d3ar Test Packages Status

Embed Size (px)

Citation preview

  • 7/26/2019 d3ar Test Packages Status

    1/2

    D3 HYDROTEST

    ITP# PUNCHLIST CLEARED NDE CLEARED QC WALKDOWN

    1

    2 8/29/2006 8/31/2006 8/31/2006

    3 8/29/2006 8/31/2006 8/31/2006

    5 8/29/2006 8/31/2006 8/31/2006

    6 OK 8/9/2006 OK

    7 OK 8/6/2006 OK

    8 OK 8/26/2006 OK

    9 9/1/2006

    10 OK 8/30/2006 OK

    11 OK 8/30/2006 OK

    12 OK PENDING PMI

    13 OK 9/1/2006

    14 9/1/2006

    15

    16 OK

    17 OK 8/31/2006 OK

    18 OK

    19 OK 8/17/2006 8/17/2006

    20 OK 8/26/2006 8/26/2006

    21 OK

    22 8/31/2006

    23 OK 9/1/2006

    25 OK

    26 8/30/2006 OK

    27 9/1/2006

    28 OK 9/1/2006

    29

    30 OK 8/31/2006

    31

    32 OK

    33

    35 OK 8/31/2006 OK

    TAG#297 OK 8/30/2006 OK

    TAG#298 8/30/2006

    TAG#300 OK 8/30/2006 OK

    TAG#301

    TAG#634 OK 8/28/2006 OK

    TAG#643 8/31/2006 OK

  • 7/26/2019 d3ar Test Packages Status

    2/2

    PIPING PACKAGES

    VALERO WALKDOWN HYDRO COMPLETED

    8/31/2006 9/1/2006

    8/31/2006

    8/31/2006 9/1/2006

    OK 8/9/2006

    OK 8/6/2006

    OK 8/26/2006

    OK 8/30/2006

    OK 8/30/2006

    OK 8/31/2006

    OK 8/17/2006

    OK 8/26/2006

    OK 8/30/2006

    9/1/2006

    OK 8/31/2006

    OK 8/30/2006

    OK 8/30/2006

    OK 8/28/2006