Upload
ace-winnie
View
878
Download
78
Tags:
Embed Size (px)
DESCRIPTION
CFBC Boiler manual
Citation preview
PROJECT
8 X 135 MW LIGNITE THERMAL POWER PLANT BHADARESH, DISTT. BARMER, RAJASTHAN - INDIA
OWNER
RAJ WEST POWER LIMITED (RWPL) RAJASTHAN - INDIA
ENGINEERS
DESEIN PRIVATE LIMITED NEW DELHI INDIA
BTG SUPPLIER
DONGFANG ELECTRIC CORPORATION CHENGDU CHINA
ORIGINATOR MANUFACTURER
DONGFANG BOILER GROUP CO., LTD. ZIGONG CHINA
Document No.: 39J SM Rev.: A
Document Title :
OPERATION INSTRUCTION FOR CFB BOILER
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 2 of 104 Rev. A
Document No. 39J-SM
OPERATION INSTRUCTION FOR
CIRCULATING FLUIDIZED BED BOILER ( CFBB )
PREP.
CHKD.
EXAM.
APPD.
AUTD.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 3 of 104 Rev. A
REVISION RECORD
PAGE REV. REVISIONS REVISED REV. DATE. REV.SHEET
No.
All A First Issue
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 4 of 104 Rev. A
PREFACE The Circulating Fluidized Bed (CFB) Boiler, whose model is DG440/13.73-II14, is specially designed and manufactured by DONGFANG BOILER GROUP CO., LTD. (DBC) for INDAI RAJ WEST POWER LIMITED POWER PLANT. The boiler is a superhigh pressure 135MWe CFB boiler. This operation instruction is issued to assist operators of DBCs equipment in obtaining the best operation results. This operation instruction is to be used as a guide for operational reference and shall not take the place of Boiler Operation Specifications. This operation instruction can only supplement the experience and judgments of personnel in charge of operation. It shall be interpreted and applied after giving careful consideration of the requirements of other relative equipment and for any particular set of circumstances. This operation instruction does not purport to cover all details or variations of equipment, including every contingency to meet during operation and / or maintenance. The recommendations contained in the operation instruction are prepared by DBC based upon the knowledge and experience gained in the manufacture of CFB boilers, and they represent our best experience and judgments at present. However, in the application of this operation instruction to pre-operation, operation and maintenance of equipment, DBC assumes no responsibility for any failure or incident resulted from incorrect operation. As the successful operation and performance depend greatly upon auxiliary systems, this operation instruction contains some brief descriptions for several vital systems such as coal feed system, air and gas system, bed material extraction system, limestone feed system, etc. They shall be understood as the fundamental requirements of the Boiler and could not be regarded as the sole principles for power plant design. Without permission, no one that is not involved in this Project is allowed to make any copy of this operation instruction.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 5 of 104 Rev. A
TABLE OF CONTENTS
DONGFANG BOILER GROUP CO., LTD. ....................................................................................................1 SECTION 1 CONSTRUCTION DESCRIPTION ............................................................................8 1.1 Design Conditions......................................................................................................................................8 1.1.1 Boiler Specifications..............................................................................................................................8 1.1.2 Boiler Main Dimensions........................................................................................................................9 1.1.3 Fuel..........................................................................................................................................................9 1.1.4 Ash Characteristics .............................................................................................................................10 1.1.5 Limestone for Desulfurization ...............................................................................................................11 1.1.6 Igniter Type ,Fuel for Ignition and Combustion Support................................................................12 1.1.7 Feedwater Quality ...............................................................................................................................13 1.1.8 Fountain ................................................................................................................................................13 1.1.9 Natural Conditions............................................................................................................................13 1.1.10 Operation Mode.................................................................................................................................14 1.1.11 Draft Mode..........................................................................................................................................15 1.2 General Description Of DONGFANG Type CFB Boiler ..........................................................................15 1.2.1 CFB Technology Description................................................................................................................15 1.2.2 DONGFANG Type CFB Boiler Process...........................................................................................17 1.3 General Description of DG440/13.73-II14 ...................................................................................................19 1.3.1 General Arrangement OF DG440/13.73-II14 Type CFBB ............................................................19 1.3.2 Boiler Steam and Water Flow Path ..................................................................................................22 1.3.3 Boiler Gas and Air Flow Paths .............................................................................................................25 1.3.4 Combustion and Circulation Process of the Materials......................................................................26 1.3.5 Fuel and Limestone Feed Systems and Ash Removal System ......................................................28 1.3.6 Expansion System .................................................................................................................................28 1.3.7 Sootblowing System ...........................................................................................................................29 1.4 Main Equipment of CFB Boiler....................................................................................................................30 1.4.1 Economizer ..........................................................................................................................................30 1.4.2 Steam Drum and Drum Internals ......................................................................................................30 1.4.3 Furnace .................................................................................................................................................30 1.4.4 Cyclone .................................................................................................................................................31 1.4.5 The Rear Pass .....................................................................................................................................32 1.4.6 LTS ........................................................................................................................................................32 1.4.7 Primary Desuperheater ......................................................................................................................32 1.4.8 PSH .......................................................................................................................................................33 1.4.9 Secondary Desuperheater .................................................................................................................33 1.4.10 HTS ........................................................................................................................................................33 1.4.11 Reheater Emergence Desuperheater ...............................................................................................34 1.4.12 LTR.........................................................................................................................................................34 1.4.13 Reheater Micro Spray Desuperheater ..............................................................................................34 1.4.14 PRH........................................................................................................................................................34 1.4.15 Air Heater ..............................................................................................................................................35 1.4.16 U Valve ..................................................................................................................................................35 1.4.17 Ash Cooler..........................................................................................................................................36 1.4.18 Ignition System ..................................................................................................................................36
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 6 of 104 Rev. A
1.4.19 Abrasion proof and refractory materials ........................................................................................37 1.4.20 Boiler Steel Structure........................................................................................................................38 1.5 Water Volumes Of Major Boiler Parts: .....................................................................................................38 SECTION 2 SAFETY PRECAUTIONS AND PREPARATION FOR OPERATION.........................40 2.1 SAFETY PRECAUTIONS......................................................................................................................40 2.2 HYDROSTATIC TESTS...........................................................................................................................43 2.3 SOLIDIFYING REFRACTORY MATERIALS .......................................................................................47 2.4 BOILING OUT........................................................................................................................................47 2.4.1 General .................................................................................................................................................47 2.4.2 Recommended Chemicals for Boiling Out.......................................................................................48 2.4.3 Preparations for Boiling Out...............................................................................................................49 2.4.4 Boiling Out Procedure.........................................................................................................................52 2.5 FEEDWATER AND BOILER WATER TREATMENT ..........................................................................54 2.6 CHEMICAL CLEANING OF ECONOMIZER AND STEAM GENERATING CIRCUIT.....................55 2.6.1 General .................................................................................................................................................55 2.6.2 Determining the Need for Chemical Cleaning.................................................................................55 2.6.3 Solvent System ....................................................................................................................................56 2.6.4 General Cleaning Operations ............................................................................................................57 2.7 CHEMICAL CLEANING OF SUPERHEATERS & REHEATERS........................................................58 2.8 BOILER SYSTEM AIR TEST..................................................................................................................58 SECTION 3 OPERATION AND MAINTENANCE .........................................................................60 3.1 GENERAL.................................................................................................................................................60 3.2 IMPORTANT PRECAUTIONS..............................................................................................................60 3.2.1 Furnace doors ....................................................................................................................................60 3.2.2 Furnace Pressure Limits ..................................................................................................................61 3.2.3 Drum Water Level and Temperature Difference...........................................................................62 3.2.4 Safety Valve Adjustment ..................................................................................................................63 3.2.5 Excess Air Requirements .................................................................................................................63 3.2.6 Bed Temperature Profile ..................................................................................................................64 3.2.7 Others..................................................................................................................................................65 3.3 COLD STARTUP PROCEDURE ...........................................................................................................67 3.3.1 Preparation Prior to Startup .............................................................................................................67 3.3.2 Purging................................................................................................................................................71 3.3.3 Warming the Unit...............................................................................................................................77 3.3.4 Start-up (Fuel Firing).........................................................................................................................81 3.4 HOT RESTART ........................................................................................................................................85 3.5 NORMAL OPERATION.........................................................................................................................88 3.5.1 Combustion ..........................................................................................................................................88 3.5.2 Boiler feedwater and steam quality ..................................................................................................90 3.5.3 Sootblowing..........................................................................................................................................90 3.5.4 Spray Attemperation ...........................................................................................................................91 3.5.5 Reheated Steam Temperature Regulation......................................................................................91 3.6 NORMAL SHUTDOWN ........................................................................................................................92 3.7 EMERGENCIES......................................................................................................................................95 3.7.1 Main Fuel Trip (MFT) ..........................................................................................................................95 3.7.2 Emergency Operating Procedure ...................................................................................................96
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 7 of 104 Rev. A
3.7.3 Overpressure Protection ....................................................................................................................99 3.8 MAINTENANCE ......................................................................................................................................99 SECTION 4 ATTACHMENT........................................................................................................103 4.1 Boiler Performance data summary sheet(I) Performance coal 100%B-MCR condition.....................103
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 8 of 104 Rev. A
SECTION 1 CONSTRUCTION DESCRIPTION
1.1 Design Conditions
1.1.1 Boiler Specifications
Boiler capacity: under such conditions as firing performance coal or check coal
stated in item 1.1.3 and limestone stated in item 1.1.4 with the size distribution
specified in fig. 1.1~1.2, design Ca/S molar ratio, rated feed water temperature, rated
main steam temperature, rated pressure and acceptable steam quality, the boiler
maximum continuous rating is 440 t/h at least.
The boiler maximum continuous rating (BMCR) is corresponding to turbine regulating
valve whole open (VWO) condition.
Pressure, temperature and flow of main superheated steam, reheated steam and
feeder water of the CFBB can match with turbine parameters.
Boiler Type: DG440/13.73-II14
BMCR
Maximum Steam Flow 440t/h
Superheat Steam Outlet Pressure 13.73MPa(g)
Superheat Steam Outlet Temperature 540 Reheat Steam Outlet Temperature 540 Reheat Steam Outlet Pressure 2.57MPa(g)
Reheat Steam inlet Temperature 320 Reheat Steam inlet Pressure 2.73MPa(g)
Reheat Steam Flow 356.114t/h
Feedwater Temperature 248.6 Notes: Above mentioned (g) indicates gauge pressure.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 9 of 104 Rev. A
1.1.2 Boiler Main Dimensions
Furnace Width (Between CL of Side Walls) 17170mm
Furnace Depth (Between CL of Front & Rear Walls) 7492mm
Elevation of Steam Drum CL 48370mm
Elevation of Boiler Top 54500mm
Boiler Width 31400mm
Boiler Depth 37100mm
1.1.3 Fuel
Performance coal in this project is asphaltite, a local reserve in the region. The coal
analysis data are as follows:
Item Symbol Unit Performance Coal Worst Coal
Sulfur as received Sar % 1.2 0.5
Hydrogen as received Har % 2.5 1.4
Carbon as received Car % 30 22.2
Nitrogen as received Nar % 0.3 0.3
Oxygen as received Oar % 9.3 7.6
Ash as received Aar % 11.7 30
Total Moisture Mt % 45 38 Volatile matter as dry and ash free Vdaf % 25 20
HHV as received Q Cal/kg 2900 2001 Coal Size Distributiondmax=12mmd50=1.8mm. (See Fig. 1.1Coal Size
Distribution Curve).
Notes: To achieve optimum conditions for the CFB combustion process, the
solid fuel has to be prepared with respect to maximum particle size and
grain size distribution. The recommended coal size distribution is based on
both the balance of solid and emission, which can achieve optimum
combustion and a reasonable emission. Solid fluidizing velocity selection is
based on coal size, and fluidizing velocity defines furnace section. So the
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 10 of 104 Rev. A
coal size is a most important parameter. If the inlet coal size is too large, it
will affect stable operation of the ash-cooler and lead to higher carbon
content in bottom ash; on the contrary, it will lead to higher carbon content
in fly ash.
Fig. 1.1 Coal Size Distribution Curve
1.1.4 Ash Characteristics
Compositions of ash (with no limestone sophisticated)
Composition Symbol Unit Performance Coal Silicon dioxide SiO2 % 5070 Aluminum trioxide Al2O3 % 1030 Ferric trioxide Fe2O3 % 26 Titanium oxide TiO2 % 12.5 Calcium oxide CaO % 0.5610 Kalium oxide K2O % 0.050.3 Sodium oxide Na2O % 014.2 Magnesia MgO % 0.414.83
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 11 of 104 Rev. A
Sulfur trioxide SO3 % 010 Chlorid Cl % 0.010.25
1.1.5 Limestone for Desulfurization
Limestone is used in this project for desulfurization. Limestone analysis data are as
follows:
Composition Symbol Unit Value Loss of combustion L.O.I 42.443.2 Calcium Carbonate CaCO3 9597 Sodium Carbonate MgCO3 0.30.75 Silicon dioxide SiO2 0.81.4 Aluminum trioxide Al2O3 0.40.6 Ferric trioxide Fe2O3 0.10.24 Calcium oxide CaO 53.9554.6 Magnesia MgO 0.20.6 Limestone Size Distributiondmax=1.5mmD50=0.45mm. (See Fig. 1.2
Limestone Size Distribution Curve).
Notes: After limestone powder is injected into the furnace, it is reacted with
SO2 and removes SO2, to guarantee the effective and economical operation
of boiler. The proper limestone size distribution is very important. If the
limestone particle is too coarse or too fine, it will affect the circulation
procedure. The too coarse particle will lead to increased limestone
consumption and will make bed temperature lower than normal value and
bottom ash quantity higher than design value; and the too fine limestone
particle will lead to its inadequate residence time in main circulating loop to
make limestone consumption increase and fly ash quantity higher than
design value.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 12 of 104 Rev. A
Fig. 1.2 Limestone Size Distribution Curve
1.1.6 Igniter Type ,Fuel for Ignition and Combustion Support
The boiler is equipped with four (4) in-duct diesel oil burners , six (6) over-bed heavy
oil burners which are located at the side waterwall, The over-bed heavy oil burners
can be only used to support the combustion at low load.
The in-duct burners firing diesel oil are only used for the low load combustion
support.
The diesel oil analysis data are as follows:
Item Unit Value
Kinematic viscosity(40) cSt 2.5 to 15.7
Density (15) (approximation kg/m3 850 - 870
Flash piont (min) o C 66
Pour point (max) o C 12(winter21 (summer)
Water(max) % vol. 0.25
Sediment and Water (max) % wt 0.10
Sulphur (max) % wt 1.8
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 13 of 104 Rev. A
Item Unit Value
Ash (max) % wt 0.02
HHVapproximation Kcal/kg 10,000
1.1.7 Feedwater Quality
Make-up water: one stage desalination and blend bed.
Boiler normal continuous blowdown rating: 0.3-1%
Boiler water and steam quality shall be in compliance with the requirements of
superhigh pressure boiler in the Quality criterion of Water and Steam for
generating unit and Steam power equipment (GB/T12145-1999).
Item Feedwater
PH value 8.8~9.3
Full salinity /
hardness 2.0mol/L
Hydrazine (N2H4) 10-50g/L (Volatility treatment)
Dissolved oxygen (O2) 7g/L
Fe 20g/L
Cu 5g/L
Oil 0.3mg/L
1.1.8 Fountain
The fountain of this power plant is from IGNP River .
1.1.9 Natural Conditions
Power plant address Bothya city of Rajasthan, Indian height above sea level 184m Maximum daily average temperature in May 40
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 14 of 104 Rev. A
Minimum daily average temperature in December 12
Maximum daily temperature 34.5 Minimum daily temperature 20.7 Recoding Maximum temperature 48.9 Recoding Minimum temperature -1.7 Humidity 2379 Maximum precipitation from July to September 263mm
Annual wind speed 8.5kmm/h Maximum wind speed 24km/h Basic wind speed 47 m/s Modulus K1 1.07 Seismic zone in India 1 Modulus K3 According to IS:875
1.1.10 Operation Mode
1) Load characteristic: The boiler will operated under normal load and can regulate
peak load. The boiler can meet double shift operation requirements.
2) Coal feeding system: Two-stage crushing plus screen system is adopted in this
project to satisfy requirements of coal size distribution.
3) Feed water regulating: Two (2) 100% BMCR motor-driven feed water pumps.
4) Bypass system: Two in-series stage bypass system with capacity of 60%BMCR.
5) Bottom ash removal: Bottom ash is discharged continuously or periodically
through ash cooler.
6) Air heater shall not be arranged in the inlet duct of air preheater.
7) The available average operating hours are more than 7500h per year.
8) Compressed air pressure: 0.5~0.7MPa; electric voltage: AC 400V/230V; DC 220V;
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 15 of 104 Rev. A
motor protection degree: IP54.
1.1.11 Draft Mode
Balanced draft is adopted for this boiler. The balance point of draft system is set at
the top of furnace (cyclone inlet).
1.2 General Description Of DONGFANG Type CFB Boiler
1.2.1 CFB Technology Description
As a cleaning coal combustion technology, the Circulating Fluidized Bed (CFB)
technology has been successfully used in boilers all over the world since 1980s.
The various types of solid fuel combustion systems historically available, such as
stokers, pulverized fuel, and cyclone-fired boilers have distinct and specific
advantages and disadvantages. A few of the disadvantages that are common to each
of them in varying degrees are: Low residence time of fuel in the combustion zone
(except stokers) requires high combustion temperatures to assure adequate
combustion efficiency without excessive unburned carbon losses. High temperatures,
usually more than 980C, contribute to the formation of nitrogen oxides, which are
environmentally objectionable. High combustion temperatures also dictate the use of
post-combustion treatment scrubbers for removal of sulfur dioxide (SO2). When the
combustion temperature is maintained between 850C and 900C, SO2 removal can
be accomplished by injecting limestone (CaCO3) directly into the furnace. The low
ash fusion temperature of many solid fuels goes against the adoption of conventional
combustion systems because the higher combustion temperatures result in the
formation of slag on boiler heat transfer surfaces. The need to overcome these
difficulties when using low-grade fuels has led to the development of fluidized bed
combustion systems. Presently, there are two distinct types of fluidized bed boilers in
commercial operation: bubbling bed and circulating bed.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 16 of 104 Rev. A
1.2.1.1 Bubbling Bed
In the bubbling bed-type boiler, a layer of solid particles (mostly limestone, sand, ash
and calcium sulfate) are concentrated on a grid near the bottom of the boiler. This
layer is maintained in a turbulent state as low velocity air is forced into the bed from a
plenum chamber beneath the grid. Fuel is added to this bed and combustion takes
place. The combustion air velocity of is kept at a minimum value, but it is quite
enough to maintain turbulence in the bed. This velocity is not high enough to carry
significant quantities of solid particles out of the furnace. This turbulent mixing of air
and fuel results in a residence time of five seconds. The combination of turbulent
mixing and residence time permits bubbling bed boilers to operate at a furnace
temperature below 890C. At this temperature, limestone is mixed with fuel in the
furnace to achieve over 90% sulfur removal. Boiler efficiency is the percentage of
total energy in the fuel that is used to produce steam. Combustion efficiency is the
percentage of complete combustion of carbon in the fuel. Incomplete combustion
results in the formation of carbon monoxide (CO) in the flue gas plus unburned
carbon in the solid particles leaving the furnace. In a regular bubbling bed boiler,
combustion efficiency can be up to 92%, with its unburned carbon loss component of
kept within the range of 2% to 5%. This is a good figure, but it is lower than that
achieved by pulverized fuel or cyclone-fired boilers. In addition, some fuels that have
very low volatile matter cannot be completely burned within the solids residence time
in bubbling bed-type boilers.
1.2.1.2 Circulating Fluidized Bed (CFB)
The need to improve the fluidized bed combustion efficiency (which also increases
overall boiler efficiency and reduces operating costs) and the desire to burn a wider
range of fuels has led to the development and application of the circulating fluidized
bed (CFB) boiler. Through the years, boiler suppliers have been increasing the size
of these high-efficiency steam generators. The CFB process offers the means for
efficiently burning a wide variety of fuels while maintaining low emissions. Fuel is fed
to the lower furnace where it is burned in an upward flow of combustion air. Fuel, ash,
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 17 of 104 Rev. A
and unburned fuel carried out of the furnace are collected by a separator and
returned to the lower furnace. Limestone, which is used as sulfur sorbent, is also fed
to the lower furnace. Furnace temperature is maintained in the range of 850C to
950C by suitable heat absorbing surface. This process offers the following
advantages:
Fuel Flexibility The relatively low furnace temperatures are less than the ash
softening temperature for nearly all fuels. As a result, the furnace design is
independent of ash characteristics, which allows a given furnace to handle a wide
range of fuels.
Low SO2 Emissions Limestone is effective sulfur sorbent in the temperature range
of 850C to 950C. SO2 removal efficiency of 95% or even higher has been
demonstrated along with good sorbent utilization.
Low NOx Emissions Low furnace temperatures (850C to 950C) plus staging of air
feed to the furnace produces very low NOx emissions.
High Combustion Efficiency The long solids residence time in the furnace resulting
from the collection/recirculation of solids via the cyclone, plus the vigorous solids/gas
contact in the furnace caused by the fluidization airflow, results in high combustion
efficiency, even with difficult-to-burn fuels. The unburned carbon loss component of
the combustion efficiency is typically in the range of 1% to 2%.
1.2.2 DONGFANG Type CFB Boiler Process
The major components of a DONGFANG CFB boiler are :
z The solids circulation loop, comprising the furnace, the cyclones, U valves.
z The rear pass.
In the CFB process, combustion and desulphurization take place within a large mass
of highly agitated fine ash particles bed at a relatively low temperature (close to 850
900C) depending upon the fuel reactivity. This temperature is chosen to facilitate the
increase of combustion rate and desulphurization efficiency for the coal considered.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 18 of 104 Rev. A
The bed temperature of this boiler is 897.
These particles or "solids" are held in suspension (fluidized) section by an upward
flow of air blown into the bottom of the furnace as the primary air through the
fluidization nozzles. The secondary air is fed into the furnace at two levels, thus
realizing staged combustion.
The bed completely fills the furnace volume (its density, high in the lower part, rapidly
decreases with height). The separation of solids from the gas solids stream at the top
of the furnace is ensured by means of cyclones.
The balance of solids is ensured by directly recirculating the solids separated from
the gas solids stream to the lower part of the furnace through material recycle
equipment (U valve). These U valves are installed to ensure that any gas flows
directly from the furnace to the cyclones.
The fluidization regime in CFB loop is characterized by very strong agitation and
mixing, high solids internal and external recirculation, high gas/solids slip velocity
and long residence time due to the high efficiency of cyclones.
All these result in excellent conditions regarding heat transfer and chemical
reactions.
The flexibility induced by the process allows burning a wide range of fuels
("opportunity fuels"), with a single design adopted.
Regarding depollution, the CFB boiler has very good performance due to the
following reasons:
The CFB boiler is able to remove sulfur dioxide directly in the furnace. This is
accomplished by contact between sulfur oxide and the calcium oxide contained in the
coal ashes or in the added limestone. The limestone is calcined in the furnace to
form calcium oxide (CaO) and then reacts with the SO2 to form calcium sulfate,
shown as follows:
CaCO3 CaO + CO2
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 19 of 104 Rev. A
CaO + SO2 + O2 CaSO4
This reaction takes place preferably at 850-900C, which can be kept under a wide
range of operating loads.
Further, the staged combustion and the relatively low combustion temperature
reduce NOx formation to a large extent.
So, CFB process offers:
z an intense internal mixing of the particles (fuel, limestone, hot ashes constituting the bed)
z a homogeneous temperature in the bed
z a long residence time of the fuel in the furnace
z the possibility to keep the temperature within the optimum range of SO2 capture by the limestone
The combination of these characteristics offers the following advantages in terms of
performance:
z high carbon burnout
z high desulphurization efficiency
z low NOx emission
z high flexibility of operation.
1.3 General Description of DG440/13.73-II14
1.3.1 General Arrangement OF DG440/13.73-II14 Type CFBB
DG440/13.73-II14 CFB boiler adopts single drum, natural circulation, circulating
fluidized bed combustion and full enclosure structure, which is mainly composed by
membrane waterwall furnace, two plate cyclones and the rear pass.
The boiler adopts membrane wall furnace. Inside the furnace, eight platen
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 20 of 104 Rev. A
superheaters, four platen reheaters and one split waterwall are arranged. Six coal
feeders and four limestone feeding inlets are arranged on the lower front waterwall.
The bottom of the furnace is a water-cooled air plenum enclosed by the waterwall
tubes, connecting with the primary air ducts which are at each side of the boiler.
There are two induct burners in each PA duct. The burners are equipped with high
energy ignitor. And six over-bed burners are arranged above the grid for low load
combustion support. In the rear of the furnace, two rolling ash-coolers are arranged.
Between the furnace and the rear pass, two plate cyclones lined with refractory are
arranged. At the bottom of each cyclone, a non-mechanical U-valve seal device is
installed. The dual-element convection rear pass (double flue) is adopted for the
steam-cooled rear pass in the RH and SH area. The cold reheater is arranged in the
front flue and the hot superheater & cold superheater are arranged in the rear flue.
After that the two gas streams will become one stream and pass through economizer.
Then gas is divided into two streams to go through tubular air heater. The air heater
is of double in-let and out-let arrangement along the boiler width direction. Two stage
spray water will be adopted to the superheater system and damper regulation is
adopted to the reheater system. And emergency and micro spray water
desuperheaters are adopted for the safety guarantee of the reheater system.
The boiler is symmetrically arranged from right to left and is suspended or supported
from the boiler steel structure. The steel structure consists of columns, beams and
bracings.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 21 of 104 Rev. A
Fig. 1.3 Side view of Boiler
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 22 of 104 Rev. A
Fig. 1.4 Plan View of Boiler
1.3.2 Boiler Steam and Water Flow Path
Single unit system is adopted in main steam, reheater steam and feeder water
system. And double in-let-and-out-let connection is adopted in main steam and
reheater steam pipe arrangement.
Feedwater is sent to the two sides of economizer inlet header in the rear pass. It
flows upstream and passes the horizontally arranged economizer tubes. Collected in
the outlet header of economizer, it is routed by the connecting pipe into the drum
from the drum head. In the period of boiler start-up, no continuous feedwater flows
into the drum. Economizer recirculation system can direct boiler water from the drum
to the inlet header of economizer, preventing water from steaming in the economizer
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 23 of 104 Rev. A
tubes.
Fig. 1.5 Steam and Water Flow
The DG440/13.73-II14 CFB boiler is of natural circulation. Boiler water circulation
system adopts centralized downcomers and decentralized feeders and risers. Water
from Economizer is directed into the water space of drum, then it enters into the
waterwall inlet header by the downcomers and feeders. Water is heated to the
mixture of steam/water and flows upward through the furnace waterwall and split
waterwall. Out of the waterwall outlet header, the mixture of steam/water is routed by
risers into the drum for steam/water separation. The split waterwall forms an
independent circuit with the separate feeder and riser for the safety and reliability of
water circulation. The separated water reenters the water space in the drum and
circulates again. The separated saturated steam is directed out from the steam
connecting pipe on the top of the drum.
Coming out of the drum, the saturated steam is directed to the upper header of the
side wall of the rear pass area by the connecting pipe. Then it passes the front, rear
walls and middle wall of the rear pass area and joins in the inlet header of low
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 24 of 104 Rev. A
temperature superheater (LTS). After flowing through the tubes of LTS, it is directly
induced into the platen superheater (PSH) in the upper furnace by the connecting
pipe. Passing the PSH, it returns to the high temperature superheater (HTS) in the
rear pass. At last, the steam with the rated pressure and temperature is directed out
from two ends of the outlet header of hot superheater.
The superheater system adopts spray desuperheating as a method for temperature
control and protection of heating surface tubes. The whole superheater system is
arranged with two stages of spray attemperation. The primary desuperheaters (on
the connection pipes of each side of the boiler) are arranged on the connecting pipe
from the LTS to the PSH for coarse adjustment. The secondary desuperheaters (also
on the connection pipes of each side of the boiler) are located on the connecting pipe
from the PSH to the HTS for fine adjustment. In the two stages of spray
attemperation, the quantity of spray water on each side can be adjusted
independently to eliminate the steam temperature difference on the right and left
sides.
The cold reheated steam coming from HP of turbine is induced into the low
temperature reheater (LTR) located in the front flue in the rear pass. After flowing
upward through two banks, it is directly induced into the platen reheaters (PRH) in
the upper furnace by connecting pipe. Heated by the PRH, the reheated steam with
the rated pressure and temperature is induced into MP of turbine.
The reheated steam temperature can be adjusted through regulating gas damper
located at the back of the double flue to adjust gas flow through RH flue. Its a main
method to regulate RH temperature. The RH spray system is also used for faster
adjustment and the safety guarantee of the RH system. The whole reheater system
is arranged with two stages of spray attemperation. The primary desuperheaters (on
the connection pipes of each side of the boiler) are arranged on the inlet connecting
pipe of the LTR for emergence condition. The secondary desuperheaters (also on the
connection pipes of each side of the boiler) are located on the connecting pipe from
LTR to the PRH for faster and more precise adjustment. In the two stages of spray
attemperation, the quantity of sprayed water on each side can be adjusted
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 25 of 104 Rev. A
independently to eliminate the reheater steam temperature difference.
1.3.3 Boiler Gas and Air Flow Paths
Material circulation in the CFB boiler is started and maintained by forced-draft fans
(including primary and secondary air fans) and induced-draft fans.
Air from the primary air fan is sent into the furnace though three paths:
The first path: Hot air after the primary air heater enters into the water-cooled air
plenum at the bottom of furnace. The air coming out of nozzles on the air distributor
fluidizes bed materials. Gas and solid-phase flow is formed, which goes upward
through the furnace.
The second path: Hot air after the primary air heater is pressurized by the blower and
is directed as coal-distributing medium to the air-swept coal spouts.
The third path: Cold air induced before the primary air heater is used as the sealing
air for the belt coal feeders.
Air from the secondary air fan is sent to the furnace from the two layers of overfire
airports on the front and rear walls after the secondary air heater.
Gas and entrained solid particles exit the furnace from the outlet on the upper rear
waterwall and enter into the cyclone from the cyclone inlet flue. In the cyclone, most
of the solid particles are separated from the gas. Cleaned gas is induced out from the
discharge pipe (inner barrel) of the cyclone and directed to the rear pass by the
cyclone outlet flue. It flows into the rear pass from the inlet on the front wall and
sweeps across the LTR, HTS, LTS, economizer and air heater, transferring heat to
the heating surfaces. Then, the gas is routed through the dust collector and finally
sent into the stack by the induced-draft fan and emitted into the atmosphere.
The U-valve seal device is equipped with three blowers with high-pressure head. The
output of each blower is 50% of the total air needed of the U -valve seal device. In
normal operation, two blowers are in service and one blower is standby. The blowers
are of constant volume type. The air flow is adjusted through bypass pipe to the
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 26 of 104 Rev. A
primary air path.
The boiler is of balanced-draft type. The balance pressure point is located at the top
of the furnace.
Full enclosure structure is adopted to this boiler. The operation floor elevation is
9.0m.
Fig. 1.6 Diagram of Air and Gas Flow, Fuel, Limestone, Ash systems
1.3.4 Combustion and Circulation Process of the Materials
The cold start-up procedure of boiler is as follows:
Feed the start-up materials to the bed and U valves;
Start the in-duct burner and send the heated combustion air with the temperature of
870 to the furnace through the water -cooled air distributor for heating the start-up materials.
As the bed temperature reaches 540 and remains stable, the crushed 0 12mm coal particles are sent into the dense-phase zone of the furnace from the six coal
feeders and the crushed limestone particles for desulphurization are sent into the
furnace from the limestone feeding inlets.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 27 of 104 Rev. A
Under the rated load condition, the primary air (about 40% of the total combustion air)
passes through the water-cooled air plenum and enters into the furnace as
combustion air and fluidizing medium of materials in the bed. The secondary air is
directed into the furnace from the two layers of overfire airports on the front and rear
walls to guarantee enough combustion air for coal particles and participate in the
adjustment of combustion. At the same time, the staged secondary air can produce
local reducing atmosphere in the furnace and inhibit oxidation of nitrogen in the fuel
so as to decrease generation of NOx.
At the bed temperature of 864 , air fully mixes with fuel and limestone in the dense-phase zone at the lower furnace. Firing of coal particles releases a part of
heat. CaCO3 is calcined to produce CO2 and CaO; the unburned coal particles are
entrained by gas in the diluted-phase zone at the upper furnace for further
combustion. The upper furnace is also a main desulphurizing zone, where CaO and
SO2 produced by combustion react to produce CaSO4.
The gas entraining rich solids passes through the furnace from two gas outlets on the
upper rear water wall. Then, it enters into two plate cyclones for the solids and gas
separation.
After leaving the plate cyclones and vortex finders, separated hot flue gas passes
through the refractory lined cross-over duct and enters into the top of the dual-flue
rear pass of the boiler. The flue gas splits and flows into the superheating section and
the reheat steaming section. The gas flow distribution of the two sections is decided
by dampers at the outlet of each section. As flue gas flows downward in this steam
cooled section, heat is transferred from the hot flue gas into the reheat steam and
superheat steam. The economizer is located directly below these steam sections. Air
heaters are located in the back of the rear pass. The horizontal tubular air heaters
are devices that heat primary/secondary air before it enters the boiler. Air is heated
as it passes inside the tubes, and the hot flue gas gives up its heat as it flows outside
the tubes. At the outlet of the boiler, gas temperature has decreased to about 149 . The separated solids by the cyclone are reinjected by means of the non-mechanical
U-valve seal device back to the furnace for circulating combustion.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 28 of 104 Rev. A
On the rear wall of the lower furnace, two bed material drain ports are arranged. By
controlling the flow of ash extraction, the bed and furnace pressure profiles are kept
within the design limits to guarantee the good operation of boiler.
1.3.5 Fuel and Limestone Feed Systems and Ash Removal System
Six (6) coal feeders and four (4) limestone feed points are located at furnace front
wall. Four (4) bed material feed points for start-up are located in U-valve, which are
used to feed bed material when boiler start-up or to add bed material during
operation if necessary.
The bed ash from furnace is drained down to two (2) rolling ash coolers. A bed ash
removal system is connected to the rolling slag cooler ash outlet, the rear pass ash
drain (below air heater) and the ESP ash drain.
1.3.6 Expansion System
The expansion centers (fixed points) are designed according to the features of boiler
arrangement and supporting structure. This boiler has seven zero expansion points,
such as:
z The center line of furnace rear wall
z The center line of cyclone support (two points)
z The center line of u valve support (two points)
z The center line of rear pass front wall
z The center line of air heater support.
Each expansion system is expanded outwards from its fixed points through the
limitation and guide equipment. At the same time, the guide equipment of thermal
expansion will transfer wind and seism load to the steel structure.
The furnace waterwall and the rear enclosure wall expand downwards as they are all
hung onto the top plates. The furnace expands from the furnace center line (fixed
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 29 of 104 Rev. A
point) toward two sides through the expansion control devices. The rear pass heating
surfaces expands from boiler center line (fixed point) toward two sides through the
expansion control devices also. Material recycle equipment, cyclone and air heater
expand upwards from their supporting bases, and symmetrically expand onwards
and backwards, leftwards and rightwards.
There is a large temperature difference between furnace, Cyclone and U valve. And
the expansion ratios of the materials for these parts are not the same. So Cyclone
and U valve are supported on the corresponding steel structures respectively. Due to
their large expansion differences and huge dimensions, non-metal expansion joint is
adopted between furnace and cyclone. Metal expansion joints are adopted between
U valve orifice and furnace and between cyclone cone section outlet and U valve to
absorb expansion difference.
The expansion indicators shall be located inside the boiler proper.
1.3.7 Sootblowing System
A complete set of automatic sootblowing equipment is provided to clean the
superheater, reheater and economizer installed in the rear pass and the air heater
elements during operation of the boiler.
Steam for the sootblowers is taken from the outlet header of the low temperature
superheater. The tube socket specification is 606. The steam parameter for sootblower is 14.1MPagand 487 at BMCR condition. There is a pressure reducing station in the sootblowing system
The sootblowers are suitable for fully programmed operation or individual operation.
The blowing sequence can be optimized by the operator in such a way that the
overall sootblowing period is reduced to a minimum.
Taking into consideration the maximum prevailing flue gas temperature at the place
of installation, retractable blowers or rotating blowers may be used.
Long-retractable, part-retractable or rotating steam sootblowers are arranged on two
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 30 of 104 Rev. A
sides of the rear pass for cleaning the high temperature superheater, low
temperature reheater and economizer surfaces.
1.4 Main Equipment of CFB Boiler
1.4.1 Economizer
The economizer located in the rear pass consists of two (2) banks of 42 spiral-finned tubes, which adopt two runs and in-line arrangement. The material of
tube is 20G.
Normal anti-abrasive methods are adopted to protect economizer tubes. Plates are
installed at the inlet of the ECO around the flue to make the gas distribute uniformly.
Feedwater enters the lower inlet header and flows upward through the outlet header,
and is piped to the feed end of the steam drum.
1.4.2 Steam Drum and Drum Internals
The steam drum is located in front of the upper furnace and across the width of
furnace. The steam drum serves as a container of series of steam-water separaters
and a water reservoir for the steam generation circuits. The drum contains
steam/water separating equipment and internal piping for distribution of chemicals to
the water, for distribution of feedwater and for blowdown. The inside diameter of
steam drum is 1600mm, and the straight section of its shell is 12.3m long.
1.4.3 Furnace
The furnace is a 17170mm width 7492mm depth combustion chamber consisting
of front, rear, side waterwalls and split waterwalls.
At the bottom of the furnace, the front wall splits to form both the plenum floor and the
fluidized bed grid floor. Together with side walls, they form the water-cooled air
plenum. The water-cooled air plenum is lined with refractory to protect the tubes from
being eroded 870 high temperature gas. The grid floor is made up of internal
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 31 of 104 Rev. A
ribbed tubes (82.55) plus flat bar. Nozzles are fixed on the bar to insure the uniform distribution of the primary air and the bed materials and at the same time, to sweep
coarse solid particles and sundries toward to the discharge port. The elevation of the
grid floor is 7000mm.
The furnace is divided into lower, middle and upper part. The longitudinal section
view of lower furnace is trapezoid-shaped as the lower front and rear wall intersects
with the horizontal plane at an angle of 72 . The tube spacing for front wall (and roof), rear wall and side walls is 80 (60 tubes). Combustion occurres mainly in lower furnace, where the bed material is most dense and most active. Total air and fuel
needed for the combustion are sent to the combustor through this part. Besides the
primary air is induced through the grid into the lower part, the staged secondary air is
also fed in.
Six (6) fuel feed points and four (4) limestone feed points are located on the front wall
of the furnace. The middle and upper waterwalls are also made up of membrane wall.
At the top of furnace, the front wall bends toward the rear wall to form the furnace
roof which terminates in the upper header.
Abrasion resistance material is laid on the lower high density zone waterwall and split
waterwall. And it is also laid on all the areas near the gas outlet of upper furnace.
1.4.4 Cyclone
2 cyclones with internal diameter 7.5m are arranged between the furnace and the
rear pass. They are made of carbon steel sheets lined with refractory material. The
upper part is columnar, and the lower part is coniform. Gas outlet (vortex finder) is of
columnar plate structure with open ends. Gas and solid is separated in the cyclone.
The clean gas leaves the cyclone through the vortex finder and the solids enter into
the material recycle equipment directly to be fed into the furnace again.
The vortex finder is made of RA-253MA, anti-abrasive high strength steel.
Purge air nozzle are located in the inlet duct of cyclone to avoid ash buildup during
low load operation or shutdown. The purge air is stopped when the boiler is operating
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 32 of 104 Rev. A
under normal condition. Purge air is from boiler compressed air.
1.4.5 The Rear Pass
The rear convection pass has a 11811mm6350mm section. The upper part of the rear pass is made up of enclosure wall superheater. The rear shaft is divided by the
middle enclosure wall into two sections (the front flue and the rear flue). Here, the
bottom elevation of enclosure wall is 36040mm, below which the rear shaft is clad
with steel plates. The rear pass houses the horizontal banks of air heater, convection
economizer, LTS, HTS and LTR.
All enclosure walls are connected through inlet and outlet headers. The rear pass
front wall top tube spacing is increased from 127mm to 381mm to form a flue gas
inlet passage. The front and rear wall top tubes bend toward the middle wall to form
the rear shaft roof. The tube specification of the front, middle, rear walls and side
walls is 51, and the specification of hanging tubes for the front and middle wall screens is 63.5.
1.4.6 LTS
LTS is located in the lower rear flue of the rear shaft, and consists of 92 pieces of
dual loop horizontal tubes (51) arranged in line across the width of the boiler (counter to the gas flow).
The bank is fixed on the enclosure wall through the fixture and expands together with
the enclosure wall.
Normal anti-abrasive methods such as wearing plates are adopted to protect LTS
tubes. The distribution plates are also installed at the inlet of LTS around the flue to
make the gas distribute uniformly.
1.4.7 Primary Desuperheater
The primary spray water desuperheater is located in the steam connecting pipe
between LTS outlet header and PSH inlet header. The desuperheater is equipped
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 33 of 104 Rev. A
with a mixing liner and spray water piping. The liner is installed at the downstream of
the spray piping to protect the desuperheater shell from thermal shock. Instruments
are installed in spray water piping to measure the water flow and the water
temperature ahead of the desuperheater.
1.4.8 PSH
PSH (8 pieces) is arranged at the upper furnace near the front wall. PSH is
membrane wall construction with tube spacing of 63.5mm. Each platen consists of 43
tubes (12Cr1MoV, 51). Below the elevation 23715mm, the platen superheater is lined with refractory. The whole platen superheater expands upwards.
An outlet header (325) is located at the elevation 43666mm.
1.4.9 Secondary Desuperheater
The secondary spray water desuperheater is arranged in the steam connecting pipe
between PSH outlet header and HTS inlet header located at the rear wall of the rear
shaft. The superheated steam temperature is further controlled by the secondary
desuperheater. The construction of secondary desuperheater is basically the same
as that of the primary desuperheater.
1.4.10 HTS
Steam from the secondary desuperheater flows through connecting pipe into the
HTS, which is located at the upper rear flue of the rear shaft. The steam is introduced
into two ends of HTS inlet header and after flowing across HTS tube banks (counter
to the gas flow) goes into HTS outlet header, and then flows into the main steam pipe
from the two ends of the outlet header.
HTS is located in the upper rear flue of the rear shaft, and consists of 92 pieces of
dual loop horizontal tubes (51) arranged in line across the width of the boiler (counter to the gas flow), which is divided into two banks (HTS1 and HTS2).
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 34 of 104 Rev. A
1.4.11 Reheater Emergence Desuperheater
The reheater emergence desuperheater is located in the upstream of LTR inlet
header to protect RH from excessive high temperature. The desuperheater is similar
to SH desuperheater. Instruments are installed in spray water piping to measure the
water flow and the water temperature ahead of the desuperheater.
1.4.12 LTR
LTR is located in the front flue of the rear shaft, and consists of 92 pieces of trinary
loop horizontal tubes (51) arranged in line across the width of the boiler (counter to the gas flow).
The bank is fixed on the enclosure wall through the fixture and expands together with
the enclosure wall.
Normal anti-abrasive methods such as wearing plates are adopted to protect cold
reheater tubes. The distribution plates are also installed at the inlet of the cold
reheater around the flue to make the gas distribute uniformly. The first row of tubes
facing the gas is covered by wearing plates.
1.4.13 Reheater Micro Spray Desuperheater
The reheater micro spray desuperheater is located in the steam connecting pipe
between LTR outlet header and PRH inlet header, which is used to regulate reheater
steam temperature together with gas dampers. The desuperheater is similar to SH
desuperheater.
1.4.14 PRH
PRH is arranged at the upper furnace near the front wall, which consists of 4 pieces.
PRH is membrane wall construction with tube spacing of 89mm. Each platen
consists of 29 tubes (76mm). Below the elevation 28782mm, PRH is lined with refractory. The whole PRH expands upward.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 35 of 104 Rev. A
The specification of its inlet header is 508mm, and the specification of its outlet header is 457.2mm.
1.4.15 Air Heater
The air heater adopts horizontal, in line and four-loop arrangement, which is located
in the lower part of the rear shaft. Air flows inside the tubes while gas flows outside
the tubes.
For each loop, 1-1/4 inch tubes are adopted to its upper two rows of tubes and the
right and the left sides of tubes, the other tubes are 40mm tubes. Q215-A tubes are used for the upper three tube banks, and 09CuPCrNi-A tubes are used for the lower
part of the fourth bank
The transverse spacing and longitudinal spacing of each tube bank are 80mm and
60mm respectively. The primary and secondary tube banks are arranged in two
parallel lines. Each two tube banks are connected by air duct to form two
independent paths. The primary air and the secondary air are supplied by
independent fans, and they go through their air ducts and heated by the flue gas
which flows across the tube banks. The primary and secondary air ducts are of
double inlet and outlet configuration and arranged along the width direction of the
boiler. The air temperature at the outlets is 290 .
1.4.16 U Valve
The solids from the cyclone flow through U valve seal device. There are two U valves
which are arranged below the cyclone and supported on the beams of boiler steel
structure. The expansion joints are located between the cyclone to U valves and U
valves to the furnace. U valves have two functions: one is to reinject solids into
furnace continuously and steadily to realize the balance of materials; the second is to
provide sealing between the cyclone (negative pressure) and the furnace (positive
pressure).
The outlet duct of each U valve is divided into two parts. So the solids from each U
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 36 of 104 Rev. A
valve return to the furnace by two passes, ensuring that the solids return evenly.
The power source of solids reinjecting is from the pressure difference from gap of
solids levels between the vertical leg and reinjecting leg of U valve. Besides the
proper air distribution by the bottom plenum, the vertical leg is equipped with five (5)
layers of aeration nozzles for fluidizing solids in order to ensure that solids are
reinjected back to the furnace continuously and steadily. The fluidizing air for U valve
is supplied by the separate blowers with high pressure and small flow.
The vertical leg is equipped with pressure-measuring instrument. By means of
controlling the pressure differences, the solids level is strictly controlled so as to
prevent the furnace gas from back-flowing into the cyclone during pressure pulsating.
The start-up bed material inlets are arranged at the reinjecting leg of U valve.
Emergence discharge ports are located at the bottom of U valve, which are used for
maintenance and emergence condition.
The shell of U valve is made of steel plates. The inner diameter of U valve is
1510mm. To prevent the abrasion due to the gas current with high temperature and
high-density dust, U valve is lined with anti-abrasion and refractory materials.
1.4.17 Ash Cooler
On the rear wall of the furnace, two rolling ash coolers are arranged. Part of the spent
bed materials comes to the bottom of the furnace and are then drained to the ash
coolers through solids transfer pipes. The drain openings of the bottom ash in the
furnace are located at the elevation of 7196mm.
The installation and maintenance of ash cooler are shown in INSTALLATION AND
MAINTENANCE MANUAL provided by the ash cooler manufacture
1.4.18 Ignition System
Two kinds of start-up ignition equipment or over-bed ignition and in-duct ignition are
adopted for this boiler. 6 pieces of over-bed heavy oil burners with heat input of 15%
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 37 of 104 Rev. A
rated load are located on both the side and rear walls of the lower furnace. 4 pieces
of in-duct burners with heat input of 15% rated load are located in the primary air
ducts below the water-cooled air plenum.
The in-duct burners for startup heat the primary air to 870. Then the hot primary air heats bed materials through air distribution device to ignition temperature. High
energy ignitor and flame scanner is provided for the burner.
1.4.19 Abrasion proof and refractory materials
Abrasion proof and refractory materials are required in all DONGFANG CFB boilers
to ensure the safe and reliable operation of the boilers.
Some parts of the CFB boiler are not pressure parts and are not cooled by the
circulating water and/or steam, but they are exposed to high temperature and high
velocity flue gas. These parts include typically cyclone, U valve etc., which are not
designed with heat transfer surface. So their inside surfaces are lined with two or
three layers of abrasion proof and refractory materials. The layer nearest to the outer
metal plate is insulating layer; the layer facing the gas is an abrasion-resistant layer.
Experience has shown that erosion in a CFB boiler can be reduced through proper
design of pressure parts and abrasion-resistant refractory coverage in key areas.
Abrasion-resistant and refractory materials selected for the protection of pressure
part also have low insulating characteristics, so the heat transfer and boiler
performance are not affected excessively. Refractory coverage of pressure parts in a
CFB boiler is primarily in the furnace. These areas include:
Lower furnace The lower part of the furnace is considered as the portion that has
the highest density of bed material. The bed material is mixed with incoming fuel and
limestone and fluidized by the grid nozzle airflow. The smaller particles are entrained
in the upward flow while the bigger particles fall back to the grid floor. The particles in
this area have very abrasiveness. So abrasion-resistant and refractory materials
shall be laid from the grid floor to the juncture of the vertical wall and the bevel wall in
the combustor. Abrasion-resistant and refractory materials are laid on both the side
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 38 of 104 Rev. A
walls (including split wall) near the furnace outlet.
Penetrations and discontinuities CFB boiler operating experience has shown
that erosion in the many locations of the furnace will not occur if there are no
discontinuities that would change the flow direction of the particles in the furnace.
Thus, the system is designed to eliminate unnecessary discontinuities. In the
locations where discontinuities must exist, such as platen surface penetrations and
the measure openings on the furnace, proper protection measures shall be taken
such as shielding or refractory coverage, or a combination of several protection
methods.
Furnace flue gas outlet This area is subject to high velocity flue gas with bed
material, so proper protection measures shall be taken to prevent the tubes in this
area from being eroded.
1.4.20 Boiler Steel Structure
The boiler steel structure is of bolted and welded construction and full enclosure
arrangement. There are eight (8) main columns for supporting boiler. The columns
are connected to the foundation at the elevation of -500mm by reinforcing bars.
Horizontal beams and vertical supports are provided between the columns to
withstand the loads of boiler proper, wind and earthquake.
The major pressure parts of the boiler (steam drum, furnace waterwalls, rear pass
gas flue, etc.) are hung by hangers from the top plates. Other components of the
boiler, such as ash cooler, air heater, in-duct burner, cyclone etc. are all supported on
the horizontal beams or on the earth by supporting devices or reinforcements.
Platforms and stairs are located in the locations where maintenance or inspection
shall be performed during boiler operation.
1.5 Water Volumes Of Major Boiler Parts:
Part Name During Hydraulic test (m3) During Operation(m3)
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 39 of 104 Rev. A
Steam Drum 27.7 12.2
Waterwalls 87.3 87.3
Superheaters 35 0
Reheaters 44.2 0
Economizers 17.7 17.7
Total 211.9 117.2
Note: 1. The volume of waterwalls includes the volumes of downcomers, feeder pipes,
split waterwall and headers.
2. The volumes of superheaters, reheaters and economizers all include the
volumes of their headers and connecting pipes.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 40 of 104 Rev. A
SECTION 2 SAFETY PRECAUTIONS AND PREPARATION
FOR OPERATION
2.1 SAFETY PRECAUTIONS
Safety is primary for any boiler operation.
The following descriptions are some of the general precautions which shall be
applied when a steam generator first comes into operation. They are intended to
supplement the experience and judgment of personnel in charge of operation and do
not cover all precautions which shall be observed.
The manufacturer has complied with the national code pertaining to the design and
fabrication of boiler. A newly erected unit, prior to being put into operation, must be
carefully inspected by the authority to assure that all components or parts accord with
the design requirements.
All boiler auxiliary facilities must be in the first class operating condition, and meet the
design operation conditions and can operate in accordance with the manufacturers
recommendations and instructions. Here is an initial start-up check list for boiler
auxiliary equipment.
NOTE
The following items shall be checked prior to start-up of the boiler.
1. All fans and blowers shall be operable. Lubrication systems shall be operable.
Equipment shall be able to operate within the allowable variation of vibration.
2. All dampers, controllers and actuators shall be subjected to internal and external
inspection. The boiler auxiliary equipment shall be operable under the full range of
operation conditions and shall be free of caking or jamming. It is confirm that all
dampers can actually move to the stipulated positions as per the control
requirements.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 41 of 104 Rev. A
3. Ensure that the ash removal system is connected with the ash cooler and that the
ash cooler is well ready for operation.
4. All remotely operated valves and slide gates shall be operable, and their limit
switches shall be checked to ensure their proper installation, thus guaranteeing
the accurate position indications.
5. All conveyors shall be trial-operated to ensure their normal operation.
6. All flow elements shall be calibrated.
7. The over-bed/in-duct burners, flame detectors and interlocks shall be operable.
8. All thermocouples and pressure sensors shall be checked and calibrated to
ensure their normal operation.
9. All flues, ducts, pipes, chutes or conduits through which air, gas, water, steam or
solids flow shall be connected accurately and reliably.
10. All expansion joints shall be inspected to ensure that proper connections have
been made.
11. All dust catchers shall be checked to ensure their normal operation.
12. All electrical connections shall be inspected to ensure their proper erection and
good insulation.
13. The remote drum water level indicator shall be checked, comparing its readings
with the readings indicated by the local water level gauge. This process must be
done periodically.
z Before a new boiler is put into service, the following items shall be checked:
1. The local drum water level gauge must be installed and checked in accordance
with the drawings prior to preliminary operation. When the water level of drum is
below the lowest visible point of the water level gauge, the gauge shall be drained.
Whenever gauge maintenance or replacement is done, it is necessary to verify
that its drain is normal.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 42 of 104 Rev. A
2. Blowdown pipeline for water level gauge shall lead to the safe zone and drain
valves must be closed. The water level gauge must properly illuminated so that
that the operators on the operating floor can observe its readings sharply.
3. All vent, drain and blowdown pipelines shall be accessible and properly
connected with a blowdown tank or shall lead to other safe locations so as to
ensure the safety of personnel.
4. Valves that are located between the drum and equalizer and water level gauge
must be in the full open position.
5. All safety valve gags and hydrostatic test closure plates must be removed and
these valves must be in good condition. The steam discharge pipes of safety
valves shall be arranged and supported in accordance with the safety valve
manufacturers recommendations.
6. Drum internals must be properly installed in accordance with the drawings to
assure that there is no steam bypassing the internals.
7. All test interfaces, as deemed necessary, must be installed.
8. A leak test shall be conducted for the steam generators air and flue gas systems,
and all leaks shall be eliminated in accordance with Paragraph 2.8.
9. Heat emission zone of the boiler shall be insulated or roped off to ensure the
safety of personnel.
10. The thermal expansion of equipment shall not be disturbed by the temporary
scaffold, ladder, fragment and any construction material left.
z In addition to the above, the following items shall be thoroughly checked each time before operation:
1. All necessary operating instruments, both permanent and temporary, must be
installed and correctly calibrated, and be able to operate reliably.
2. All areas must be sufficiently illuminated to guarantee the safety operation of
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 43 of 104 Rev. A
boiler.
3. All hazardous barriers shall be cleared away. Unobstructed walkways and
platforms as well as ladders or stairways shall be arranged in the locations where
operation and observation are performed.
4. Air and gas passages must be unobstructed and can be thoroughly purged by the
circulating air of the unit.
5. The boiler feedwater must be ample, uninterrupted and qualified once the unit is
put into operation.
6. An ample and reliable fuel /limestone supply shall be available.
7. All access and observation doors must be closed after it is ascertained that no
one is inside the unit.
8. Drum manholes must be closed and sealed properly.
After it is assured that the above precautions are fully understood and have been
complied with, subsequent operations such as Drying Out, Boiling Out, Initial
Starting and Normal Starting can be initiated.
2.2 HYDROSTATIC TESTS
The steam generating unit shall be subjected to a hydrostatic test after the erection of
pressure parts is completed. A hydrostatic test shall also be made upon the
completion of each general overhaul or any repair affecting pressure parts of the unit,
or at any time when it is desirable to perform leak inspection.
CAUTION
THE BOILER TO BE TESTED SHALL BE FILLED WITH TREATED
WATER.
If the unit is not to be put into service after the hydrostatic test, proper treatment shall
be done, namely 200300ppm hydrazine plus sufficient ammonia or morpholine is used to raise the pH to 10. If the unit is to be put into service within a short time, the
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 44 of 104 Rev. A
treatment may be done as per the normal operation procedures. It is strongly
recommended that the unit be filled with the demineralized water or condensed water
for the test.
If the inventory of demineralized water or condensed water is limited, certain parts of
the unit may be filled with treated potable water or other water free of corrosive and
suspended materials. This water is not to remain in the unit for wet storage because
only demineralized water or condensed water can be used for wet storage.
For the test of drainable parts, the water with chloride content of less than 50ppm and
temperature of less than 52 may be used. But these parts must be subsequently be rinsed with condensed or demineralized water prior to operation.
The standard Supervision code for safety technology of steam generation boiler,
issued by the Labor Ministry of the Peoples Republic of China, specifies that the unit
shall be subjected to a hydrostatic test prior to the first operation or upon the
completion of any repair or change of pressure part. The hydrostatic test of the
primary water-steam system covers most pressure parts including superheaters,
furnace and economizer (as a whole), and its test pressure is 1.25 times of the drum
design pressure. The hydrostatic test of the reheat steam system, also called the
secondary steam system, covers LRH and PRH, and the test pressure of the reheat
steam system is 1.5 times of the inlet working pressure of LRH. The water
temperature of all hydrostatic tests is 2070 and shall be higher than the ambient temperature. Before applying a hydrostatic test to the unit, a thorough internal and
external inspection shall be done to ensure the completion of the following items:
1. All sundries and tools have been removed.
2. No one is inside the unit.
3. The manometer has been correctly calibrated and erected on the drum outlet
piping, with valves open.
4. Any part which is designed not to withstand the hydrostatic test pressure is
properly isolated or blanked off from such pressure.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 45 of 104 Rev. A
5. All valves are operable and in the right position.
6. All steam system spring hangers are pinned in the fixed position.
7. All safety valves are gagged; all power actuated relief valves are decoupled.
After the foregoing items have been carefully checked:
1. Verify that drum manholes are properly closed.
2. Close stop and check valves, all drain and blowdown valves and other valves for
any gage or other internal equipment which is designed not to withstand the
hydrostatic test pressure.
3. Open the vents on the highest point of each component or part of the unit.
4. Be sure that the water will not be frozen during test and the unit will not be
subjected to freezing conditions following the hydrostatic test.
5. If during hydrostatic test, the water temperature is above 50 , it is necessary for the operators close to the unit to be careful in order to avoid the possible scald
from water leakage.
6. Check that only authorized personnel are in the vicinity of the unit to be tested.
When starting to fill the unit with water, the water temperature shall be close to the
metal wall temperature of the drum. The temperature of all other pressure parts shall
not be less than 20 .
CAUTION
WHENEVER THE HYDROSTATIC TEST PRESSURE EXCEEDS
5.1MPa, THE MINIMUM DRUM METAL WALL TEMPERATURE
AND WATER TEMPERATURE20MUST BE OBSERVED TO INSURE THAT THE HYDROSTATIC TEST IS PERFORMED ABOVE
THE BRITTLE TO DUCTILITY TRANSITION TEMPERATURE FOR
THE METAL.
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 46 of 104 Rev. A
z To obtain this hydrostatic test temperature, the following procedures are recommended (items 1 and 2).
1. If the boiler in-duct burner system cannot function, as may be the case for the
initial operation, any of the following methods (1), (2) and (3) is recommended.
(1) Use an external thermal source to heat so that the recommended
minimum temperature is obtained, as indicated by the drum surface
thermocouples.
(2) Use small oil and/or gas guns aimed through doors or resting on the grid
nozzles to raise the temperature to the recommended one. The boiler
tubes shall be kept away from the flame.
(3) If the medium temperature in the drum is below 20 , saturated steam may be fed into the drum through the drum blowdown or chemical feed
pipes to heat the water and the drum shell to the required temperature.
When the drum water level reaches the normal operating level, the
water shall be heated to a temperature 2 5 more than the recommended temperature so that the final water temperature will not
be below the recommended minimum temperature.
2. If the boiler in-duct burner system can function, the following procedure is
recommended:
(1) After the unit water level reaches the normal water level, the in-duct
burners are ignited to raise the drum temperature to 25 more than the recommended temperature.
(2) Switch off the in-duct burners and continue to fill the unit with water, and
at the same time inspect the drum drain pipelines and manholes for
leaks. Close the vent valves when water pours out of the vents located
at the highest points of the unit.
(3) Raise the pressure to the test pressure slowly. The recommended rate of
pressure rise shall not exceed 0.3MPa per minute to avoid the
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 47 of 104 Rev. A
occurrence of excessive pressure fluctuate.
(4) If the hydrostatic test pressure exceeds the design pressure, it is
necessary to reduce the pressure slowly. When the pressure is equal to
the operating pressure or the design pressure, the unit shall be
thoroughly inspected for leaks only at operating or design pressure. After
this inspection is completed, release pressure slowly at the
recommended rate of pressure release (not exceeding 0.3MPa per
minute), and open the vent and drain valves. Superheater system must
be thoroughly drained.
(5) If temporary manhole gaskets are used during the initial hydrostatic test,
they are to be replaced with proper gaskets before refilling the unit for
operation.
(6) Remove gags from safety valves and pins from spring hangers after the
test has been completed.
2.3 SOLIDIFYING REFRACTORY MATERIALS
All refractory materials shall be cured solidified and dried at the field by the erection
company in accordance with the refractory manufacturers recommendations to
assure that their actual performances meet the relative requirements.
2.4 BOILING OUT
2.4.1 General
Boiling out is a process to remove oil and grease inside the unit, and the cleaning
medium is usually a strong alkaline solution.
The presence of even very thin films of oil or grease or their decomposition products
on the boiler heating surfaces will seriously retard heat transfer. This film acts as a
dangerous heat insulating film and retards the rapid transmission of heat from the
metal to the boiler water. The resultant increase in metal temperature may cause
Doc.No.: 39J-SM Operation Instruction for CFB Boiler Page 48 of 104 Rev. A
overheating and blistering of boiler tubes and even burst of tubes at high loads.
During the boiling out process, the gage glass may become badly discolored and
permanently etched. Our suggestion is that the customer has spare gage glass
fittings on hand. All the inoperable gage glasses shall be restored after boiling out
and chemical cleaning and before refilling the unit with water. The ordering and
replacement of gage glass shall be based on the manufacturers instruction.
The chemical shall be dissolved in water before being fed to the boiler and shall
never be fed to the boiler in the solid form. When handling corrosive materials, it is
necessary to ensure that the eyes, skin or clothing of the operator are bespattered by
them. When mixing these materials, it is recommended that goggles, rubber gloves
and cotton clothing be employed.
The chemical solution shall not be fed to the boiler in high concentration through the
regular chemical feed system because the high concentration solution may block up
the chemical feed piping and valves.
If the chemicals for boiling out must be injected to the boiler drum through the
chemical feed system, the solution concentration in the mixing tank shall be diluted,
namely 5% ahead of the chemical feed pump suction, and the pump and chemical
feed pipelines shall be flushed thoroughly after the pumping is completed.
2.4.2 Recommended Chemicals for Boiling Out
Alkaline chemicals such as soda ash and caustic soda are commonly used for boiling
out because these agents possess the ability to saponify the oils and greases to form
a soap compound that is easily removed through high pressure blowdown during the
boiling out process, and after the completion of boiling out, the unit shall be flushed
with cold water through a high pressure hose.
Phosphate (trisodium phosphate and disodium phosphate, accompanied by either
caustic soda or soda ash) may also be used as an agent to thoroughly clean the
internal surfaces of the boiler. In this connection, an embrittlement inhibitor and a
commercial wetting agent shall be added in the boiling-out solution.
Doc.No.: 39J