Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
DATE OF NOTICE: December 9, 2016
COURTESY PUBLIC NOTICE
DEVELOPMENT SERVICES DEPARTMENT
SAP No. 24005875
The City of San Diego Development Services Department, as the Lead Agency circulated for a 45-day public review
period a draft EIR on the Town and Country project (Project No. 424475 / SCH No. 2015121066). At the conclusion
of the public review period, it was identified that Water System Analysis (Appendix K) was inadvertently omitted
from the distribution of the draft EIR. The Notice and associated documents have been placed on the City of San
Diego web-site at http://www.sandiego.gov/city-clerk/officialdocs/notices/index.shtml under the “California
Environmental Quality Act (CEQA) Notices & Documents” section. In addition, the Notice was also distributed to the
Central Library as well as the Mission Valley Branch Library.
This information is being provided as a courtesy for a 30-day public review period. Please contact E. Shearer-
Nguyen, Environmental Planner, City of San Diego Development Services Center, 1222 First Avenue, MS 501, San
Diego, CA 92101 or via e-mail to [email protected] with the Project Name and Number in the subject line.
Availability in Alternative Format: To request this Notice, the draft Environmental Impact Report, and/or
supporting documents in alternative format call the Development Services Department at 619-446-5460 or (800)
735-2929 (TEXT TELEPHONE).
Additional Information: For environmental review information, contact E. Shearer-Nguyen at (619) 446-5369. The
draft Environmental Impact Report and supporting documents may be reviewed, or purchased for the cost of
reproduction, at the Fifth floor of the Development Services Center. If you are interested in obtaining additional
copies of either a Compact Disk (CD), a hardcopy of the draft Environmental Impact Report, or the separately bound
technical appendices, they can be purchased for an additional cost. For information regarding public
meetings/hearings on this project, contact the Project Manager, Jeff A. Peterson, at (619) 446-5237. This
notice was published in the SAN DIEGO DAILY TRANSCRIPT and distributed on December 9, 2016.
Kerry M. Santoro
Deputy Director
Development Services Department
ATTACHMENTS: Affected Distribution List
Cover Letter (dated December 8, 2016)
Water System Analysis (Appendix K), May 4, 2016
Distribution:
FEDERAL GOVERNMENT
U.S. Fish and Wildlife Service (23)
STATE OF CALIFORNIA
Caltrans, District 11 (31)
California Department of Fish and Wildlife (32)
State Clearinghouse (46A)
California Transportation Commission (51)
California Department of Transportation (51A)
California Department of Transportation (51B)
Native American Heritage Commission (56)
CITY OF SAN DIEGO
Mayor’s Office (91)
Councilmember Lightner, District 1 (MS 10A)
Councilmember Harris, District 2 (MS 10A)
Councilmember Gloria, District 3 (MS 10A)
Councilmember Cole, District 4 (MS 10A)
Councilmember Kersey, District 5 (MS 10A)
Councilmember Zapf, District 6 (MS 10A)
Councilmember Sherman, District 7 (MS 10A)
Councilmember Alvarez, District 8 (MS 10A)
Councilmember Emerald, District 9 (MS 10A)
Development Services Department
EAS
Transportation
Code Enforcement Division
Engineering
Geology
Landscaping
Planning Review
Project Manager
Planning Department
Park and Recreation
Plan-Airport
Plan-Facilities Financing
Plan-Historic
Plan-Long Range Planning
Plan-MSCP
San Diego Police Department
San Diego Fire and Recue
Environmental Services Department
Transportation Development - DSD (78)
Development Coordination (78A)
Fire and Life Safety Services (79)
Library Department - Government Documents (81)
Central Library (81A)
Mission Valley Branch Library (81R)
Historical Resources Board (87)
Environmental Services (93A)
City Attorney (93C)
OTHER INTERESTED INDIVIDUALS/GROUPS
San Diego Association of Governments (108) Metropolitan Transit System (112)
San Diego Gas & Electric (114)
Metropolitan Transit System (115)
San Diego Unified School District (125)
Rancho Santa Ana Botonic Garden at Claremont (161)
The San Diego River Park Foundation (163)
The San Diego River Coalition (164)
Sierra Club (165)
San Diego Canyonlands (165A)
San Diego Natural History Museum (166)
San Diego Audubon Society (167)
San Diego Audubon Society (167A)
San Diego River Conservancy (168)
San Diego Tracking Team (187)
California Native Plant Society (170)
KEA Environmental Inc. (178)
Citizens Coordinate for Century III (179)
Endangered Habitats League (182A)
Carmen Lucas (206)
South Coastal Information Center (210)
San Diego History Center (211)
San Diego Archaeological Center (212)
Save Our Heritage Organisation (214)
Ron Christman (215)
Clint Linton (215B)
Frank Brown – Inter-Tribal Cultural Resources Council (216)
Camp Band of Mission Indians (217)
San Diego County Archaeological Society, Inc. (218)
Kumeyaay Cultural Heritage Preservation (223)
Kumeyaay Cultural Repatriation Committee (225)
Native American Distribution [Notice Only] (225A-S)
Mission Valley Center Association (328)
Friars Village HOA (328A)
Mary Johnson (328B)
Mission Valley Community Council (328C)
Union Tribune News (329)
Friends of Mission Valley Preserve (330B)
Mission Valley Planning Group (331)
General Manager, Fashion Valley (332)
Gary Akin - San Diego Gas & Electric (381)
The San Diego River Coalition (334)
Peter Casellini
Gideon, Law Office of Gideon Kracov
Cody Elliott, Adams Broadwell Joseph & Cardozo Francisco, CA 94090
Mark Polinsky
Tony LoPresti, Altshuler Berzon LLP
Rick Bates, UNTHERE Local 30
Jim Peugh, Conservation Chair, San Diego Audubon Society
Jesse Colorado Sanhuyser
1222 First Avenue, Mail Station 301
San Diego, CA 92101- 4101
T (619) 446-5000
sandiego.gov
December 8, 2016
State Clearinghouse and Affected Distribution
1400 Tenth Street
Sacramento, CA 95814
SUBJECT: Town and Country, (Project No. 424475 / SCH No. 2015121066)
To Whom It May Concern:
A draft Environmental Impact Report (EIR) was circulated on August 18, 2016 for a 45-day public
review period for the above referenced project. At the conclusion of the public comment period on
October 17, 2016, it was identified that Water System Analysis, dated May 4, 2016, (Appendix K)
technical report was inadvertently omitted from the distribution of the draft EIR. Although the
technical study was not attached, the data was accurately captured and summarized in the
appropriate draft EIR section. The inadvertent omission does not alter the analysis or the conclusion
of impacts.
In order to ensure that all interested parties who received a Notice of Availability of the draft EIR
have an opportunity to review the technical study, the City of San Diego has prepared a Notice of
Availability and is also formally submitting the technical study through the State Clearinghouse for a
30-day review period.
If you have any questions or comments, please do not hesitate to contact me directly at (619) 446-
5369.
Sincerely,
Elizabeth Shearer-Nguyen
Senior Planner
cc: Environmental File
Project File
Attachments: Affected Distribution List
Cover Letter (dated December 8, 2016)
Water System Analysis (Appendix K), May 4, 2016
Town & Country Project Appendices
Environmental Impact Report August 2016
APPENDIX K
WATER SYSTEM ANALYSIS
DEXTER WILSON ENGINEERING, INC.
WATER ● WASTEWATER ● RECYCLED WATER
CONSULTING ENGINEERS
2234 FARADAY AVENUE ● CARLSBAD, CA ● (760) 438-4422
WATER SYSTEM ANALYSIS
FOR THE
TOWN AND COUNTRY PROJECT
IN THE CITY OF SAN DIEGO
May 4, 2016
WATER SYSTEM ANALYSIS
FOR THE
TOWN AND COUNTRY PROJECT
IN THE CITY OF SAN DIEGO
May 4, 2016
Prepared by:
Dexter Wilson Engineering, Inc.
2234 Faraday A venue
Carlsbad, CA 92008
Job No. 556-010
DEXTER WILSON ENGINEERING, INC.
May 4, 2016
Fuscoe Engineering, Inc.
6390 Greenwich Dr.
Suite 200
San Diego, CA 92122
Attention: Nick Psyhogios, Project Manager
DEXTER S. WILSON, P.E.
ANDREW M. OVEN, P.E.
STEPHEN M. NIELSEN, P.E.
NATALIE J. FRASCHETTI, P.E.
556-010
Subject: Water System Analysis for the Town and Country Project in the City of San
Diego.
Introduction
This report provides a water system analysis for the Town and. Country project in the City
of San Diego. The project is located in Mission Valley directly north of Hotel Circle North
and directly east of Fashion Valley Road. Figure 1 provides a location map for the project.
The project encompasses a total of approximately 40 acres and the existing land is
currently composed of the Town and Country Resort, related amenities and parking. The
project proposes to redevelop a portion of the site to incorporate 840 high-density
residential units. Water service elevations on the project range from 28 feet to 35 feet
above mean sea level (AMSL).
2234 FARADAY AVENUE • CARLSBAD, CA 92008 • (760) 438-4422 • FAX (760) 438-0173
� Iwa::::::> c.,
w vi
i
FASHION -----.
VALLEY ROAD
HOTEL
CIRCLE N
HOTEL
CIRCLE S
PROJECT
LOCATION
DEXTER WILSON ENGINEERING, INC.
CONSULTING ENGINEERS
(760) 438-4422
�
N
I NOT TO SCALE
FIGURE 1
VICINllY MAP
TOWN AND COUNTRY
Nick Psyhogios May 4, 2016
Purpose of Study
The purpose of this study is to provide recommended water system improvements for the
Town and Country project. These improvements include modifications to some existing
onsite private water lines along with proposed improvements to the public water system to
allow adequate domestic and fire protection service to be provided to the project. This
report will verify that the recommended public improvements comply with the City of San
Diego Water Department water system design standards.
Study Area
The study area for this report is the boundary of the Town and Country project. The extent
of the existing water system which was incorporated into the analysis of the project site
was based on the existing 390 Zone distribution system that serves the area. Adjacent
water mains were included in the computer model to ensure that the dynamics of the
existing water system were analyzed as closely as possible without modeling the entire City
system.
Design Criteria and Water Demands
The design criteria utilized in the analysis of the Town and Country project water system
are in accordance with the current City of San Diego Water Department Capital
Improvements Program Guidelines and Standards, Book 2, Facility Design Guidelines,
Chapter 2, Water Demands and Service Criteria, November 2002. The design criteria
include a minimum static pressure of 65 pounds per square inch (psi) and maximum static
pressure of 120 psi. Residual pressure with all pipes open must be a minimum of 40 psi
and pressure loss at any location must not exceed 25 psi below static pressure. For one
source out of service, residual pressures at all locations must not be less than 40 psi below
static pressure.
DEXTER WILSON ENGINEERING, INC. PAGE 3
Nick Psyhogios May 4, 2016
For fire flow scenarios, minimum residual pressure must be 20 psi in the area of the fire.
The 25 psi and 40 psi maximum pressure drop requirements apply for the remaining
portions of the system for all pipes open and one source out of service, respectively. A key
criterion is that velocities in the water mains under maximum day demand plus fire flow
demands cannot exceed 15 feet per second.
Table 1 summarizes the water duty factors for each of the land uses encountered on the
project from the City Design Guidelines as well as the planning fire flow rates by land use
category. Residential water duty factors are based on a unit demand of 150 gpd per person.
Actual existing and projected water demands for this study are based on the more site
specific evaluation prepared by the City for this project in the April 2016 Water Supply
Assessment Report for the Town and Country Project.
TABLE 1
WATER DUTY FACTORS
Fire Flow
Land Use Density
Persons/DU Average Water
Requirements, DU/Acre Duty Factor
gpm
R-4 74-109 1.8 270 gpd/DU 3,000
R-4C >109 1.5 225 gpd/DU 3,000
Hotel -· .. 6555 gallons/net acre 4,000
As stated previously, the existing site is already developed and much of that development is
proposed to remain. Table 2 presents the existing water demands on the project site as well
as projected water demands for the proposed uses of the site and the projected net change
in average daily demand.
DEXTER WILSON ENGINEERING, INC. PAGE 4
Nick Psyhogios May 4, 2016
TABLE 2 EXISTING AND PROPOSED WATER DEMANDS
Density Land Use Quantity Demand Factor
du/ac
Existing
Hotel 26.7 ac ... ...
Total Existing Water Demand
Proposed
Multi-Family 840 du 176 gpd/du2 ...
Residential
Hotel 700 rooms -- 118.4 gpd/room2
Conference Hall 177,137 SF ... 0.0367 gpd/SF2
Restaurant 12,800 SF ... 1.192 gpd/SF2
Restaurant 250 people --·- 60 gpd/personz
Employee
Landscaping 649,044 SF ... 0.049 gpd/SF2
Total Proposed Water Demand
Increase in Demand
1 Based on actual data per April 2016 Water Supply Assessment Report2 Per April 2016 Water Supply Assessment Report
Water Demand,
_l!Dd
122,3001
122,300
147,840
82,880
6,503
15,262
15,000
31,853
299,338
177,038
As shown, the projected average daily water demand is 0.30 mgd. To convert average day
demands to maximum daily demands and peak hour demands, Figures 2-2 and 2-1 from the
Water Design Guide were used, respectively. Using the peaking curves for the
"Coastal/Downtown" area, maximum day and peak hour factors of 2.1 and 5.1 were used,
respectively. Thus, the projected maximum day demand for the project is 0.63 mgd (437
gpm) and the projected peak hour demand is 1.53 mgd (1,060 gpm).
DEXTER WILSON ENGINEERING, INC. PAGE 5
Nick Psyhogios May 4, 2016
Existing Water System
There are existing public water facilities directly adjacent to the Town and Country project
site. A 16-inch water main is located in Fashion Valley Road along the west side of the
project. An 8-inch water main connects to the 16-inch line and runs along Hotel Circle
Road and Camino De La Reina along the south side of the project. Both thel6-inch line and
8-inch line are supplied by the Alvarado 1st Pipeline which is a 30-inch transmission main
at a hydraulic gradeline of 390 feet. The existing public water facilities in the vicinity of
the project are shown on Figure 2.
In addition to the public water facilities serving the existing project site there are existing
private facilities on-site. These on-site facilities consist of 8-inch fire service connections to
the 16-inch line in Fashion Valley Road to supply onsite hydrants as well as a separate
private domestic system. In general, several of the existing private onsite water facilities
will stay in service and be expanded to serve the remaining and proposed non-residential
component of the project.
Water System Computer Model
The University of Kentucky KYPIPE computer program was used to conduct a hydraulic
model of the proposed water system within the study area. This computer program utilizes
the Hazen-Williams equation for determining headloss in pipes; the Hazen-Williams "C"
value used for all pipes is 120.
The model for this analysis includes existing public and proposed public lines in the area as
well as the existing private fire service that supplies the onsite hydrants. The existing
private fire line is included in the model in order to demonstrate the capability of the
proposed system to ensure adequate fire flow to the project. To simulate losses through the
backflow preventer where the private fire service connects to the public system, a minor
loss "K" value coefficient of 12. 7 was calculated and input into the model.
DEXTER WILSON ENGINEERING, INC. PAGE 6
..----,.-
6"'----�F�RfARSY0@----- I - '- 16" - - - ..!RIARs-RoAD --
---��--L---
----
� ------ I ------
---' -- I --------,---
( I _______ ..,
8" '
I I 8.. I ------
I� L---�
I
LEGEND I
to1I
_../ _1. ____ _
� --PROJECT BOUNDARY _1 __________ R�R_WALK DRJVL - -1
I I ,, I oo I
L------' '----
I
� I
r :5 - - - - - - - - - EXISTING PUBLIC WATER LINE I
� {390 PRESSURE ZONE)
� _ _ rt:_ _____ -� I I �-- -
! �i
;� l�!J-,--1
IO • II TOWN AND COUNTRY I 1' 1 PROJECT
� I 11 I 1 ------1 I ZI I0 $ 1
� �I rl x
r· I /.
� � N
I I /�� �- 11 �Qj /�
' � "' -...; - �ll I ,.;;. ��� -- I �
/..::..o I §ii--- L /��-.... a:: ..... - - - - I -----, _,.,
� �;:: ...... , 1---------8..-----1 ---------r--�� �-8;- C
tJ':A--::-. / HOTEL CIRCLE SOUTH &:,/ • I HOTEL CIRCLE NORTH \ INTERSTATE 8=----1.'=- -1. 30" t01 - -:::. :::. :::.- - - - - - - - - - _ / .-_J_ 30.. / ALVARADO 1ST
- - - ::::: /:i.. Jo• - ::: = == == = = - ==- - - , PIPELINE �� �� �----- h
8" -- :::: ::: /'* -- -- ---
I .. -
/ I
I I
I l
,--..J..---L-...11._
---,--_J
30" _ -./.-
---
DEXTER WILSON ENGINEERING, INC.
CONSUL TING ENGINEERS
(760) 438-4422
0
I 400
_, FEET
FIGURE 2
EXISTING
WATER SYSTEM
TOWN AND COUNTRY
Nick Psyhogios May 4, 2016
For the computer modeling it was assumed that the 30-inch transmission line would supply
the 16-inch and 8-inch lines in the vicinity of the property at a hydraulic grade line of 380
feet, 10 feet less than the maximum hydraulic grade line of the zone.
Water Service Overview
The project proposes to receive water through the existing 16-inch and 8-inch water mains
adjacent to the property. The existing 8-inch line in Camino de la Reina and Hotel Circle
North is proposed to be replaced with a 12-inch line and connected to an existing 10-inch
line in Camino de la Reina. These mains are within the 390 Zone and receive water from
the Alvarado 1st Pipeline, a 30-inch transmission main that runs south of the project. The
pad elevations on-site result in static pressures that are between 154 and 157 psi. These
static pressures exceed the City of San Diego's current criteria of 120 psi, but the site is
currently being served with similar static pressures.
To supply water to the new residential buildings, two connections are proposed to the
existing public system with back.flow preventers to supply the onsite private fire protection
system. Separate domestic service connections, with meters and back.flow preventers, will
be made to serve the residential parcels. The preliminary sizing of private domestic lines
has been provided in this report, but will need to be confirmed by the Building Department
once the product types and water fixture unit counts have been determined.
Water System Analysis and Results
Results of the computer hydraulic analysis are provided in Appendix A and Exhibit A
provides the corresponding node and pipe diagram. The system was modeled under
average day demand, peak hour demand, and maximum day demand plus fire flow
scenarios considered.
The results of the analysis indicate that the project can be served through the existing
16-inch line in Fashion Valley Road and replacement of an existing 8-inch line with a new
12-inch line in Hotel Circle South/Camino De La Reina. With the inclusion of the existing
private fire system, this analysis verifies that the site will have adequate fire flow for all
scenarios considered.
DEXTER WILSON ENGINEERING, INC. PAGE 8
Nick Psyhogios May 4, 2016
Conclusions and Recommendations
The following conclusions and recommendations are summarized based on the water
system analysis prepared for the Town and Country project.
1. The Town and Country project will be supplied from the 390 Zone system.
2. Static pressures will be higher than those deemed acceptable by the City of San
Diego Water Department Capital Improvements Program Guidelines and
Standards, however pressures will not exceed those already existing at the project
site.
3. Figure 3 provides the recommended water system layout for the project.
4. All new onsite water mains will be private and can be constructed of minimum PVC
Class 165 (DR 25) per A WW A C900 standards.
5. All building services will receive service pressures in excess of 80 psi and should
have individual pressure regulators to meet Uniform Plumbing Code criteria.
6. The sizing of private domestic lines and water meters to serve the residential parcels
will be determined by the Building Department based on the Water Meter Data
Card information provided for each building service.
7. If any water lines to be constructed by this development are metallic, a California
Licensed Corrosion Engineer will be required to perform a soil corrosivity study and
to design a Corrosion Control System.
Dexter Wilson Engineering, Inc.
Stephen M. Nielsen, P .E.
SMN:pjs
DEXTER WILSON ENGINEERING, INC. PAGE 9
m 0
(0
I (X)
I
0
0::
I w 0:: ::,
c., PROPOSED c.; FIRE � BACKFLOW � PREVENTER
I I I I
11
11
BAU.ROOM
�-=-==-=��-_J_�� -�����-::-:::-�:::::::�
a I �I
I I
REPLACE EXISTING 8" WATER LINE WllH 12" LINE
-----�--- 30" ----------- --------- ----------
-------
RES10ENTIAL PARCEL 4
PARKING S1RUC1URE
�
I
I��=�-�-��----�-----·----� -------------�/---------- ! ---
( N
I r----.------1 i I I I I I
0 200
�FEET
,I-
----' I I PROPOSED 6"
DOMESTIC LINE I
I ("
........__ CONNECT TO EXISTING 1 O" WATER LINE
-- PROPOSED DOMESTIC METER & BACKFLOW PREVENTER
LEGEND
-------- PROJECT BOUNDARY
EXISTING PUBLIC WATER LINE
EXISTING PRIVATE WATER LINE
EXISTING FIRE HYDRANT
PROPOSED PUBLIC WATER LINE
PROPOSED PRIVATE WATER LINE
PROPOSED FIRE HYDRANT
FIGURE 3 INTERSTATE 8
PROPOSED FIRE SYSTEM BACKFLOW PREVENTER
PROPOSED
WATER SYSTEM DEXTER WILSON ENGINEERING, INC.
CONSUL TING ENGINEERS
(760) 438-4422 TOWN AND COUNTRY
APPENDIX A
COMPUTER MODELING OUTPUT
The following conditions were modeled:
1. Average Day Demand
2. Peak Hour Demand
3. Maximum Day Demand plus 4,000 gpm Fire Flow Split at Nodes 24 and 52
Project: Town and Country Water System Analysis
Date: 01/28/16
Job Number: 556-010
Scenario: Average Day Demand
Node No. Node El. HGLZone
Ft. Ft.
4 30 380
8 25.5 379.99
12 32 379.99
14 32 379.99
16 30 379.99
18 32 379.94
20 31.S 379.86
24 33.5 379.85
28 35 379.99
36 31 379.97
40 24.5 379.96
44 28.5 379.95
46 28.S 379.99
48 35 379.99
52 28 379.99
56 35 379.99
Static P Model Run Delta P
psi P, Psi From Static
151.65 151.67 -0.02
153.60 153.61 -0.01
150.78 150.79 -0.01
150.78 150.79 -0.01
151.65 151.66 -0.01
150.78 150.77 0.01
151.00 150.96 0.04
150.13 150.09 0.04
149.48 149.49 -0.01
151.21 151.22 -0.01
154.03 154.03 0.00
152.30 152.29 0.01
152.30 152.31 -0.01
149.48 149.49 -0.01
152.51 152.53 -0.02
149.48 149.49 -0.01
Project: Town and Country Water System Analysis
Date: 01/28/16
Job Number: 556-010
Scenario: Peak Hour Demand
Node No. Node El. HGLZone
Ft. Ft.
4 30 380
8 25.5 379.8
12 32 379.74
14 32 379.74
16 30 379.71
18 32 378.57
20 31.5 376.97
24 33.5 376.77
28 35 379.74
36 31 379.43
40 24.5 379.21
44 28.5 378.92
46 28.5 379.74
48 35 379.74
52 28 379.74
56 35 379.74
Static P Model Run Delta P
psi P, Psi From Static
151.65 151.66 -0.01
153.60 153.53 0.07
150.78 150.69 0.09
150.78 150.69 0.09
151.65 151.54 0.11
150.78 150.18 0.60
151.00 149.7 1.30
150.13 148.75 1.38
149.48 149.39 0.09
151.21 150.99 0.22
154.03 153.71 0.32
152.30 151.85 0.45
152.30 152.2 0.10
149.48 149.39 0.09
152.51 152.42 0.09
149.48 149.39 0.09
Project: Town and Country Water System Analysis
Date: 01/28/16
Job Number: 556-010
Scenario: Maximum Day Demand 2000gpm Fire Flow (4000 gpm total) at Nodes 24 and 52
Node No. Node El. HGLZone Static P Model Run
Ft. Ft. psi P, Psi
4 30 379.95 151.65 151.64
8 25.5 377.37 153.60 152.47
12 32 375.93 150.78 149.04
14 32 344.59 150.78 135.46
16 30 375.12 151.65 149.55
18 32 339.75 150.78 133.36
20 31.5 260.66 151.00 99.3
24 33.5 227.74 150.13 84.17
28 35 335.97 149.48 130.42
36 31 376.02 151.21 149.51
40 24.5 374.5 154.03 151.66
44 28.5 372.92 152.30 149.25
46 28.5 340.49 152.30 135.2
48 35 331.23 149.48 128.37
52 28 299.49 152.51 117.65
56 35 299.49 149.48 114.61
Delta P
From Static
0.01
1.13
1.74
15.32
2.10
17.42
51.70
65.96
19.06
1.70
2.37
3.05
17.10
21.11
34.86
34.87
Project: Town and Country Water System Analysis
Date: 01/28/16
Job Number: 556-010
Scenario: Average Day Demand
Pipe No. Pipe Size
(Inches)
101 30
105 16
109 16
113 16
115 8
117 8
121 8
125 8
133 8
137 8
141 12
143 8
145 8
149 8
153 8
157 12
159 8
161 8
Model Run Model Run
Flow(gpm) Velocity (fps)
225.1 0.1
194.39 0.31
105.57 0.17
75.57 0.12
75.57 0.48
50.38 0.32
25.19 0.16
0 0
30.71 0.2
30.71 0.2
119.53 0.34
0 0
0 0
0 0
0 0
88.82 0.25
0 0
0 0
Project: Town and Country Water System Analysis
Date: 01/28/16
Job Number: 556-010
Scenario: Peak Hour Demand
Pipe No. Pipe Size
(inches)
101 30
105 16
109 16
113 16
115 8
117 8
121 8
125 8
133 8
137 8
141 12
143 8
145 8
149 8
153 8
157 12
159 8
161 8
Model Run Model Run
Flow(gpm) Velocity (fps)
1148.01 0.52
991.4 1.58
538.41 0.86
385.41 0.61
385.41 2.46
256.94 1.64
128.47 0.82
0 0
156.61 1
156.61 1
609.6 1.73
0 0
0 0
0 0
0 0
452.99 1.28
0 0
0 0
Project: Town and Country Water System Analysis
Date:01/28/16
Job Number: 556-010
Scenario: Maximum Day Demand 2000 gpm Fire Flow (4000 gpm total) at Nodes 24 and 52
Pipe No. Pipe Size Model Run Model Run
(inches) Flow(gpm) Velocity (fps)
101 30 4472.71 2.03
105 16 4026.17 6.42
109 16 2962.24 4.73
113 16 2158.7 3.44
115 8 2158.7 13.78
117 8 2105.8 13.44
121 8 2052.9 13.1
125 8 -740.54 -4.73
133 8 446.54 2.85
137 8 446.54 2.85
141 12 1510.48 4.28
143 8 1259.46 8.04
145 8 1259.46 8.04
149 8 2000 12.76
153 8 0 0
157 12 1063.93 3.02
159 8 740.54 4.73
161 8 740.54 4.73
Town and Country Redevelopment Project Public Water System Analysis
FLOWRATE IS EXPRESSED IN GPM AND PRESSURE IN PSIG
A SUMMARY OF THE ORIGINAL DATA FOLLOWS
PIPE NO. NODE NOS. LENGTH DIAMETER ROUGHNESS
(FEET) (INCHES)
101 0 4 100.0 30.0 120. 0
105 4 8 270.0 16.0 120. 0
109 8 12 265. 0 16.0 120.0
113 12 16 270.0 16.0 120.0
115 16 18 10.0 8.0 120.0
THERE IS A CHECK VALVE IN LINE NUMBER115
117 18 20 940.0 8.0 120.0
121 20 24 410.0 8.0 120.0
125 48 28 390.0 8.0 120.0
133 4 36 825.0 8.0 120.0
137 36 40 320.0 8.0 120.0
141 40 44 250.D 12.0 120.0
143 44 46 10.0 8.0 120.0
THERE IS A CHECK VALVE IN LINE NUMBER143
145 46 48 285.D 8.0 120.0
149 48 52 415.0 8.0 120.0
153 52 56 275.0 8.0 120.0
157 8 40 870.0 12.0 120.0
159 12 14 10.0 8.0 120.0
161 14 28 710.0 8.0 120.0
JUNCTION NUMBER DEMAND ELEVATION CONNECTING
4 .00 30.00 101 105
8 .00 25.50 105 109
12 30.00 32.00 109 113
14 .00 32.00 159 161
16 .00 30.00 113 115
18 25.19 32.00 115 117
20 25.19 31.50 117 121
24 25.19 33.50 121
28 .00 35.00 125 161
36 .00 31.00 133 137
40 .00 24.50 137 141
44 119. 53 28.50 141 143
46 .00 28.50 143 145
48 .00 35.00 125 145
52 .00 28.00 149 153
56 .00 35.00 153
Job No. 556-010 File Name: 556010Bl
January 28, 2016
MINOR LOSS K FIXED GRADE
.00 380.00
.00
.00
.00
11. 70
.00
.00
.00
.00
.00
.DO
32.00
.DO
.00
.00
.OD
90.00
.00
PIPES
133
157
159
157
149
OUTPUT SELECTION: ALL RESULTS ARE OUTPUT EACH PERIOD
THIS SYSTEM HAS 18 PIPES WITH 16 JUNCTIONS , 2 LOOPS AND 1 FGNS
Page 1 of 5
Town and Country Redevelopment Project Public Water System Analysis
Job No. 556-010 File Name: 556010Bl
January 28, 2016
THE RESULTS ARE OBTAINED AFTER 5 TRIALS WITH AN ACCURACY .00068
TOWN AND COUNTRY WATER ANALYSIS - AVERAGE DAY DEMAND
PIPE NO. NODE NOS. FLOWRATE HEAD LOSS PUMP HEAD MINOR LOSS VELOCITY
101 0 4 225.10 .00 .00 .00 .10
105 4 8 194.39 .01 .00 .00 .31
109 8 12 105.57 .00 .00 .00 .17
113 12 16 75.57 .00 .00 .00 .12
115 16 18 75.57 .00 .00 .04 .48
117 18 20 50.38 .08 .00 .00 .32
121 20 24 25.19 .01 .00 .00 .16
125 48 28 .00 .00 .00 .00 .00
133 4 36 30. 71 .03 .00 .00 .20
137 36 40 30. 71 .01 .00 .00 .20
141 40 44 119. 53 .01 .00 .00 .34
THE CHECK VALVE IN LINE NUMBER 143 IS CLOSED
145 46 48 .00 .00 .00 .00 .00
149 48 52 .00 .00 .00 .00 .00
153 52 56 .00 .00 .00 .00 .00
157 8 40 88.82 .03 .00 .00 .25
159 12 14 .00 .00 .00 .00 .00
161 14 28 .00 .00 .00 .00 .00
JUNCTION NUMBER DEMAND GRADE LINE ELEVATION PRESSURE
4 .00 380.00 30.00 151. 67
8 .00 379.99 25.50 153.61
12 30.00 379.99 32.00 150.79
14 .00 379.99 32.00 150.79
16 .00 379.99 30.00 151. 66
18 25.19 379.94 32.00 150.77
20 25.19 379.86 31.50 150.96
24 25.19 379.85 33.50 150.09
28 .00 379.99 35.00 149.49
36 .00 379.97 31. 00 151. 22
40 .00 379. 96 24.50 154.03
44 119.53 379.95 28.50 152.29
46 .00 379.99 28.50 152.31
48 .00 379.99 35.00 149.49
52 .00 379.99 28.00 152.53
56 .00 379.99 35.00 149.49
THE NET SYSTEM DEMAND 225.10
SUMMARY OF INFLOWS ( +) AND OUTFLOWS(-) FROM FIXED GRADE NODES
PIPE NUMBER FLOWRATE
101 225.10
THE NET FLOW INTO THE SYSTEM FROM FIXED GRADE NODES
Page 2 of 5
225.10
HL/1000 .00
.03
.01
.01
.18
.08
.02
.00
.03
.03
.06
.00
.00
.00
.03
.00
.00
Town and Country Redevelopment Project Public Water System Analysis
Job No. 556-010
File Name: 556010Bl
January 28, 2016
THE NET FLOW OUT OF THE SYSTEM INTO FIXED GRADE NODES .00
A SUMMARY OF CONDITIONS SPECIFIED FOR THE NEXT SIMULATION FOLLOWS
THE DEMANDS ARE CHANGED FROM ORIGINAL VALUES BY A FACTOR 5.10
THE RESULTS ARE OBTAINED AFTER 2 TRIALS WITH AN ACCURACY
PEAK HOUR DEMAND
.00000
PIPE NO. NODE NOS. FLOWRATE HEAD LOSS PUMP HEAD MINOR LOSS VELOCITY
101 0 4 1148.01 .00 .00 .00 .52
105 4 8 991. 40 .19 .00 .00 1.58
109 8 12 538.41 .06 .00 .00 .86
113 12 16 385.41 .03 .00 .00 . 61
115 16 18 385.41 .04 .00 1.10 2.46
117 18 20 256.94 1. 61 .00 .00 1. 64
121 20 24 128.47 .19 .00 .00 .82 125 48 28 .00 .00 .00 .00 .00
133 4 36 156.61 .56 .00 .00 1.00 137 36 40 156.61 .22 .00 .00 1. 00
141 40 44 609.60 .29 .00 .00 1. 73
THE CHECK VALVE IN LINE NUMBER 143 IS CLOSED
145 46 48 .00 .00 .00 .00 .00
149 48 52 .00 .00 .00 .00 .00
153 52 56 .00 .00 .00 .00 .00
157 8 40 452.99 .59 .00 .00 1.28
159 12 14 .00 .00 .00 .00 .00
161 14 28 .00 .00 .00 .00 .00
JUNCTION NUMBER DEMAND GRADE LINE ELEVATION PRESSURE
4 .00 380.00 30.00 151. 668 .00 379.80 25.50 153.53
12 153.00 379.74 32.00 150.69
14 .00 379.74 32.00 150.69
16 .00 379. 71 30.00 151'.54
18 128.47 378.57 32.00 150.18
20 128.47 376.97 31. 50 149.70
24 128.47 376.77 33.50 148.75
28 .00 379.74 35.00 149.39
36 .00 379.43 31. 00 150.99
40 .00 379.21 24.50 153.71
44 609.60 378.92 28.50 ,151.85
46 .00 379.74 28.50 152.20
48 .00 379.74 35.00 149.39
52 .00 379.74 28.00 152.42
56 .00 379.74 35.00 149.39
Page 3 of 5
HL/1000
.04 .71 .23
.12
3.62 1. 71
.47
.00
. 68
. 68
1.18
.00
.00 .00 . 68
.00
.00
Town and Country Redevelopment Project Public Water System Analysis
Job No. 556-010 File Name: 556010Bl
January 28, 2016
THE NET SYSTEM DEMAND 1148. 01
SUMMARY OF INFLOWS(+) AND OUTFLOWS(-) FROM FIXED GRADE NODES
PIPE NUMBER
101
FLOWRATE
1148. 01
THE NET FLOW INTO THE SYSTEM FROM FIXED GRADE NODES =
THE NET FLOW OUT OF THE SYSTEM INTO FIXED GRADE NODES
1148. 01
.00
A SUMMARY OF CONDITIONS SPECIFIED FOR THE NEXT SIMULATION FOLLOWS
THE DEMANDS ARE CHANGED FROM ORIGINAL VALUES BY A FACTOR 2.10
THE FOLLOWING SPECIFIC DEMAND CHANGES ARE MADE :
JUNCTION NUMBER
24
52
DEMAND
2052.90
2000.00
THE RESULTS ARE OBTAINED AFTER 6 TRIALS WITH AN ACCURACY = .00065
MAXIMUM DAY DEMAND PLUS 4,000 GPM FIRE FLOW SPKIT BETWEEN NODES 24 AND 52
PIPE NO. NODE NOS. FLOWRATE HEAD LOSS PUMP HEAD MINOR LOSS VELOCITY HL/1000
101 0 4 4472.71 .05 .00 .00 2.03 .54
105 4 8 4026.17 2.58 .00 .00 6.42 9.56 109 8 12 2962.24 1. 43 .00 .00 4.73 5.41
113 12 16 2158.70 .81 .00 .00 3.44 3.01 115 16 18 2158.70 .88 .00 34.48 13. 78 88.10
117 18 20 2105.80 79.10 .00 .00 13.44 84.15
121 20 24 2052.90 32.91 .00 .00 13.10 80.27
125 48 28 -740.54 -4.74 .00 .00 -4.73 -12.15
133 4 36 446.54 3.93 .00 .00 2.85 4.76
137 36 40 446.54 1. 52 .00 .00 2.85 4.76
141 40 44 1510.48 1. 58 .00 .00 4.28 6.31
143 44 46 1259.46 .32 .00 32.10 8.04 32.48
145 46 48 1259.46 9.26 .00 .00 8.04 32.48
149 48 52 2000.00 31. 74 .00 .00 12.76 76.49
153 52 56 .00 .00 .00 .00 .00 .00
157 8 40 1063.93 2.87 .00 .00 3.02 3.30
159 12 14 740.54 .12 .00 31.22 4.73 12.15
161 14 28 740.54 8.62 .00 .00 4.73 12.15
JUNCTION NUMBER DEMAND GRADE LINE ELEVATION PRESSURE
4 .00 379.95 30.00 151. 64
8 .00 377.37 25.50 152.47
12 63.00 375.93 32.00 149.04
14 .00 344.59 32.00 135.46
Page 4 of 5
Town and Country Redevelopment Project Job No. 556-010
Public Water System Analysis File Name: 556010Bl
January 28, 2016
16 .00 375.12 30.00 149.55 18 52.90 339.75 32.00 133. 3620 52.90 260.66 31. 50 99.3024 2052.90 227.74 33.50 84.1728 .00 335.97 35.00 130.4236 .00 376.02 31. 00 149.5140 .00 374.50 24.50 151. 6644 251. 01 372. 92 28.50 149.2546 .00 340.49 28.50 135.2048 .00 331.23 35.00 128.3752 2000.00 299.49 28.00 117. 6556 .00 299.49 35.00 114. 61
THE NET SYSTEM DEMAND = 4472.71
SUMMARY OF INFLOWS(+) AND OUTFLOWS(-) FROM FIXED GRADE NODES
PIPE NUMBER 101
FLOWRATE 4472. 71
THE NET FLOW INTO THE SYSTEM FROM FIXED GRADE NODES = THE NET FLOW OUT OF THE SYSTEM INTO FIXED GRADE NODES
Page 5 of 5
4472.71 .00
I:,
<( ...J
m 0
(0 -I
co N I
0
0
0 (0 I{) I{)
(.) F 0:: <(
.-
PROPOSED FIRE SYSTEM
BACKFLOW PREVENlER
--, ----/
--------
/ �@JI I x� 1
,---------
___ J. ----
/ © Lu REPLACE EXISTING s•
/ . _ l EX 30• _L,© WAlER LINE WllH 12• LINE
-Jt--- ---:::=====- J 101 I�= 4--- EX
� � ��-----�30" �---� ��--
--- ---- ,/' I
- --
I
I
/
I
I
I
)
- ---
PROPOSED DOMESTIC
SYSlEM BACKFLOW
PREVENlER
PROPOSED FIRE BACKFLOW PREVENlER
INTERSTATE 8
--.....::
'-:: '-::
� ------
L---
IXXI
----1
LEGEND
250
PROJECT BOUNDARY
EXISTING PUBLIC WATER UN �---·
EXISTING PRIVATE WATER LINE
EXISTING FIRE HYDRANT
PROPOSED PUBLIC WATER LINE
PROPOSED PRIVATE WATER LINE
PROPOSED FIRE HYDRANT
COMPUTER MODEL NODE
EXHIBIT A
PROPOSED WATER
NODE AND PIPE DIAGRAM DEXTER WILSON ENGINEERING, INC.
CONSUL TING ENGINEERS (760) 438-4422 TOWN AND COUNTRY