PANTHER VILLAGEPhase II
11/16/2012 ConstructionUpdate
CURRENT WORK
West Wing- Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1st Floor: Final coat
of paint, casework installed, tile and grout installed- 2nd Floor: Final coat of paint, tile and casework installed- 3rd Floor: Tile and casework installed- Attic: doors installed (no hardware yet)
East Wing- Exterior: Masonry and shingles complete, fascia and soffit work ongoing- 1st Floor: Final coat of paint, casework and counter tops being installed - 2nd Floor: Painting, tile work mostly completed, casework being installed- 3rd Floor: Mudding and taping drywall, rough sanding
Central Lounge Area- Masonry completed
West Parking Lot- Paving completed
PANTHER VILLAGE
PANTHER VILLAGE
Brick and cast stone completed at Northwest lounge and stair area, curtain walls nearing completion .
PANTHER VILLAGE
Northwest lounge area curtain walls nearing completion.
PANTHER VILLAGE
Brick and cast stone complete on East wing. Northeast stair curtain wall not yet installed, flashing has started.
PANTHER VILLAGE
Brick and cast stone completed at central lounge and stair. Weather barrier also installed on cornice.
PANTHER VILLAGE
Temporary exterior enclosures installed.
PANTHER VILLAGE
Temporary heat installed throughout entire building to accommodate acceptable working conditions and protection for products.
PANTHER VILLAGE
First floor West corridor study/lounge area, metal stud framing completed.
PANTHER VILLAGE
First floor West corridor four bedroom apartment, kitchen cabinets and some counter tops installed.
PANTHER VILLAGE
First floor West corridor bedrooms, final coat of paint applied, visual display rails installed, shelving installed.
PANTHER VILLAGE
First floor East corridor studio apartment, kitchen cabinets installed, counter tops soon to be installed.
PANTHER VILLAGE
First floor East corridor bathrooms, tile floor and cabinets installed.
PANTHER VILLAGE
Cabinet Unit Heater installed in West corridor staircase.
PANTHER VILLAGE
West corridor third floor, curtain walls installed in private study room.
PANTHER VILLAGE
East corridor two bedroom corner apartment ready for first coat of paint.
PANTHER VILLAGE
Third floor central lounge area drywall being installed.
PANTHER VILLAGE
Forms set for stoops located at the Northwest entrance. Will soon be pouring concrete.
PANTHER VILLAGE
Bioswale located between the West wing of the building and the West parking lot.
PANTHER VILLAGE
Storm sewer line running from West parking lot to bioswale in place.
PANTHER VILLAGE
West parking paving complete.
PANTHER VILLAGE
Concrete work completed at loading dock area.