Upload
vucong
View
215
Download
3
Embed Size (px)
Citation preview
VISCED Interim Evaluation 1 Evaluator: Dr Maggie McPherson
Interim Evaluation Report
Deliverable: D9.1
Project Agreement Number:
511578–LLP–1–2010–1–GR-KA3-KA3MP
Project funded by the European Commission
Document Title VISCED – Quality Evaluation Interim Report
Deliverable no. D9.2
Date of issue 15 January 2012
Author Maggie McPherson
Contact name Maggie McPherson
Organisation University of Leeds
Address School of Education
Hillary Place
Leeds LS2 9JT
United Kingdom
Telephone +44
Email [email protected]
Contributors to document Project partners
Quality Reviewers Paul Bacsich
Contractual date of delivery 31st
December 2011
Actual date of delivery 15th
January 2012
Approval status Reviewed internally
Abstract
This report summarises the evaluation of each Work Package,
with evidence from partner self-evaluation, ethnographic
observations and documentary analysis.
Keyword list Work Package; quality and evaluation
Distribution list EU Commission [DG3]; VISCED partners
Method of distribution Email
Electronic copy filed “VISCED files” in VISCED Dropbox
Confidentiality status PU
History
Version number Date Revised by Revision date
1.0 15th
January 2012
VISCED Interim Evaluation 2 Evaluator: Dr Maggie McPherson
Table of Contents
1 Introduction: Validity of Project Design ........................................................................ 4
2 WP1 Project Planning and Management [Led by Sero] ................................................... 5
Pre-project meeting in London, January 2011 ....................................................................... 5
Boot Camp Meeting, Brussels, February 9th - 11th ............................................................. 5
Additional Ad-hoc Project Meeting (April 2011) ............................................................... 7
1st Flash Project Partner Meeting (8 June 2011) .............................................................. 7
2nd Flash Project Partner Meeting (6 July 2011) .............................................................. 7
Project Partner Meeting 2 Oeiras (13 September 2011) .................................................. 7
Project Partner Meeting 2 Oeiras (13 September 2011) – WP1 Project Management
[Sero] ..................................................................................................................................... 8
3rd
Flash Project Partner Meeting (12 October 2011) ............................................................ 8
4th
Flash Project Partner Meeting (10 November 2011) ........................................................ 8
3 WP2 Field Research [led by Sero] ................................................................................... 10
Additional Ad-hoc Project Meeting (April 2011) ............................................................. 10
1st Flash Project Partner Meeting (8 June 2011) ............................................................ 10
2nd Flash Project Partner Meeting (6 July 2011) .............................................................. 10
Project Partner Meeting 2 Oeiras (13 September 2011) ................................................ 10
3rd Flash Project Partner Meeting 12 October 2011 ........................................................ 10
4th Flash Project Partner Meeting (10 November 2011) ................................................. 10
WP2 Summary .................................................................................................................... 11
4 WP3 Analysis & Recommendations [MENON] ............................................................... 12
1st Flash Project Partner Meeting (8 June 2011).............................................................. 12
Project Partner f2f Meeting 2 Oeiras (13 September 2011) ........................................... 12
3rd Flash Project Partner Meeting (12 October 2011) ..................................................... 12
4th Flash Project Partner Meeting (10 November 2011) ................................................. 13
WP3 Summary .................................................................................................................... 13
5 WP4 Critical Success Factors ........................................................................................... 13
6 WP5 Consultation of Experts in this Field [led by Lambrakis] ..................................... 15
1st Flash Project Partner Meeting (8 June 2011).............................................................. 15
2nd Flash Project Partner Meeting (6 July 2011) .............................................................. 15
1st IAC f2f Meeting Oeiras (13 September 2011) ............................................................. 15
3rd Flash Project Partner Meeting (12 October 2011) ..................................................... 15
4th Flash Project Partner Meeting (10 November 2011) ................................................. 16
2nd IAC f2f Meeting Berlin (30 November) ....................................................................... 16
WP5 Summary .................................................................................................................... 18
7 WP6 Piloting [led by Tensta] ........................................................................................... 19
3rd Flash Project Partner Meeting (12 October 2011) ..................................................... 19
8 WP7 Dissemination [led by AtiT] .................................................................................... 20
Project flyer ...................................................................................................................... 20
Project website ................................................................................................................. 20
Project wiki ....................................................................................................................... 20
Project Presentations in 2011 .......................................................................................... 20
Project Presentations considered for 2012...................................................................... 20
Project newsletters. ......................................................................................................... 20
Other Dissemination Avenues .......................................................................................... 20
9 WP8 Exploitation [led by Lambrakis] ............................................................................. 20
VISCED Interim Evaluation 3 Evaluator: Dr Maggie McPherson
10 WP9 Quality and Evaluation ........................................................................................... 21
Project Progress .................................................................................................................. 21
Evaluation of Effectiveness ......................................................................................... 21
Project Challenges ........................................................................................................ 21
Analysis of project activities to-date ........................................................................ 22
Appendix 1: VISCED Meeting 1 (Kickoff) Evaluation Responses ........................................ 23
VISCED Interim Evaluation 4 Evaluator: Dr Maggie McPherson
1 Introduction: Validity of Project Design
This aspect of the interim project evaluation will take into account the baseline condition at
the outset of project. Given that the proposal built on an earlier project that investigated
Virtual Campuses (Re.ViCa), this project had a logical and coherent plan based on previous
experience. It was while the Re.ViCa project was being carried out that it became apparent
that there was a deficit of knowledge in terms of what has been happening with regard to
younger learners taking part in online learning during their formal school years.
Consequently the underlying problem was to discover to what extent there has been an
uptake of online education for virtual schools and further education colleges.
The main strategy for the first year of the project was to properly establish the status quo
for this particular sector. The main strategic components of the project for evaluation
during 2011 are as follows:
• WP1 Project Planning & Management
• WP2 Field Research
• WP3 Analysis & Recommendations
• WP5 Consultation of Experts in this Field
• WP6 Piloting
• WP7 Dissemination
• WP8 Exploitation
• WP9 Quality and Evaluation
This report will chart the progress and report any discrepancies with planned activities and
outputs during the first year of the project.
VISCED Interim Evaluation 5 Evaluator: Dr Maggie McPherson
2 WP1 Project Planning and Management [Led by Sero]
The project management was predominantly carried out by SERO in the UK. The acceptance
of this project for funding was made somewhat later than hoped. As a consequence, this
delay meant that the initial project start up project meeting could not be held in January as
planned, and this had to be postponed until February. Despite the fact that these delays
made management overall more difficult, in order to avoid losing momentum, a few key
partners decided to turn this to advantage by going ahead with holding an early ad hoc
meeting.
Pre-project meeting in London, January 2011
Prior to the first official project launch meeting, a preliminary meeting was held in London
during the BETT Show. The attendees were partners had already arranged to attend the
conference or were in a reasonable position to get to London. This provided the opportunity
for representatives from SERO, Lambrakis, ATiT and Leeds to have an early discussion, which
in turn helped with initial thinking about adjustments needed for the project planning.
Boot Camp Meeting, Brussels, February 9th - 11th
As stated before, the late start to the project led to the launch meeting being delayed until
February. The agenda for this meeting began with clarification of Commission arrangements
and new financial rules. The initial provisional VISCED timeline was presented for to
attendees.
During this first kick-off meeting, it was deemed necessary to have some discussion around
competing stakeholder interests and how these could be aligned. It was noted that although
earlier alliances to the project (e.g. EU School Net) were no longer in a position to become
involved, working relationships with national ministries would continue to play a role. It was
recorded that a communications strategy was needed to ensure partners received
information in a timely manner. This was followed by colleagues’ presentations of their own
institution, philosophy and anticipated contribution to the project. This was not only
intended as an information-sharing exercise, but also contributed an essential element to
team-building and collaborative spirit.
An essential explanation regarding the VISCED wiki ensued. Issued covered were how this
should be edited, that the emphasis would be on exemplars, how experiences from Re.ViCa
might contribute to research results. It was clarified that the emphasis would be on
secondary level education (i.e. pre-tertiary levels) and that final reports would be subject to
peer-review. While discussing WP3 (Influence Maps), consideration was given to countries
might affect others’ ICT policy and implementation, the need to understand of scope issues,
and other such issues. It was explained that the altered start date meant that WP4 could
not begin till year 2. With regard to WP5, it was suggested that the International Advisory
Committee needed to be set up promptly in order to enable attendance at 4 meetings and
to get value from their input and advice. The dissemination plan was outlined, a by line for
the VISCED leaflet was decided upon, project website discussed, and dissemination
strategies presented. The mid-agenda items set out exploitation and evaluation strategies.
The meeting was concluded with final project management issues and future meeting dates
were proposed:
VISCED Interim Evaluation 6 Evaluator: Dr Maggie McPherson
1. Meeting 1 - Brussels Feb’11
2. IAC 1 - Dublin June ‘11
3. Meeting 2 – Athens Oct ’11
4. IAC 2 - Berlin ‘11
5. Meeting 3 – Stockholm May ‘12
6. IAC 3 - Stockholm May ‘12
7. Meeting 4 – Berlin ’12
8. IAC 4 – Berlin ’12
VISCED Interim Evaluation 7 Evaluator: Dr Maggie McPherson
Following the Boot Camp, there were then further delays caused by uncertainty about the
status of P1 Lambrakis as an acceptable applicant, creating some more unavoidable
challenges. Partners were understandably reluctant to commit time, resources and
intellectual energy whilst there was uncertainty about the overall financial status of the
project. To mitigate this hold-up, the team deemed that it was necessary to add in a
supplementary unbudgeted continuation meeting in Brussels at the end of April to discuss
matters related to Work Package 2 and 3, which were key deliverables for 2011.
Additional Ad-hoc Project Meeting (April 2011)
The minutes for this meeting clearly indicate that there was a necessity for another face-to-
face meeting in order to clarify a number of management issues to get the project on track.
Clarification regarding payment was made and an agreement for disbursement of the same
was made. Issues related to communication (Wiki pages, and Dropbox to reduce number of
project emails) were ironed out. To supplement the less frequent face to face (f2f)
meetings, it was decided that regular online Flash meetings were required. SERO agreed to
circulate budget reviews, update Gantt chart of deliverables, and to set up a Risk Register.
ATiT agreed to create a template for reporting.
1st Flash Project Partner Meeting (8 June 2011)
The project managers highlighted a number of issues that had to be attended to. The
budget check revealed a couple of returns from April were still outstanding and partners
were reminded that the next one would be at the start of July. The GANNT chart has been
updated and re-circulated so that timeline for deliverables could be discussed, and it was
noted that WP3 dates needed amendments. The Risk Register was not discussed but the
notes stated that a draft was attached for partners’ comments. The draft Report Template
was still to be completed and would follow. It was noted that with delays and changes to
meetings over the past few months, there was a need to review the project document and
incorporate decisions that have been made in partner meetings and some minor budget
alterations that had resulted from these.
2nd Flash Project Partner Meeting (6 July 2011)
Partners were prompted regarding the imminent six-monthly budget check, and were told
that updated spreadsheets would be circulated. Partners were also reminded about
timescales, i.e. that deliverables to the Commission had to be included with the interim
report at the end of the year, and therefore it was necessary to review internal deadlines
and to strictly adhere to these. As few partners were to be available in August, the next
project gathering would be the 2nd
f2f partner meeting (be held alongside the EFQUAL
meeting, to maximise opportunities to engage experts for consultation).
Project Partner Meeting 2 Oeiras (13 September 2011)
It was hoped that this would allow members identified as being suitable to join the
International Advisory Committee (IAC) to attend. During the preparatory stages for this, it
transpired that this was not the best option for the meeting after all, and the date was
brought forward. In the final event, this meeting was held in Oeiras, Portugal. This proved
fortuitous because it was then also possible to enlist new members to attend a full day IAC
meeting and these experts were able to offer insights into the project achievements so far
and allowed the VISCED team to make timely adjustments to activities still outstanding.
VISCED Interim Evaluation 8 Evaluator: Dr Maggie McPherson
Adjustments were made to the planned meetings, with the first full f2f of 2012 meeting
proposed for Sheffield in May, and the final f2f meeting proposed for Brussels, probably in
October 2012. It was decided that partner meetings should be decoupled from IAC
meetings.
Project Partner Meeting 2 Oeiras (13 September 2011) – WP1 Project
Management [Sero]
Partner Name Attendance Partner Name Attendance
Aarhus - - MENON Claudio Dondi PM only
ATiT Nikki Cortoos All day MENON/Scienter Daniela Proli All day
ATiT Sally Reynolds All day Sero Paul Bacsich All day
EITF Jüri Lõssenko All day Sero Barry Phillips All day
EFQUEL - - Tensta - -
Lambrakis Nikos Zygouritsas All day TIEKE - -
Leeds University Maggie McPherson All day
Work Package 1
Item Notes Action
Next project
partner
meetings
Next Flash meeting not discussed June Sero suggest this be held on Wednesday 12th
October, 1400 – 1600 BST; 1500-1700 CET;
1600-1800 eastern Europe time. Can all partners
confirm that at least one representative can
‘attend’? Sally to organise and book time &
circulate URL to partners
To be confirmed at next Flash meetings
Maggie suggested it would be useful if
partners unable to attend meetings
submitted a vidcast in advance
To be considered at next Flash meeting
Interim
budget
check
[Post-meeting note] Partners are reminded
that the next review of expenditure [Jan-
Sept 2011] will be required shortly
Giles to circulate budget review spreadsheet for
completion and return by partners before 20th
October.
Project
Timeline
GANNT chart to be updated and re-
circulated for comments
Giles & Paul to do this – will be circulated early
in October
this meeting in Berlin prior to the Online Educa Conference during early November 2011.
3rd Flash Project Partner Meeting (12 October 2011)
Project management issues raised during this meeting were the budget check, and it was
noted that some partners were having travel budget problems due to expensive airfares.
The project managers were to whether the EC would strike out expenditure perceived as
excessive. Sero asked all partners to communicate if they were likely to have any problems
meeting deadlines up to end of 2011 at which point it would be possible to review timescale
and amend as appropriate and reissue before next Flash meeting.
4th Flash Project Partner Meeting (10 November 2011)
All partners were asked to complete and return the end-of-year budget check to ensure the
Commission would accept progress report. In addition, partners were asked to inform Sero
know a.s.a.p. if they were likely have any problems meeting deadlines up to end of 2011 and
were asked to respond to progress report requests in a timely fashion.
VISCED Interim Evaluation 9 Evaluator: Dr Maggie McPherson
VISCED Interim Evaluation 10 Evaluator: Dr Maggie McPherson
3 WP2 Field Research [led by Sero]
The project was built on a logical assumption that partners would be able to bring local
knowledge to the field research and that this would speed up the data gathering process for
WP2. The research team found that this work package suffered the knock-on effects of a
delayed start as explained in WP1. However, while for the most part the planned activities
seemed to be realistic and coherent, in reality and in a true spirit of research, the
investigation of virtual schools was delving into an unfamiliar environment.
Additional Ad-hoc Project Meeting (April 2011)
The second part of the meeting was concerned with the WP2 Field Research deliverables.
Colleagues considered levels, context/dimensions, drivers, parental attitudes, quality and
accreditation etc. and how these would relate to exemplars. It was also agreed that
additional guidance for wiki use would be provided.
1st Flash Project Partner Meeting (8 June 2011)
Although some partners were able to report making progress with data gathering, country
reports had not yet been uploaded, giving the appearance of being seriously behind with
completing and loading. All were urged to contribute to the wiki as soon as possible, and
where partners had not yet really started work, their ‘home’ country was recommended as a
good point to start. Partners were also asked for brief CVs.
2nd Flash Project Partner Meeting (6 July 2011)
Whilst it was noted that there was a great increase in populating the wiki, partners were
urged to continue uploading material on to the wiki as soon as it is drafted, even if it needed
further editing. Additionally, it was apparent that progress was being made on finding
potential exemplars. Partners were reminded to upload brief CVs for themselves as soon as
possible.
Project Partner Meeting 2 Oeiras (13 September 2011)
This was a useful meeting to update project management issues, but more importantly, an
opportunity to clarify field research issues. The importance of time entries of wiki entries for
country reports was emphasised and additional possibilities were welcomed. All partners
were reminded to help with newsletter dissemination.
3rd Flash Project Partner Meeting 12 October 2011
The discussion revealed that country research had progressed and that a considerable
number of virtual schools had been identified, albeit in varying states of evolution. Partners
were asked to ensure that all exemplars found in were included as separate wiki entries.
Nevertheless, it seemed that country reports were sufficiently solid state as to provide a
reasonable basis for starting on WP3.
4th Flash Project Partner Meeting (10 November 2011)
Despite the fact that many virtual schools had been identified, not all exemplars had been
given separate wiki entries and partners were reminded to do this. This left continental
reports to be addressed and Sero made a commitment to do this early in 2012.
VISCED Interim Evaluation 11 Evaluator: Dr Maggie McPherson
WP2 Summary
Despite time constraints, since finding a shared intellectual understanding was crucial for the
success of a project of this nature, the partners involved in this work felt that it was
necessary to hold to lengthy debates about taxonomy and typology, i.e. to identify what
would be in scope and what would not fit. This inevitably led in turn to some delays in data
collection in terms of country and regional reports, for both within Europe and beyond. As a
consequence, the quality and depth of these reports is variable. Although it the project
managers hope to remedy this in the second year of the project, it has meant that the
quality and quantity of reliable information available for Interim List of Exemplars [D2.3] is
currently not as complete as it was originally envisaged it would be at this stage of the
project.
From an outsider insider point of view, it is thought that in this project, as is the case in most
large partnerships, there has been varying levels of commitment. The effect of this is that
some colleagues have been less involved in implementation than project managers hoped
for. Yet it is sometimes difficult to determine how the strategic aims of this particular
project fits into other workload demands of project partners. Furthermore, on occasion, in
large organisations, it may be that colleagues simply do not have the capacity or the level
influence to change local and urgent demands on their time. Despite this, the project
managers appear to have overcome a number of difficulties and are hopeful of achieving
some success in getting close to the planned objectives, albeit a little later than hoped for,
with some of the exemplars being submitted very recently.
With this in mind, as an evaluator, it has been useful to receive the following detailed
reflection on this activity as highlighted below:
“My main contribution to research and report writing has been in compiling country reports for
Scotland and Latin America, writing the continent report for Latin America [all for D2.2] and editing
and producing D2.3, the interim list of exemplars. This has been a fascinating task and has
highlighted a number of issues for me:
• the extent to which many European virtual schools operate 'under the radar' as far as governmental
awareness and regulatory frameworks are concerned;
• the numbers of virtual schools in Europe is greater than we originally anticipated, but in several
western European and Latin American countries expansion seems to have stalled in the second half
of the first decade of the C21;
• although there are relatively few examples of failed virtual schools, few outside the USA, Canada and
some countries of Australasia have grown to any significant size;
It is likely that our lack of research capacity to cover Asia [especially China] fully has resulted in us
missing a number of virtual schools and colleges in this region - there are certainly plenty of
commercial organisations marketing a range of virtual and distance learning products in the
region.”
As a final word on this work package, the project managers are aware of the knock-on effect
of delayed on WP3 and WP4, and have made a note to update the project Risk Register to
take account of this and detail the remedial measures that need to be taken during Year 2.
VISCED Interim Evaluation 12 Evaluator: Dr Maggie McPherson
4 WP3 Analysis & Recommendations [MENON]
This deliverable was built on the assumption that partners would typify instances of Virtual
Schools & Colleges, create EU Influence Maps, identify potential Critical Success Factors
(CSFs), identify innovative ‘Good Practice’ for piloting, create Interim Policy
recommendations and make interim recommendations for teacher training.
1st Flash Project Partner Meeting (8 June 2011)
Since the analysis depended on work completed in the previous work package, it was not
surprising that not much had been done on WP3 at the point of this meeting – therefore it
was noted that slight adjustments to timings might be necessary. Partners were informed
that the colleges typology would be relatively straightforward as this built directly on work
completed in Re.ViCa, but that developing the typology for virtual schools would be more
difficult and that it was necessary to create a much larger list of potential exemplars. It was
noted that this WP was central, and that USA experiences of virtual schools would add
considerably to this. It was of interest that whilst in some countries, such as Italy, there
were several virtual universities but that this had not translated into similar initiatives in the
high school sector. Partners were encouraged to look beyond Europe as exemplars beyond
this zone would be very informative.
Project Partner f2f Meeting 2 Oeiras (13 September 2011)
Partners reviewed the current state of progress country and regional reports of virtual
schools discovered thus far and it seemed that most zones were covered to some extent, but
it appeared that there was still more work to be done. Drawing from WP5, and with respect
to WP3, it transpired from IAC advice that there was a move towards blended rather than
pure online. In response, a possible taxonomy of virtual schools as a continuum was
suggested, and a 6-level hierarchy with 5 intermediate points for groups of entities
proposed. Partners were warned that the deadline for Influence Maps was approaching.
With regard to Case Studies, different levels were possible and Susan Patrick offered to
share a template being used by iNACOL for this. The minutes of the meeting mentioned that
it was premature to discuss CSFs at this point but that partners were encouraged to identify
innovative good practice from that point on.
3rd Flash Project Partner Meeting (12 October 2011)
It appeared that examples of virtual schools being found outside Canada and USA were
somewhat smaller than expected and it was identified as a point for further investigation.
There was conjecture that this may be related to the way they were being run, but was also
suggested that there were inconsistencies between the start-up incentives and the needs
and targeting of the venture (programmes, etc.) in countries where schools have more
autonomy. Partners looked to MENON to provide Influence Maps.
It was noted that the first draft of the typology was not yet ready, but project team was
warned to learn from Re.ViCa and to not over-analyse this. It was decided a pragmatic
approach was more appropriate and the USA taxonomy would provide a way forward for
producing case studies. A list of thirteen potential case studies was proposed – ultimately
this would be refined and brought down to around nine – so partners were called upon to
offer more so that these could be chosen from a long list of twenty five. A good discussion
on this issue ensued and it’s clear partners have given due consideration to this task.
VISCED Interim Evaluation 13 Evaluator: Dr Maggie McPherson
Concern was expressed about deadlines and project managers agreed to review timescales.
Attention was drawn to the teacher training circulated before the Oeiras meeting. In
response, a comment was made that small European virtual schools may not concern
themselves with this issue and partners do not yet have the knowledge of teacher training –
this required analysis of the US/Canada experience.
4th Flash Project Partner Meeting (10 November 2011)
A preparatory document was provided, and this was discussed in the introduction. It was
noted that this had turned out to be a much larger work package than initially envisaged,
and in an ideal world, it would have been divided into 4 separate WPs at the outset. It was
suggested that in this project schools should be regarded as more important than colleges
and that partners should concentrate on these. Follow-up on the typology indicated that
virtual schools are not simply about use of technology, but it was necessary to take a cross-
dimensional approach, e.g. innovation, curriculum development and institutional autonomy,
with others to be added in due course. With regard to Influence Maps, it was decided not to
embark on a metric analysis, but to concentrate on Estonia, Finland and UK as key countries
to illustrate significant differences. Given the progress on the other work packages, it was
noted that Sero was now in a position to begin work on potential success factors. The task
on identifying innovative good practice for teachers was discussed, and partners were
reminded that this was essentially a literature search, and that both existing practice and
innovative practice that could potentially be used in virtual schooling could be included.
National level documents are limited to England, Finland, and Estonia at this point, but for
the final report, documentation for Sweden, Flanders, Scotland is still needed to make
ministry-level policy recommendation. With regard to the Case Studies, work is ongoing,
and partners were asked to do a case study outside own country if nothing was found at
home, and to consider various dimensions, e.g.: geography, culture, GNP, target audience
etc.
WP3 Summary
The project activities did appear to be logical, coherent and realistic but the goals were also
very ambitious, and it is not surprising that this has proved challenging to the team. The
early WPs are crucial for the success of the project as they provide a foundation for the work
in the second year, and the late start date have had an impact in terms of creating
unavoidable delays. Despite this, and partners not always being totally focused, the project
managers have redoubled their efforts to keep everyone to task and to time, whilst being
realistic about what is achievable. A Risk Register has been used to monitor obstacles and to
work out what needs to be adjusted. Overall, through regular meetings the partners in this
WP have been encouraged to think strategically, and now appear to be working more
effectively towards achieving the planned objectives.
5 WP4 Critical Success Factors
This WP has not discussed at the first year meetings as it will only be properly embarked on
in the second year of the project.
VISCED Interim Evaluation 14 Evaluator: Dr Maggie McPherson
VISCED Interim Evaluation 15 Evaluator: Dr Maggie McPherson
6 WP5 Consultation of Experts in this Field [led by Lambrakis]
Although discussed at the Brussels meeting in April, little had been done by the time of the
1st
Flash Meeting (discussed next).
1st Flash Project Partner Meeting (8 June 2011)
The urgency of identifying suitable experts to join the IAC was noted, and partners was
entreated to provide names from ministries and associated agencies. An introductory letter
was drafted for distribution. Given that two IAC meetings had been proposed, it was
suggested that a smaller IAC meeting should be planned for the EFQUEL Innovation Forum in
Portugal in September, with possibilities for other mini-IAC meetings – e.g. ALT-C [Leeds –
September], EMINENT [Italy – 3rd week in November], MEDEA [end of November] to be
considered. Since the location, schedule and associated costs of IAC meetings are
substantially different to what was originally envisaged, there is a need to revisit the
proposal budget. It was debated whether Informed Consent for IAC members was required,
but this has not been considered necessary. It would however be important to put proper
ethical procedures in place for the piloting, especially when working with younger people.
2nd Flash Project Partner Meeting (6 July 2011)
By this time the desired 110 names were received for the long list. This was reduced to less
than 50 invitations, many of who had already replied in the affirmative. As few were from
industry, it was muted that this may need to be addressed. It was confirmed that the first
IAC meeting would take place on Wednesday 14th September in Oeiras. It was noted that
there would be still a necessity to revisit the IAC budget (as previously mentioned).
1st IAC f2f Meeting Oeiras (13 September 2011)
Greater light was cast on country and regional reports by comments from International
Advisory Committee (IAC) when the meeting was held in Oeiras. Significant contributions
came from Professor Morten Paulsen and Susan Patrick [iNACOL, who works with more than
50 national Ministries worldwide]. At the start of the meeting Susan Patrick gave an
introduction and overview of the work of iNACOL (Policy, QA, working with Foundations)
and parallels with VISCED. It was noted that the wiki provided a much needed resource and
the partners were complimented on this contribution. The other main comments related to
WP3, and is reported in more detail there.
3rd Flash Project Partner Meeting (12 October 2011)
Concerns were voiced about low IAC membership numbers from industry. It was noted that
it was important to know what influence international vendors and suppliers (e.g. Pearson,
Cisco and VLE suppliers in Latin America) were having on virtual developments. It was
agreed that the second IAC meeting would focus on policy and would take place in the
Palace Hotel, Berlin, at the end of November to take advantage of input from experts
already attending Online Educa. Future meetings are as follows: 3rd
meeting (to be organised
by Sero) to be held in Sheffield in May 2012, to coincide with a conference which is currently
being planned and will have a focus on practitioners. The 4th
and final meeting (to be
organised by MENON) is to be held in Brussels in October 2012, and will focus on policy.
VISCED Interim Evaluation 16 Evaluator: Dr Maggie McPherson
Organising partners were reminded to refer to the project budget for details of allowances
for organising accommodation, meeting room, catering and attendees’ expenses.
4th Flash Project Partner Meeting (10 November 2011)
There was an initial concern about the number of definite acceptances - to make the
meeting useful, 12 attendees were desirable. It was agreed that some additional work to
boost attendance was required.
2nd IAC f2f Meeting Berlin (30 November)
In the event, nine experts were able to attend and provided some valuable feedback. It was
noted that some countries/institutions were more active than others (e.g. Turkey, Open
Institute of Catalonia), and some institutions might be active but not defining their activities
as virtual schooling. Other comments were divided into two parts; general comments and
specific comments about VISCED activities.
General comments can be broken down again into positive factors (inclusion strategies;
‘necessity’ as a driving factor/motivation, i.e. for learners where there is no other way of
accessing education; power of IT as a good driver for learning) and barriers (safety;
infrastructure or security/firewall issues; exams / accreditation; tradition; investment into
classroom equipment). Furthermore, in the USA there is a differentiation between
‘awarding institutions’ (schools) and ‘course providers’ (e.g. commercial sector online
content providers) – this is a taxonomic feature which needs addressing, and pricing was a
driving factor in the growth of the Virtual Universities in the US (because prices are so high).
The question arose as to whether cultural/traditional issues of childminding, socialisation,
etc. do not exist in the US with the growth of Virtual Schools in the same way they do in
Europe. It was also mentioned that Pearsons are delivering 2 virtual degree courses.
IAC feedback on Country Reports on the wiki included suggestions for additional schools and
colleges (in Spain, France, Canada, and Scotland) and suggested others for follow up (US,
Finland, Denmark, Australia, e.g. Connected Classrooms, Sri Lanka, Nepal and UAE). Some
corrections were offered (e.g. Devoirs.fr is not a Virtual School) and additions (in France
there are numerous virtual vocational colleges and courses; the ‘new’ Finland Virtual School
is a Swedish-speaking one). An additional US policy paper was recommended to follow up.
It was noted that there are pitfalls too (the Finland Ministry of Education recently sued a
Virtual School provider for return of funding after it had enrolled students from outside of its
geographical mandate – a judgement is due later this year). The landscape is also fluctuating
(e.g. there has been a change of administration in Denmark and a restructuring of Ministries
– there is now no Ministry of Education – to a Ministry of Child and Teaching and a Ministry
of Education and Innovation) and there may be some additional categories of learner (e.g. in
the Netherlands, there are children of diplomats; Roma; children of Rhine river-shipping
communities; and in the US there are schools for Jewish groups – which apparently could
even go global; Gay and Lesbian groups).
When discussion turned to Success Factors, the IAC group considered two points of
particular importance: the degree of innovation (regular reviewing and updating of both
technologies and pedagogies), and the relevance of tools and activities to the specific
learning environments of the target audience.
VISCED Interim Evaluation 17 Evaluator: Dr Maggie McPherson
The IAC also went on to make a number of general comments about Success Factors:
• “Success depends on Motivation/Access/Knowledge and Skills – if any of these is
missing then success is impossible;
• Consider sub-factors dependent upon the group of learners targeted by the Virtual
School, i.e. success factors for a Bednet type of target group will be different than
those for an iScoil type of target group;
• Virtual Schools have been successful where ‘there is something to be solved and
these schools have solved it’ and can demonstrate this to society;
• We need to agree what we mean by success – and also agree on the extent to which
sustainability is important to this discussion;
• Sustainability is connected to the quality of the Virtual School but notions of scale
also have an impact: a school can be successful but may not be sustainable;
• The importance of a glossary where readers and researchers can check for common
understanding of terms;
• We should consider constructing models to take in account (aspects to do with the
school and how it operates; and aspects to do with state and national policy).
• Could we develop a diagrammatic representation - ‘A systemic model of a school that
operates successfully’ which would show interdependencies?
• This list of Success Factors could be used to educate people as to the range (and
potential) of Virtual Schools.”
With regard to the VISCED taxonomy, there was a general agreement from the IAC that
“tagging everything which may be of use to everyone was a thankless task, and one which
may ultimately be an impediment to those using the wiki”. The experts did not dispute the
main dimensions identified. As such, the following is the full list of potential, additional
dimensions for which there was also general agreement that the information would be of
value. Some (such as Technology used) were simply an attempt for the group to clarify what
the ‘tags’ might look like.
There was not enough have time to discuss the suggested list in depth but the list could
useful as a cross-check with Case Study questions. The ‘tags’ are areas identified by the IAC
members as being of key interest (hence their suggestion that these be explicitly identified).
Several IAC members expressed a desire for some identification of the ‘pedagogical
paradigms’ e.g. the blend, the typology, learner-centric, etc. There was also a question as to
whether it would be useful to add ‘Open’ to Full-time and Supplementary in cases where it
was not known when students are studying because it is ‘open’, although some members
felt this was included by implication under Supplementary. With regard to the Case Study
list , it was suggested that VISCED should look at the updated list of Success Factors and
cross-reference this to see which success factors are not represented – this could then be
used to canvass the IAC via e-mail for suggestions which might ‘fill the gaps’. It was thought
that once a Case Study has been completed and categorised, VISCED should create and
publish a list of institutions that have similar characteristics or may be of interest to anyone
looking at this initial Case Study. Finally, IAC members noted there was no Case Study with a
specific focus on ‘accelerated learning’ but one expert suggested she could supply one from
the USA.
VISCED Interim Evaluation 18 Evaluator: Dr Maggie McPherson
WP5 Summary
The late start of the project meant that the first IAC was held later than originally envisaged,
with the consequence that the experts’ first input came a little bit more behind schedule
than would have been desirable in ideal conditions. Given that this task contributed and is
logically linked to the planned objectives of Work Packages 3 and 4, the project managers
indicated at that point that this would be recorded in the Risk Register in order that
mitigating actions can be taken to avoid adverse affects on upcoming tasks. Nevertheless,
the second meeting was very fruitful in terms of feedback and suggestions for improvement.
VISCED Interim Evaluation 19 Evaluator: Dr Maggie McPherson
7 WP6 Piloting [led by Tensta]
This work package was delayed for reasons already mentioned, but planning for this began
in earnest after the 2nd
f2f meeting in Oeiras.
3rd Flash Project Partner Meeting (12 October 2011)
The Greek pilot is planned for launch with a Study & Jobs Consultancy programme for
teachers and students in some 10 Upper Secondary Schools and the Institutes of pre-service
VET. It will be run through the Network for School Innovation and Lambrakis undertook to
submit a report with the "terms of reference", description, details of the pilot by November.
The first English pilot will be with Notre Dame Catholic High School, Sheffield and has
already started. A teacher has been appointed to lead on extending their use of Moodle for
transition from GCSE to A level Maths, but also seeking to develop the use of the virtual
school element into ‘normal’ classes, thereby encouraging a more blended learning delivery
by all teachers. Maths results improved dramatically last year and this has been attributed
to Moodle, which allowed a great deal of home-based revision leading up to the summer
exams. The shortlist for the second pilot is Sheffield College GCSE or A level English, The
Rowan Centre, Rotherham, or ‘Historiana’ based in the Netherlands. The final choice is still
to be made but Sheffield College seems to be the most viable option at present.
In Sweden, Tensta have started three activities: (i) a series of interactive PowerPoint
presentations for use either in the classroom or for distance learning; (ii) a wiki for
Geography has been set up – also for classroom or distance learning; and (iii) work with
websites and teacher use is being observed.
In all cases, partners in this task were reminded to pay attention to good ethics procedures
before involving young and possibly vulnerable people in sensitive data collection.
VISCED Interim Evaluation 20 Evaluator: Dr Maggie McPherson
8 WP7 Dissemination [led by AtiT]
Throughout the first year, dissemination has been high on the agenda and tasks for this WP
included creating the following:
Project flyer
The flyer was produced promptly after the project started.
Project website
The website too has been available from early on.
Project wiki
The wiki has been the vehicle for sharing ongoing work (WP2 and WP3 in particular)
although there was a question as to whether this should have RSS feeds.
Project Presentations in 2011
ALT-C [Leeds; September]
CONCEDE [Portugal; September]
MEDEA [November]
Project Presentations considered for 2012
EDEN Open Classroom (Oporto June, 2012)
EDUCA (consider workshop
EDEN Research Conference (possible but unlikely), and
e-Learning Expo (Athens – October 2012).
Project newsletters.
The target was 12 articles per newsletter and this was met.
The circulation list is 700 and IAC members will be on copy list.
Other Dissemination Avenues
A VISCED LinkedIn Group has been set up.
A project blog was created.
A full dissemination report will be one of this WP’s deliverables.
9 WP8 Exploitation [led by Lambrakis]
An exploitation plan has been devised and made available to partners - this encourages
identifying innovative practices, piloting these in new environments and developing them in
different contexts, gradually incorporating them into formal and informal systems of
training, into the methods used by business and associations, and into the learning
experience of every individual, all the while making sure that the project outputs are
effectively disseminated as widely as possible.
VISCED Interim Evaluation 21 Evaluator: Dr Maggie McPherson
10 WP9 Quality and Evaluation
Project Progress
The indicators for various tasks described in the original project document were appropriate
and useful for assessing the project’s progress. Project documentation, including the
minutes for meetings, were kept in an accessible form for all partners. Thus it has been
possible for all to keep a check on whether objectives were being achieved. Where outputs
have not been forthcoming in a timely manner, the project managers have been actively
prompting action to try and keep tasks on track.
Evaluation of Effectiveness
Overall, despite some setbacks, the project appears to be making sufficient progress towards
its planned objectives and is likely to achieve its planned objectives upon completion. The
quantity and quality of the outputs produced so far have been reasonable although some
contributions have been more satisfactory than others. It was useful to get feedback from
the IAC that the project approach was producing a useful resource that provided information
well beyond that previously available. Thus, the outputs appear to be contributing to the
project’s aims and objectives and it is hoped that outcomes at the end will meet
expectations. The project organisation has, by and large, achieved the goal of driving
partners onwards to meet targets, which is a great accomplishment, and regular
communication should be maintained to keep the momentum going. Due to time
constraints, there were some preliminary shortfalls in the country reports, but this appears
to be on the road to being addressed. Given the circumstances, it is not entirely clear that
alternative strategies would have been any more effective in achieving the project’s
objectives.
Project Challenges
In general, European projects have a reputation for complicated regulations, even if these
have been put in place for good reasons. Even where project teams have previous
experience of other programmes, to understand the EC Project Handbook and forms for the
LLP and to learn the precise rules for this particular programme, a considerable amount of
time is required.
It has also proved quite complicated understanding the different perspectives of partners in
a wide range of EU countries, both about the intellectual territory of the project and in terms
of their timeliness and attitudes towards responding to project management requests.
The project managers have had to spend a great deal of time chasing a few slow-moving
partners who did not appear to appreciate the urgency for financial data and deliverables to
be provided in a timely fashion. A knock-on effect has been a consequent delay in receiving
the pre-financing payment and distributing it amongst all partners. This has come at a
considerable cost to the project management team in terms of the additional effort that has
had to be committed to achieving the outcomes on time.
A result of the delays outlined, effective research work did not really start until after this
meeting. Despite losing almost six months, partners did not want to ask the Commission for
an extension. This meant that a year's work has to be telescoped into eight months in order
VISCED Interim Evaluation 22 Evaluator: Dr Maggie McPherson
to bring the project timescale back on track. Although this has largely been achieved, this
has been at a high cost of expensive project management time and resources.
Analysis of project activities to-date
Most partners have now taken ownership of relevant work packages and it is hoped that
others will follow this lead. Most of the initial tasks envisaged at the inception of the
project, and yet to be undertaken, are still relevant. However, it is possible that the piloting
will reveal as yet unknown needs that the project (or a future project) should address. The
feedback from IAC appears to link well to the project and will prove useful in improve
outputs further.
Overall, the VISCED has been on something of a roller-coaster ride in its first year. Given
good organisation and timely contributions from all partners, the project managers feel it
should be possible to complete an appropriate successor to Re.ViCa by the end of 2012.
VISCED Interim Evaluation 23 Evaluator: Dr Maggie McPherson
Appendix 1: VISCED Meeting 1 (Kickoff) Evaluation Responses
Meeting Preparation – did you receive all preparatory information in a timely manner?
Definitely Mostly Moderately Limited Definitely not
xxxxxxxxx xx x
Meeting Organisation – was the meeting run efficiently and sessions kept to time?
Definitely Mostly Moderately Partially Definitely not
xxxxxxxx xxxx
Meeting Agenda – were all the essential issues and topics covered?
Definitely Mostly Moderately Partially Definitely not
xxxxx xxxxx
Presentations – were the WP leader sessions well delivered, useful and informative?
Definitely Mostly Moderately Partially Definitely not
xxxxxx xxxxxx
Meeting Discussions – was there sufficient time to discuss essential issues and topics?
Definitely Mostly Moderately Partially Definitely not
xxxxxxxxx xxx
Participant Questions – do you feel that any questions you had have been properly
answered?
Definitely Mostly Moderately Partially Definitely not
xxxxxx xxxxxx
If you have additional questions, could you please elaborate below:
Could parallel working sessions on topics be more useful and effective in coming planning meetings?
Maybe too diluted, 1 day and ½ or 2 would possibly have been enough!
Project Planning – do you feel that you are sufficiently now well prepared for future
activities?
Definitely Mostly Moderately Partially Definitely not
xxxxxxxxxxx x x
If you need additional preparation, could you please elaborate below:
Target groups needs to be clarified, interaction between partners, review cycles, etc. might be drafted.
Deciding SMART objectives in the end for each partner.
VISCED Interim Evaluation 24 Evaluator: Dr Maggie McPherson