21CN Migration process overview. Dave D’Arcy & Jim Feenan BT Wholesale. The dates and other information about BT's 21CN programme in this presentation are based on the best information currently available. As in any programme of this size and complexity, they may be subject to change. - PowerPoint PPT Presentation
Citation preview
1
21CN Migration process overview
Dave D’Arcy & Jim Feenan
BT Wholesale
The dates and other information about BT's 21CN programme in this presentation are based on the best information currently available. As in any programme of this size and complexity, they may be subject to change
2
Introduction
• The purpose of this presentation is to explain the process of migration to 21CN:– Testing activities across the programme.
– What happens before, during and after each migration phase.
– Quality gate process and role of the Migration Control Centre (MCC).
– Migration into business as usual.
– Fallback and emergency & critical services.
• The intended audience is:– Communication providers (CPs) and resellers.
3
What’s been done to date?
Consult21 - ensure industry is aware of the 21CN vision and BT’s progress towards it.
Proof of process - consultation, engagement, transparency.
Testing - lab tests.
- test calls.
- CPE compatibility tests.
Pre-migration work – infrastructure, products.
switched-on – the industry-wide, non-commercial campaign to communicate about the process of migration.
….and the migration has started!
4
Pathfinder migration in south Wales
Pontypridd
Cowbridge
Wick
Llantwit MajorSt Athan
Bonvilston
Rhoose
Barry Sully
PencoedLlantrisant
Peterston-S-Ely
Cardiff
Culverhouse
DinasPowys
Porthcawl
Pentyrch
Tonyrefail
OgmoreValley
Pontycymmer
Maesteg
Aberkenfig
Bridgend
Southerndown
TreorchyFerndale
Kenfig Hill
NewtownLlantwit
Llanrumney
RoathLlandaff
Radyr
Taffs Well
Nelson
Porth
Tonypandy
Mountain Ash
Caerphilly
Treforest
Llanishen
Whitchurch
Hengoed
BargoedBedlinog
Ynysowen
Treharris
Abercynon
Ynysybwl
Senghenydd
Penarth
Llanedeyrn
end user migration boundary
5
Customer migration is underway
• The first customer migrations began on 28th November 06 in Wick, near Cardiff.
• The principle of building up gradually, ensuring infrastructure and full testing at each stage, is supported by industry.
• Customers in Cardiff, Bridgend and the Pontypridd area will be the next to have their services transferred.
• By the end of 2007, around 350,000 lines in south Wales are expected to have been migrated to the new infrastructure.
• Migration will be underway in all regions of the UK during 2008.
• By the end of the decade 21CN migration will be substantially complete.
• Customer experience is key to success.
6
The many facets of testing• Proof of Concept
• Vendors testing– Conformance Testing (CT), Multi-Vendor CT (MVCT) and
Network Integration Testing (NIT)
• Operational Support Systems (OSS) testing– Integration Verification & Validation Testing (IVV&T),
end-to-end OSS testing
• Infrastructure/network testing– NIT and First Office Application (FOA)
• Service testing– User & Live Acceptance Testing (UAT/LAT), Service FOA
(SFOA), Consult21 Conformance Testing Working Group, Experience Development Centre (EDC), CP test facility Swansea
• Transfer engineering (TE)
• Test tools and test automation
100,000s
10sTest complexity
Test numbers
7
Lab Testing
• Network Integration Testing (NIT) and Verification and Validation (IVVT)– 600,000 tests (100,000) since November 2006.– 9,500 trouble reports cleared.– Test labs at Adastral and Swansea (BT) and Solihull, Guilford and Reading (vendors
with BT).– Test model equivalent to 20% UK inner core capacity.
• Customer Premise Equipment (CPE)– Hundreds of CPE tested in the LAB and Swansea CP test facility. – Industry invited to offer CPE for testing.– Results published in open forum to industry via Consult21 test database.
• Test management & automation– Central management of all test cases.– Audit trail of test configuration.– Database of test results.– Test planning and statistics on test execution.
8
Infrastructure FOA
FOA Approach
Core
Core
Metro
Metro
MSAN
MSANData Centre
DC
Tx FOA
IP FOA
V MSAN FOA
BB MSAN FOA
Voice Service FOA1
Broadband Service FOA1
BRAS FOA
BRAS
CS FOA
CS
Core
Core
Metro
Metro
Transfer Engineering FOA1
OperationalTesting
Data services FOA1
BRAS Broadband Remote Access Server
MSAN Multi Service Access Node
FOA First Office Application
IP Internet Protocol
DC Data Centre
CS Call Server
Tx Transmission
V Voice
BB Broadband
Element Managers and OSS
9
Activity schedule timeline example (Taken from Broadband) Scenario Activity Schedule - Fulfilment:
OSS – Integration & Initiation
Provide – Mixed Products
Provide – BT Trial End-Users
Home Movers – Incl. Sim. Provides
Modify
Cease
Migration
Management Information Systems
BTW End to End
Forced Failure
Billing
Customer Reporting
c 150 Plus Scenarios
Time
10
PHASE 1Proof of Concept
Trials / Lab Testing
PHASE 2 Out of Service
Trials(FOA1)
PHASE 3In Service /
Live Trials(Pathfinder / FOA2)
• Proving the manual/automated methods for preparing the frame for TE.
• Producing quality procedures.
• Testing the synthetics used in modelling resources.
• Assessing the impacts on customer service.
• Progressively introducing the testing and trialling of Voice, Broadband and ISDN, migration methodologies.
• Use of business scenarios / test cases to provide end-to-end testing of migration.
TE trials and testing, three phased approach
11
Timetable update: South Wales
Apr/May/June 07 July/Aug/Sept 07 Oct/Nov/Dec 07 Jan to June 08
Wick andBedlinog for
voice (non ISDN)
Migration of voice (non ISDN) on
next 12 exchanges
(58,000 lines)
Migration of voice (non ISDN) on
next 55 exchanges
(290,000 lines)
BroadbandMigration trial
in West Midlands
July to Dec 08
South Wales Industry review period
ISDN2 & 30Migrations
ISDN Trials
12
Timetable update: Overall programme
First stage of migration for POTS
(South Wales)
2007/08* 2008/09* 2009/10* 2010/11* 2011/12*
National Migration Begins
(Broadband lines initially)
National Migration(Voice, Broadband and ISDN)
National migration
(voice, non
ISDN)
New enhanced testing capability available for industry service testing
ISDN 2and
ISDN 30(South Wales)
* Periods indicated are financial years, April to March.
13
Our goal = seamless customer transfer to 21CN
Generic migration process
Transfer completion
Configure and verify
Prepare the network
On the night migration Monitor
Frames Cleansed
Data Audited
Frame preparation
From 36 to 12 weeks
prior
Connect to 21CN
Data Extracted
Transform
Load
Pre-transfer Testing
From 12 weeks prior
Cutover to 21CN
Data Activation
Call Re Routing to
21CN
On the night
Post transfer tests &
monitoring
Up to 7 days after
14
21CN – Principles of end user migration• Smooth switchover planned
– Designed & scheduled in consultation with industry.
– Every effort made to minimise end user disruption.
• Acting responsibly
– Migration control centre will manage transfer process.
– Special measures for emergency and critical services.
– Established incident procedures come into play for unforeseen circumstances.
15
Migration Command and Control structure
End Customers
Communication ProvidersEnd Customer Contact Centre
(Communications Working Group) BTW Service Centres
Migration Control Centre Network Management
CentreCore Business Functions:• Pre-Migration Management• Migration Management• Schedule Change Management• Fault Management• Fallback Management
• Alarm Monitoring
• 2nd / 3rd line fault support
INF
OR
MA
TIO
N F
LO
W
16
21CN migration process summary
• Migration Timetable
• The preparation of the network
• Testing
• Configure and verify
• On the night migration via the MCC to deliver and execute
• Monitoring
• Transfer completion
• Customer experience at the forefront of all we do
• Engagement, open and transparent
17 http://21cntestingdb.bt.com/
18
WEBCALLS Update
18 April Product retirements
24 April 21CN overview
2 May Migration process
22 May CPE compatibility testing programme
31 May Switched-on communications campaign
27 Sept Migration portal overview
19
SOURCES OF FURTHER INFORMATION
• Information and support for communication providers on the 21CN programme:
http://www.btwholesale.com/consult21
• The independent public information website covering the process of migration:
http://www.switchedonuk.org
• For general information about BT’s 21CN programme go to:
http://www.btplc.com/21CN/
20
Answers
Questions