Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
ORWRDP PHASES• Phase 1 – Raising of Flag
Boshielo Dam (Completed in 2006)
• Phase 2A – Construction of the new De Hoop Dam
• Phases 2B to 2H
– Bulk Water Supply Pipelines to Mines & Municipalities
– Pump Stations
– Reservoirs
– Balancing Dams and Weirs
– TCTA implementing agency
• Municipalities distribute to communities
MAIN FEATURES OF THE DAM
1. Gross Storage Capacity [million m3] 347,4
2. Catchment Area [km2] 2 865
3. Approximate Length [m] 1 017
4. Approximate Height [m] 88
5. Total Excavation – Dam Footprint [m3] 415 000
6. Total Excavation – Quarry [m3] 1 300 000
7. Total Estimated Concrete Volume of the Dam [m3] 1 100 017
DE HOOP DAMMain Components:
• River Diversion
(Three (3) Stages)
• Outlet Works
• RCC NOC sections
• RCC Spillway (Stepped)110 m
• Total Length of Dam Wall: 1 017 m
• Access Roads
• River Gauging Structures
OUTLET WORKSThe Outlet Works will essentially comprise the following:
• Wet Well Intake Works on the upstream side comprising two bays each;
• Staggered Bell-Mouth Intakes;
• A Service Shaft will be provided in the concrete body of the dam immediately downstream of the Wet Well bays between the two vertical pipe stacks;
• This shaft will be used to remove the selector valves situated in pockets on either side of the shaft from the body of the dam;
• A Staircase Shaft as well as a Lift Shaft will also be provided;
RIVER GAUGING STRUCTURES• For operational purposes of the dam,
River Gauging Structures are required;
• Three (3) River Gauging Structures were constructed as part of the project:
– De Hoop Dam Gauging Weir
(Situated immediately downstream of the Spillway);
– Taung Gauging Weir
(Situated approximately 80 km downstream of the dam, near the influence with the OlifantsRiver); and
– De Hoop Upper Gauging Weir
(Situated approximately 30 km upstream of the dam).
DEVELOPMENT OF RCC AT DE HOOP DAM
Original RCC Mix: OPC 68
PFA 172
Total cementitious 240
53mm aggregate 316
38mm aggregate 505
19mm aggregate 631
sand 816
Additive (plasticizer)
Additive (retarder)
Water 120
W/C Ratio 0.52
DEVELOPMENT OF RCC AT DE HOOP DAM
Properties of the Original Mix:
• Low paste mix;
• Harsh mix;
• Difficult to apply and to achieve density;
• Segregation occured;
• Permeable mix; and
• Requires “Skin Concrete” or “Grout Enrichment”.
IV-RCC MIX DEVELOPMENT• International Expertise was utilized to
assist with Mix Development in order to stay in touch with International trends;
• IV-RCC (Immersion Vibrated Roller Compacted Concrete) was developed;
• IV-RCC is a high paste concrete mix;
• Eliminates the need for “Skin Concrete” as normally used in RCC dams;
• Placement in 300 mm thick layers;
• Recently altered methodology to placement in 400 mm layers and testing density by means of Strata Gauge;
• Development of IV-RCC is truly a ground breaking achievement.
RCC ACRONYMS
• Current known acronyms used in the International RCC industry:
– GERCC (Grout Enriched RCC)
– GEVRCC (Grout Enriched Vibrated RCC)
• New Acronym created at De Hoop Dam:
– IV-RCC (Immersion Vibrated RCC)
IV-RCC MIX DEVELOPMENT
Mix Description RCC (15/38) Original
RCC (15/38)Spillway
Conventional Concrete (15/38)
OPC 68 62 87
PFA 172 145 203
Total Cementitious 240 207 290
53mm Aggregate 316
38mm Aggregate 505 883 789
19mm Aggregate 631 483 511
Sand 816 877 821
Water 120 122 145
Additive (retarder) 2500cc
Additive (plastisizer) 2400cc
W/C ratio 0.52 0.59 0.50
Technical Design Information of the Mix:
CONSTRUCTION PROGRESS• May 2009 International expertise utilized (F Ortega)
New IV-RCC Mix Development Commenced
RCC PLACEMENT RECORD ATTEMPT (NOVEMBER 2010)
• The Contractor attempted to break the South African record for RCC placement in a month;
• Previous record was 40 600 m3, placed at Wolwedans Dam;
• The Contractor was successful and a total of 103 000 m3 was placed in 21 Days;
RCC PLACEMENT RECORD ATTEMPT
(NOVEMBER 2011)• A further attempt to break this record was conducted in November 2011
and the Contractor was successful in placing 131 000 m3 was placed in 28 Days;
OVERALL PROGRESS
• Overall Progress– 89% Complete (Measured against time);
• Commencement of Impoundment– Closure of Second (2nd ) Stage River
Diversion (Diversion Culvert) and diverting river flow towards Compensation Water Pipe until water level rise sufficiently for operation of the Outlet Works to commence;
– Impoundment is expected to commence towards October 2012;
• Estimated Completion– Overall Completion is expected towards
March 2013.