Upload
phoebe-page
View
220
Download
0
Tags:
Embed Size (px)
Citation preview
December 2, 2004 CongestionCauses and Effects
Presented to WMSJanuary 14, 2005
Beth Garza
BGarza / January 14, 2005 / WMS
2
Issue Statement
Transmission Outages on Dec 2 & 3 lowered the NE-N CSC limit to a level where TCRs became very valuable and payments to TCR holders exceeded congestion payments by over $6 M which was uplifted through BENA
BGarza / January 14, 2005 / WMS
3
Topics to Cover
• Day Ahead Info
• Prices
• Transmission Outages
• BENA/Uplift effects
• TCR Auction vs. Day Ahead Limit
• Pre-controlling CSC limits
BGarza / January 14, 2005 / WMS
4
Transmission Limits to Be MonitoredFor: Thursday 12/02/2004
The maximum total loading on the following Zonal and Local Constraint monitored elements should be maintained. Local constraints will be resolved with Real Time Contingency Analysis
Time
South to North
SDSES–TMPSW
__ Potential IROL
Northeast to North
(Sum of 2 Farmerville - Royse)
__Potential IROL
South to Houston
(Sum of 3 STP-DOW & STP-WAP)
__ Potential IROL
West to North
Graham – Parker/ Benbrook
__ Potential IROL
North to Houston
Gibbons Creek – O’BrienJewett – T.H. WhartonJewett – TomballRNS – Kuykendahl
__ Potential IROL
00:00- 06:00
840400
1660 600 2460
06:00 -12:00
840100
1660 600 1670
12:00 -23:00
840100
1660 600 1670
23:00 -24:00
840400
1660 600 2460
Northeast => North Loss of single 345 kV circuit Collin-Carrolton results in overloading of Krugerville-Denton Arco 138 kV line
Above Zonal limitations are based on the following:
BGarza / January 14, 2005 / WMS
5
Transmission Limits to Be MonitoredFor: Thursday 12/02/2004 REVISED[1]
The maximum total loading on the following Zonal and Local Constraint monitored elements should be maintained. Local constraints will be resolved with Real Time Contingency Analysis
Time
South to NorthSDSES–TMPSW
__ Potential IROL
Northeast to North(Sum of 2 Farmerville - Royse)__Potential IROL
South to Houston
(Sum of 3 STP-DOW & STP-WAP)__ Potential IROL
West to NorthGraham – Parker/ Benbrook__ Potential IROL
North to HoustonGibbons Creek – O’brienJewett – T.H. WhartonJewett – TomballRNS – Kuykendahl __ Potential IROL
00:00- 06:00
840400
1660 600 2460
06:00 -11:00
840100
1660 600 1670
11:00-12:00
840270
1660 600 1670
12:00 -23:00
840270
1660 600 1670
23:00 -24:00
840400
1660 600 2460
Northeast => North
Loss of single 345 kV circuit Collin-Carrilton results in overloading of Krugerville-Denton Arco 138 kV line
[1] Revision was made to reflect a change in online units from the day-ahead study.
BGarza / January 14, 2005 / WMS
6
MCPE by Interval Ending
-$2,500.00
-$2,000.00
-$1,500.00
-$1,000.00
-$500.00
$0.00
$500.00
$1,000.00
Interval Ending
MC
PE
($)
NORTH
SOUTH
WEST
HOUSTON
NORTHEAST
December 2, 2004
BGarza / January 14, 2005 / WMS
7
Interval Ending MCPE Results
02-Dec-04 NORTH SOUTH WEST HOUSTONNORTHEAST
3:15 $76.43 $14.08 $74.69 $41.15 $77.32
3:30 $86.55 $8.12 $84.37 $42.17 $87.68
3:45 $72.89 $19.33 $71.40 $42.58 $73.66
4:00 $76.93 $25.80 $75.51 $48.00 $77.67
4:15 $54.15 $30.68 $53.50 $40.87 $54.49
4:30 $51.12 $35.28 $50.68 $42.16 $51.35
4:45 $89.06 $9.07 $86.84 $43.80 $90.21
5:00 $442.54 $5.50 $369.84 $194.39 $9.10
5:15 $101.73 $2.50 -$223.75 $41.06 -$2240.71
5:30 $459.19 -$198.33 -$298.20 $46.00 -$299.00
5:45 $459.19 -$11.40 -$298.20 $73.15 -$299.00
6:00 $459.19 $35.00 -$298.20 $73.15 -$299.00
6:15 $459.19 -$20.00 -$289.00 -$872.20 -$299.00
6:30 $41.88 $41.88 $41.88 $41.88 $41.88
Balancing Energy Information for Market Day: 2-Dec-04
BGarza / January 14, 2005 / WMS
8
Zonal Shift Factors for NE-N CSC
The most effective combination to relieve NE-N congestion is to Balance Down in the NE / Up in the North.– 41.31% impact
West
+0.23%
North-5.51%
NE
+35.8%
South
-3.76%
Hou
-4.44%
ZoneMarginal Cost
MW deployed
Shift Factor on NE-N
MW impact Cost
Northeast 9.1 -2.42 35.80% -0.867 ($22)
North 442.54 2.42 -5.51% -0.133 1072
0 -1 $1049
BGarza / January 14, 2005 / WMS
9
Shadow price and Northeast MCPE calculation for December 2 / 05:15
ZoneMarginal Cost
MW deployed
Shift Factor on NE-N
MW impact Cost
Houston
41.06 107.34 -4.44% -4.766 $4407
West -223.75 -6.75 0.23% -0.016 $1510
South 2.50 -100.64 -3.76% 3.784 ($252)
North 101.73 .05 -5.51% -0.003 $ 5
0 -1 $5670 Shadow Price
Power balance is maintained while reducing flow on NE-N CSC
Once Down Balancing in the Northeast is exhausted, the system looks to other zones
MCPE for the Northeast is now determined from its relation to these costs
MCPEz – MPCE NE = SP*(SFNE – SFz)
MCPEz – SP*(SFNE – SFz) = MCPENE = $2241
BGarza / January 14, 2005 / WMS
10
Hour Price MW Hour Price MW Hour Price MW
7 40 270
5 14 36 6 14 36 7 14 313
5 13 71 6 13 71 7 13 356
5 12 107 6 12 107 7 12 399
5 11 143 6 11 143 7 11 441
5 10 179 6 10 179 7 10 484
5 9 214 6 9 214 7 9 527
5 8 250 6 8 250 7 8 570
5 7 278 6 7 278 7 7 592
5 6 306 6 6 306 7 6 614
5 5 333 6 5 333 7 5 637
5 4 361 6 4 361 7 4 659
5 3 389 6 3 389 7 3 681
5 2 417 6 2 417 7 2 703
5 1 444 6 1 444 7 1 726
5 0 472 6 0 472 7 0 748
5 -1 500 6 -1 500 7 -1 770
5 -299 505 6 -299 505 7 -299 775
5 -1000 505 6 -1000 505 7 -1000 775
Aggregated Balancing Energy Down BidsNortheast Zone - December 2, 2004
Hour
Generation Scheduled
MW% Offered as DBES
5 2148 – 2222 22-23%
6 2482 – 2924 17-20%
7 3388 23%
BGarza / January 14, 2005 / WMS
11
Key Transmission Outages
Element Requested Start End
Olinger – Ben Davis /138kV 10/13 12/1 07:0012/1 06:50
12/2 17:0012/1 17:13
Olinger – Firwheel /138kV 10/13 12/3 07:0012/3 06:50
12/4 17:0012/4 17:23
Collin SES – Bridges /138kVUpdated
11/1211/23
11/15 00:1511/20 08:03
12/3 12:0012/4 20:00
Royse Switch CB_4620Removes Royse SW – Allen SW /345kV 11/16
11/29 07:0011/29 08:55
12/12 20:0012/11 13:33
Dalrock Road – Rockwall TapRowlett Tap – RowlettRowlett Tap – RockwallRowlett Tap – Garland /138kV 11/24 12/1 18:15 12/15 19:00
Roanoke – West Denton /345kVRemoves Denton AT
11/28 12/1 06:3012/1 07:33
12/4 16:0012/4 15:50
McKinney SW – McKinney White StMcKinney SW – McKinney
11/29 12/2 06:0012/2 06:06
12/3 20:0012/3 15:17/15:05
Forney Switch – Rockwall South / 138kVCancelled
11/2912/2 05:12
12/2 06:00 12/9 19:00
BGarza / January 14, 2005 / WMS
12
BGarza / January 14, 2005 / WMS
13
OOME, LBE, OOMC, BENA, RMR
$0.00
$0.50
$1.00
$1.50
$2.00
$2.50
$3.00
$ p
er M
Wh
2004 Actual YTD 2003 Actual Daily Actual
12/2/2004 - $7.04
BGarza / January 14, 2005 / WMS
14
Northeast - North
12/2/04 Interval ending Limit CSCI
Shadow Price
Zonal Congestion
Charge TCRsPayment to TCR holders
Zonal Congestion
Shortfall Collected
Through BENA
3:00 9999 474.4713 0 $0.00 1851 $0.00 $0.00
3:15 9999 477.1653 0 $0.00 1851 $0.00 $0.00
3:30 9999 473.2188 0 $0.00 1851 $0.00 $0.00
3:45 9999 460.9552 0 $0.00 1851 $0.00 $0.00
4:00 9999 439.38 0 $0.00 1851 $0.00 $0.00
4:15 9999 360.0779 0 $0.00 1851 $0.00 $0.00
4:30 610 340.2008 0 $0.00 1851 $0.00 $0.00
4:45 590 336.6925 0 $0.00 1851 $0.00 $0.00
5:00 530 348.6249 1063.8 $92,716.79 1851 ($492,273.45) ($399,556.66)
5:15 530 446.2523 5670.4 $632,607.26 1851 ($2,623,977.60) ($1,991,370.34)
5:30 500 460.3259 1835.37 $211,217.09 1851 ($849,317.47) ($638,100.38)
5:45 500 463.9667 1835.37 $212,887.64 1851 ($849,317.47) ($636,429.83)
6:00 525 458.0223 1835.37 $210,160.10 1851 ($849,317.47) ($639,157.37)
6:15 650 828.7812 1835.37 $380,280.04 1851 ($849,317.47) ($469,037.43)
6:30 9999 818.6716 0 $0.00 1851 $0.00 $0.00
$1.7 million ($6.5 million) ($4.8 million)
BGarza / January 14, 2005 / WMS
15
Zonal Congestion
Charge($000)
Payment to TCR Holders
($000)
Zonal Congestion Shortfall Collected
Through BENA($000)
Dec 2 NE-N $1,740 ($6,514) ($4,774)
Dec 2 S-N $156 ($245) ($89)
Dec 2 Total $1,896 ($6,759) ($4,863)
Dec 3 NE-N $1,589 ($3,155) ($1,566)
Dec 3 S-N $337 ($585) ($248)
Dec 3 Total $1,926 ($3,740) ($1,814)
2 Day NE-N $3,329 ($9,669) ($6,340)
2 Day Total $3,822 ($10,499) ($6,677)
Summary of 2 Day Congestion Costs
BGarza / January 14, 2005 / WMS
16
Daily CSC limits vs TCRsAnnual TCRs include PCRs
0
500
1000
1500
2000
2500
1-Jul 31-Jul 30-Aug 29-Sep 29-Oct 28-Nov 28-Dec
NE-NAnnual TCRs
Daily OC0 Limit
Total TCRs
Monthly OC0
BGarza / January 14, 2005 / WMS
17
Possible reasons for discrepancy between the Monthly TCR calculation and the Daily CSC limits calculation
:
• Monthly TCR calculation occurs 45 days in advance– TSPs only required to submit outages 3 days in advance
• There were several line-ratings changes that occurred in November not considered in the monthly calculation
• No generator outages are considered in the monthly calculation
• No dynamic ratings are used in the monthly calculation• Operations case vs. SSWG case• Generators not adjusted individually in monthly
calculation• Overloads on lines with PTDF’s of less than 4.0% are
ignored• Settlement Adjustment consideration differences
BGarza / January 14, 2005 / WMS
18
December NE – N TCR Calculation with Actual Transmission Outages
Line Outages:• December TCR study included 33
line outages.• 130 line and transformer outages
actually occurred on December 2.• Using a 5-day outage criteria,
there were 67 line and transformer outages on December 2.
Variables considered:• Line Outages (All, 5-Day window)• Updated Ratings (with and without
the 11/12/2004 update)• Normally, the limiting contingency
is chosen by MUST. One case using the 5-day window outages was run using the contingency chosen by operations.
1851
364
324
401
374
827
1393
-155
-155
-120
-106
348
-500 0 500 1000 1500 2000
Original
All Outages
5 day Outages
All Outages with Update
5 day Outages with Update
Using Op Contingency 5day
Avaliable TCRs OC 0
BGarza / January 14, 2005 / WMS
19
Requested Days Prior Planned Start
0
500
1000
1500
2000
2500
3000
3500
3 17
31
45
59
73
87
10
1
11
5
12
9
14
3
15
7
17
1
18
5
19
9
21
3
22
7
24
1
25
5
26
9
28
3
29
7
31
1
32
5
33
9
35
3
Days Prior Outage
Transmission
BGarza / January 14, 2005 / WMS
20
•2.2.2 OC1 Limits for Outage Support
Step # Procedural Steps
NOTE: If step 1.2 is required, use the MIS and post that ERCOT is controlling to a limit other than the one posted.Typical Script: The “CSC Name” limit will change to “MW Amount” at “Time”. ERCOT will start controlling to this limit in accordance with Section 2.2.2 of the Transmission Security Desk procedures.
1 Adjust OC1 limits as required to support an outage.1.1 If flow across a CSC is already below the limit required to support an outage, then it is permissible to wait and adjust the OC1 limit at the scheduled start time of the outage.1.2 IF flow across a CSC is above the limit required to support an outage, then adjust the OC1 limits for intervals preceding the scheduled outage start time such that flow across the constraint is gradually reduced to at or below the limit required to support the specific outage. While this action might result in over-constraining for a brief period, it is preferable to the negative effects of a sudden reduction in the OC1 limit.
2 When a CSC limit changes, immediately change the limit in RTMONI. Record this event in the Transmission Security log.
ERCOT Operating Procedure ManualTransmission & Security Desk
Procedures
Version 3 Rev 32 – December 20, 2004 Page 11
BGarza / January 14, 2005 / WMS
21
Additional background slides
BGarza / January 14, 2005 / WMS
22
Transmission Limits to Be MonitoredFor: Wednesday 12/01/2004
The maximum total loading on the following Zonal and Local Constraint monitored elements should be maintained. Local constraints will be resolved with Real Time Contingency Analysis
Time
South to NorthSDSES–TMPSW__ Potential IROL
Northeast to North(Sum of 2 Farmerville - Royse) Potential IROL
South to Houston
(Sum of 3 STP-DOW & STP-WAP)__ Potential IROL
West to NorthGraham – Parker/ Benbrook__ Potential IROL
North to HoustonGibbons Creek – O’BrienJewett – T.H. WhartonJewett – TomballRNS – Kuykendahl __ Potential IROL
00:00- 08:00
830520
1840 600 2200
08:00 -12:00
830520
1840 600 1900
12:00 -18:00
830520
1840 600 1900
18:00 -24:00
830520
1840 600 2200
South => North Loss of Double Austrop-Sandow 345 kV circuit overloads Austrop Auto.
Northeast => North Base case activation of an SPS (ALNSW-BNDVS) and post-contingency overload of Collin-Frisco 138 kV line on the forced outage of Carrollton-Collin 345 kV.
South => Houston Loss of Dbl STP – DOW 345kV Lines loads Blessing – Lane City.
West => North Loss of MGSES - SWCOG loads multiple underlying 69kV lines.
North=> Houston Loss of Double circuit Gibbons Creek-Twin Oak overloads Jewet-Watson Chapel
Above Zonal limitations are based on the following:
BGarza / January 14, 2005 / WMS
23
Transmission Limits to Be MonitoredFor: Friday 12/03/2004
The maximum total loading on the following Zonal and Local Constraint monitored elements should be maintained. Local constraints will be resolved with Real Time Contingency Analysis
Time
South to NorthSDSES–TMPSW__ Potential IROL
Northeast to North(Sum of 2 Farmerville - Royse) Potential IROL
South to Houston
(Sum of 3 STP-DOW & STP-WAP)__ Potential IROL
West to NorthGraham – Parker/ Benbrook__ Potential IROL
North to HoustonGibbons Creek – O’brienJewett – T.H. WhartonJewett – TomballRNS – Kuykendahl __ Potential IROL
00:00- 06:00
840650
1990 600 2100
06:00 -12:00
840300
1990 600 2100
12:00 -23:00
840300
1990 600 2100
23:00 -24:00
840650
1990 600 2100
South => North Loss of Double Sandow – Temple 345kV lines overloads Sandow – Rogers 138kV Line.
Northeast => North Base case activation of NE SPS Allen Switch – Ben Davis above trigger point. Offpeak – outage of NW Carrillton-Collin overloads Krugerville-Denton Arco &
South => Houston Loss of Double Sandow – Temple 345kV lines overloads Sandow – Rogers 138kV Line.
West => North Loss of MGSES - SWCOG loads multiple underlying 69kV lines.
North=> Houston Loss of Double circuit GIBBON CRK - O’BRIEN & - ROANS PRAIRIE results in overload of 345kv line Jewett –T.H. Wharton.
Above Zonal limitations are based on the following:
BGarza / January 14, 2005 / WMS
24
Transmission Limits to Be MonitoredFor: Saturday 12/04/2004
The maximum total loading on the following Zonal and Local Constraint monitored elements should be maintained. Local constraints will be resolved with Real Time Contingency Analysis
Time
South to NorthSDSES–TMPSW__ Potential IROL
Northeast to North(Sum of 2 Farmerville - Royse) Potential IROL
South to Houston
(Sum of 3 STP-DOW & STP-WAP)__ Potential IROL
West to NorthGraham – Parker/ Benbrook__ Potential IROL
North to HoustonGibbons Creek – O’brienJewett – T.H. WhartonJewett – TomballRNS – Kuykendahl __ Potential IROL
00:00- 07:00
8301190
2090 600 2220
07:00 -12:00
8301190
2090 600 2150
12:00 -16:30
8301190
2090 600 2150
16:30 -24:00
8301190
2090 600 2220
South => North Loss of Double Sandow – Temple 345kV lines overloads Sandow – Rogers 138kV Line.
Northeast => North Loss of NW Carrollton-Collin 345 kV overloads Collin – Frisco 138 kV(Adjusted Forney Generation for overload of Royse – Ben Davis 345 kV)
South => Houston Loss of Dbl STP – Dow 345 kV overloads Waller – Prairie View 138 kV
West => North Loss of MGSES - SWCOG loads multiple underlying 69kV lines.
North=> Houston Loss of Double circuit GIBBON CRK - O’BRIEN & - ROANS PRAIRIE results in overload of 345kv line Jewett –T.H. Wharton. (07:00 – 16:30)Loss of Dbl THW-Jewett / Obrien—Gibbons Creek 345 kV overloads Waller – Prairie View 138 kV (00:00 – 07:00 and 16:30 –24:00)
Above Zonal limitations are based on the following:
BGarza / January 14, 2005 / WMS
25
-350
-300
-250
-200
-150
-100
-50
0
50
100
0 100 200 300 400 500 600 700 800 900
$/M
WH
HE 5
HE 6
HE 7
Northeast DBES BidsDecember 2, 2004
BGarza / January 14, 2005 / WMS
26
BES Deployments by Zone
-2500
-2000
-1500
-1000
-500
0
500
1000
1500
2000
NORTH
SOUTH
WEST
HOUSTON
NORTHEAST
December 2, 2004
BGarza / January 14, 2005 / WMS
27
Interval Ending BES Deployments (MW)
02-Dec-04 NORTH SOUTH WEST HOUSTONNORTHEAST
3:15 222 -382 47 657 0
3:30 355 -409 47 848 0
3:45 336 -365 47 887 0
4:00 336 -340 47 943 0
4:15 309 -348 83 177 0
4:30 264 -345 95 384 0
4:45 469 -408 197 637 0
5:00 582 -479 531 1022 -215
5:15 986 -874 68 150 -501
5:30 1319 -1316 -14 579 -505
5:45 1372 -1462 -74 883 -505
6:00 1424 -974 -74 883 -505
6:15 1802 -2028 -216 -741 -675
6:30 0 -842 83 -60 -274
Balancing Energy Information for Market Day: 2-Dec-04
BGarza / January 14, 2005 / WMS
28
Net Balancing Energy
(2,500)
(2,000)
(1,500)
(1,000)
(500)
0
500
1,000
1,500
2,000
3:00 3:15 3:30 3:45 4:00 4:15 4:30 4:45 5:00 5:15 5:30 5:45 6:00 6:15 6:30 6:45 7:00
Net Balancing Energy DeployedDecember 2, 2004
BGarza / January 14, 2005 / WMS
29
South - North
12/2/04Interval ending Limit CSCI
Shadow Price
Zonal Congestion
Charge TCRsPayment to TCR holders
Zonal Congestion
shortfall collected
through BENA
3:00 9999 296.1346 0 $0.00 513 $0.00 $0.00
3:15 399 319.0686 152.07 $12,130.19 513 ($19,502.98) ($7,372.79)
3:30 380 319.0061 191.31 $15,257.26 513 ($24,535.51) ($9,278.24)
3:45 380 316.4442 130.64 $10,335.07 513 ($16,754.58) ($6,419.51)
4:00 400 314.0429 124.72 $9,791.86 513 ($15,995.34) ($6,203.48)
4:15 400 342.6532 57.23 $4,902.51 513 ($7,339.75) ($2,437.24)
4:30 410 340.2185 38.63 $3,285.66 513 ($4,954.30) ($1,668.64)
4:45 390 336.5086 195.11 $16,414.05 513 ($25,022.86) ($8,608.81)
5:00 370 328.466 1020.52 $83,801.53 513 ($130,881.69) ($47,080.16)
5:15 370 497.031 0 $0.00 513 $0.00 $0.00
5:30 400 484.7868 0 $0.00 513 $0.00 $0.00
5:45 450 469.6484 0 $0.00 513 $0.00 $0.00
6:00 450 450.8654 0 $0.00 513 $0.00 $0.00
6:15 9999 402.5651 0 $0.00 513 $0.00 $0.00
6:30 9999 388.3698 0 $0.00 513 $0.00 $0.00
$155,918.13 ($244,987.00) ($89,068.87)
BGarza / January 14, 2005 / WMS
30
2004 Auction Total Revenues W-N S-N S-H N-H E-N
Annual $18,266,528.01$493,362.1
4$5,066,699.9
2 $6,597,486.72$2,901,444.5
3$3,207,534.7
0
January $839,550.13 $20,811.54 $209,008.81 $213,698.58 $129,084.00 $266,947.20
February $577,990.44 $11,575.37 $168,512.91 $174,072.73 $0.00 $223,829.42
March $1,284,884.09 $65,498.78 $0.00 $352,844.98 $0.00 $866,540.33
April $1,540,363.60 $30,344.68 $108,543.84 $508,367.15 $149,114.49 $743,993.45
May $2,028,690.98 $12,547.77 $295,080.89 $553,266.67 $24,362.14$1,143,433.5
1
June $1,405,099.01 $24,356.51 $301,527.36 $963,827.41 $84,200.76 $31,186.97
July $2,827,311.04 $24,918.17 $671,374.55 $1,432,122.62 $568,917.83 $129,977.87
August $1,693,186.18 $45,083.16 $312,693.16 $814,746.34 $383,068.33 $137,595.19
September $731,937.19 $20,959.56 $0.00 $546,395.03 $164,582.60 $0.00
October $1,064,492.31 $23,388.25 $0.00 $828,435.16 $176,275.99 $36,392.91
November $1,221,575.75 $41,726.70 $0.00 $777,077.68 $284,077.81 $118,693.56
December $1,036,694.42 $39,793.29 $127,649.53 $575,084.70 $253,623.19 $40,543.72
Total $34,518,303.16$854,365.9
2$7,261,090.9
6$14,337,425.7
7$5,118,751.6
8$6,946,668.8
3
2004 ERCOT TCR AuctionsYear to Date Revenues
BGarza / January 14, 2005 / WMS
31
Daily CSC limits vs TCRsAnnual TCRs include PCRs
0
200
400
600
800
1000
1200
1-Jul 31-Jul 30-Aug 29-Sep 29-Oct 28-Nov 28-Dec
S-NAnnual TCRs
Daily OC0 Limit
Total TCRs
Monthly OC0
0
500
1000
1500
2000
2500
1-Jul 31-Jul 30-Aug 29-Sep 29-Oct 28-Nov 28-Dec
S-HAnnual TCRs
Daily OC0 Limit
Total TCRs
Monthly OC0
0
500
1000
1500
2000
2500
3000
1-Jul 31-Jul 30-Aug 29-Sep 29-Oct 28-Nov 28-Dec
N-HAnnual TCRs
Daily OC0 Limit
Total TCRs
Monthly OC0
0
100
200
300
400
500
600
700
800
1-Jul 31-Jul 30-Aug 29-Sep 29-Oct 28-Nov 28-Dec
W-NAnnual TCRs
Daily OC0 Limit
Total TCRs
Monthly OC0