane-miles would not yield the same results achieved by the program.

Page 14: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

CTR Benefit Versus Traditional Construction?

14

Theoretical Cost of a 40.3 mile long lane added to the existing freeway

Costs for adding an additional lane to an existing freeway+

$4.1 to $14.7 million per lane-mile in 2015 dollars, small urban area Low estimate of $7.5 million per lane-mile in 2015 dollars, large urbanized area

Cost of adding 40.3 miles From $166 million to $591 million, small urbanized environment A low estimate of $304 million, large urbanized environment

+Per-mile cost of adding a lane is outlined below, per FHWA’s Table 6-1. Elemental Capital Improvement Costs, in 2002 dollars

https://www.fhwa.dot.gov/asset/hersst/pubs/tech/tech06.cfm

*The following calculator was used to convert from 2002 to 2015 dollars. This calculator is tied to the consumer price index (CPI) http://www.usinflationcalculator.com/

Since the program is administered in multiple areas throughout the state, the simple addition of 40.3 lane-miles would not yield the same results achieved by the program.

Right of way acquisition costs vary widely depending on the area. The above estimates may be high for rural areas and low for large urban areas.

Page 15: CTR Performance WSDOT Nisqually Board Room December 4, 2015 Lynn Peterson Secretary of Transportation 2013/2014 Cycle Additional CTR Performance Paul Mason

Question for the Board

15

Now is a good time to discuss assumptions and methodologies

Additional methods and analyses can be applied to existing program data

Calculations can be simplified, where appropriate

Can the performance committee convene to discuss the above items and more?