Custom Experience Report RUAG DefenceQuality Gate Management (SAP Solution Manager 7.1)
Christoph Bornhauser / Daniel Müller SAP (Switzerland) AGBusiness Analyst / Project LeaderRUAG Switzerland AG, RUAG Defence
Lausanne, September 3, 2014
2 | RUAG Defence | 08.09.2014
Agenda
• The company RUAG
• System consolidation
• Use Case Quality Gate Management
• Usage within RUAG Defence
• Experience and Outlook
The company RUAG
4 | RUAG Defence | 08.09.2014
The Group RUAG
5 | RUAG Defence | 08.09.2014
The Group – Head office in Switzerland andworldwide subsidiaries
Civil Aerospace
SwedenGermany Hungary
AustriaFranceUSA
Australia
total Defence
Employees: 8’200 1’400
Trainees: 420 140
Net Sales: 1’752 Mio. 357 Mio.
Data as at 31/12/2013
6 | RUAG Defence | 08.09.2014
RUAG DefenceLocations in Switzerland, Germany and France
Hamburg
Munich
Lichtenau
Toulouse
Employees: 1’400
Trainees: 140
Net Sales: 357 Mio.
Data as at 31/12/2013
7 | RUAG Defence | 08.09.2014
RUAG Defence
NEO ServicesBe prepared! Secure communication leads tosuccessful command.
Simulation & TrainingBe prepared! Practice to improve skills.
Land SystemsBe prepared! Upgrade for missing success.
45%
8 | RUAG Defence | 08.09.2014
System Consolidation
9 | RUAG Defence | 08.09.2014
System ConsolidationMotivation:• Creation of Business Synergies by the different divisions• Consolidation and harmonization of business processes• Consolidation and harmonization of IT Applications• Consolidation of SAP systems
Starting Position:• Merging 2 divisions in 2011• New modeling of the business processes• IT has no business process oriented view Module oriented
…2010 2011 2012 2013 2014 2015 2016 2017
Mobile InternationalHELIOS
RUAG Defence Cooperation
OrganizationSales / Finance /
Human Resources
Airolo +Airolo
Data flowValue flow
Material flow
Optimization
Project Mgmt.Resources
CRM
MMI
AppsTicketingService
One ERP
RUAG Electronics
RUAGLand Systems
10 | RUAG Defence | 08.09.2014
System consolidation withSAP SLO Service
2 productive landscapes
2 customizing clients
Transfer of 1’200 tables
> 20 peripheral systems
> 80 interfacesProductive SAP landscape PSE
Project landscape Airolo
Upcoming consolidated SAPlandscape PSW+
Productive SAP landscape PSW
peripheral systems / interfaces
2011 2012 2013 2014 2015 2016 2017
HELIOS Airolo Airolo + Mobile International
11 | RUAG Defence | 08.09.2014
Goal:
1. Acceleration of the system harmonization using efficient tools and information2. Consistently transparent business processes up to technical settings3. Show the Impact of technical harmonization of the system settings on business processes4. Elicit and document the differences of technical settings (SLO – MC Delta) in regard to business processes
Approach:
a. Consistent combination of the SLO tools (harmonization of technical settings) with Solution Manager(Harmonization of processes)
b. Increase of transparency, quality and security of system harmonization by business – and application viewc. Transparent presentation of the SLO analysis in regard to customizingd. Identify impacts on business processes as preparation for testing
Technical ApproachSolution Manager SLO
12 | RUAG Defence | 08.09.2014
Success Factors for a successful systemharmonization
Existing RUAG SAP landscapes PSE und PSW
Consolidated SAP landscape
Harmonization of businessprocesses
Process Management
Project support by the ALMLife-Cycle Tool
ALM Services and ToolsSolution Manager
Harmonization of the SAPERP systems
SLO Services & Tools
PSE
MWB
PSW+
> 500 business processes
Business support
ALM introduction in the project
Technical Know-How
Process knowledge
13 | RUAG Defence | 08.09.2014
Use Case Quality Gate Management
14 | RUAG Defence | 08.09.2014
SAP Change Control Management
The Quality Gate Management(QGM) is part of the ChangeControl Management
The QGM runs in parallel with theChange Request Management(ChaRM)
Project- and operational normalchanges can be handled with oneuniformly tool.
15 | RUAG Defence | 08.09.2014
Change process within QGM
Scope Build Test Deploy
Development Quality Assurance Production
Q-Gate 1 Q-Gate 2
Division of thesystem landscapewith Quality Gates
Change
Transport
Transport
Bulk import of transports .Copy of transport
16 | RUAG Defence | 08.09.2014
Usage within RUAG Defence
17 | RUAG Defence | 08.09.2014
Quality Gate Management @ RUAGMotivation:• SAP system changes have to be implemented in a controlled way• Sustained documentation of system changes• Transparent change process for SAP system changes
Starting Position:• No consistently, process oriented change management in the SAP systems• Two transport lines, «productive» changes and «project oriented» changes• Insufficient documentation of changes
Goal:• Controlled SAP Change Control Management with linkage to the transport management• Differentiation of the «productive» and «project oriented» changes• Transparent and sustainable change process• Risk minimization for the productive system
18 | RUAG Defence | 08.09.2014
System landscape RUAG Defence
Project oriented changemanagement for the projectAirolo with Solution Manager
QGM
Complete documentation ofsystem changes with QGMand ChaRM
Operative changemanagement for operationswith Solution Manager
ChaRM
DEV
QSB
QUA PRO
PSB
201
099
QG
QGQGM
ChaRM
System landscape forproject AIROLO
System landscape foroperation
19 | RUAG Defence | 08.09.2014
Structure of QGM for the project Airolo
Central interface for all system technical projectchanges
Structuring of the changes within a project (e.g.by sub-projects)
Consistent assignment of transports to projectchanges
Overview at important transport information likestatus, type or critical objects
Project relatedchanges
Transport requestsper change request
20 | RUAG Defence | 08.09.2014
Quality Gates for the project Airolo (View Test 1)
Presenting the Quality Gates of the projects, incl.planned date and status
Two-stage process for opening the Quality Gates
(Traceability of the changes on the states of theQuality Gates)
Project relatedQ-Gates
Status of theQ-Gates
Protocol of theQ-Gates
21 | RUAG Defence | 08.09.2014
Risks and system landscape graphs
Show the transport risks within theproject
Reflect the system landscape forthe project
Tools for the transportmanagement
System relatedrisks
Project oriented overview ofthe change information
22 | RUAG Defence | 08.09.2014
Experience and OutlookRUAG Defence
23 | RUAG Defence | 08.09.2014
RUAG Defence – Experience and Outlook
Ensuring no carrying of transports from different phases into the system by Quality Gates
Minimization of transport risks by the comprehensive implementation of Change Control Management
The transportation of transport copies during the project was a huge support.
Quality Gate Management is not solving all transport problems but it offers an important assistance
Outlook:
Quality Gate Management will be increasingly used for SAP projects in the future. In additionthe use of QGM is tested for the coordination of development waves.
24 | RUAG Defence | 08.09.2014
Referent:SAP Consulting Switzerland
Daniel MuellerALM Senior Consultant
+41 79 250 28 [email protected]