77
REGION 8 BUNDLED BRIDGES (CONTRACT 3) PIN 89A1.DB, Contract D900025 DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS Draft February 5, 2015

DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · 2015. 2. 5. · PART 3 PROJECT REQUIREMENTS Draft February 5, 2015. This Page is intentionally left blank. New York State

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

  • REGION 8 BUNDLED BRIDGES(CONTRACT 3)

    PIN 89A1.DB, Contract D900025

    DB CONTRACT DOCUMENTS

    PART 3PROJECT REQUIREMENTS

    Draft February 5, 2015

  • This Page is intentionally left blank

  • New York State Department of Transportation

    Superstructure and Bridge Replacement in R8 i Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    Table of Contents

    SECTION 1 GENERAL ........................................................................................................11.1 PURPOSE .................................................................................................................................. 11.2 SCOPE ...................................................................................................................................... 11.3 SCOPE OF WORK – MAJOR ITEMS ................................................................................................ 21.4 COORDINATION WITH OTHER PROJECTS ....................................................................................... 31.5 THIRD PARTY AGREEMENTS (NON-UTILITY) .................................................................................. 31.6 DESIGN CODES AND MANUALS..................................................................................................... 31.7 REQUIREMENTS ......................................................................................................................... 71.8 DELIVERABLES ........................................................................................................................... 81.9 INDICATIVE PLANS ...................................................................................................................... 81.10 DIRECTIVE PLANS ....................................................................................................................... 81.11 CADD ...................................................................................................................................... 81.12 SCHEDULE OF PROJECT COMPLETION .......................................................................................... 81.13 WORK PAYMENT SCHEDULES ...................................................................................................... 81.14 INTERIM COMPLETION MILESTONES ........................................................................................... 12

    SECTION 2 PROJECT MANAGEMENT ............................................................................132.1 DESIGN-BUILDER’S ROLE .......................................................................................................... 132.2 DESIGN-BUILDER’S KEY PERSONNEL .......................................................................................... 132.3 MANAGEMENT PLANS AND SCHEDULES ....................................................................................... 15

    2.3.1 Management Plans and Schedule Requirements .......................................................... 152.3.2 Workforce Participation Plan ......................................................................................... 152.3.3 Safety Plan ................................................................................................................... 152.3.4 Quality Control Plan ...................................................................................................... 152.3.5 Overall Design-Build Team Organizational Plan ............................................................ 162.3.6 Design Management Plan ............................................................................................. 162.3.7 Construction Management Plan .................................................................................... 16

    2.4 BASELINE PROGRESS SCHEDULE ............................................................................................... 162.5 MEETINGS ............................................................................................................................... 172.6 COMPUTER AND NETWORKING REQUIREMENTS ........................................................................... 172.7 DEPARTMENT’S CONSULTATION AND WRITTEN COMMENTS ........................................................... 182.8 PROJECT WISE ........................................................................................................................ 18

    SECTION 3 ENVIRONMENTAL COMPLIANCE ................................................................193.1 SCOPE .................................................................................................................................... 193.2 ENVIRONMENTAL APPROVALS ........................................................................................... 193.3 REQUIREMENTS ....................................................................................................................... 21

    3.3.1 General ........................................................................................................................ 213.3.2 Environmental Plans ..................................................................................................... 233.3.3 Soil Erosion and Water Pollution Control ....................................................................... 243.3.4 Asbestos-Containing Materials ..................................................................................... 243.3.5 Inaccessible/Assumed ACMs ........................................................................................ 253.3.6 Environmental Plan Deliverables .................................................................................. 25

    3.4 THREATENED AND ENDANGERED SPECIES COORDINATION .......................................... 26

    SECTION 4 GENERAL PROJECT SCOPE OF WORK .....................................................284.1 SCOPE .................................................................................................................................... 284.2 STANDARDS ............................................................................................................................. 284.3 REQUIREMENTS ....................................................................................................................... 28

    4.3.1 Field Office ................................................................................................................... 28

  • New York State Department of Transportation

    Superstructure and Bridge Replacement in R8 ii Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    4.3.2 Construction Vehicles on Bridge ................................................................................... 294.3.3 Salvage ........................................................................................................................ 294.3.4 Surplus Quantity ........................................................................................................... 294.3.5 Sidewalk Plowing Coordination During Winter Shutdown .............................................. 29

    SECTION 5 SURVEYING AND GIS ...................................................................................305.1 SCOPE .................................................................................................................................... 305.2 STANDARDS ............................................................................................................................. 305.3 REQUIREMENTS ....................................................................................................................... 30

    5.3.1 Project Survey Control .................................................................................................. 305.3.2 Department-supplied Data ............................................................................................ 305.3.3 Survey Reports, Records and Maps.............................................................................. 305.3.4 Permanent Survey Markers .......................................................................................... 31

    5.4 SURVEYING AND GIS DELIVERABLES .......................................................................................... 31

    SECTION 6 RIGHT-OF-WAY .............................................................................................326.1 SCOPE .................................................................................................................................... 326.2 REQUIREMENTS ....................................................................................................................... 32

    6.2.1 Right-of-Way Fencing ................................................................................................... 326.2.2 Property Interests Identified by the Design-Builder for its Convenience ......................... 32

    SECTION 7 PUBLIC INVOLVEMENT ................................................................................337.1 SCOPE .................................................................................................................................. 337.2 STANDARDS ......................................................................................................................... 337.3 REQUIREMENTS .................................................................................................................. 33

    7.3.1 Public Notification Plan, Stakeholder Coordination Meetings and General OutreachActivities 337.3.2 Public Notification Plans: .............................................................................................. 337.3.3 Stakeholder Coordination Meetings: ............................................................................. 347.3.4 General Outreach Activities: ......................................................................................... 347.3.5 Media Relations ............................................................................................................ 36

    SECTION 8 UTILITIES .......................................................................................................378.1 SCOPE .................................................................................................................................... 378.2 STANDARDS ............................................................................................................................. 378.3 GENERAL REQUIREMENTS ......................................................................................................... 37

    8.3.1 Utility Relocation Agreements ....................................................................................... 388.3.2 Other Utility Conflicts .................................................................................................... 38

    SECTION 9 GEOTECHNICS ..............................................................................................399.1 SCOPE .................................................................................................................................... 399.2 STANDARDS ............................................................................................................................. 399.3 DESIGN REQUIREMENTS ........................................................................................................... 39

    9.3.1 Geotechnical Work Plan ............................................................................................... 399.3.2 Geotechnical Investigations .......................................................................................... 409.3.3 Minimum Number of Borings......................................................................................... 409.3.4 Subsurface Investigation Records ................................................................................. 409.3.5 Software Requirements ................................................................................................ 409.3.6 Geotechnical Data Report ............................................................................................. 409.3.7 Retaining Walls ............................................................................................................ 419.3.8 Geotechnical Instrumentation & Construction Monitoring .............................................. 419.3.9 Slope Stability............................................................................................................... 419.3.10 Rock Slope Stability ...................................................................................................... 429.3.11 Temporary Works ......................................................................................................... 42

    9.4 CONSTRUCTION REQUIREMENTS ................................................................................................ 429.4.1 Dewatering and Groundwater Control ........................................................................... 42

  • New York State Department of Transportation

    Superstructure and Bridge Replacement in R8 iii Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    9.4.2 Deep Foundations ........................................................................................................ 429.4.3 Soil and Rock Excavations and Embankments.............................................................. 429.4.4 Condition Surveys ........................................................................................................ 42

    9.5 DELIVERABLES ......................................................................................................................... 43

    SECTION 10 STRUCTURES ...............................................................................................4410.1 SCOPE .................................................................................................................................... 4410.2 STANDARDS ............................................................................................................................. 4410.3 DESIGN REQUIREMENTS ......................................................................................................... 44

    10.3.1 Components ................................................................................................................. 4510.3.2 Specific Aesthetic Requirements for BIN 5500969 ........................................................ 48

    10.4 DEMOLITION REQUIREMENTS ............................................................................................ 4810.4.1 Scope ........................................................................................................................... 4810.4.2 Standards ..................................................................................................................... 49

    10.5 CONSTRUCTION REQUIREMENTS ...................................................................................... 4910.6 DELIVERABLES ......................................................................................................................... 49

    SECTION 11 LANDSCAPE ARCHITECTURE .....................................................................5111.1 SCOPE .................................................................................................................................... 5111.2 STANDARDS ............................................................................................................................. 5111.3 GENERAL LANDSCAPE DEVELOPMENT ........................................................................................ 51

    11.3.1 Existing Vegetation ....................................................................................................... 5111.3.2 Tree Replacement Factors ........................................................................................... 5111.3.3 Replacement Locations ................................................................................................ 5211.3.4 Proposed Planting ........................................................................................................ 5211.3.5 Location Specific Landscape Development Concerns ................................................... 52

    SECTION 12 SIGNAGE, PAVEMENT MARKING AND SIGNALS.......................................5312.1 SCOPE .................................................................................................................................... 5312.2 STANDARDS ............................................................................................................................. 5312.3 REQUIREMENTS ....................................................................................................................... 53

    12.3.1 Design Requirements ................................................................................................... 5312.3.2 Construction Requirements .......................................................................................... 54

    12.4 DELIVERABLES ......................................................................................................................... 54

    SECTION 13 LIGHTING .......................................................................................................5513.1 SPECIFIC LIGHTING REQUIREMENTS FOR BIN 1040550 ................................................... 55

    13.1.1 Scope ........................................................................................................................... 55

    SECTION 14 INTELLIGENT TRANSPORTATION SYSTEMS (ITS) ....................................5614.1 SCOPE .................................................................................................................................... 56

    SECTION 15 WORK ZONE TRAFFIC CONTROL AND ACCESS .......................................5715.1 SCOPE .................................................................................................................................... 5715.2 STANDARDS ............................................................................................................................. 5715.3 REQUIREMENTS ....................................................................................................................... 57

    15.3.1 General Requirements .................................................................................................. 5715.3.2 Work Zone Traffic Control Plan ..................................................................................... 5815.3.3 General Restrictions ..................................................................................................... 5915.3.4 Access to Commercial Properties and Driveways ......................................................... 6015.3.5 Closure Restrictions ..................................................................................................... 6015.3.6 Minimum Lane Widths during Construction ................................................................... 6015.3.7 Portable Variable Message Signs ................................................................................. 6015.3.8 Temporary and Interim Pavement Markings .................................................................. 6115.3.9 Coordination with Regional Traffic Management Center ................................................ 6115.3.10 Emergency Response and Transportation Management Plans ..................................... 61

  • New York State Department of Transportation

    Superstructure and Bridge Replacement in R8 iv Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    SECTION 16 PAVEMENT DESIGN AND CONSTRUCTION ...............................................6216.1 SCOPE .................................................................................................................................... 6216.2 STANDARDS ............................................................................................................................. 6216.3 REQUIREMENTS ....................................................................................................................... 62

    16.3.1 Full Depth Reconstruction ............................................................................................. 6216.3.2 Milled and Resurfaced Roadways ................................................................................. 6316.3.3 Utility Trench Restoration.............................................................................................. 63

    SECTION 17 DRAINAGE AND STORMWATER .................................................................6417.1 SCOPE .................................................................................................................................... 6417.2 STANDARDS ............................................................................................................................. 6417.3 REQUIREMENTS ....................................................................................................................... 64

    17.3.1 General ........................................................................................................................ 6417.3.2 Drainage Report ........................................................................................................... 6417.3.3 Connections to Existing Systems .................................................................................. 6517.3.4 Spill Management ......................................................................................................... 65

    17.4 DELIVERABLES ......................................................................................................................... 65

    SECTION 18 HIGHWAY DESIGN ........................................................................................6618.1 SCOPE .................................................................................................................................... 6618.2 STANDARDS ............................................................................................................................. 6618.3 REQUIREMENTS ....................................................................................................................... 66

    18.3.1 General ........................................................................................................................ 6618.3.2 Design Requirements ................................................................................................... 6618.3.3 Barrier Systems and Impact Attenuators ....................................................................... 6718.3.4 Clear zone .................................................................................................................... 68

    18.4 DESIGN EXCEPTIONS AND NON-STANDARD FEATURES ................................................................. 68

    SECTION 19 STANDARDS .................................................................................................6919.1 GENERAL REQUIREMENTS ......................................................................................................... 6919.2 SPECIFIC REQUIREMENTS ......................................................................................................... 69

    SECTION 20 SECURITY ......................................................................................................70

  • This Page is intentionally left blank

  • New York State Department of Transportation

    Region 8 Bundled Bridges 1 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    SECTION 1 GENERAL

    1.1 PURPOSE

    This Part 3 establishes the basic Requirements of the Project. The Contract Documents,NYSDOT standard drawings, manuals and specifications, and the referenced Design Codesand Manuals shall be followed for the preparation of design and construction documents andthe execution of the Work. Any proposed deviation from the Contract requirements or NYSDOTstandards shall be submitted to the Department’s Design Quality Assurance Engineer forreview, and shall require the submission of a Non-conformance Report.

    All designs shall be prepared in U.S. Customary units. The Design-Builder shall be responsiblefor converting any mapping, plans, etc. into U.S. Customary units as necessary for thecompletion of the Project.

    The Design shall be in conformance with the latest edition of the New York State Department ofTransportation, Standard Specifications, with addenda, issued by the Office of Engineering,current as of the date of Proposal submission, except as noted in these Contract Documents.

    The Design-Builder shall prepare Project Specifications for the Project, for Work Items notcovered by the NYSDOT Standard Specifications or applicable Special Specifications, and shallprepare Design Plans for the Project in accordance with NYSDOT standards for general contentand format, and in accordance with the Contract.

    Deviations may be proposed within the framework of these Design Requirements to meet therequirements of a particular situation. However, any deviation, discrepancy, or unusual solutionrequires review by the Department’s Design Quality Assurance Engineer before it can beincluded in the design. It is the responsibility of the Design-Builder to identify, explain, andjustify any deviation from the established criteria to the Department’s Design Quality AssuranceEngineer.

    The Design-Builder shall prepare and submit a Non-conformance Report (in accordance withthe provisions of DB §105-16) for any Work performed that does not conform to the Contractrequirements and for any deviations from NYSDOT standards.

    1.2 SCOPE

    The Design-Builder shall be responsible for complying with all terms of the Contract Documents.The Design-Builder shall review and understand all terms and conditions of the ContractDocuments prior to the commencement of the Project and shall be responsible for determiningthe full Scope of the Project by undertaking a thorough examination of the Contract Documents,the Reference Documents and the Project Site.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 2 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    1.3 SCOPE OF WORK – MAJOR ITEMS

    The scope of work for the Project includes but is not limited to the following items:

    A) Superstructure replacement and abutment and pier rehabilitation for the following bridge:

    BIN County Municipality Carried Crossed

    1040550 Orange Village of Washingtonville Route 208 Moodna Creek

    Work at the structure in the above table shall include but not be limited to the following:

    a) Removal of the existing superstructure;

    b) Modifications to the substructures as necessary to accommodate the newsuperstructure;

    c) Construction of new superstructure and approach slabs;

    d) Approach roadway reconstruction necessary to connect existing roadway to new bridgeincluding curbs and sidewalks;

    e) Development of a WZTC plan;

    f) Remediation and disposal of possible asbestos containing materials;

    g) Utility work and involvement.

    B) Full Replacement of the following bridges:

    BIN County Municipality Carried Crossed

    5500969 WestchesterVillage/

    Town of Mount Kisco andTown of Bedford

    Saw Mill River Parkway(Route 987D) Kisco Avenue

    5500870 Westchester Village of Pleasantville Saw Mill River Parkway(Route 987D Saw Mill River

    5500890 Westchester Village of Pleasantville Saw Mill River Parkway(Route 987D Saw Mill River

    5521680 Westchester City of New Rochelle EHPA DPW Road Hutchinson River

    Work at each of the structures in the above table shall include but not be limited to the following:

    a) Removal of the existing substructures and superstructures;

    b) Replacement of the existing bridges; including new foundations, substructures,superstructures and approach slabs;

    c) Approach roadway reconstruction necessary to connect existing roadways to the new

    bridges;

    d) Construction of speed change lanes (BIN 5500969);

    e) Design and construction of a noise barrier (BIN 5500969);

    f) Reconstruction of median (BIN 5500969);

  • New York State Department of Transportation

    Region 8 Bundled Bridges 3 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    g) Development of a WZTC plan for each site;

    h) Remediation and disposal of asbestos containing materials;

    i) Remediation and disposal of lead based paint (BIN 5500969);

    j) Removal of silt bar (BIN 5521680);

    k) Utility work and involvement.

    C) Bridge rehabilitation (pipe lining) for the following bridge:

    BIN County Municipality Carried Crossed

    1005080 Westchester Town of Cortlandt Route 9 Dickey Brook

    Work at the structure in the above table shall include but not be limited to the following:

    a) Lining of existing pipes;

    b) Removal of vegetation and installation of rip-rap on the upstream and downstream endsof the pipes.

    1.4 COORDINATION WITH OTHER PROJECTS

    The table below lists the projects currently scheduled to occur within or adjacent to the Contractlimits prior to the Project Completion Date.

    Sponsor Project Location

    NYSDOT8811.97 Maintenance

    by Contract BridgeRegion Wide

    BINs 5502091 and 5502092 Route 987G(Taconic State Parkway) over Route 987D SawMill River Parkway and Ramps

    WestchesterCounty

    Department ofPublic Works and

    Transportation

    13-510

    Pleasantville Road paving project (traversingboth Briarcliff Manor and Pleasantville) is fromSouth State Road to Bedford Roard and fromNorth State Road to the Ossining Line. Thebridge (BIN 3348030) carrying PleasantvilleRoad over the Pocantico River will also berehabilitated.

    1.5 THIRD PARTY AGREEMENTS (NON-UTILITY)

    No Third Party Agreements have been developed in connection with this Project.

    For information regarding Preliminary DB Utility Work Agreements, Refer to Section 8 of thisPart 3.

    1.6 DESIGN CODES AND MANUALS

    In addition to this Part 3, Project Requirements, the Design-Builder must comply with allapplicable engineering codes and standards, including those of the various Federal, State, andlocal jurisdictions.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 4 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    If codes, standards and/or manuals are specified herein for the design of an element of theProject, then the edition(s) in effect on the Proposal due date shall be applicable to the Project.Responsibility for design remains with the Design-Builder in accordance with the terms andconditions of the Contract. If a code, manual or standard is subsequently modified by theissuer, the Design-Builder shall notify the Department of such modification(s) and request theDepartment’s decision regarding application of the modification(s).

    All work shall conform to the following documents. In the event of a conflict between the codesand reference documents listed below, the more stringent requirements, as determined by theDepartment, shall apply.

    For Work not specifically covered by the individual sections of the Project Requirements, theDesign-Builder shall, at a minimum, apply the Standards normally applied by NYSDOT for suchWork, to the extent they do not conflict with express requirements in the Contract Documents.The Design-Builder shall be solely responsible for ensuring that it identifies and applies allcorrect Standards.

    AASHTO:

    A Guide for Accommodating Utilities within Highway Right-of-Way

    A Policy on Design Standards - Interstate System

    A Policy on Geometric Design of Highways and Streets

    Construction Handbook for Bridge Temporary Works

    Guide Design Specifications for Bridge Temporary Works

    Guide for the Design of Pavement Structures (with Supplement)

    Guide Specification for Bridge Railings (1989)

    Guide Specifications for LRFD Seismic Bridge Design

    LFRD Bridge Construction Specifications

    LFRD Bridge Design Specifications

    Manual for Assessing Safety Hardware (MASH)

    Manual for Bridge Evaluation

    Manual on Subsurface Investigations

    Mechanistic-Empirical Pavement Design Guide (MEPDG)

    Roadside Design Guide

    Standard Specifications for Highway Bridges

    Standard Specifications for Structural Supports for Highway Signs, Luminaires andTraffic Signals

    Guide Specifications for Structural Design of Sound Barriers, 1992 Interim

    AISC: Steel Construction Manual

    ANSI

  • New York State Department of Transportation

    Region 8 Bundled Bridges 5 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    ANSI/AASHTO/AWS D1.5-95 Bridge Welding Code

    ANSI/IES Approved Recommended Practice for Roadway Lighting, RP-8-00

    Asphalt Institute: Drainage of Asphalt Pavement Structures

    ASTM: E2213-03 Standard Specification for Telecommunications and Information Exchange

    Between Roadside and Vehicle Systems

    E2259-03 Standard Guide for Archiving and Retrieving ITS-Generated Data

    E2468-05 Standard Practice for Metadata to Support Archived Data ManagementSystems

    E2655-08 Standard Guide for Reporting Uncertainty of Test Results and Use of theTerm Measurement Uncertainty in ASTM Test Methods

    Federal Geographic Data Committee: GIS Standards

    FHWA: FHWA NHI-00-043 Mechanically Stabilized Earth Walls and Reinforced Soil Slopes

    Design and Construction Guidelines

    FHWA Ground Improvement Methods

    FHWA NHI-05-123 Soil Slope and Embankment Designs

    FHWA NHI-11-032 GEC No. 3 LRFD Seismic Analysis and Design of TransportationGeotechnical Features and Structural Foundations

    FHWA HI-99-007 Rock Slopes Reference Manual

    HEC 18 Evaluating Scour at Bridges

    HEC 23 Bridge Scour and Stream Instability Countermeasures

    Manual of Uniform Traffic Control Devices (MUTCD)

    Pavement Publications

    Standard Highway Signs and Markings (SHSM) Book

    Steel Bridge Design Handbook

    Technical Advisory T6640.8A, 10/30/87 (environmental analyses)

    Traffic Monitoring Guide

    Guidance Noise Barriers – Design and Construction

    NFPA: NFPA 70 – National Electrical Code (NEC)

    502: Standard for Road Tunnels, Bridges, and Other Limited Access Highways

  • New York State Department of Transportation

    Region 8 Bundled Bridges 6 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    NYSDEC: Standards and Specifications for Erosion and Sediment Control (SESC)

    Stormwater Management Design Manual (SMDM)

    NYSDOT: Annual Report titled "Axle Factor Update"

    Approved Materials List

    Bridge Detail (BD) Sheets US Customary (NYSDOT BD Sheets)

    Bridge Inspection Manual

    Bridge Inventory Manual

    Bridge Manual

    Bridge Safety Assurance Seismic Vulnerability Manual

    Comprehensive Pavement Design Manual

    Consultant Instructions (CIs)

    Design Consultant Manual

    Engineering Bulletins (EBs)

    Engineering Instructions and Directives (EIs and EDs)

    Environmental Procedures Manual (EPM) / The Environmental Manual (TEM)

    GCP-17, Procedure for the Control of Granular Materials

    Geotechnical Design Manual, including all appendices

    Highway Design Manual (HDM)

    Land Surveying Standards and Procedures Manual

    LRFD Blue Pages / LRFD Bridge Design Specifications

    Manual for Uniform Record Keeping

    Materials Bureau - Applicable Sampling and Testing Manuals, Inspection Manuals, andMaterials Methods

    New York State Supplement to the Manual on Uniform Traffic Control Devices

    Overhead Sign Structure Design Manual

    Policy and Standards for the Design of Entrances to State Highways

    Policy on Highway Lighting

    Prestressed Concrete Construction Manual (PCCM)

    Project Development Manual

    Reference Marker Manual

    Rules and Regulations Governing the Accommodation of Utilities within the StateHighway Right of Way

  • New York State Department of Transportation

    Region 8 Bundled Bridges 7 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    Special Specifications as indicated in the Contract Documents

    Standard Specifications for Construction and Materials

    Steel Construction Manual (SCM)

    Structures Design Advisories

    Structures Technical Advisories

    U.S. Customary Standard Sheets

    Work Zone Traffic Control Manual

    The above is a partial listing of applicable NYSDOT Engineering Manuals and Guidelines. TheDesign-Builder shall perform the Work in conformance with all NYSDOT Engineering Manualsand Guidelines in effect on the Proposal due date.

    OSHA:

    PART 1926 - Safety And Health Regulations For Construction

    SPC: Society of Protective Coatings Standards

    USDOJ: ADA Accessibility Guidelines for Buildings and Facilities

    USDOT: ADA Standards for Transportation Facilities

    1.7 REQUIREMENTS

    The “Requirements” subsection of the individual sections of Part 3 – Project Requirementsestablishes the Department’s expectations with respect to specific Project elements. Theseinclude administrative, managerial and technical considerations as deemed appropriate to thesubject, and encompass performance specifications, design criteria, and directive instructionsas the Department deems best suited to the subject. The Design-Builder shall develop itsDefinitive Design, Design Plans and Project Specifications in conformance with this Part 3 –Project Requirements.

    The Design-Builder shall be responsible for meeting all requirements and terms contained inthis Part 3 – Project Requirements unless explicitly stated otherwise.

    The specific requirements in this Part 3 – Project Requirements may be more stringent and shallgovern over the criteria given in the Standards. However, where a specific requirement in thisPart 3 – Project Requirements is more stringent than the criteria specified in a Standard, saidspecific requirement shall become the basis for determining compliance. Non-standard featuresneeding justification and FHWA and/or NYSDOT approval are defined as those not meeting thecriteria cited in the Standards listed in this Part 3 – Project Requirements.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 8 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    1.8 DELIVERABLES

    The subsection entitled “Deliverables” in each section of this Part 3 – Project Requirementsestablishes the Department’s expectations. These shall supplement the review plan andconsultation and written comment cycles cited in DB §111-8 through DB §111-14. The Design-Builder may submit deliverables for the Department’s consideration or consultation and writtencomment in addition to those requested. The Design-Builder shall include such additionalsubmittals in its review plan and revise the review plan as necessary to incorporate sufficientadvance notice to the Department.

    Unless otherwise indicated in a specific section of this Part 3 – Project Requirements, alldeliverables shall be submitted in both electronic format and hardcopy format. Acceptableelectronic formats include Bentley Microstation .dgn format and Bentley InRoads.alg and dtmformat, Microsoft Word®, Microsoft Excel®, ArcMAP, or searchable portable document format(PDF) files, with no copy or password protection on the file content, unless otherwise indicatedin a specific section of this Part 3 - Project Requirements or a Standard cited in a specificsection of this Part 3 - Project Requirements.

    1.9 INDICATIVE PLANS

    The Indicative Plans, if provided to the Design-Builder in Part 6 – RFP Plans, convey an overallpotential solution to the Project’s needs. The Indicative Plans are not mandatory, with theexception of elements specifically mentioned elsewhere in this Part 3.

    1.10 DIRECTIVE PLANS

    The Directive Plans, if provided to the Design-Builder in Part 6 – RFP Plans, depict requiredelements and components of the Project within specifically defined parameters. The Design-Builder has no latitude to adjust components or details shown on Directive Plans, unlessspecifically noted or through an approved Alternative Technical Concept (ATC).

    1.11 CADD

    CADD formatting for Design and As-Built Plans shall conform to the Department’s CADDDrafting Standards and CADD Design Standards in effect on the Proposal due date.

    1.12 SCHEDULE OF PROJECT COMPLETION

    All work on the design and on the construction shall be completed in accordance with Part 1, DBAgreement, Article 2, Contract Time, but in no case shall the Project Completion Date be laterthan October 30, 2017.

    1.13 WORK PAYMENT SCHEDULES

    Progress Payments will be made as each Work Item is completed to the satisfaction of theDepartment’s Construction Quality Assurance Engineer. Progress payments shall be subject tothe requirements of DB §109-2. Payments for Design, Construction Inspection and Laboratoryactivities will be made in conformance with DB § 109-2.2.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 9 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    WORK PAYMENT SCHEDULE – BIN 1040550

    WORK ITEM

    MAXIMUMPERCENT OFLUMP SUM

    PRICE

    PERCENT OFLUMP SUM PRICE(To be completed

    by D-B)1

    Work Zone Traffic Control – Off-Site Detour InOperation 5%

    Demolition and Removal of Existing Superstructure 20%Demolition and Removal of Existing Approach Slabs 5%Rehabilitation of Abutments and Pier 15%Fabrication and Installation of Bearings 5%Construction of Bridge Superstructure and ApproachSlabs 25%

    Installation of Gas Main Casing on Bridge 10%Installation of Permanent Sanitary Force Main Sewer 5%Reconstruction of the Bridge Approaches IncludingCurbs and Sidewalks 10%

    Fabrication and Installation of Bridge Rail andApproach Guide Rail 10%

    Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

    WORK PAYMENT SCHEDULE – BIN 5500969

    WORK ITEM

    MAXIMUMPERCENT OFLUMP SUM

    PRICE

    PERCENT OFLUMP SUM PRICE(To be completed

    by D-B)1

    Construction of Noise Barrier 10%Work Zone Traffic Control – 5% for Each Stage(Assume 3 Stages) 15%

    Stage I Demolition and Removal of Existing BridgeElements 15%

    Stage II Demolition and Removal of Existing BridgeElements 15%

    Stage I Construction of Foundations 5%Stage II Construction of Foundations 5%Stage I Construction of Abutments and Wing Walls 10%Stage II Construction of Abutments and Wing Walls 10%

  • New York State Department of Transportation

    Region 8 Bundled Bridges 10 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    Stage I Construction of Bridge Superstructure andApproach Slabs 10%

    Stage II Construction of Bridge Superstructure andApproach Slabs 5%

    Stage III Construction of Bridge Superstructure andApproach Slabs 5%

    Construction of Drainage System 2.5%Reconstruction of Median 2.5%Rock Excavation is Completed 2.5%Construction of Speed Change Lanes 2.5%Milling and Inlay Paving and Sidewalk Replacement onKisco Avenue 2.5%

    Fabrication and Installation of Signage and PavementMarkings 2.5%

    Fabrication and Installation of Bridge Rail andApproach Guide Railing and Highway Guide Railing 2.5%

    Completion of Miscellaneous Items 2.5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

    WORK PAYMENT SCHEDULE – BIN 5500870

    WORK ITEM

    MAXIMUMPERCENT OFLUMP SUM

    PRICE

    PERCENT OFLUMP SUM PRICE(To be completed

    by D-B)1

    Work Zone Traffic Control 25%Demolition and Removal of Existing Bridge Elements 35%Installation of Foundations 5%Construction of Abutments and Wing Walls 5%Fabricate and Install Bearings 5%Installation of Replacement Structure 25%Reconstruction of the Highway Bridge Approaches 5%Fabrication and Installation of Bridge Barrier andApproach Guide Railing 5%

    Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

  • New York State Department of Transportation

    Region 8 Bundled Bridges 11 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    WORK PAYMENT SCHEDULE – BIN 5500890

    WORK ITEM

    MAXIMUMPERCENT OFLUMP SUM

    PRICE

    PERCENT OFLUMP SUM PRICE(To be completed

    by D-B)1

    Relocation of Sanitary Sewer and Installation of SewerStub 5%

    Work Zone Traffic Control 25%Demolition and Removal of Existing Bridge Elements 35%Installation of Foundations 5%Construction of Abutments and Wing Walls 5%Fabricate and Install Bearings 5%Installation of Replacement Structure 25%Reconstruction of the Highway Bridge Approaches 5%Fabrication and Installation of Bridge Barrier andApproach Guide Railing 5%

    Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

    WORK PAYMENT SCHEDULE – BIN 5521680

    WORK ITEM

    MAXIMUMPERCENT OFLUMP SUM

    PRICE

    PERCENT OFLUMP SUM PRICE(To be completed

    by D-B)1

    Removal of Existing Corrugated Pipes Stage I 15%Removal of Existing Corrugated Pipes Stage II 15%Installation of Replacement Structure Stage I 35%Installation of Replacement Structure Stage II 35%Installation of Approach Slabs Stage I 2.5%Installation of Approach Slabs Stage II 2.5%Reconstruction of the highway bridge approaches 5%Fabrication and Installation of Bridge Rail andApproach Guide Railing 5%

    Complete Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

  • New York State Department of Transportation

    Region 8 Bundled Bridges 12 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    WORK PAYMENT SCHEDULE – BIN 1005080

    WORK ITEM

    MAXIMUMPERCENT OFLUMP SUM

    PRICE

    PERCENT OFLUMP SUM PRICE(To be completed

    by D-B)1

    Installation of Pipe Liner 50%Removal of Vegetation and installation of Stone Fillingon Slope

    30%

    Removal of Silt/Sand Bar 30%Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

    Notes: (1) See Work Payment Schedule included in ITP, Appendix E.

    (2) Subsequent to Selection of Best Value, the Design-Builder may submit to theDepartment a more detailed Work Payment Schedule which breaks individual workitems into multiple stages, for the Department’s review and acceptance. However,the sum of the percentages proposed for each stage shall equal the percentage forthat work item submitted by the Design-Builder included on Form WPS, and in nocase shall the payment for any individual stage be more than 50% nor less than 10%of the total percentage bid for that work item.

    1.14 INTERIM COMPLETION MILESTONES

    This Project’s Interim Completion Milestones, if applicable, are defined as shown in Part 5 –Special Provisions of the RFP.

    The Interim Completion Milestone Dates may not be changed without written approval by theDepartment’s Project Manager.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 13 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    SECTION 2 PROJECT MANAGEMENT

    2.1 DESIGN-BUILDER’S ROLE

    The Design-Builder shall have responsibility for controlling and managing the Work, includingthe responsibility for quality management as defined in the Contract Documents, Part 2 - DB §§111, 112 and 113. This section identifies the Design-Builder’s Key personnel and summarizesthe Management Plans to be produced by the Design-Builder in accordance with the ContractDocuments.

    2.2 DESIGN-BUILDER’S KEY PERSONNEL

    The positions listed below shall be the Design-Builder’s key personnel for the Project. KeyPersonnel are preferred to have experience on projects of a similar size, type of work, andcomplexity as this Project, and should meet the qualifications described below. Proposed staffwith qualifications less than those described below will receive a reduced score compared tostaff that meet or exceed the described qualifications. Any requirements described as “shallhave...” or “shall be…”are determined to be minimum response requirements. The Design-Builder shall provide personnel that meet these minimum requirements.

    The Design-Builder’s Project Manager shall be the Design-Builder’s representative and singlepoint of contact with the Department.

    The Department’s Project Manager may designate other Key Personnel positions as needed atany time during the Contract.

    A) Project Manager: Shall have a minimum of 10 years, but preferably 15 years ofdemonstrated experience in construction and construction management of majortransportation and infrastructure projects. Projects should be of similar size and type ofwork as this Project, including projects with compressed timelines, and communityinformation requirements. Such experience in construction and management-of-construction should include at least one bridge infrastructure construction project havinga construction value in excess of $15,000,000. The Project Manager, who should haveDesign-Build experience and have extensive project management experience, can holdonly this one Key Personnel position. The Project Manager should dedicate no less than50% of their work time to this Project. It is preferred, but not required, that this individualbe licensed and currently registered as a Professional Engineer in the State of NewYork.

    B) Design Manager: Shall be licensed and currently registered as a Professional Engineerin the State of New York, shall be an owner or employee of the Designer and shall havea minimum of 15 years demonstrated experience in managing design for infrastructureprojects of similar scope as this Project. The Design Manager, should preferably haveDesign-Build experience, and should have specific experience on projects of similar sizeand type. The Design Manager can hold only this one Key Personnel position. TheDesign Manager should dedicate no less than 75% of their work time to this Project.

    C) Construction Manager: Should preferably be licensed and currently registered as aProfessional Engineer in the State of New York and should have a minimum of 15 yearsof demonstrated construction experience in civil works projects with experience inmanaging the site work of superstructure and bridge replacement and highway

  • New York State Department of Transportation

    Region 8 Bundled Bridges 14 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    construction and reconstruction projects. Experience should include work of the natureanticipated in the Project, and should preferably include Design-Build contracts. TheConstruction Manager should dedicate no less than 50% of their work time to thisProject.

    D) Quality Manager: Should have demonstrated experience in bridge design and majorinfrastructure construction with at least 10 years experience in quality assurance andquality control activities, including preparation and implementation of Quality Plans andprocedures for design and construction. The Quality Manager can hold only this KeyPersonnel position. The Quality Manager should dedicate no less than 40% of their worktime to this Project. The Quality Manager shall have experience of quality systemsbased on ISO 9001, and preferably have experience with the quality systems of theDepartment.

    E) Resident Engineer: Should be licensed and currently registered as a ProfessionalEngineer in the State of New York and should have demonstrated at least 10 yearsexperience in bridge and highway construction inspection, including at least 5 years as aResident Engineer. The Resident Engineer should have performed Resident Engineerduties on a project within the last 3 years.

    F) Lead Structural Engineer: Shall be licensed and currently registered as a ProfessionalEngineer in the State of New York and shall have demonstrated at least 10 yearsexperience in structural analysis and design.

    G) Lead Civil Engineer: Shall be licensed and currently registered as a ProfessionalEngineer in the State of New York and shall have at least 10 years experience in civilroadway design, including congestion management and the preparation of Work ZoneTraffic Control Plans.

    H) Lead Geotechnical Engineer: Shall be licensed and currently registered as aProfessional Engineer in the State of New York and shall have a minimum of 10, butpreferably 15 years of experience which should include the following: planning andoverseeing subsurface exploration programs for highway structures/facilities; thedevelopment of design soil/rock profiles, for the purpose of geotechnical analysis,design, and construction; design of structure foundations and earth support structures;analysis and design for static and dynamic (seismic) loading under current LRFD;analysis and design of mitigation measures for embankment settlement and stability;analysis and design of both temporary and permanent earth support structures; andinterpreting geotechnical instrumentation programs.

    I) Project Superintendent: Should have at least 5, but preferably 10 years ofdemonstrated experience overseeing work on bridge and highway construction projects.Experience should include directing and coordinating the activities of a contractor’sworkforce and all subcontractors, ensuring work progressed according to schedule,within budget and that material and equipment were delivered to the site on time. TheProject Superintendent should have experience as Project Superintendent on a bridgeproject valued at $15,000,000 or more.

    J) Lead Public Involvement Specialist: Shall have a minimum of 10 years experienceworking in the field of transportation planning/public involvement. Individual shall have

  • New York State Department of Transportation

    Region 8 Bundled Bridges 15 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    demonstrated experience in the development and successful implementation of publicnotification plans and associated tasks such as, but not limited to: organizing, preparingfor, and facilitating stakeholder meetings and public meetings; development of publicinformational materials for public meetings and project websites; drafting of Project pressreleases; and so on.

    2.3 MANAGEMENT PLANS AND SCHEDULES

    2.3.1 Management Plans and Schedule Requirements

    The Design-Builder shall submit to the Department’s Project Manager, for review and commentor approval (as applicable), all the Management Plans listed in Table 2-1. Following receipt ofthe Department’s acceptance or approval of the individual Management Plans, as described inthe Contract Documents, the Management Plans shall be resubmitted to the Department’sProject Manager as the Design-Builder’s consolidated Project Management Plan for the Project.

    Table 2-1 – Project Management Plans

    Plan Title Contract DocumentReferenceInitial Plan to beSubmitted withthe Proposal?

    SubmittalDeadline

    Workforce Participation Plan DB § 102-9.4B No 45 Days after NTP

    Safety Plan * DB § 107-7.5 No 30 Days after NTP

    Quality Control Plan * DB § 113 Yes 25 Days after NTPOverall Design-Build TeamOrganization Plan

    Project RequirementSection 2.3.5 Yes 25 Days after NTP

    Design Management Plan Project RequirementSection 2.3.6 Yes 30 Days after NTP

    Construction Management Plan Project RequirementsSection 2.3.7 Yes 45 Days after NTP

    * Requires Department approval

    2.3.2 Workforce Participation Plan

    The Design-Builder shall develop a Workforce Participation Plan to meet the requirements ofDB §102-9.4B and submit it to the Department’s Project Manager for review and comment.

    2.3.3 Safety Plan

    The Design-Builder shall develop a Safety Plan to meet the requirements of Part 2, DB §107-7.5and submit it to the Department’s Project Manager for written approval in accordance with DB§107-7.8. No construction Work shall progress and no payment shall be made to the Design-Builder until the Safety Plan is approved by the Department.

    2.3.4 Quality Control Plan

    The Design-Builder shall use the Initial Quality Control Plan submitted with the TechnicalProposal, modify and develop it, as necessary, to include the content required by Part 2, andsubmit it to the Department’s Project Manager for written approval in accordance with Part 2 DB§113. The Quality Control Plan shall be revised and resubmitted to the Department’s Project

  • New York State Department of Transportation

    Region 8 Bundled Bridges 16 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    Manager within 14 calendar days of receipt of the Department’s written comments andresubmitted as required until Approved by the Department’s Project Manager. No offsitefabrication Work or Construction Work shall commence before the Quality Control Plan hasbeen approved by the Department’s Project Manager. No payment will be made to the Design-Builder until the Quality Control Plan has been approved by the Department.

    2.3.5 Overall Design-Build Team Organizational Plan

    The Design-Builder shall update the Initial Overall Design-Build Team Organization Plandescribing the design and construction organizational arrangements it intends to implement.The organizational arrangements described should clearly identify responsibilities and reportinglines of staff, particularly relating to Key Personnel.

    The Design-Builder shall include an organization chart (on an 11" x 17" sheet of paper),illustrating the Proposer’s Key Personnel and their prospective roles and responsibilities, as wellas other principal participants and any known Subcontractors having a material role in theProject’s design Work, design check Work, construction Work and construction inspection Work.

    The Design-Builder shall describe the interrelationships and interfaces between each disciplinewithin the Proposer’s organization (e.g., design, design check, shop drawing preparation andreview, construction, and quality management).

    The Overall Design-Build Team Organization Plan shall also describe the interrelationships andinterfaces between the Design-Builder’s organization, the Department and other governmentalagencies, utility owners, stakeholders, businesses, the public and other contractors working inthe vicinity and impacted by the construction of the Project. This description shall also, at aminimum, address the following activities:

    A) Reviews of plans and permits;

    B) Progress, workshop, partnering and utility coordination meetings; and

    C) Construction, engineering and inspection activities.

    2.3.6 Design Management Plan

    The Design-Builder shall update the Initial Design Management Plan submitted with its Proposaland submit it to the Department’s Project Manager for Review and Comment.

    2.3.7 Construction Management Plan

    The Design-Builder shall update the Initial Construction Management Plan submitted with itsProposal and submit it to the Department’s Project Manager for Review and Comment.

    2.4 BASELINE PROGRESS SCHEDULE

    The Design-Builder shall expand and Preliminary Utility Work Agreements update the InitialBaseline Progress Schedule submitted with the Technical Proposal and modify and develop it,as necessary, in accordance with DB §108-1 and Part 5, Special Provision SP-3.

    Design shall be considered complete when all Design related documents have been completedand accepted by the Department including: all calculations, specifications, records of design

  • New York State Department of Transportation

    Region 8 Bundled Bridges 17 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    quality control reviews and procedures; descriptions of and justification for any non-standardfeatures created or retained as a result of the design; resolution of any non-conformancereports; and submission of “As Built” drawings.

    Construction shall be considered complete when: the entire Scope of Work has beencompleted; any damage to the area caused by the Design-Builder’s performance of the Workhas been repaired to the satisfaction of the Department; all construction quality controldocuments, test and inspection reports and forms have been completed; As-Built drawings havebeen completed; and the work site(s) have been cleaned of any debris.

    2.5 MEETINGS

    The Design-Builder shall convene or participate in meetings as indicated in Part 2 DB §105-17.

    It is the Department’s policy to use the principles of partnering to guide the management ofDesign-Build contracts and the Design-Build program within the parameters covered by thelaws, regulations, and other policies that govern the work. The Design-Builder shall convene orparticipate in meetings designed to foster the principles of partnering in accordance with Part 2DB §103-2.

    The Design-Builder shall record the minutes for each meeting.

    2.6 COMPUTER AND NETWORKING REQUIREMENTS

    The Design-Builder shall provide Computer and Networking equipment to the ConstructionInspection Professional Engineering Firm (CIPE) as necessary. The Department will issue Citrixconnection accounts to the Design-Builder and its CIPE firm. It is recommended that theDesign-Builder test the network connection success prior to fully equipping its staff and theCIPE firm, to ensure both hardware and software compatibility.

    The following computer related specifications reflect the current technology utilized by theDepartment when making Citrix Connections and are provided for informational purposes only:

    2/HM65 Chipset, and Intel HD Graphics 3000 (or equivalent); 2nd Generation Intel Core i5 2620M Processor, 2.70GHz (Turbo up to 3.40GHz),

    1333MHz, 4MB L3 Cache; Mobile Intel HM65 Chipset; 14” diagonal LED-backlit HD anti-glare (1366x768); Intel HD Graphics 3000; 4 GB 1333 MHz DDR3 SDRAM – Dual Channel Active; 250 GB 7200 RPM 2.5 inch hard drive – or 120 GB Intel SSD; DVD R/W SuperMulti DL Drive; Full Keyboard; Broadcom 4313 GN 802.11 g/b/n 1x1 WiFi Adapter; 65W Hardware Kit; 6 cell Li-ion Battery; and Integrated Gigabit Ethernet

    Computers shall have Citrix Receiver installed, which can be accessed at:

    http://receiver.citrix.com/

  • New York State Department of Transportation

    Region 8 Bundled Bridges 18 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    2.7 DEPARTMENT’S CONSULTATION AND WRITTEN COMMENTS

    The Department’s review, oversight, audit, and inspection activities are referred to as“consultation and written comment” (see Part 2, DB §105-16). The Department’s consultationand written comment will be provided to the Design-Builder in writing. The Design-Builder shallbe responsible for addressing the Department’s comments and shall indicate in writing whetherit concurs with the comments. If the Design-Builder does not concur with the Department’scomments, then the Department and Design-Builder will work together to resolve the issuebefore proceeding.

    If agreement cannot be reached, the issue must be resolved as provided in the ContractDocuments for dispute resolution in accordance with Part 2 DB §109-10.

    2.8 PROJECT WISE

    ProjectWise shall be used to organize, manage and archive electronic Project designdocuments for NYSDOT. These documents typically include but are not limited to:

    All design reports including drafts and final;

    All studies and supporting reports;

    Permits;

    Survey and ROW mapping;

    Photos taken prior to and during design;

    CADD and 2D/3D models files including current NYSDOT-supported Microstation andInRoads file formats;

    Engineering calculations to support designs;

    All electronic plan sheets;

    Engineer of Record’s estimate based on Payment Breakdown Structure; and

    Public Information.

    All files posted to ProjectWise shall be in accordance with the file naming convention andsubmission procedures as defined in Appendix 14 of the NYSDOT Project DevelopmentManual. In addition the Payment Breakdown Structure (PBS) shall be used in the file namingconvention, specifically the work item number in the PBS.

    The Design-Builder may obtain a ProjectWise account by contacting the Department’s ProjectManager and providing the required account information per Appendix 14 of the ProjectDevelopment Manual.

    The Design-Builder shall ensure that all electronic design documents are stored in ProjectWise.Updates of engineering documents shall be provided on a monthly basis.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 19 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    SECTION 3 ENVIRONMENTAL COMPLIANCE

    3.1 SCOPE

    Except as otherwise detailed herein, the Design-Builder shall be responsible for preparing itsdesign, obtaining environmental approvals, carrying out construction activities, performingQuality Control, and undertaking other activities as needed to ensure compliance with theProject’s Environmental Requirements and all applicable environmental laws and regulations.

    This Project Requirement identifies certain required actions to be performed by the Design-Builder to ensure that the Environmental Requirements are complied with throughout theduration of the Project.

    3.2 ENVIRONMENTAL APPROVALS

    The Department has determined that this Project is a NEPA Class II Categorical Exclusion.Class II actions that do not individually or cumulatively have a significant environmental effectare excluded from the requirement to prepare an Environmental Impact Statement (EIS) or anEnvironmental Assessment (EA).

    Because the work has an effect on two (2) National Register Eligible structures (BINs 5500870and 5500890), the Department has determined that this Project is a SEQR Non-Type II Actionin accordance with 17 NYCRR Part 15 - Procedures for Implementation of State EnvironmentalQuality Review Act. SEQR Non-Type II projects include actions for which the environmentalimpacts are not clearly established and require an Environmental Assessment (EA). The ProjectScoping Report/Final Design Report acts as the Project’s Environmental Assessment underSEQRA.

    The Design-Builder is responsible to obtain all environmental permits and approvals needed forthe Project. Approvals previously secured for the Project are included in Part 7 – EngineeringData.

    The following environmental approvals have been obtained by the Department:

    BIN 1005080

    o A Federal Aid Notification, including a Federal Consistency Assessment Form,was submitted to New York State Department of State (NYSDOS) on April 1,2014 and general concurrence was received on May 27, 2014.

    o In a letter received by the Department on April 3, 2014, New York StateDepartment of Environmental Conservation (NYSDEC) concurred with theDepartment’s assessment that the proposed work is not likely to result in a “take”of NY-listed species, pursuant to mitigation measures detailed in Part 3 Section3.4 - Threatened And Endangered Species Coordination.

    o In a letter received by the Department on May 19, 2014, the United States Fishand Wildlife Service (USFWS) concurred with the Department’s determinationsas detailed in Part 3 Section 3.4 - Threatened And Endangered SpeciesCoordination, pursuant to the commitments therein.

    BIN5500870

  • New York State Department of Transportation

    Region 8 Bundled Bridges 20 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    o A Determination of No Significant Effect (DONSE) was filed in accordance with17 NYCRR 15.10.

    o In a letter received by the Department on April 3, 2014, the NYSDEC concurredwith the Department’s assessment that the proposed work is not likely to result ina “take” of NY-listed species.

    o In a letter received by the Department on May 19, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

    o Per New York State Historic Preservation Act Section 14.09 the Departmentprepared a No Adverse Effect Finding Document and sent it to SHPO.SHPO concurred with the determination in a letter dated May 28, 2014.

    BIN 5500890

    o A Determination of No Significant Effect (DONSE) was filed in accordance with17 NYCRR 15.10.

    o In a letter received by the Department on April 3, 2014, the NYSDEC concurredwith the Department’s assessment that the proposed work is not likely to result ina “take” of NY-listed species.

    o In a letter received by the Department on May 19, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

    o Per New York State Historic Preservation Act Section 14.09, the Departmentprepared a No Adverse Effect Finding Document and sent it to SHPO;SHPO concurred with the determination in an email dated March 28, 2014.

    BIN 5500969

    o NYSDOT concluded that there will be no historic properties affected by theproject. NYSDOT requested concurrence from the SHPO on March 28, 2014.SHPO concurred with the determination in a letter dated May 28, 2014.

    o In a letter dated December 8, 2014 USFWS concurred with the Department’sdeterminations as detailed in Part 3 Section 3.4 - Threatened And EndangeredSpecies Coordination, pursuant to the commitments therein.

    BIN 1040550

    o In a letter dated August 18, 2014, the NYSDEC concurred with the Department’sassessment that the proposed work is not likely to result in a “take” of NY-listedspecies, pursuant to mitigation measures detailed in Part 3 Section 3.4 -Threatened And Endangered Species Coordination.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 21 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    o In a letter received by the Department on May 21, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

    BIN 5521680

    o In a letter received by the Department on April 3, 2014, the NYSDEC concurredwith the Department’s assessment that the proposed work is not likely to result ina “take” of NY-listed species.

    o In a letter received by the Department on May 19, 2014, USFWS determinationsas detailed in Part 3 Section 3.4 - Threatened And Endangered SpeciesCoordination, pursuant to the commitments therein.

    The Department has not secured any environmental permits associated with this project. It isthe Design-Builder’s responsibility to secure all environmental permits associated with andrequired for construction of this project.

    If during detailed design the Design-Builder introduces design elements, variations, ormethodologies that may result in environmental effects beyond those already identified duringpreliminary engineering, then the Design-Builder shall re-evaluate environmental impacts forthis Project. This requirement also applies to proposed variations which may affect resourcescovered under Section 106, Section 4(f), Executive Order 11990 (wetlands), and otherapplicable federal and state environmental regulations. The environmental screening limitsused during preliminary engineering are provided as Reference Documents. The Design-Builderis responsible to obtain all environmental permits and approvals needed for the Project.

    3.3 REQUIREMENTS

    3.3.1 General

    A) The Design-Builder shall procure all Environmental Approvals as needed for all Design-Builder-located areas, including staging, borrow and disposal sites, and any other areasused by the Design-Builder, for its convenience, in the execution of the Project;

    B) The Design-Builder shall be responsible for preparing all permit application materials andobtaining all Environmental Approvals necessary for the Project and not already obtainedby the Department, including those that are precipitated by the Design-Builder’s design oractions that deviate from the requirements of any acquired permit(s) (if any). For any suchapprovals required to be obtained by the Design-Builder that must formally be issued in theDepartment's name, the completed application shall be sent to the Department for signatureand transmission to the permitting agencies. The Design-Builder shall assume seven (7)calendar days to be taken by the Department for this action and for each timecorrespondence passes between the Design-Builder and a regulatory agency.

    C) The Design-Builder shall be solely responsible for compliance with and violations of anyEnvironmental Requirements; and

    D) The Design-Builder is responsible for any fines, non-compliance, violations, or damagesincurred by reason of failure of the Design-Builder to comply with Environmental Approvals.Resulting fines or damages shall be deducted from monies owed the Design-Builder.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 22 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    E) NYSDEC Article 15 – Streams

    For any locations involving work in or within 50 feet of a stream, compliance with theNYSDEC-NYSDOT Memorandum of Understanding (MOU) regarding EnvironmentalConservation Law Articles 15 and 24 is required. The MOU is provided as a ReferenceDocument.

    In-water work must occur between the allowable work periods listed in Table 3-1 NYSDECArticle 15 Stream Classifications and Allowable Work Periods, unless waived in writing byNYSDEC.

    Table 3-1 – NYSDEC Article 15 Stream Classifications and Allowable Work Periods

    BIN Road Stream/featurecrossed ClassificationAllowable Work

    Period

    5500870 Route 987D SAW MILL RIVER B, B(T) May 1 - Sept 30

    1005080 Route 9 DICKEY BROOK C, C None

    5500969 Route 987D KISCO AVE. N/A None

    1040550 Route 208 MOODNA CREEK C, C None

    5500890 Route 987D SAW MILL RIVER B, B(T) May 1 - Sept 30

    5521680 Route 97 HUTCHINSON RIVER C, C None

    F) New York City Water Supply Watershed

    BIN 5500969: This bridge is located within the boundaries of the New York City (NYC)Water Supply Watershed – East of Hudson. Coordination, including final design plans andSWPPP review, with the NYC Department of Environmental Protection East of HudsonStormwater Program is required in accordance with NYS Executive Order 51 (EO 51) andthe Memorandum of Understanding (MOU) between NYSDOT and NYCDEP. EO 51 andthe MOU are provided as Reference Documents. The Design-Builder shall allow 30 days forreview by NYCDEP.

    G) Section 106 of the National Historic Preservation Act and Section 14.09 of the NYS HistoricPreservation Act

    BIN 5500870: A historic property eligible for inclusion in the National Register of HistoricPlaces, the bridge carrying Bedford Road over Saw Mill River Parkway (BIN 5500860), islocated within the Project’s area of potential effect. The Department has committed to theState Historic Preservation Officer (SHPO) that there would be no physical changes to themasonry arches and parapets, or distinctive arcaded brick corbels of BIN 5500860.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 23 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    BIN 5500890: A historic property eligible for inclusion in the National Register of HistoricPlaces, the bridge carrying Pleasantville Road and Route 117 over the Saw Mill Parkwayand Saw Mill River (BIN 3037170), is located within the Project’s area of potential effect.The Department committed to the SHPO that there would be no impacts to the contributingelements of historic BIN 3037170 on the façade of the bridge elevation. Specifically, thereshall be no physical changes to the masonry arches and parapets, or distinctive arcadedbrick corbels of BIN 3037170.

    H) Regulated Floodways and Floodplains

    BINs 1040550, 5500870, 5500890, 5521680, and 1005080: These BINs are located withinthe limits of 100 year floodplains and/or regulatory floodways. NYSDOT has committed tohaving no encroachment on the floodways.

    I) Stormwater Outfall Mapping

    BINs 5500969, 5500870, 5500890, 5521680, and 1005080 are within a mapped MunicipalSeparate Storm Sewer System (MS4). Therefore, new and relocated stormwater outfallsare required to be mapped per Engineering Instruction (EI) 07-033, Stormwater OutfallMapping Inventory Guidance for NYSDOT Regional Data Exchange. Information is to bedirected to the NYSDOT Project Manager.

    J) BINS 5500870 and 5500890 Tree Removal Restriction

    Part 3 Section 3.5 indicates that the environmental screening area for the two above bridgesincludes an estimated tree removal of 110 and 140 trees respectively. However, treeremoval at these two bridges shall be minimized and will not be permitted west of the SawMill River.

    K) Noise Abatement Measures

    BIN 5500969: The Department has committed to noise abatement measures in the form of anoise barrier located along the north side of the Saw Mill River Parkway and west of thebridge to provide noise reduction for the residents of Pinecrest Manor.

    See Section 10 for Noise Barrier structural requirements.

    L) Lead Based Paint

    BIN 5500969: Lead-based paint, a hazardous material, is present on this bridge. TheDesign-Builder shall comply with the hazardous materials and lead safety and healthrequirements specified in DB §107.

    3.3.2 Environmental Plans

    The Design-Builder shall be responsible for preparing the following documents in conformitywith all Environmental Requirements. The Design-Builder shall submit the followingEnvironmental Documents:

  • New York State Department of Transportation

    Region 8 Bundled Bridges 24 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    A) Stormwater Pollution Discharge Elimination System (SPDES) Permit application; see SoilErosion and Water Pollution Control;

    B) Stormwater Pollution Prevention Plan (SWPPP; see Section 19 – Drainage andStormwater).

    3.3.3 Soil Erosion and Water Pollution Control

    The Design-Builder shall prepare and maintain on file a SWPPP complying with the New YorkState SPDES General Permit for Stormwater Discharges from Construction Activities (GP-0-10-001 or current version). The SWPPP is to include but is not limited to construction entrance(s),construction phasing, drawings showing size and location of permanent (e.g., swales, checkdams, etc.) and temporary (e.g., silt fence, temporary seed, mulch, etc.) erosion controls, anddetails. The SWPPP shall include plans and details for water quality volume, runoff reductionvolume, stream channel protection, overbank flood, and extreme flood controls, as appropriate.The Design-Builder shall apply for coverage under the SPDES General Permit for StormwaterDischarges from Construction Activities after preparing a compliant Erosion Control Plan andSWPPP as noted. The Design-Builder shall prepare the final SWPPP and a conforming Noticeof Intent (NOI), sign/complete the Contractor/Subcontractor SPDES Permit Certification form(CONR 5), and submit the NOI to NYSDEC for approval. Discharges covered under the SPDESgeneral permit shall not commence until the date authorized on the SPDES AcknowledgementLetter from NYSDEC. The SWPPP can be subject to review and comment by the Departmentand/or NYSDEC upon request of the Design-Builder.

    For BINs 1040550, 5500870, 5500890, 5521680, and 1005080, soil disturbance in excess ofone (1) acre will require a SWPPP. For BIN 5500969, since it is in the New York CityWatershed east of the Hudson River, soil disturbance in excess of 5,000 square feet will requirea SWPPP. If a SWPPP is required for both BIN 5500870 and BIN 5500890, one SWPPP shallbe prepared to cover both of these sites.

    See also Section 19 – Drainage and Stormwater.

    3.3.4 Asbestos-Containing Materials

    An Asbestos Screening and Assessment of the impacted right-of-way and structures wasperformed by a NYS Department of Labor licensed firm using certified inspection staff.Asbestos-containing materials identified during this screening/assessment were sampled andpositively analyzed for asbestos content; suspect asbestos-containing materials are presumedpositive. The complete Asbestos Assessment Reports are located in the Reference Documentssection of the Project Web Site.

    BINs 1040550, 5500969, and 5500890: Confirmed or suspect asbestos containing material(s)(ACM) were identified.

    BIN 5500890: subsequent to completion of the Asbestos Assessment Report, the Village ofPleasantville identified the presence of an 8” transite sanitary sewer pipe in the work area. Thispipe shall be considered an assumed ACM.

    BINs 5500870, 5521680, and 1005080: No confirmed or suspect ACM was identified.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 25 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    ACMs may be associated with various underground utilities located within the Project limits.Any ACMs associated with private utilities shall be the responsibility of the utility owner. AnyACMs associated with public utilities shall be the responsibility of the Design-Builder. TheDesign-Builder shall coordinate with the private utility owners for the remediation of any ACMswhich may be identified.

    The Design-Builder shall be responsible for the abatement design, containment, removal anddisposal of all confirmed and assumed asbestos containing materials if such materials will bedisturbed during the performance of the Work, except as noted in Section 3.3.7 below. Theremoval and disposal of ACMs shall be performed in accordance with the applicable safety andhealth codes and all applicable State and Federal regulations. See also DB Section 112-5.5,Asbestos.

    If during the course of work, any asbestos-containing materials not already documented in theasbestos screening report or project record plans are encountered, the Design-Builder shall beresponsible for performing all abatement, containment, removal and disposal activities andprovide project/air monitoring services as part of this Contract in accordance with 12 NYCRR56. Furthermore, should removal and disposal of asbestos-containing materials be required, itshall be performed in accordance with all applicable safety and health codes. This additionalwork shall be paid for under the Force Account pay item.

    New York State Department of Labor (NYSDOL) asbestos licensure and applicable staffcertification(s) are required for Work where confirmed or presumed asbestos-containingmaterials are impacted. All necessary asbestos inspection, Project design and project/airmonitoring work shall be conducted in conformance with policy and guidance provided in theNYSDOT Environmental Procedures Manual (EPM)/The Environmental Manual (TEM).

    At the completion of the asbestos abatement activities, the Design-Builder shall be responsiblefor providing two (2) hard copies and one (1) electronic copy of the complete set of abatementrecord documents, including chain-of-custody records, worker sign-in/sign-out sheets, proof ofworker certifications, and other such records required by law to be kept on record. The recordsfor each bridge shall be assembled as a single, logical report, with all information boundtogether. The information shall be directed to the NYSDOT Project Manager.

    3.3.5 Inaccessible/Assumed ACMs

    ACMs may be associated with various underground utilities located within the Project limits.Any ACMs associated with these utilities shall be the responsibility of either the private utilityowner or the Department (for municipally-owned utilities). The Design-Builder shall coordinatewith the private utility owners for the remediation of any ACMs which may be identified.

    3.3.6 Environmental Plan Deliverables

    At a minimum, the deliverables shall include the items listed in Table 3-2 – EnvironmentalCompliance Deliverables for the Department’s review.

    Each of the deliverables listed in Table 3-2 – Environmental Compliance Deliverables, shall beprovided to the Department 30 days prior to the relevant on site activity, including start ofconstruction.

  • New York State Department of Transportation

    Region 8 Bundled Bridges 26 Part 3 - Project RequirementsPIN 89A1.DB, Contract D900025 Draft February 5, 2015

    Table 3-2 – Environmental Compliance Deliverables

    DeliverableNumber of Copies Reference

    SectionDeliverable

    DateHardcopy Electronic

    Stormwater Pollution Discharge EliminationSystem (SPDES) Notice of Intent andStormwater Pollution Prevention Plan(SWPPP)

    3 1 3.3.2 60 days¹

    ¹ Prior to start of construction.

    ² Prior to relevant on-site activity.

    3.4 THREATENED AND ENDANGERED SPECIES COORDINATION

    A Biological Assessment (BA) was prepared for BIN 5500969, and a Biological Evaluation (BE)was prepared for BINs 1040550, 5500870, 5500890, 5521680, and 1005080, to addresspotential impacts on federal and state protected threatened, endangered, or proposed species.The BA is included in Part 7 – Engineering Data. The BEs are available upon request. For allsix locations, a may affect, not likely to adversely affect determination was concluded for Indianabat and northern long-eared bat. Tree removals (direct count or acreage) are estimated asfollows:

    BIN 1040550 - 48 trees;

    BIN 5500969 - 3.3 acres identified in the BA;

    BIN 5500870 – 110 trees;

    BIN 5500890 – 140 trees;

    BIN 5521680 – 9 trees;

    BIN 1005080 – 20 trees.

    Actual tree removals may be less.

    Tree removals in excess of those stated above may require the Department to coordinate withthe lead Federal Agencies and US Fish and Wildlife Service. The Design-Builder shall preparethe necessary documentation for the Department’s use in gaining the needed approvals.

    For BIN 5500969, a may affect, not likely to adversely affect determination was also concludedfor the bog turtle.

    In order to maintain USFWS and/or NYSDEC threatened and endangered species concurrence,the Design-Builder shall comply with the following mitigation measures:

    All locations: Removal of any trees greater than 3 inches in diameter at breast heightshall occur between October 31 and March 31.

    BIN 5500969: The Design-Builder is responsible for fulfilling all constructioncommitments to USFWS that are contained in the BA for this bridge. Constructioncommitments include, but are not lim