USSD The Challenges of Dams in Cold Climates September 2017 Dams in Cold Climates: Design Considerations and Challenges of Construction Doug Johnson, P.E., FERC Division of Dam Safety and Inspections Regional Engineer, Portland OR

Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

USSD The Challenges of Dams in

Cold Climates – September 2017

Dams in Cold Climates:

Design Considerations and

Challenges of Construction

Doug Johnson, P.E., FERC Division of Dam Safety and Inspections

Regional Engineer, Portland OR

Page 2: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

FERC-regulated Dams in Alaska

Susitna-Watana

Page 3: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Hebgen Dam in MT

Hebgen Dam

Page 4: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Portland Region Dams

> 5000 feet Elevation.

Dam NameCrest

ElevationState Hazard Class

Mystic Dike 7675 MT H

Mystic Lake 7674 MT H

Viva Naughton 7249 WY H

Hebgen Dam 6546 MT H

Georgetown Dam 6443 MT H

Soda 5725 ID H

Grace Dike 5559 ID S

Grace Main 5559 ID S

Ashton 5147 ID H

Page 5: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Portland Region Dams

at Highest Elevations In Alaska

Dam Name Crest Elevation State Hazard Class

Collection Pond (Goat Lake) 2885 AK L

Middle Fork Diversion (Bradley Lk.) 2204 AK L

Shotgun Creek Div 1931 AK L

Falls Creek Div 1650 AK L

Rolling Rock Creek Div 1485 AK L

Stetson Creek Diversion 1430 AK L

Terror Lake 1428 AK L

Allison Creek 1300 AK L

Crystal Lake 1299 AK H

Nuka River Div 1286 AK L

Cooper Lake 1220 AK H

Page 6: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Allison Creek Dam

If we keep digging we may find where we stopped working last summer!

Page 7: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Challenges of Constructing

FERC Projects In Cold Regions

Page 8: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Salmon Creek Dam

Page 9: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

View looking up Valley at Dam

Height = 170 ft.Crest Length = 650 ft.Storage ≈ 12,000 ac-ft

Page 10: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Downstream Face of Dam

First Constant Angle Arch

Dam in US.

Completed 1914

Page 11: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Upstream Face showing severe

freeze-thaw damage

Page 12: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Close-up view of eroded area of

upstream face

Page 13: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Rubble at base of dam is remnant of

shotcrete facing applied in 1960’s

Page 14: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Cold Climate Design Considerations

Dam built in 1914 – no air entrainment, poor consolidation, segregation of concrete

Severe Freeze-thaw environment

Tried to shotcrete faces of dam in 60s – most of that has fallen off.

Dam has lost over 2 feet in thickness.

As result dam is under reservoir restriction due to seismic instability – 32 foot drawdown

However, even without the drawdown the dam still retains sufficient thickness to resist static loads

Cost to rehab is prohibitive due to remote access – AEL&P has decided to live with restriction

Page 15: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Lake Dorothy Hydroelectric

Project

Alaska Electric Light and Power

Juneau, Alaska

2006 - 2010

Page 16: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Juneau

Page 17: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused
Page 18: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused
Page 19: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Lake Dorothy looking north toward outlet

Page 20: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Lake Dorothy

Tunnel Entrance

Page 21: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Final Round - 12’ dia. By 12’ Thick 8/19/2008

Water then fills tunnel up to plug

Valve on pipe side of plug is opened or closed to control water out of Lake

Page 22: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Actual Tunneling Begins July 2007

Page 23: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Downstream face of tunnel plug

Page 24: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Lake Tap

Lake tap was initiated from Lake Dorothy shoreline to allow observation of air pocket and energy from the blast emerge from below the water line

The final lake tap blast took place on August 19, 2008.

Page 25: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

LAKE DOROTHY IS TAPPED!

Page 26: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Bifurcation of 60-inch penstock

Page 27: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused
Page 28: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused
Page 29: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Barge Landing Facility

Substation & Camp

Shop & Crew Quarters

Powerhouse

Access Road

Page 30: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Losing Downhill Slope

Page 31: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Completed Road

Page 32: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Construction of concrete face panels

Page 33: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Reservoir Elevation 985 feet

Page 34: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

6.4 cfs

Page 35: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Lake Dorothy Powerhouse

The Lake Dorothy Project went into operation on Aug. 31, 2009

Page 36: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Challenges Constructing the

Lake Dorothy Project

Page 37: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Only Access to Site by Air

Page 38: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Seasonal Working

Conditions

Page 39: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Initial landing areas were limited

Page 40: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

All Tunneling Equipment Airlifted in Pieces

Page 41: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Fog and rain can move in very quickly

Page 42: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Weather Impacts

Good weather where crew could easily access tunnel - Rates of 40 feet per day

Typical advance rates averaged 25 feet per day

Changing weather conditions prevented mining crews from achieving steady advancement rates.

Fog and wind could quickly show up and force an early exit form the portal

2007 – 35 weather related delay days

2008 – 33 weather related delay days

Page 43: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Allison Creek DamConstruction 2014-16

Main Project Features

• 16-foot-high, 95-foot-wide concrete gravity diversion dam with 50-foot-wide spillway

• 42-inch-diameter, 7,200-foot-long steel penstock

• 700-foot-long, 16-foot-diameter access tunnel through which a segment of the penstock would be routed

• 65 foot by 65 foot powerhouse with two turbine/generating units with a combined capacity of 6.5-MW

Page 44: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Alyeska Oil Terminal

Page 45: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Powerhouse foundation construction with lower tunnel

portal in background

Page 46: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Upper Portal August 2014 – Tunnel near completion

Page 47: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Pioneering Road from Upper Portal to Dam Site

August 2014

Page 48: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Diversion Dam Site July 2015

Twin 48-inch-diameter CMP diversion conduits carry

Allison Creek through right abutment

Page 49: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

View of Penstock Below Lower Tunnel Portal and

Powerhouse Below July 2015

Page 50: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Concrete being placed for diversion dam intake structure.

August 2015

Page 51: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Allison Creek diversion dam at spring break-up 2016

getting ready for final construction season to start.

Page 52: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Allison Creek Powerhouse at spring break-up 2016

Page 53: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Allison Creek Diversion Dam nearing completion

June 2016

Page 54: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Mass excavation of steep slope in reach 4 continues before

penstock installation (dashed line) can resume.

Page 55: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Upstream face of completed diversion dam with reservoir

full to the top of the spillway. August 2016

Page 56: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Downstream View of Completed Diversion Dam

Page 57: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Completed Powerhouse

Page 58: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Cold Climate Design Considerations

Rugged terrain, no existing roads – the use of tunnels is common in Alaska. Construction can continue through winter.

The Allison tunnel was designed to serve as both the penstock route and construction access road to site.

Very Limited window for construction – June to September. Took 3 years to complete project.

Frigid temps and deep snow necessitated burying penstock

Project can only generate 6 months out of the year due to deep snow and frozen conditions at diversion dam.

Page 59: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Hebgen Lake Dam

Page 60: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Hebgen Lake Dam

Dam Height = 88ftCrest Length = 721 ftNormal Storage 386,000 af

Page 61: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Hebgen Lake Dam

Underwent 2 major rehab projects in the 2008-2016 period.

Failure of Outlet Tower Stoplogs in Aug 2008 + seismic inadequacy –necessitated rehab of tower 2008-14

Spillway removal and replacement 2015-16

Page 62: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Outlet Tower Rehab

Had to build cellular cofferdam first to dewater front of tower.

Work could not proceed in winter, due to ice, snow, and reservoir lowering which required use of outlet instead of spillway.

Cofferdam provided with a spillway gate to discharge wintertime flows.

Scope of Project was to first stabilize tower, then improve seismic stability, replace the intake gates, and install a guard gate

Page 63: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Cellular cofferdam

Outlet tower

Page 64: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Winter comes early here

December 8, 2010

Page 65: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Work was able to continue despite cold and snow

Page 66: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

View inside Outlet Tower

Extreme danger posed by ice overhead from

leaking stoplogs.

Page 67: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Rebar and concrete damaged from winter flows.

June 3013

Page 68: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Eventually, the structure was competed, in 2015!

Which leads us to the next phase…..

Page 69: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Spillway Removal and

Replacement Once Intake was completed and functional,

spillway removal could start

Contractor reused sheetpiling from outlet cellular cofferdam to construct new cofferdam in front of spillway.

Cofferdam installed in December 2015 so that it would be in place come spring, when reservoir was filled.

New Outlet Tower acted as only spillway during

construction.

Page 70: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Being December, it wasn’t the most hospitable

condition for construction!

Page 71: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Sheet Piling being installed

Page 72: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

View of ongoing removal of cofferdam from intake

structure.

Page 73: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Not surprisingly, come the following spring, there

was a lot of seepage through the cofferdam!

550 gpm.

Page 74: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Subsequently, a second cofferdam and sheetpile

wall was constructed along with a sump to improve

seepage control at the site

Page 75: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

View of cofferdam with spillway fully removed

Page 76: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Once again, construction extended into December

Placing embankment fill around core wall

Page 77: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Blankets were placed on fill surface at night to

keep snow off and prevent freezing.

Page 78: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Snow was cleared off and blankets removed in

morning prior to fill placement.

Page 79: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Finished Spillway and closure embankment in

2017

Page 80: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Finished Spillway Chute

Page 81: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Takeaway Points

Short construction seasons mean that work must be done in multi-year stages. Detailed scheduling and planning ahead are critical.

Severe weather conditions can damage recently completed work. Protecting partially completed work from damage can prevent delays in construction schedule.

Tunneling work can be done year round. This makes building a combined power tunnel (or penstock) and construction access road attractive.

Page 82: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

Takeaway Points

Portable structures such as tents and canopies can help extend the construction seasons but may require dis/re-assembly for winter snow loading.

In Alaska, lack of access is as much a problem as the cold climate. Equipment and supplies must be barged or helicoptered in, making construction costs much higher and advanced planning for deliveries critical.

Page 83: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused

QUESTIONS?