Revision 0
Customer : PT GASPRO SENTRACO
Plant Site : SUBANG, WEST JAVA
Item Name : FUEL GAS SCRUBBER
Tag No. : FGS-01
MFG Serial No. : MF-2080
Job No. : S-14049
Drawing No. : MF-S14049-FGS-01-001
Year Built :
Rev Date Checked
Doc. No : MF-DS-S14049-FGS01-001
ENGINEERING DEPARTMENT
Prepared Approved
20-May-14 Issued for Approval0 MGY MJY4 AP
S-14049FGS-01
2014
PT MULTI FABRINDO GEMILANG
Description Page
ASME "U" STAMPED VESSEL
Client App'd
Per ASME Sect.VIII Div.1 2013 Code Application
DATA SHEET Sheet 1Job No.Tag No.
ENGINEERING DEPARTMENT
Revision
NO. LOADING REQUIREMENT
1 INTERNAL DESIGN PRESSURE
2 EXTERNAL DESIGN PRESSURE
3OPERATING INCLUDE THE ADDITIONAL PRESSURE DUETO STATIC HEAD OF LIQUID
4 WEIGHT OF THE VESSEL AND NORMAL CONTENTS UNDERTHE TEST CONDITIONS INCLUDE THE ADDITIONAL PRESSUREDUE TO STATIC HEAD OF LIQUID
5 SUPERIMPOSED STATIC REACTIONS FROM WEIGHT OF MOTOR
6 SUPERIMPOSED STATIC REACTIONS FROM WEIGHT OF MACHINERY
7 SUPERIMPOSED STATIC REACTIONS FROM WEIGHT OF OTHER VESSEL
8 SUPERIMPOSED STATIC REACTIONS FROM WEIGHT OF PIPING
9 SUPERIMPOSED STATIC REACTIONS FROM WEIGHT OF LINING
10 SUPERIMPOSED STATIC REACTIONS FROM WEIGHT OF INSULATION
11 THE ATTACHMENT OF INTERNALS
12 THE ATTACHMENT OF VESSEL SUPPORT (SKIRT, LUGS, ETC)
13 CYCLIC AND DYNAMIC REACTIONS DUE TO PRESSURE
14 CYCLIC AND DYNAMIC REACTIONS DUE TO THERMAL VARIATIONS
15 CYCLIC AND DYNAMIC REACTIONS DUE TO EQUIPMENT MOUNTEDON VESSEL
16 CYCLIC AND DYNAMIC REACTIONS DUE TO MECHANICAL LOADINGS
17 WIND REACTIONS
18 SNOW REACTIONS
19 SEISMIC REACTIONS
20 IMPACT REACTIONS SUCH AS THOSE DUE TO FLUID SHOCK
21 TEMPERATURE GRADIENTS AND DIFFERENTIAL THERMALEXPANSION
22 ABNORMAL PRESSURE, SUCH AS THOSE CAUSED BY DEFLAGRATION
WEIGHT OF THE VESSEL AND NORMAL CONTENTS UNDER
PT MULTI FABRINDO GEMILANG
Job No. S-14049 Vessel Loading Requirements 1Tag No. FGS-01 ASME Sect. VIII Div. 1 2013 Ed. Sheet 2
ENGINEERING DEPARTMENT
1
12 ASME VIII Div 1, 2013 Ed MATERIAL SPEC.3 Construction Category SA 516 Gr 704 SA 516 Gr 70/SA 1055 SA 106 Gr B6 Service HC Gas SA 516 Gr 707 Operating Condition SA 1058 Temperature 100 OF -9 Pressure 110 Psig SA 36
10 Design Condition SA 3611 Temperature 32 / 200 OF Note 312 Pressure 200 Psig 316 SS13 MAWP 260 Psig Not Required14 H.T Press.( 1.3 x MAWP.) 338 Psig Not Required15 Specific Gravity 0.55 Not Required16 Capacity 39.94 ft3 SS 31617 ID Vessel 30 in - Nut SS 31618 Length of Vessel (TL/WL) 90 in External Attachment SA 516 Gr 70/ SA 3619 Shell Thickness 0.394 in External - Bolt SA 193 B720 Head Thick (min.) 0.315 in - Nut SA 194 2H21 Corrosion Allowance 0.118 in Name Plate 304 SS22 Weld Joint Efficiencies Foundation Bolt / Nut SA 307 Gr B23 Shell Earthing Boss SA 3624 Head Material Impact Testing Req'd Not Required25 Non Destructive Testing26 Radiography27 Ultrasonic As per Code Type of Head 2 : 1 Ellipsoidal / Top Flange28 Magnetic Particle Type of Support Leg29 Dye Penetrant Platform / Ladder Not Required30 Post Weld Heat Treatment Manway Davit Required31 Insulation Earthing Boss Required32 Fire Proofing Litfing Lug Required33 External Painting Name Plate Required34 Primer Coat35 Intermediate Coat Empty 3387.4 lbs36 Top Coat Operating 3497.6 lbs37 Internal Painting Test 4518.4 lbs383940 NOTE :41 1. Vendor shall confirm all data lat location marked with (*)42 2. Vendor shall reponsible for detailed engineering of the vessel. Vendor to confirm that fabrication, inspection and testing43 shall follow the Codes and Standards44 3. Vendor shall provide weight information45 4. Manway to be supplied c/w davit, gasket, cover, bolt & nut.46 5. Part directly welded to shell / head474849505152535455
CONSTRUCTION
ESTIMATED WEIGHT
ASME Sect. VIII Div. 1 2013 Ed.
"U" Stamp
Vertical
Job No. S-14049 Vessel Loading Requirements RevisionTag No. FGS-01 Sheet 3
PARTShellHeadNozzle Neck (pipe / plate)Reinforcing Pad
OrientationDesign Code
CONSTRUCTION MATERIAL
DESIGN DATA
FlangeFittingSupportBase PlateGasketDemisterVortex BreakerInlet DeviceInternal AttachmentInternal - Bolt
N/AN/AN/AYesN/A
1.00
RT1
PT MULTI FABRINDO GEMILANG
N/APolyurethaneEpoxyZinc Silicate
1.00
PT MULTI FABRINDO GEMILANG ENGINEERING DEPARTMENT
1Sheet 4
QTY SIZE (in) RATING1 2" 150# Gas Inlet1 2" 150# Gas Outlet1 2" 150# Drain1 8" 150# Handhole c/w cover, gasket, bolt & nut
Job No. S-14049 Vessel Loading Requirements RevisionTag No. FGS-01 ASME Sect. VIII Div. 1 2013 Ed.
REMARKSSERVICENOZZLE LIST
WNRFWNRFWNRF
MARKN1N2N3H1
TYPE