Dallas County Community College District Purchasing Department 4343 IH-30 Mesquite, Texas 75150 August 23, 2017 ADDENDUM NO. 1 Bid No. 12407 Chiller Addition Brookhaven College Opening Date: August 29, 2017 2:00 p.m. Please take note that the above referenced Request for Bid is amended as follows: 1. Clarifications from the consultant are attached. There are no further changes/additions at this time. If there are any questions concerning this request for bid, please contact the Purchasing Department at 972/860-7771. END OF ADDENDUM

Dallas County Community College District Purchasing Department · PDF fileDallas County Community College District Purchasing Department 4343 IH-30 Mesquite, Texas 75150 August 23,

Embed Size (px)

Citation preview

Dallas County Community College District Purchasing Department 4343 IH-30 Mesquite, Texas 75150

August 23, 2017 ADDENDUM NO. 1 Bid No. 12407 Chiller Addition Brookhaven College Opening Date: August 29, 2017

2:00 p.m. Please take note that the above referenced Request for Bid is amended as follows: 1. Clarifications from the consultant are attached. There are no further changes/additions at this time. If there are any questions concerning this request for bid, please contact the Purchasing Department at 972/860-7771. END OF ADDENDUM

1616 Corporate Court, Suite 100 Irving, TX 75038 Phone 972-929-1199

ADDENDUM #1 NARRATIVE

Project Name: Brookhaven College Chiller AdditionProject No.: 16030Revision Date: 08/22/2017

Revision items: ME000, G101, DM200, M200

The specifications and drawings have been revised as follows:

SPECIFICATIONS:

Specification Section 23 64 16 – Centrifugal Chillers Deleted paragraph 2.14.B.2.c requiring factory performance testing at varying entering condenser water

temperatures. Deleted paragraph 2.14.B.2.d requiring Owner selected part load factory performance testing conditions. Deleted paragraph 2.14.B.3 requiring Owner and engineer access to factory performance testing.

DRAWINGS

ME000: Revised HVAC System Description to describe final system arrangement after completion of project. Removed Electrical section describing temporary electrical work.

DM200: Added Keyed Note 2 regarding temporary removal of existing standby generator exhaust flue. Added Keyed Note 3 regarding temporary removal of existing louver sections.

M200: Added Keyed Note 2 regarding re-installation of existing standby generator exhaust flue. Added Keyed Note 3 regarding re-installation of existing of louver sections. Added note regarding termination of new refrigerant relief piping (RR) above roof line.

END OF ADDENDUM #1

CENTRIFUGAL WATER CHILLERS 23 64 16 - 16BROOKHAVEN COLLEGE CHILLER ADDITION ADDEDNUM #1 08/22/17

a. Vane operated to actuate a double-pole, double-throw switch, with one pole field wired to the chiller control panel and the other pole field wired to the DDC system for HVAC.

b. Contacts: Platinum alloy, silver alloy, or gold-plated switch contacts with a rating of 10 A at 120-V ac.

c. Pressure rating equal to pressure rating of heat exchanger.d. Construct body and wetted parts of Type 316 stainless steel.e. House switch in a NEMA 250, Type 4 enclosure constructed of die-cast aluminum.f. Vane length to suit installation.

3. Pressure-Differential Switches:

a. Construction: Wetted parts of body and trim constructed of Type 316 stainless steel.

b. Performance: Switch shall withstand, without damage, the full-pressure rating of the heat exchanger applied to either port and exhibit zero set-point shift due to variation in working pressure.

c. Set Point: Screw type, field adjustable.d. Electrical Connections: Internally mounted screw-type terminal blocks.e. Switch Enclosure: NEMA 250, Type 4.f. Switch Action: Double-pole, double-throw switch, with one pole field wired to the

chiller control panel and the other pole field wired to the DDC system for HVAC.

B. Vibration Isolation:

1. Chiller manufacturer shall furnish vibration isolation for each chiller.2. Neoprene Pad:

a. Two layers of 0.375-inch-thick, ribbed- or waffle-pattern neoprene pads separated by a 16-gage, stainless-steel plate.

b. Fabricate pads from 40- to 50-durometer neoprene.c. Provide stainless-steel square bearing plate to load the pad uniformly between 20

and 40 psig with a 0.12- to 0.16-inch deflection.

2.14 SOURCE QUALITY CONTROL

A. Perform functional run tests of chillers before shipping.

B. Factory Performance Testing:

1. Factory performance test chillers, before shipping, according to AHRI 550/590.2. Test the following conditions:

a. Design conditions indicated.b. Reduction in capacity from design to minimum load in steps of 10 with condenser

fluid at design conditions.c. Reduction in capacity from design to minimum load in steps of 10 with varying

entering condenser-fluid temperature from design to minimum conditions in 5 deg F increments.

d. At five point(s) of varying part-load performance to be selected by Owner at time of test.

3. Allow Owner and Engineer access to place where chillers are being tested. Notify Owner in writing at least 14 days in advance of testing.

CODES:MECHANICAL: 2015 INTERNATIONAL MECHANICAL CODE*

ELECTRICAL: 2015 NATIONAL ELECTRIC CODE*PLUMBING: 2015 INTERNATIONAL PLUMBING CODE*

ENERGY: 2015 INTERNATIONAL ENERGY CONSERVATION CODE*

- WITH CITY OF FARMERS BRANCH AMENDMENTS

HVAC SYSTEM DESCRIPTION:AT THE COMPLETION OF THE PROJECT, THE CHILLED WATER SYSTEM WILL CONSIST OF THREE WATER-COOLED

CHILLERS (CH-1, CH-2, AND CH-3), THREE PRIMARY CHILLED WATER PUMPS (PCHP-1, PCHP-2, AND PCHP-3), AND TWO

SECONDARY CHILLED/HEATING WATER PUMPS. CH-1 IS A 700-TON CHILLER, CH-2 IS A 300-TON CHILLER, AND CH-3 IS A 400-TONCHILLER.

DOMESTIC COLD WATERPIPING

DOMESTIC HOT WATER PIPING

DOMESTIC HOT WATERRECIRCULATION PIPING

SANITARY VENT PIPING

COMPRESSED AIR PIPING

CONDENSATE DRAIN PIPING

CHEMICAL TREATMENT PIPING

CHILLED WATER RETURNPIPING

CHILLED WATER SUPPLYPIPING

CONDENSER WATER SUPPLYPIPING

CONDENSER WATER RETURNPIPING

DRINKING WATER PIPING

FIRE PROTECTION PIPING

FUEL OIL RETURN PIPING

FUEL OIL SUPPLY PIPING

FUEL OIL VENT PIPING

NATURAL GAS PIPING

GREASY WASTE PIPING

REFRIGERANT HOT GAS PIPING

HIGH PRESSURE STEAMCONDENSATE PIPING

HIGH PRESSURE STEAM PIPING

HEATING HOT WATER RETURNPIPING

HEATING HOT SUPPLY PIPING

LOW PRESSURE STEAMCONDENSATE PIPING

LOW PRESSURE STEAM PIPING

MAKE-UP WATER PIPING

OVERFLOW STORM DRAINPIPING

PUMPED COOLING COILCONDESATE DRAIN PIPING

PRIMARY CHILLED WATERRETURN PIPING

PRIMARY CHILLED WATERSUPPLY PIPING

PRIMARY HEATING HOT WATERRETURN PIPING

PRIMARY HEATING HOTSUPPLY WATER PIPING

REFRIGERANT LIQUID PIPING

REFRIGERANT RELIEF PIPING

REFRIGERANT SUCTION PIPING

SANITARY WASTE PIPING

SECONDARY CHILLED WATERRETURN PIPING

SECONDARY CHILLED WATERSUPPLY PIPING

SECONDARY HEATING HOTWATER RETURN PIPING

SECONDARY HEATING HOTWATER SUPPLY PIPING

STORM DRAIN PIPING

TEMPERED DOMESTIC WATERPIPING

CHANGE OF ELEVATION - RISE

(R) DROP (D)

EXISTING DUCT

EXISTING DUCT TO BEREMOVED

NEW DUCT

INDICATES DIRECTION OFAIRFLOW

DUCT TURNED UP, NEGATIVE

PRESSURE. FIRST FIGURE IS

TOP DIMENSION

DUCT TURNED UP, POSITIVE

PRESSURE. FIRST FIGURE IS

TOP DIMENSION

EXHAUST DUCT SECTION UP

RETURN DUCT SECTION UP

SUPPLY DUCT SECTION UP

EXHAUST DUCT SECTIONDOWN

RETURN DUCT SECTION DOWN

SUPPLY DUCT SECTION DOWN

BACKDRAFT DAMPER

HORIZONTAL FIRE DAMPER

VERTICAL FIRE DAMPER

HORIZONTAL FIRE/SMOKEDAMPER

VERTICAL FIRE/SMOKEDAMPER

HORIZONTAL SMOKE DAMPER

VERTICAL SMOKE DAMPER

MANUAL VOLUME DAMPER

DUCT CAP

MOTORIZED DAMPER

CEILING DIFFUSER

CEILING EXHAUST/RETURNGRILLE

SIDEWALL GRILLE ORREGISTER

SLOT DIFFUSER OR GRILLE

CAP

PIPE TURNED DOWN

PIPE TURNED UP

PIPE ELBOW

PIPE CROSS

PIPE TEE

COMBINATION WYE ANDEIGHTH BEND

PIPE TEE BOTTOMCONNECTION

PIPE TEE UP

PIPE TEE TOP CONNECTON

PIPE FLANGE

PIPE UNION

CONCENTRIC PIPE REDUCER

ECCENTRIC PIPE REDUCER

PIPE STRAINER

CLEANOUT PLUG

TRAP

AUTOMATIC BUTTERFLY VALVE

ANGLE VALVE

BALANCING VALVE

BALL VALVE

BUTTERFLY VALVE

CALIBRATED BALANCINGVALVE

CHECK VALVE

GAS COCK

GATE VALVE

GLOBE VALVE

HOT TAP

NEEDLE VALVE

PLUG VALVE

PRESSURE REDUCING VALVE

PRESSURE REGULATOR

REGULATOR

PRESSURE RELIEF VALVE

SOLENOID VALVE

THERMOSTATIC MIXING VALVE

THREE WAY CONTROL VALVE

TWO WAY CONTROL VALVE

TAMPER SWITCH VAVLE

VALVE MOUNTED IN VERTICAL

TRAP PRIMER VALVE

WATER HAMMER ARRESTER

HOSE BIBB

P-TRAP

PENETRATION

CARBON DIOXIDE SENSOR

CONNECT NEW TO EXISTING

DIFFERENTIAL PRESSURESWITCH

FLOW METER

FLOW METER

FULL ENCIRCLEMENT TEE

HUMIDISTAT

HUMIDITY SENSOR

HYDROGEN SENSOR

PRESSURE GAUGE

PUMP

PUMP

ROUND

THERMOMETER

SPRINKLER HEAD

STATIC PRESSURE SENSOR

TEMPERATURE SENSOR

TEMPERATURE WELL

THERMOSTAT

VARIABLE FREQUENCY DRIVECONTROLLER

WATER HAMMER ARRESTER

DIFFUSER,

REGISTER,

GRILLE TAG

TERMINAL

UNIT TAG

CA

CD

CHEM

CHR

CHS

CR

CS

DW

F

FOR

FOS

FOV

GAS

GW

HG

HPC

HPS

HR

HS

LPC

LPS

MUW

OSD

PCD

PCHR

PCHS

PHR

PHS

RL

RR

RS

SAN

SCHR

SCHS

SHR

SHS

SD

TW

D

BDD

FD

FD

FSD

FSD

SD

SD

M

CO2

DPS

FM

H

HYD

SP

T

VFD

NECK SIZE20010"ØA

SCHEDULE DESIGNATION

AIR QUANTITY (CFM)

AIR QUANTITY (CFM)2000VAV-1 SCHEDULE DESIGNATION

REPRESENTS DEMO WORK

LOW VOLTAGE

CONDUIT

UNDERGROUND/UNDERFLOOR

CONDUIT

WIRE MOLD

HOMERUN

NEUTRAL CONDUCTOR

HOT CONDUCTOR

GROUND CONDUCTOR

SINGLE RECEPTACLE

DUPLEX RECEPTACLE

ABOVE COUNTER DUPLEX

RECEPTACLE

QUADRAPLEX RECEPTACLE

MOUNT @ 44" A.F.F. U.N.O.

ABOVE COUNTER

QUADRAPLEX RECEPTACLEMOUNT @ 44" A.F.F. U.N.O.

SPECIAL PURPOSE

RECEPTACLE (VERIFY EXACTNEMA CONFIGURATION)

FLUSH FLOOR MOUNT DUPLEX

RECEPTACLE

CEILING MOUNTED DUPLEX

RECEPTACLE

FLOOR MOUNTEDQUADRAPLEX RECEPTACLE

CEILING MOUNTEDQUADRAPLEX RECEPTACLE

FLUSH FLOOR

DUPLEX/DATA/TELE OUTLET

FLUSH FLOORQUAD/DATA/TELE OUTLET

TRANSFORMER

208/120V ELECTRICAL PANEL

BOARD

480/277V ELECTRICAL PANEL

BOARD

I LINE PANEL BOARD

SWITCH BOARD

DATA COMMUNICATIONSOUTLET RUN 3/4" E.C. TO 6"

ABV. CLG.

TELEPHONE OUTLET RUN 3/4"

E.C. TO 6" ABV. CLG.

TELEPHONE / DATA OUTLET

RUN 3/4" E.C. TO 6" ABV. CLG.

FIREMAN'S TELEPHONE JACK

FLUSH FLOOR DATA OUTLET

FLUSH FLOOR TELEPHONE

OUTLET

FLUSH FLOOR TELE/DATA

OUTLET

CEILING MOUNTED DATA

OUTLET

CEILING MOUNTED TELEPHONE

OUTLET

CEILING MOUNTED TELE/DATA

OUTLET

PUSH-BUTTON

DISCONNECT SWITCH

FUSED DISCONNECT SWITCH

COMBINATION MOTOR

STARTER

VFD (VARIABLE FREQUENCY

DRIVE)

SPD (SURGE PROTECTIVE

DEVICE)

ENCLOSED CIRCUIT BREAKER

DISCONNECT

POWER POLE

MOTOR

JUNCTION BOX

WALL MOUNTED JUNCTION

BOX

J/BOX FOR VOICE/DATA

COMMUNICATIONS CABLE FORMODULAR FURNITURE SYSTEM.

RUN 1-1/4" E.C. W/PULL STRING

TO 6" ABOVE CEILING

J/BOX FOR POWER TO

MODULAR FURNITURE SYSTEM.

SWITCH

THREE-WAY SWITCH

FOUR-WAY SWITCH

MOTOR RATED SWITCH

TIMER SWITCH

DIMMER SWITCH

WALL MOUNTED OCCUPANCY

SENSOR

CEILING MOUNTED

OCCUPANCY SENSOR

BUZZER

GROUND ROD W/TEST WELL

SECURITY KEY PAD

KEY PAD

CARD READER SECURITY

SYSTEM CAM-LOCK DEVICE

DOOR CONTACT

MAGNETIC LOCK

MAGNETIC HOLD-OPEN DEVICE

PHOTOELECTRIC CELL

TIME CLOCK

INTERCOM

INTERCOM CALL MASTER

STATION

SQUARE D POWERLOGIC

CIRCUIT MONITOR

VESDA CONTROL PANEL

VEEDER ROOT

REMOTE FIRE ALARM

CONTROL PANEL

FIRE ALARM SYSTEM TAMPER

SWITCH

FIRE ALARM ANNUNCIATORPANEL

FIRE ALARM CONTROL PANEL

GENERATOR REMOTE ALARM

GENERATOR REMOTE

ANNUNCIATOR PANEL

GENERATOR

CLEAN AGENT RELEASE

CLEAN AGENT STORAGE

BOTTLE

AUDIO/VISUAL FIRE ALARM

DEVICE

CEILING FIRE ALARM DEVICE

FIRE STROBE

PULL STATION

METER

METER

KIRK-KEY INTERLOCK

VESDA

CEILING SPEAKER, NOTE: SUBSCRIPT 'F' DENOTES FIREALARM

WALL HUNG SPEAKER, NOTE:SUB SCRIPT 'F' DENOTES FIRE

ALARM SMOKE DETECTOR

UNDERFLOOR SMOKE

DETECTOR

DUCT MOUNTED SMOKE

DETECTOR

REMOTE PILOT LIGHT

HEAT DETECTOR

HEAT DETECTOR BELOW

FLOOR

FLAME DETECTOR

TELEVISION OUTLET MTD 96"

A.F.F. WITH 3/4" CONDUIT

CONNECTION TO OTHER

DEVICES, U.N.O.

2' X 4' FLUORESCENT -REFERENCE LIGHT FIXTURE

SCHEDULE

SAME AS 2' X 4' EXCEPT WITHEMERGENCY NICAD BATTERY

PACK

2' X 2' FLUORESCENT -REFERENCE LIGHT FIXTURE

SCHEDULE

SAME AS 2' X 2' EXCEPT WITHEMERGENCY NICAD BATTERY

PACK

FLUORESCENT STRIP -REFERENCE LIGHT FIXTURE

SCHEDULE

FLUORESCENT STRIP -EMERGENCY NICAD BATTERY

PACK

DOWNLIGHT - REFERENCE

LIGHT FIXTURE SCHEDULE

WALL WASHER - REFERENCE

LIGHT FIXTURE SCHEDULE

SAME AS DOWNLIGHT EXCEPTWITH EMERGENCY BATTERY

PACK

WALL MOUNTED LIGHTFIXTURE - REFERENCE LIGHT

FIXTURE SCHEDULE

LIGHT FIXTURE - REFERENCE

LIGHT FIXTURE SCHEDULE

LIGHT FIXTURE - REFERENCE

LIGHT FIXTURE SCHEDULE.

NOTE: REFERENCE PLANS FORNUMBER OF FIXTURE HEADS

SINGLE FACE EXIT SIGN -

SHADED AREA INDICATESILLUMINATED FACE -

REFERENCE LIGHT FIXTURE

SCHEDULE

DOUBLE FACE EXIT SIGN -

SHADED AREA INDICATESILLUMINATED FACE -

REFERENCE LIGHT FIXTURE

SCHEDULE

WALL MOUNTED EXIT SIGN -REFERENCE LIGHT FIXTURE

SCHEDULE

EMERGENCY LIGHTING

FIXTURE MK 'EM' U.N.O. -

REFERENCE LIGHT FIXTURESCHEDULE

DELTA CONNECTION

WYE-CONNECTION

CIRCUIT BREAKER

DISCONNECT/INTERRUPTER

SWITCH

FUSE

CAPACITOR

SERVICE WEATHERHEAD

GROUND CONNECTION

TRANSFORMER

CONTROL POWER

TRANSFORMER

POTENTIAL TRANSFORMER

CURRENT TRANSFORMER

CABLE POT HEAD

BUS DUCT

GROUND FAULT RELAY

FUSED CUTOUT

CONTACTOR, NORMALLY

CLOSED

CONTACTOR, NORMALLY OPEN

TRANSFER SWITCH

SWITCH

BATTERY

LIGHTNING ARRESTER

DRAWOUT CONNECTION

ELECTRIC RESISTANCEHEATER

GROUND BAR

CCTV CAMERA

VIA LIGHTING CONTACTOR

MEDIUM VOLTAGE CIRCUITBREAKER

TIME DELAY ANDINSTANTANEOUS

OVERCURRENT PROTECTIVERELAY

LV

F

3

4

M

T

D

OC

K

KP

CR

DC

ML

MH

PC

TC

IC

ICM

CM

VESDA

VR

RCP

TS

FAA

FACP

GEN

GAP

TV52

ABV ABOVE

ADAAMERICANS WITH DISABILITIES

ACT

AD AREA DRAIN

AFF ABOVE FINISHED FLOOR

AL ALUMINUM

AI ANALOG INPUT

AO ANALOG OUTPUT

APD AIR PRESSURE DROP

ASTABOVE GROUND STORAGETANK

BASBUILDING AUTOMATION

SYSTEM

BFF BELOW FINISHED FLOOR

BFP BACKFLOW PREVENTER

BDD BACKDRAFT DAMPER

BHP BRAKE HORSEPOWER

BOD BOTTOM OF DUCT

BOE BOTTOM OF EQUIPMENT

BTU BRITISH THERMAL UNIT

BTUHBRITISH THERMAL UNIT PER

HOUR

C CONDUIT

CA COMPRESSED AIR

CB CIRCUIT BREAKER

CD CONDENSATE DRAIN

CFM CUBIC FEET PER MINUTE

CFS CUBIC FEET PER SECOND

CLG CEILING

CHR CHILLED WATER RETURN

CHS CHILLED WATER SUPPLY

CO CLEANOUT

CR CONDENSER WATER RETURN

CS CONDENSER WATER SUPPLY

CW DOMESTIC COLD WATER

CU COPPER

DB DRY BULB

DCO DOUBLE CLEANOUT

DI DIGITAL INPUT

DN DOWN

DO DIGITAL OUTPUT

DT DAY TANK

(E) EXISTING

EAGEXHAUST AIR

GRILLE/REGISTER

EAT ENTERING AIR TEMPERATURE

E.C. EMPTY CONDUIT

EFF EFFICIENCY

EPO EMERGENCY POWER OFF

ERVENERGY RECOVERY

VENTILATION

ESP EXTERNAL STATIC PRESSURE

EWC ELECTRIC WATER COOLER

EWH ELECTRIC WATER HEATER

EWTENTERING WATERTEMPERATURE

EXH. EXHAUST

(F) FUTURE

ºF DEGREES FARENHEIT

FCO FLOOR CLEANOUT

FD FIRE DAMPER

FDCFIRE DEPARTMENT

CONNECTION

FDS FUSED DISCONNECT SWITCH

FLA FULL LOAD AMPS

FLD FLOOR DRAIN

FL FLOW LINE

FO FLAT OVAL DUCT

FOR FUEL OIL RETURN

FOS FUEL OIL SUPPLY

FP FIRE PROTECTION WATER

FPI FINS PER INCH

FPM FEET PER MINUTE

FSDCOMBINATION FIRE SMOKEDAMPER

FT FEET

FU FIXTURE UNITS

FV FACE VELOCITY

G GAS

GCO GRADE CLEANOUT

GE GENERAL EXHUAST

GFI GROUND FAULT INTERUPTER

GM GAS METER

GND GROUND

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GRS GALVANIZED RIGID STEEL

GW GREASY WASTE

GWH GAS WATER HEATER

HB HOSE BIBB

HD HUB DRAIN

HG REFRIGERANT HOT GAS

HI HARDWIRE INTERLOCK

HP HORSEPOWER

HR HEATING HOT WATER RETURN

HS HEATING HOT WATER SUPPLY

HW DOMESTIC HOT WATER

HWCDOMESTIC HOT WATER

RECIRCULATION

HX HEAT EXCHANGER

IG ISOLATED GROUND

IWHINSTANTANEOUS WATERHEATER

IW INDIRECT WASTE

IWV INDIRECT WASTE VENT

KW KILOWATT

L LAVATORY

LAT LEAVING AIR TEMPERATURE

LE LAB EXHAUST

LBS POUNDS

MATVMASTER ANTENNA TELEVISION

SYSTEM

MB MOP BASIN

MBHTHOUSANDS OF BTUS PER

HOUR

MCA MINIMUM CIRCUIT AMPS

MFG MANUFACTURER

MOCPMAXIMUM OVERCURRENT

PROTECTION

MTD MOUNTED

(N) NEW

NC NOISE CRITERIA

NIC NOT IN CONTRACT

N3R NEMA 3R

O OXYGEN

OA OUTSIDE AIR

OBD OPPOSED BLADE DAMPER

OCD OVERFLOW CONDENSATION

OCPDOVERCURRENT PROTECTIVE

DEVICE

OFCIOWNER FURNISHED

CONTRACTOR INSTALLED

OFD OVERFLOW ROOF DRAIN

OSD OVERFLOW STORM DRAIN

PBD PARALLEL BLADE DAMPER

PH PHASE

PP POWER POLE

PSI POUNDS PER SQUARE INCH

PSIGPOUNDS PER SQUARE INCH

(GAGE)

PVC POLYVINYL CHLORIDE PIPE

(R) RELOCATED

RA RETURN AIR

RABL RETURN AIR BOOT (L-SHAPED)

RABU RETURN AIR BOOT (U-SHAPED)

RAG RETURN AIR GRILLE/REGISTER

RD ROOF DRAIN

RL REFRIGERANT LIQUID

RPM REVOLUTIONS PER MINUTE

RPZ REDUCED PRESSURE ZONE

RS REFRIGERANT SUCTION

RTU ROOFTOP UNIT

S SINK

SA SUPPLY AIR

SAG SUPPLY AIR GRILLE/REGISTER

SAN SANITARY SEWER

SD STORM DRAIN

SF SQUARE FEET

SMD SMOKE DAMPER

SP STATIC PRESSURE

SPD STATIC PRESSURE DROP

TPV TRAP PRIMER VALVE

TPD TOTAL PRESSURE DROP

TP TOTAL PRESSURE

TW DOMESTIC TEMPERED WATER

U URINAL

UF UNDERFLOOR

UG UNDERGROUND

U.N.O UNLESS NOTED OTHERWISE

V VENT

VAC VACUUM

VFD VARIABLE FREQUENCY DRIVE

VIF VERIFY IN FIELD

VTR VENT THROUGH ROOF

W SANITARY WASTE

WB WET BULB

WC WATER CLOSET

WCO WALL CLEANOUT

WP WEATHER PROOF

WPD WATER PRESSURE DROP

WSHP WATER-SOURCE HEAT PUMP

" WC INCHES WATER COLUMN

" WG INCHES WATER GAUGE

WM WALL MOUNTED

XFMR TRANSFORMER

ABBREVIATIONS

MECHANICAL AND PLUMBING SYMBOLS

ELECTRICAL AND LIGHTING SYMBOLS

BASIS OF DESIGN

Sheet Title:

Sheet No.:

Issue Date:

Project Number:

DC

CC

D M

AIN

TE

NA

NC

E P

RO

JE

CT

S

FA

RM

ER

S B

RA

NC

H, T

EX

AS

BR

OO

KH

AV

EN

CO

LLE

GE

CH

ILLE

R A

DD

ITIO

N3939 V

ALLE

Y V

IEW

LA

NE

Date

08/22/17

Description

SUBMISSION LOG

16030

ME000

MECHANICAL/ELECTRICAL

ABBREVIATIONS AND

SYMBOLS

05/08/17

1

1

(E)34/16 SA

(E)2

6/14

SA

(E)1

4/14

SA

(E)AHU-NO. A-5

(E)CHP-1

(E)CHP-2

(E)24" CS

(E)12" CR

(E)12" CR

(E)1

0" B

YP

AS

S

(E)8

" C

R

(E)1

2" C

R

(E)1

6" C

S

(E)8" CS

(E)8" CS & CR

(E)CWP-3

(E)CWP-1

(E)10" CS & CR

(E)CWP-2

(E)8

" C

R

(E)8

" C

HR

/HR

(E)1

0" C

HR

/HR

(E)BOILER #2

(E)6" PCHR DN

TO (E)PCHP-3

(E)8

" C

HR

/HR

(E)6" DN TO

(E)PCHP-1

(E)8" CS

(E)8

" C

S

(E)1

0" C

HS

/HS

(E)8

" B

YP

AS

S

(E)CS SUMP

(E)8" CS

(E)1

0" C

HS

/HS

(E)1

0" C

HS

/HS

(E)8" CHS/HS

(E)BOILER #1

(E)8" PCHR DN

TO (E)PCHP-2

(E)6" PCHR

TO BOILERS FROM BOILERS

(E)10" CHR

(E)1

0" C

HR

/HR

(E)SEPARATOR

(E)8" BYPASS

(E)PCHP-1

(E)PCHP-2

(E)PCHP-3

(E)10" CHS/HS

(E)6" PCHS

(E)8

" C

HS

/HS

(E)16/14 EXH DN

(E)8" CHS/HS

(E)10" PCHR

(E)10" PCHS

(E)16/14 EXH

(E)10" HS

(E)1

0" C

HS

/HS

(E)18/24 EXH

(E)16/14 EXH

(E)10" CHS/HS

(E)10"

(E)EQUIPMENT PAD (TYPICAL)

FD

(E)26/20 EXH(E)26/20 EXH

(E)16/14 EXH DN

(E)EFCP-1

(E)1

4/14

SA

(E)SIDEWALL GRILLE

(E)14/6 SA

(E)14/14 SA

(E)6" CHR/HR

(E)6" CHS/HS

(E)6" PCHR

(E)GENERATOR

(E)CH-3

(400 TON)

(E)CH-1

(700 TON)

(E)CONTROL VALVE

(E)CONTROL

VALVE

1

(E)REFRIGERANT SENSOR

(E)REFRIGERANT SENSOR

(E)REFRIGERANT MONITORING PANEL

CENTRAL MECH PLANTA101

CORRIDORA103

TELEPHONE

EQUIP. RM.

A102

OFFICE

AREAWAY

TOILET

(E)8" CR

(E) 3" REFRIGERANT

RELIEF PIPING

HR

HS

(E)FM

2

3

3

Sheet Title:

Sheet No.:

Issue Date:

Project Number:

DC

CC

D M

AIN

TE

NA

NC

E P

RO

JE

CT

S

FA

RM

ER

S B

RA

NC

H, T

EX

AS

BR

OO

KH

AV

EN

CO

LLE

GE

CH

ILLE

R A

DD

ITIO

N3939 V

ALLE

Y V

IEW

LA

NE

Date

08/22/17

Description

SUBMISSION LOG

16030

KEY PLAN

RT

QMP

S

X

J K

CF

D

H

S

B AU

E

AREA OF WORK

DM200

PARTIAL BASEMENT

MECHANICAL DEMOLITION

PLAN

05/08/17SCALE: 1/4" = 1'-0"N

NORTH

01PARTIAL BASEMENT MECHANICAL DEMOLITION PLAN

KEY PLAN

RT

QMP

S

X

J K

CF

D

H

S

B AU

E

AREA OF WORK

REMOVE EXISTING PRIMARY CHILLED WATER PUMP

AND ASSOCIATED SUCTION AND DISCHARGE PIPING

BETWEEN ISOLATION VALVES AND PUMP.

PRIOR TO INSTALLATION OF NEW CHILLER ,

TEMPORARILY REMOVE EXISTING STANDBY

GENERATOR EXHAUST FLUE.

TEMPORARILY REMOVE NORTH AND CENTER SECTIONS

OF EXISTING LOUVER TO FACILITATE INSTALLATION OF

NEW CHILLER.

KEYED NOTES BY SYMBOL " "

11111

2

33333

1

1

1

8" CS 8" CR

6" PCHR

6" PCHS

CH-2

(300 TON)

02

M200

(E)34/16 SA

(E)2

6/14

SA

(E)1

4/14

SA

(E)AHU-NO. A-5

(E)CHP-1

(E)CHP-2

(E)24" CS

(E)12" CR

(E)12" CR

(E)1

0" B

YP

AS

S

(E)8

" C

R

(E)1

2" C

R

(E)1

6" C

S

(E)8" CS(E)CWP-3

(E)CWP-1

(E)10" CS & CR

(E)CWP-2

(E)8

" C

R

(E)8

" P

CH

R(E

)10"

PC

HR

(E)BOILER #2

(E)6" PCHR DN

TO (E)PCHP-3

(E)8

" P

CH

R

(E)6" DN TO

(N)PCHP-2

(E)8" CS

(E)8

" C

S

(E)1

0" P

CH

S

(E)CS SUMP

(E)8" CS

(E)8" PCHS

(E)BOILER #1

(E)8" PCHR DN

TO (E)PCHP-2

(E)6" PCHR

(E)SEPARATOR

(N)PCHP-2

(E)PCHP-1

(FORMERLY (E)PCHP-2)

(E)PCHP-3

(E)10" PCHS

(E)6" PCHS

(E)8

" P

CH

S

(E)16/14 EXH DN

(E)8" PCHS

(E)10" PCHR

(E)16/14 EXH

(E)10" HS

(E)18/24 EXH

(E)10"

(E)EQUIPMENT PAD (TYPICAL)

FD

(E)26/20 EXH(E)26/20 EXH

(E)16/14 EXH DN

(E)EFCP-1

(E)1

4/14

SA

(E)SIDEWALL GRILLE

(E)14/6 SA

(E)14/14 SA

(E)6" PCHR

(E)6" PCHS

(E)6" PCHR

(E)GENERATOR

(E)CH-3

(400 TON)

(E)CH-1

(700 TON)

(E)CONTROL VALVE

(E)CONTROL

VALVE

(E)REFRIGERANT SENSOR

(E)REFRIGERANT SENSOR

(E)REFRIGERANT MONITORING PANEL

CENTRAL MECH PLANTA101

CORRIDORA103

TELEPHONE

EQUIP. RM.

A102

OFFICE

AREAWAY

TOILET

(E)8" CR

(E)16/14 EXH

(E)3"

(E)3"

(E)3"

RR

RR

RR

RR

RR

RR

RR

3"(E)3"

(E)FM

(E)8

" B

YP

AS

S(E)1

0" C

HS

/HS

(E)1

0" C

HS

/HS

TO BOILERS FROM BOILERS

(E)10" CHR

(E)1

0" C

HR

/HR

(E)8" BYPASS

(E)10" PCHS

(E)10" HS

(E)1

0" C

HS

/HS

(E)10" CHS/HS

HR

HS

1

3" RR UP. TERMINATE

ABOVE ROOF LEVEL.

2

3

3

(E)8

" C

S

(E)8

" C

R

(E)6" CHR

(E)6" CHS

8" C

S

8" C

R

THERMOMETER (TYP.)

PRESSURE GAUGE (TYP.)

6" PCHS & PCHR

70" AFF CHR CONNECTION

78" AFF CHS CONNECTIONCHS & CHR CONNECTIONS

@ 77" AFF

CONTROL VALVE

(E)4" HOUSEKEEPING PADBASEMENT FLOOR SLAB

CH-2

NEOPRENE PAD (TYP.)

Sheet Title:

Sheet No.:

Issue Date:

Project Number:

DC

CC

D M

AIN

TE

NA

NC

E P

RO

JE

CT

S

FA

RM

ER

S B

RA

NC

H, T

EX

AS

BR

OO

KH

AV

EN

CO

LLE

GE

CH

ILLE

R A

DD

ITIO

N3939 V

ALLE

Y V

IEW

LA

NE

Date

08/22/17

Description

SUBMISSION LOG

16030

KEY PLAN

RT

QMP

S

X

J K

CF

D

H

S

B AU

E

AREA OF WORK

M200

PARTIAL BASEMENT

MECHANICAL PLAN

05/08/17SCALE: 1/4" = 1'-0"N

NORTH

01PARTIAL BASEMENT MECHANICAL PLAN

02SECTION AT CH-2SCALE: NONE

RENAME EXISTING PRIMARY CHILLED WATER PUMP

(FORMERLY PCHP-2) TO PCHP-1.

RE-INSTALL EXISTING GENERATOR EXHAUST FLUE

AFTER NEW CHILLER CH-2 HAS BEEN SET IN PLACE.

RE-INSTALL EXISTING LOUVER SECTION AFTER NEW

CHILLER CH-2 HAS BEEN SET IN PLACE.

KEYED NOTES BY SYMBOL " "

1

2

3

1

1

1