8
Power Turbo-Systems/Power Environment Plants SUPPLIER MONITORING INTERVENTION REPORT IRN: T8A8-IR020 Expediting Final Conformity Inspection Q. Surveillance/Intermediate Inspection Pre-shipment Inspection Project: ASTORIA II Unit: #301and #401 Equipment : HRSG-Casing/C-Frame Modules Equipment specification : Rev. : Inspection & Test Plan : T8A8PSP-1 Rev.06-C-Frame Module Assembly T8A8PSP-2 Rev.02-C Frame casing T8A8PSP-3 Rev.01-Finned Tubes Order No. : 100605 IO Reference Contract No.: 0620 EFU list : Rev. : Supplier: PT AP ESI Surabaya, Indonesia Sub-supplier : Place of intervention : PT AP ESI Surabaya, Indonesia Telephone No : +62 (31) 329 2080/2088 Fax No : +62 (31) 329 2168 Attendees: See list on the page 2 of 4 bellows in this report. Date of Intervention: 1, 3-4 June 2009. WORKSHOP DELIVERY DATES (Ex-works) MANUFACTURING PROGRESS PERCENTAGE Contractual Expected Realised Supplier / Sub-supplier Unit 301 : 12 Aug. 09 Unit 401 : 12 Aug. 09 14 July 09 12 Aug. 09 - Procurement : - Manufacturing : - Final testing : Discrepancies report attached : Yes / No Discrepancies (Number off) : Major : Minor : SUMMARY: Next visit schedule is 10-11 June 2009. All improper works on non pressure parts: C-frame & Boiler casing primer paint/Field Weld able primer, rectification of cutting surface of Stub column for module 1A and visually spatter on C-frame after painted have to be closed out before final inspection of each component. The balance Mock up test report of finned tubes is not ready to offer for review during this visit. APESI to speed up for completion of mock up test report. APESI need to maintain all plastic caps being installed at all nozzles opening during storage of harps assembly after hydro test. Two plastic caps were missed from nozzle opening of harps assembly at bay 6. Actions: APESI has to be improved all works of non pressure parts to meets drawing and specification. Attached Documents : None Inspector/Date/Signature : Condro Widiyarto/QA-APW Rep. 8 June 2009 Distribution : Quality Coordinator/Date/Signature : Report Reference: T8A8- IR0020

Daily Report

Embed Size (px)

DESCRIPTION

Daily report for customer representative

Citation preview

  • Power Turbo-Systems/Power

    Environment

    Plants

    SUPPLIER MONITORING INTERVENTION REPORT IRN: T8A8-IR020

    Expediting Final Conformity Inspection

    Q. Surveillance/Intermediate Inspection

    Pre-shipment Inspection

    Project: ASTORIA II Unit: #301and #401

    Equipment :

    HRSG-Casing/C-Frame Modules

    Equipment specification : Rev. :

    Inspection & Test Plan : T8A8PSP-1 Rev.06-C-Frame Module Assembly

    T8A8PSP-2 Rev.02-C Frame casing

    T8A8PSP-3 Rev.01-Finned Tubes

    Order No. : 100605 IO

    Reference Contract No.: 0620

    EFU list : Rev. :

    Supplier: PT AP ESI Surabaya, Indonesia Sub-supplier :

    Place of intervention : PT AP ESI Surabaya, Indonesia Telephone No : +62 (31) 329 2080/2088

    Fax No : +62 (31) 329 2168

    Attendees: See list on the page 2 of 4 bellows in this report.

    Date of Intervention: 1, 3-4 June 2009.

    WORKSHOP DELIVERY DATES (Ex-works) MANUFACTURING PROGRESS PERCENTAGE

    Contractual Expected Realised Supplier / Sub-supplier Unit 301 : 12 Aug. 09

    Unit 401 : 12 Aug. 09

    14 July 09

    12 Aug. 09

    - Procurement :

    - Manufacturing :

    - Final testing :

    Discrepancies report attached : Yes / No Discrepancies (Number off) : Major :

    Minor :

    SUMMARY: Next visit schedule is 10-11 June 2009.

    All improper works on non pressure parts: C-frame & Boiler casing primer paint/Field Weld able primer,

    rectification of cutting surface of Stub column for module 1A and visually spatter on C-frame after

    painted have to be closed out before final inspection of each component.

    The balance Mock up test report of finned tubes is not ready to offer for review during this visit. APESI

    to speed up for completion of mock up test report.

    APESI need to maintain all plastic caps being installed at all nozzles opening during storage of harps

    assembly after hydro test. Two plastic caps were missed from nozzle opening of harps assembly at bay

    6.

    Actions: APESI has to be improved all works of non pressure parts to meets drawing and specification.

    Attached Documents : None

    Inspector/Date/Signature :

    Condro Widiyarto/QA-APW Rep. 8 June 2009

    Distribution :

    Quality Coordinator/Date/Signature :

    Report Reference: T8A8- IR0020

  • Power Turbo-Systems/Power Environment

    Plants

    QUALITY SURVEILLANCE / INTERMEDIATE INSPECTION

    Reference Document

    Description / Action

    Responsibl

    e and

    due date 1. SUMMARY/FINDINGS:

    Proposed of this meeting:

    The purpose of the meeting was to surveillance inspection witness of

    fabrication of header, harps assembly, hydro test of harps assembly and

    non pressure parts fabrication includes review non pressure part &

    pressure parts quality documents/reports at PT. APESI Held for HRSG-C

    Frame module assembly ASTORIA II project.

    Attendees:

    1) Gunawan Risdianto-APESI PM

    2) Lucky R Prastiawan-APESI QCM

    3) Luluk Utomo-APESI QC Inspector

    4) Samsul & Fauzi-APESI QC Inspector

    5) Condro Widiyarto-EURTREU Inspector-QA APW Rep.

    Documents used to carry out this inspection was organized with the following documents:

    o ITP no.: T8A8PSP-1 Rev. 06-C Frame Module Assembly, T8A8PSP-2

    Rev. 00-C Frame casing and T8A8PSP-3 Rev.00 Finned Tubes.

    o EQS-7808-0004 Rev. B -Specification for material control & trace

    ability

    o Drawing for pressure parts and pressure parts

    2. Shop surveillance inspection of Non Pressure parts and pressure Parts 2.1. Non Pressure Parts:

    The following unit #301C-frame side panel module was observed during shop inspection at Bay 4.2:

    o Column stub pre assembly to unit # 301 side panel C frame

    module-1A that found gap 0 up to 1.5 mm on column C was

    observed does not meet drawing no. 07808-1E2060 Rev. A

    Fig. Column stub pre assembly to side panel module 1A with gap 0-1.5

    mm on column C (Column D with gap 0 mm).

    o Witnessed UT on unit # 301 upper panel: In-flange to side panel

    column C of C-frame module-1A and out-in flange column D & in

    flange column-C module-1B that found indication does not meets

    to AWS D1.1 table 6.2.

  • Fig. UT on roof panel (Flange-In) to side panel column F module-2B that

    found indication in deep 16 mm (Thickness of flange 32 mm)

    o Witnessed UT on unit upper panel-out flange to side panel

    column C & in/out flange column D of C-frame module-1A

    that found acceptable were meets to AWS D1.1 table 6.2.

    Fig. UT on roof panel (Flange-Out) to side panel column F module-2B

    that found acceptable.

    o Witnessed MT examination on the welding of unit # 301 floor

    panel flange to side panel flange module-3A that found

    acceptable, however on the column J found indication and

    at the day was rectified that found acceptable.

    o General visual inspection on the following C-frame panel after

    primer painting of unit # 301 that found spatter on the gusset

    plate to side panel & rectification on un-acceptable visual

    welding of floor panel flange to side panel flange was

    observed and touch up paint on the certain location is

    required: All spatter was cleaned up by grinding and touch up

    painting was done at the day that found acceptable.

    MDL-3A-1-U301

    MDL-3B-1-U301

    Fig. Spatter and improper primer painting on side panel MDL-3A-1-

    301 and MDL-3B-1-U301 was observed.

  • 2.2 Pressure Parts-The following shop inspection during this surveillance visit:

    T8A8PSP-1 Rev.06 item 4.0-Visual inspection (Final pass) of the following

    stub to pipe header of manifold assembly: that found acceptable was

    meets QCP-7.2 rev. 09 Visual Inspection of Weld and Code ASME

    Section I PW-31, 33 and 35 requirements ((All of the irregularities of welds

    were corrected by grinding).

    o U301-ML11-P1/1

    o U301-MU-12-P1/2

    o U301-M12-P1/2

    Fig. Performed visual inspection of unit # 301 Manifold assembly

    T8A8PSP-1 Rev.06 item 4.0- Witness MT examination of the stub to pipe

    header of manifold assembly: 301-ML-11-P1/1, 301-MU-12-P1/2 and 301-

    M12-P1/2 that found acceptable was meets QCP-7.4 rev.12 Visual

    Inspection of Weld and Code ASME Section I PW-31, 33 and 35

    requirements and was performed by qualified MT level-2 personnel as

    per SNT-TC-1A requirements (Sutopo MT Level-2 x expire date 12

    January 2012 and Abdullah MT Level-2 x expire date 23 May 2011)

    ITPITPITPITP----T8A8PSPT8A8PSPT8A8PSPT8A8PSP----1 Rev. 06 item 5.0 1 Rev. 06 item 5.0 1 Rev. 06 item 5.0 1 Rev. 06 item 5.0 Witness Hardness test in the following Manifold assembly (BM and WM of P5B manifold stub/End Plate/Nozzle to manifold header after PWHT that found acceptable were meets specification MS-HRSG-0008 and SOP-029:

    Manifold # BM Hardness values (HB)

    WM hardness values (HB)

    Accept/Reject

    301-ML-11-P1/2 208 - 219 227 - 258 Accepted

    301-MU-12-P1/2 198 - 214 225 - 238 Accepted

    301-MU14-P1/1 197 - 214 204 - 216 Accepted

    Fig. Witnessed Pin BRINNEL hardness on Unit # 301 manifold assembly (P5B

    material) U301-MU-12-P1/2 at Bay 7.2.

  • o Spot witness of Liquid Penetrant Test (PT) on Harps Assembly unit

    # 401 HA-23B-24B,(> 10% PT as per Job routing no.), HA-73A and

    HA-83A (100% PT) that found acceptable were meets

    specification QCP 7.3 Rev. 16 and was performed by NDE

    qualified personnel PT Level-II as per ASNT-TC-1A name Sutopo

    certificate no. 93/PT/08 x expire date 12 January 2012.

    Fig. Overview PT examination on unit # 401 HA-83A

    o Unit # 401 Harps Assembly dimensional inspection was

    performed that found acceptable.

    Harps

    no.

    Drawing No. Selected dim.

    (mm) 3 mm

    Actual dimension

    (mm) Left/Right

    Accept/

    reject

    HA-23B 07808-1E0160 Rev. A 21019 21021/21022 Accepted

    HA-24B 07808-1E0160 Rev. A 21019 21022/21017 Accepted

    HA-73B 07808-1E0161 Rev. B 21044 21044/21045 Accepted

    Fig. Witness dimensional inspection before PWHT of Harps Assembly unit

    # 401 HA-23B

    ITPITPITPITP----T8A8PSPT8A8PSPT8A8PSPT8A8PSP----1 Rev. 06 1 Rev. 06 1 Rev. 06 1 Rev. 06 item 5.0 item 5.0 item 5.0 item 5.0 Witness Hardness test: Witness Hardness test: Witness Hardness test: Witness Hardness test: Harp Assembly #401 HA-73A - 75A with actual hardness found acceptable were meets specification MS-HRSG-0008 Rev. G and SOP-

    030 (MIC TEN) for tubes to header weld joint and SOP-029 (Pin Brinnel)

    for nozzle/end plate to header:

    Fig. Witness Hardness test: : : : Harp Assembly #401 HA-74A.

  • ITP-TA8APSP-02 Rev. 5 item 4.12-Unit 401- Witnessed hydro test on the following Harps assembly:

    o The potable water employed for hydro testing with Chlorine reading

    is 50 PPM (The acceptable range is less than 100 PPM) and added

    Protectsol 770 ferrous metal powdered corrosion inhibitor with the

    concentration was checked = 880-920 mho by used of EP-10

    Conductivity Meter: Accepted (The acceptable range is 800 1000

    mho) and Conductivity meter during testing are calibrated in

    accordance with the suppliers gauge control program.

    o Harps Hydro tested in supported on a slope jig > 5 angle to ensure

    adequate drainage of hydro test water and the component was

    blown by air supply to remove excess water from bottom header

    was observed : satisfactory.

    o Witnessed includes verify calibration Pressure Gauges to the

    following hydro test that found acceptable meets to specification

    MS-HRSG-0003 Rev. 07 and drawing no. 07808-1E0160 Rev. A for DN

    80 (No leakage or sweating was observed during the test period): Unit #401 Harps Assy. No.

    Report no Pressure gage no. and calibrate exp. Date

    Spec. Design Pressure (DP) Test Pressure (TP)

    Actual

    HA-16A,

    17A & 18A

    (DN80)

    8A8-H-059

    # 401

    PSG-15: 15/6/09

    PSG-17: 15/6/09

    (Range 0-600 PsiG)

    DP : 170 PsiG

    TP : 255 PsiG

    HT: min.15 mints.

    DP: 180 PsiG

    TP: 270 PsiG

    HT: 35 mints.

    HA-10B &

    12B

    (DN80)

    8A8-H-060

    # 401

    PSG-108: 28/11/09

    PSG-112: 28/11/09

    (Range 0-2,000 PsiG)

    DP : 500 PsiG

    TP : 750 PsiG

    HT: min.15 mints.

    DP: 530 PsiG

    TP: 785 PsiG

    HT: 20 mints.

    HA-73A &

    83A

    (DN100)

    8A8-H-066

    # 401

    PSG-82: 29/10/09

    PSG-85: 29/10/09

    (Range 0-10,000 PsiG

    DP : 2250 PsiG

    TP : 3375 PsiG

    HT: min.15 mints.

    DP: 2300 PsiG

    TP: 3500 PsiG

    HT: 20 mints.

    HA-66B

    (DN100)

    8A8-H-067

    # 401

    PSG-82: 29/10/09

    PSG-85: 29/10/09

    (Range 0-10,000 PsiG

    DP : 2250 PsiG

    TP : 3375 PsiG

    HT: min.15 mints.

    DP: 2300 PsiG

    TP: 3500 PsiG

    HT: 20 mints.

    HA-74B &

    75B

    (DN100)

    8A8-H-071

    # 401

    PSG-82: 29/10/09

    PSG-85: 29/10/09

    (Range 0-10,000 PsiG

    DP : 2250 PsiG

    TP : 3375 PsiG

    HT: min.15 mints.

    DP: 2300 PsiG

    TP: 3500 PsiG

    HT: 20 mints.

    Fig. Observed hydro test of unit # 401 HA-74B-75B with actual TP 3500 Psig &

    DP 2300 Psig

    o Harps Assembly storage at out side of shop (at Bay 6) after hydro test

    that found with out plastic cap on (Missed) certain location (Two

    locations). APESI need to maintain all plastic cap was installed at

    nozzles opening of harps assembly.

  • T8A8PSP-1 Rev.06 item 4.0 in process welding inspection: P5B Harps

    assembly to P5A stub manifold (MU-11) Unit # 301 module assembly-2A

    by GTAW welding with following items was verified/observed and

    inspected: Accepted were meets Job routing J8A8-MD-200 Op. 130.

    o WPS no. T5.5HH-025 Rev. 01 with supporting PQR no. APESI GTA-

    5.5H-018

    o Filler metal: ER90S-B3 x 2.4 mm & 3.2 mm o Verify Pre heating >205 C was utilized and maintained

    throughout entire welding cycle by tempil stick temperature

    that found acceptable were meets approved WPS

    o Welding was performed by qualified welder name Bahrul Ulum

    (F-065) x last welded on 17 Feb. 2009 and Sutrisno (T658) x last

    welded 03 Feb. 09: Accepted

    o Calibrated welding machine WM-001 x expired 01 August 2009

    and WM-023 x expire date15 August 2009: Accepted

    o Grounding cable from calibrated welding machines was

    attached directly to the parts being welded.

    o Visual inspection was performed on the final pass that found

    acceptable were meets specification QCP-7.2 Rev.9.

    o Extend/re bake temperature 350 C x 70 minutes was performed

    on the joint stub manifold MU-11 (P5A) BW-1 to harps nozzle HA-

    72A (P5A) module-2A was verified that found acceptable were

    meets WPS T5.5HH-025 Rev.01

    3. Review The following APESI quality documents includes review Radiographic film of splice joint:

    Review NDE record:

    o 11 sheet PT record no. T8A8-PT-401-40, 43 up to 52 for unit # 401

    Harps Assembly (Selection 10% of welded joint) that found

    acceptable were meets specification MS-HRSG-0001 Rev. 11 by

    qualified NDE PT level II Sutopo certificate no. 93/PT/08 expire date

    12 January 2012,Yugi 33/PT/08 x 21 April 2011, Agus Hariyono and

    Huda were evaluated by NDT Level III Adipadmo ID no. 126596

    including practical examination that found acceptable were

    meets QS-7507-0009 Rev. B.

    Review PWHT chart record:

    o 3 sheet PWHT charts: 905151 (U401 HA-81A & 83B), 905143

    (U401HA-45B-47B) and 905138 (U401 HA-67A, 81B-82B, 905135

    (U401 HA-40A-42A) were reviewed that found acceptable were

    meets job routing J8A813A-200 Op.210, J8A812A-200 Op.130,

    J8A812B-200 Op.130

    4. Others: The following balance issued was not close out yet:

    The balance buildup beam W8 x 67 x 3400 x 4 ea from PT MULCINDO:

    EN Material S335 J2 being used for build up beam instead of A572

    Grade 50. WPS with supporting PQR was approved by APESI and

    followed review inspection and NDE reports for release/send of build up

    beam to APESI

    Balance MILL country origin for MTR from MILL ILSEN BURGER BROBBLECH

    still needs APESI clarification/reply.

    The balance of mock test report of finned tubes manufactured by APESI

    is not ready to offer for review at this time surveillance visit.

  • Verify the RN09-089 (NCR 09-106): NCR was closed out, however to help

    close any gap insulation that exist is still required.

    Module-2B: improper primer painting on certain location on Floor panel

    of C-frame module 2B was observed. APESI need touch up improper

    primer before final inspection of C-frame.

    Module 1A: improper flame cutting on the Stub column after machining

    still observed that found not acceptable.

    Field weld areas and exposed inside edges of casing plate with one (1)

    coat of Deoxaluminate paint was not done yet on loose boiler casing

    on the following casing side location of duct burner. Its does not meets

    to the drawing 07808 Rev. B note9: o Unit # 301: BC-318-U301, BC-1-U301, BC-E-21-U301 and BC-E10-

    U301

    o Unit # 401: BC-27-U401

    5. Attached Photographs:

    T8A8-IR020-1: Overview Module Assembly # 301 MDL-2A, 1A, 2B & 1B

    at Bay 4.2 (Install and welding of manifold to harps assembly on

    module-2A & 2B are in progress)

    T8A8-IR020-2: Overview Module Assembly # 301 MDL-3A, 3B & 4B at

    Bay 4.1

    T8A8-IR020-3: Overview Boiler casing ceramic fiber insulation at Bay

    2.1

    T8A8-IR020-4: Overview SCR, Filler panel & duct burner assembly

    # 301/# 401Bay 2.2