Daily Program January-2012

Embed Size (px)

Citation preview

  • 8/13/2019 Daily Program January-2012

    1/25

  • 8/13/2019 Daily Program January-2012

    2/25

    S.l.

    No.Description Work Program of January 2,2012 Achievement of January 1,2011 Remarks

    CC Casting of Cable trench. Base CC (15rm)

    CC Casting of 1 no manhole. CC casting of 2 nos gully hole

    Singles Laying 2nd layer(520mm thick) / Ch 78-

    137

    Singles Laying 2nd layer(520mm thick) / Ch 78-137

    in progress

    Rebar fabrication of longitudinal sleepers (Ch 0-

    78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)

    in progress

    3 Pre-cast pile driving(Seg-1A) Preparation of load test Preparation of load test in progress

    4 Segment 2A Settlement Record Settlement Record in progress for 71th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress

    Back filling at Navy gate Back filling at Navy gate in progress

    CC Casting (CH 1000-1040) Earth excavation finished (CH 1000-1040)

    Earth Excavation (Ch 1125-1140)Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard

    side

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600)

    9 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    10 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress

    11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    12 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    13 RCC Drainage Pipe Concrete pouring(800mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)

    14 PDB Relocation Old pole removing Old pole removing in progress

    15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,000 Nos)

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 2,2012

    Segment 15

    1

    RMG (Seg-1A)2

    6

    Rail Relocation8

    Segment-2

    Open Deep Drain7

  • 8/13/2019 Daily Program January-2012

    3/25

    S.l.

    No.Description Work Program of January 3,2012 Achievement of January 2,2011 Remarks

    Base CC (15rm) Earth excavation (15rm)Singles Laying 2nd layer(520mm thick) / Ch 78-

    137

    Singles Laying 2nd layer(520mm thick) / Ch 78-137

    in progress

    Rebar fabrication of longitudinal sleepers (Ch 0-

    78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)

    in progress

    3 Pre-cast pile driving(Seg-1A) Preparation of load test Preparation of load test in progress

    4 Cable Trench (Seg-1A) CC Casting Earth Excavation executed.

    5 Segment 2A Settlement Record Settlement Record in progress for 72th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress

    Back filling at Navy gate Back filling at Navy gate in progress

    Rebar fabrication of Base (CH 1000-1040) CC Casting (CH 1000-1040)

    Earth Excavation (Ch 1125-1140)Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard

    side

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress

    12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    13 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    14 RCC Drainage Pipe Concrete pouring(800mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)

    15 PDB Relocation Old pole removing Old pole removing in progress

    16 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    17 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,200 Nos)

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 3,2012

    Segment 16

    Yard Drainage1

    RMG (Seg-1A)2

  • 8/13/2019 Daily Program January-2012

    4/25

    S.l.

    No.Description Work Program of January 4,2012 Achievement of January 3,2011 Remarks

    Side CC (30rm) Base CC executed (30rm)

    Pipe Installation 30 rm(300mm dia)

    Wall casting of 01 No Manhole Base Casting of 02 Nos Gully hole & 01 No Manhole

    Ballast Laying (300mm thick) / Ch 78-137Singles Laying 2nd layer(520mm thick) / Ch 78-137

    finished

    Rebar fabrication of longitudinal sleepers (Ch 0-

    78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)

    in progress

    3 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sand bagging for load test in progress

    4 Cable Trench (Seg-1A) CC Casting Earth Excavation executed.5 Segment 2A Settlement Record Settlement Record in progress for 73th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Pre-cast Bracing installation

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress(500 sqm)

    Back filling at Navy gate Back filling at Navy gate in progressBase casting (CH 1000-1040) Rebar fabrication of Base (CH 1000-1040)

    Bracing fixing (6rm)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Electric Sub station Shuttering & Rebar binding of slab (2nd portion)Shuttering & Rebar binding of slab (2nd portion) in

    progress

    12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    13 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    14 RCC Drainage Pipe Concrete pouring(800mm=03 Nos,900mm=02 Nos) Concrete Pouring (800mm=03Nos & 900mm=02 Nos)

    15 PDB Relocation Old pole removing Old pole removing in progress

    16 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    17 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=10,500 Nos)

    18 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 4,2012

    Segment 16

    RMG (Seg-1A)2

    Yard Drainage1

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

  • 8/13/2019 Daily Program January-2012

    5/25

    S.l.

    No.Description Work Program of January 7,2012 Achievement of January 6,2011 Remarks

    1 Yard DrainageBase Casting of 02 Nos Gully hole & 01 No Man

    hole.

    Rebar binding of Base (02 Nos Gully hole & 01 No Man

    hole)

    Shingles Laying (180mm thick) / Ch 78-137Ballast layer compaction (300mm thick) / Ch 78-

    137 finished

    Longitudinal sleeper casting (Ch 0-10)Rebar fabrication of longitudinal sleepers(Ch 0-10)

    finished.

    3 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sand bagging for load test in progress

    4 Sheet Pile Driving Preparation of Pile shifting to bank.

    5 Cable Trench (Seg-1A) CC Casting CC Casting executed.

    6 Segment 2A Settlement Record Settlement Record in progress for 77th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress(500 sqm)

    CC Casting (Outlet point) Soling executed.

    Wall casting / Port side/1st lift (CH 1015-1040) Rebar fabrication executed (CH 1015-1040)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    12 Electric Sub station Shuttering & Rebar binding of slab (2nd portion)Shuttering & Rebar binding of slab (2nd portion) in

    progress

    13 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    14 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=10,500 Nos)

    17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    8

    Rail Relocation10

    Segment-2

    Open Deep Drain9

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 7,2012

    Segment 17

    RMG (Seg-1A)2

  • 8/13/2019 Daily Program January-2012

    6/25

    S.l.

    No.Description Work Program of January 9,2012 Achievement of January 8,2011

    15 m Base CC casting (300mm) 15m Earth Excavation

    Wall Casting of 03 Nos Gully hole . Rebar binding executed (wall of 03 Nos Gully hole)

    Shingles Laying (180mm thick) / Ch 78-137Shingles Laying (180mm thick) / Ch 78-137 in

    progress

    Longitudinal sleeper casting (Ch 0-10)Rebar fabrication of longitudinal sleepers(Ch 0-10)

    in progress.

    3 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    4 Water Supply Line Leak test of 50m pipe (250mm dia) 50 m pipe welding completed (250mm dia)

    5 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving FDD test executed at 300mm sand blanket

    Wall casting / Navy side/2nd lift (CH 1015-1040) Wall casting / Port side/1st lift (CH 1015-1040)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Electric Sub station Slab casting of 2nd portion executed

    12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,400 Nos)

    15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 9,2012

    Segment 16

    RMG (Seg-1A)2

    Yard Drainage(Seg-1A)1

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

  • 8/13/2019 Daily Program January-2012

    7/25

    Remarks

    Assistant Engineer

    NCT Back-up/CPA

  • 8/13/2019 Daily Program January-2012

    8/25

    S.l.

    No.Description Work Program of January 10,2012 Achievement of January 9,2011

    300mm Pipe installation(15rm) 15 m Base CC casting executed.

    Wall Casting of 03 Nos Gully hole and base casting

    of 02 Nos Gully hole.Wall Casting of 03 Nos Gully hole executed

    Rolling of Shingles Layer (180mm thick) / Ch 78-

    137Shingles Laying (180mm thick) / Ch 78-137 finished

    Rebar fabrication of longitudinal sleepers(Ch 0-

    10) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 0-10)

    in progress.

    3 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    4 Water Supply Line Leak test of 50m pipe (250mm dia) 50 m pipe welding completed (250mm dia)

    5 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Earth Excavation (CH 1040-1060)

    Wall casting / Yard side/2nd lift (CH 1015-1040) Wall casting / Navy side/2nd lift (CH 1015-1040)executed.

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=11,300 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 10,2012

    Segment 16

    RMG (Seg-1A)2

    Yard Drainage(Seg-1A)1

  • 8/13/2019 Daily Program January-2012

    9/25

    Remarks

    Assistant Engineer

    NCT Back-up/CPA

  • 8/13/2019 Daily Program January-2012

    10/25

    S.l.

    No.Description Work Program of January 14,2012 Achievement of January 13,2011

    1 Yard Drainage(Seg-1A) Side CC Casting/30rm/300mm dia pipe Shuttering executed

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-

    30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)

    in progress.

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm

    dia

    Painting of Pipe & wrapping by Polythene/250mm dia in

    progress.

    6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (40,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Base Casting (CH 985-1015) Rebar binding executed.

    Wall casting / Yard side/2nd lift (CH 1015-1040) Rebar binding executed.

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (02 Nos) in progress

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,300 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 14,2012

    8

    Rail Relocation10

    Segment-2

    Open Deep Drain9

  • 8/13/2019 Daily Program January-2012

    11/25

    Remarks

    Assistant EngineerNCT Back-up/CPA

  • 8/13/2019 Daily Program January-2012

    12/25

    S.l.

    No.Description Work Program of January 15,2012 Achievement of January 14,2011

    Side CC Casting/30rm/300mm dia pipe Shuttering executed

    Wall casting of 03 Nos Gully hole and 01 No Man

    holeShuttering executed

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-

    30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)

    in progress.

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm

    dia

    Painting of Pipe & wrapping by Polythene/250mm dia in

    progress.6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Base Casting (CH 1000-1015) Base Casting (CH 985-1000)

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (06 Nos) in progress

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Rebar fabrication and Shuttering executed.

    12 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,200 Nos)

    15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 15,2012

    8

    Rail Relocation10

    Segment-2

    Open Deep Drain9

    Yard Drainage(Seg-1A)1

  • 8/13/2019 Daily Program January-2012

    13/25

    Remarks

    Assistant Engineer

    NCT Back-up/CPA

  • 8/13/2019 Daily Program January-2012

    14/25

    S.l.

    No. Description Work Program of January 16,2012 Achievement of January 15,2011 Remarks

    Side CC Casting/30rm/300mm dia pipe

    Wall casting of 01 No Gully hole and 01 No Man

    holeWall casting of 02 Nos Gully hole and 01 No Man hole .

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-

    30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)

    in progress.

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm

    dia

    Painting of Pipe & wrapping by Polythene/250mm dia in

    progress.

    6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Wall casting 1st lift(CH 985-1015) Base Casting (CH 1000-1015)

    Pre-cast Bracing Casting (06 Nos)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit f ixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Rebar fabrication and Shuttering executed.

    12 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=13,600 Nos)

    15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    9 Open Deep Drain

    10 Rail Relocation

    8 Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 16,2012

    1 Yard Drainage(Seg-1A)

  • 8/13/2019 Daily Program January-2012

    15/25

    S.l.

    No.Description Work Program of January 17,2012 Achievement of January 16,2011 Remarks

    02 Nos 300mm dia pipe,01 No 700mm dia pipe

    fixing.

    Shuttering & Rebar fabrication of 02 Nos Gully hole. Wall casting of 01 No Gully hole and 01 No Man hole

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-

    30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)

    in progress.

    3 Seg-1A(mosque portion) Sand filling & Soling work Sand filling & Soling work in progress

    4 Sub-station Building Plaster work Plaster work in progress.

    5 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    6 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm

    dia

    Painting of Pipe & wrapping by Polythene/250mm dia in

    progress.

    7 Cable Trench (Seg-1A) Plastering of wall.

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    9 Segment-2 Clearing & Grubbing Clearing & Grubbing in progress

    Soling & CC work (CH 1015-1030) Earth Excavation executed.

    Wall casting 1st lift(CH 985-1015) Shuttering & Rebar fabrication executed.

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (06 Nos)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bi t fixing in progress (Ch 0-600)

    12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting (10 Nos) in progress.

    13 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    15 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,250 Nos)

    16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    11 Rail Relocation

    Open Deep Drain10

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 17,2012

    1 Yard Drainage(Seg-1A)

  • 8/13/2019 Daily Program January-2012

    16/25

    S.l. No. Description Work Program of January 18,2012 Achievement of January 17,2011 Remarks

    Side CC Casting of 10rm 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing.

    Shuttering & Rebar fabrication of 02 Nos Gully hole.Shuttering & Rebar fabrication of 02 Nos Gully hole and

    02 Nos Manhole.

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 30-

    40) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    3 Seg-1A(mosque portion) Sand filling & Soling work Sand filling & Soling work in progress

    4 Sub-station Building Plaster work Plaster work in progress.

    5 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    6 Water Supply Line/Seg-1A Painting of Pipe & wrapping by Polythene./250mmdia

    Painting of Pipe & wrapping by Polythene/250mm dia inprogress.

    7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    150mm local sand laying 150mm local sand laying in progress

    200mm sand blanket laying 200mm sand blanket laying in progress

    Rebar fabrication of Base (CH 1015-1030) Soling & CC work (CH 1015-1030)

    Rebar fabrication of Wall 1st l ift(CH 985-1015)/Navyside.

    Wall casting 1st lift(CH 985-1015)/Yard Side

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (05 Nos)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bi t fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.

    13 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    15 Interlocking Block ILB production (Quantity=13000 Nos)

    16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    11 Rail Relocation

    Open Deep Drain10

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 18,2012

    1 Yard Drainage(Seg-1A)

    Segment-29

  • 8/13/2019 Daily Program January-2012

    17/25

    S.l. No. Description Work Program of January 20,2012 Achievement of January 19,2011 Remarks

    Rebar fabrication of 03 Nos Gully hole

    Wall Shuttering of 02 Nos Man hole Wall casting of 02 Nos Gully hole

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    Pre-cast sleepers shifting to Seg-1

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Service Area Sub-base material laying Bed preparation finished

    5 Sub-station Building Plaster work & Parapet shuttering Plaster work & Parapet casting in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm

    dia

    Painting of Pipe & wrapping by Polythene/250mm dia in

    progress.

    8 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    9 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    150mm local sand laying 150mm local sand laying in progress

    200mm sand blanket laying 200mm sand blanket laying in progress

    Shuttering of wall (CH 1015-1030) Base casting (CH 970-990)

    Back filling(CH 990-1015)/Navy side. Wall casting 1st li ft(CH 990-1015)/Navy Side

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rai l bit fixing in progress (Ch 0-600)

    13 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.

    14 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=11000 Nos)

    17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 20,2012

    1 Yard Drainage(Seg-1A)

    RMG Track(Seg-1A)2

    Segment-210

    12 Rail Relocation

    Open Deep Drain11

  • 8/13/2019 Daily Program January-2012

    18/25

    S.l. No. Description Work Program of January 21,2012 Achievement of January 20,2011 Remarks

    Rebar fabrication of 03 Nos Gully hole Rebar fabrication of 03 Nos Gully hole in progress

    Wall Shuttering of 02 Nos Man hole Wall Shuttering of 02 Nos Man hole in progress

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress

    3 Seg-1A(mosque portion) Rebar binding of raft foundation. Soling work finished.

    4 Service Area Sub-base material compaction. Sub-base material laying finished.

    5 Sub-station Building Plaster work & Parapet casting. Plaster work & Parapet shuttering.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving 300mm sand blanket compaction finished.

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 2nd lift (CH 990-1015)/Navy Side Earth excavation (CH 950-970)

    Soling & CC (CH 950-970)/Navy side. Back filling(CH 990-1015)/Navy side.

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rai l bit f ixing (Ch 0-600) Sleepers & Rail bit f ixing in progress (Ch 0-600)

    12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.

    13 Road Type-1 Field density test of sub-base. Sub base material placement (2nd layer) finished.

    14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    15 Interlocking Block ILB production (Quanti ty=13000 Nos) ILB production (Quantity=12000 Nos)

    16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-29

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 21,2012

    1 Yard Drainage(Seg-1A)

    11 Rail Relocation

    Open Deep Drain10

    RMG Track(Seg-1A)2

  • 8/13/2019 Daily Program January-2012

    19/25

    S.l. No. Description Work Program of January 22,2012 Achievement of January 21,2011 Remarks

    1 Yard Drainage (Seg 1A) Man hole wall casting (01 No) Man hole wall casting (01 No)

    Concrete Pouring (CH 0-20)

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress

    3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    4 Service Area Sub-base material compaction. Sub-base material laying finished.

    5 Sub-station Building Plaster work . Plaster work & Parapet casting.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 2nd lift (CH 990-1015)/Yard Side Wall casting 2nd lift (CH 990-1015)/Navy Side

    CC (CH 950-970) Soling (CH 950-970)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rai l bit f ixing (Ch 0-600) Sleepers & Rail bit f ixing in progress (Ch 0-600)

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Trial Mix design (40 Mpa)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=11500 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 22,2012

    11 Rail Relocation

    Open Deep Drain10

    RMG Track(Seg-1A)2

    Segment-29

  • 8/13/2019 Daily Program January-2012

    20/25

    S.l. No. Description Work Program of January 23,2012 Achievement of January 22,2011 Remarks

    1 Yard Drainage (Seg 1A) Man hole wall casting (01 No) Shuttering executed.

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) in progress.

    Concrete Pouring (CH 0-10)

    3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    4 Service Area Sub-base material laying Sub-base material laying in progress

    5 Sub-station Building Plaster work . Plaster work in progress

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 1st lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Navy Side

    Earth Excavation (CH 935-950) Soling & CC (CH 950-970)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=10500 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 23,2012

    11 Rail Relocation

    Open Deep Drain10

    RMG Track(Seg-1A)2

    Segment-29

  • 8/13/2019 Daily Program January-2012

    21/25

    S.l. No. Description Work Program of January 24,2012 Achievement of January 23,2011 Remarks

    1 Yard Drainage (Seg 1A) Man hole wall casting (01 No)

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    4 Service Area Sub-base material laying & compaction Sub-base material laying & compaction in progress

    5 Sub-station Building Plaster work . Plaster work in progress

    6 Segment-2A Surcharge Removing Surcharge Removing in progress.

    7 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    8 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    9 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (40,000cft)

    PVD Driving

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 2nd lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Yard Side

    Earth Excavation (CH 935-950) Earth Excavation (CH 935-950) In progress

    Bracing fixing (06 Nos)

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quanti ty=13200 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 24,2012

    RMG Track(Seg-1A)2

    Segment-210

    Open Deep Drain11

  • 8/13/2019 Daily Program January-2012

    22/25

    S.l.

    No.Description Work Program of January 25,2012 Achievement of January 24,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    2 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    3 Service Area Sub-base material compaction Sub-base material laying finished.

    4 Sub-station Building Plaster work . Plaster work in progress

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    PVD Driving PVD Driving in progress.

    150mm local sand laying. 150mm local sand laying in progress.

    Wall casting 2nd lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Yard Side

    CC ,Soling (CH 935-950) Earth Excavation (CH 935-950)

    Bracing fixing (06 Nos)

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=13000 Nos)

    12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 25,2012

    RMG Track(Seg-1A)1

    Segment-28

    Open Deep Drain9

  • 8/13/2019 Daily Program January-2012

    23/25

    S.l.

    No.Description Work Program of January 26,2012 Achievement of January 25,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    2 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    3 Service Area Lean concrete casting

    4 Sub-station Building Bricks masonry work

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (42,000cft)8 Segment-2 150mm local sand laying. 150mm local sand laying in progress.

    Wall casting 2nd lift (CH 970-990)/Yard Side

    Rebar binding of Base (CH 935-970) CC ,Soling (CH 935-950)

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=14200 Nos)

    12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 26,2012

    RMG Track(Seg-1A)1

    Open Deep Drain9

    NCT BACK UP PROJECT CHITTAGONG

  • 8/13/2019 Daily Program January-2012

    24/25

    S.l.

    No.Description Work Program of January 30,2012 Achievement of January 29,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    2 Yard Drainage Base casting of 03 Nos Gully holes & wallcasting of 01 No Manhole.

    Rebar fabrication and shuttering executed.

    3 Sub-station Building Bricks masonry work Bricks masonry work in progress.

    FDD Test of 150mm local sand layer

    FDD Test of 200mm sand blanket layer

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (45,000cft)

    Wall casting 1st lift (CH 955-970)/Navy Side Wall casting 1st lift (CH 935-955)/Navy Side

    9 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    10 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=14200 Nos)

    11 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 30,2012

    RMG Track(Seg-1A)1

    Open Deep Drain8

    Segment-24

    NCT BACK UP PROJECT CHITTAGONG

  • 8/13/2019 Daily Program January-2012

    25/25

    S.l.

    No.Description Work Program of January 31,2012 Achievement of January 30,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.

    2 Yard Drainage Earth excavation for pipe laying. Base casting of 03 Nos Gully holes & wall casting of01 No Manhole.

    Bricks masonry work Bricks masonry work in progress.

    Bricks masonry work of Safety Tank. CC Casting executed.

    FDD Test of 150mm local sand layer

    FDD Test of 200mm sand blanket layer

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.(60,000 cft)

    6 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (45,000cft)

    Wall casting 1st lift (CH 955-970)/Yard Side Wall casting 1st lift (CH 955-970)/Navy Side

    8 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    9 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=13,850 Nos)

    10 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 31,2012

    RMG Track(Seg-1A)1

    Open Deep Drain7

    Segment-24

    Sub-station Building3