Upload
dangkhuong
View
217
Download
2
Embed Size (px)
Citation preview
Railway Track Science &
Engineering
Ballast: Issues and Challenges
International Workshops
Decision process
for ballast cleaning
and/or renewal at
INFRABEL
Paul Godart
Chief Civil Engineer
Paris 05-06 december 2013
Map of Belgian network
05-06.12.2013 Ballast: Issues and Challenges International Workshops 2
1. Network specifications
Infrastructure - Some Figures ( 2012)
• Length of main tracks : 6468 km
• Length of lines : 3600 km
• High speed tracks (300 km/h) : 273 km
• Length of secondary tracks: 2 506 km
• Turnouts : 4 470
• Level crossings: 1 857
• Bridges : 4 527 Tunnels : 177
• Global cost for track
• maintenance and renewal :
277 013 687 €
05-06.12.2013 Ballast: Issues and Challenges International Workshops 3
1. Network specifications
Ballast : some
figures
• According to UIC figures : in 2010 : 1 020 953 km railway lines in
the world ;
• More than 95 % are ballasted tracks : ballastless track is in
development but remains limited ( high speed lines, …) ;
• 1 km of plain track : 3 000 to 4 000 T/ballast;
• 1 T ballast : between 8 to 12 €/T ex quarry;
• Transportation costs : from 0,1 €/T/km for a direct train to 0,45
€/T.km for a single wagon; 0,20 €/T.km by truck;
• 1 km ballast renewal : between 120 000 and 180 000 €/km. 4 05-06.12.2013 Ballast: Issues and Challenges International Workshops
Ballast functions
• Distribute vertical loads from sleepers to subgrade
• Lateral and longitudinal resistance of the track ( continuous welded rails, braking, acceleration)
• Drainage
• Attenuate train vibrations, noise absorption
• Mechanical maintenance : restore track geometry with tamping machines
05-06.12.2013 Ballast: Issues and Challenges International Workshops 5
2. Ballast specifications
Q
Typical cross section of double track
05-06.12.2013 Ballast: Issues and Challenges International Workshops 6
2. Ballast specifications
Ton of ballast for a double track : approximately 6 to 7 tons/m
Subgrade
Monobloc sleeper Bi-bloc sleeper
Blanket layer
Geotextile
Drainage tube
Drainage material
Foundation layer
Footpath
Footpath material Channel
Concrete
Rail
Natural ditch
Catenary pool
Subsoil
Ballast
Ballast
classification
Four quality classes for ballast :
• Class IA : - very hard stones and with high cleanliness
- for speed > 220 km/h
- for speed > 160 km/h (with blanket layer)
- in tunnels
• Class IB : - very hard stones for the most important lines
- for speed ≥ 140 km/h
• Class II : - hard stones for other lines
• Class III : - stones for secondary tracks
05-06.12.2013 Ballast: Issues and Challenges International Workshops 7
2. Ballast specifications
Ballast Specifications
The ballast must meet several criteria based on European
standard EN 13450:2013 ( revised version of first standard 2002) :
• Particle size distribution
• Flakiness index
• Shape index
• Cleanliness
• Assessment of fines
• Mechanical and physical properties :
- resistance to fragmentation ( Los Angeles)
- resistance to wear (micro Deval)
05-06.12.2013 Ballast: Issues and Challenges International Workshops 8
2. Ballast specifications
Ballast renewal :
life cycle
• Why is it necessary to
clean and/or relay
the ballast ?
After how many years?
• Factors of pollution :
- Organic materials;
- Fine particles brought by wind;
- Particles ( clay, silt, …) going up from the formation;
- Poor drainage;
- Materials falling from the wagons;
- Wear and fragmentation of the stones due to dynamic
loads and tamping operations.
9 Ballast: Issues and Challenges International Workshops 05-06.12.2013
Ballast renewal : decision process
05-06.12.2013 Ballast: Issues and Challenges International Workshops 10
3. Renewal Process
1) Proposal for ballast to be relaid.
- line importance
- age and type of ballast ( according to technical inventory);
- track geometry degradation ;
- local problems ( mud spots,
poor drainage, …)
- tamping intervals to restore
track geometry ;
- together with sleeper renewal.
Ballast renewal
05-06.12.2013 Ballast: Issues and Challenges International Workshops 11
3. Renewal Process
2) Validation process.
Borings with a special boring
machine.
Ballast renewal
05-06.12.2013 Ballast: Issues and Challenges International Workshops 12
3. Renewal Process
- Borings every 100 m to a
depth of 1,5 m under top
of the rail
visual examination of
samples (thickness of sound
and clogged ballast, nature of
subsoil, …) ;
- Every 400 m, grain size
distribution analysis in
laboratory (percentage of
elements smaller than 22,4
mm);
Ballast renewal – Decision process
05-06.12.2013 Ballast: Issues and Challenges International Workshops 13
3. Renewal Process
Criteria based on expert
committe ERRI D 182 : 1995
( European Rail Research
Institute , former research
institute of UIC)
« Ballast has to be cleaned
when the percentage of
elements passing through a
sieve of 22,4 mm is higher
than 30 % in weight). ».
Ballast renewal – Boring results
05-06.12.2013 Ballast: Issues and Challenges International Workshops 14
3. Renewal Process
Clogged ballast thickness
Top level of ballast
Level cess
Boring depth
Percentage of elements < 22.4mm if > 30 % then renewal
if < 30 % then no renewal
Hectometer Localisation
Ballast renewal
05-06.12.2013 Ballast: Issues and Challenges International Workshops 15
4. In the future
Renewal of a section
based on degradation
rate of the geometrical
parameters of the track.
The track geometry
recording car runs 2
tilmes/year on all the
main lines.
It measures the quality
of track levelling every
25 cm and calculates the
standard deviation
(sigma) every 200m.
Ballast renewal – works execution
05-06.12.2013 Ballast: Issues and Challenges International Workshops 16
3. Renewal Process
Planning of the works : contractor, track interception,
logistical part, ballast screening machine, ballast reprofiling,
tamping, stabilization…
Ballast renewal – works execution
05-06.12.2013 Ballast: Issues and Challenges International Workshops 17
3. Renewal Process
Last years production : due to low budget, priority has been given
to renewal works with high influence on safety ( rail, switches and
crossings). It is necessary to increase the quantities for the next
years.
Site’s length
(km) Speed (m/h)
Renewed
length
(km)
Unrenewed
length(km)
Evacuated
product
(x1000 t)
Evacuated
product
per meter
(t/m)
2008 64 118 53 11 56 0.88
2009 74 132 68 6 55 0.75
2010 45 172 44 1 28 0.62
2011 21 137 19 2 18 0.86
2012 18 169 17 1 13 0.72
Ballast renewal – In the future
05-06.12.2013 Ballast: Issues and Challenges International Workshops 18
4. In the future
Use of Ground penetrating radar (GPR) + endoscopic analysis
for proposals validation.
Ballast renewal – In the future
Use of Georadar :
the interpretation of GPR results needs experience !!!
Ballast renewal – In the future
05-06.12.2013 Ballast: Issues and Challenges International Workshops 20
4. In the future
Endoscopic analysis Georadar interpretation
Panda analysis
Ballast renewal – In the future
05-06.12.2013 Ballast: Issues and Challenges International Workshops 21
4. In the future
Georadar vs boring
Advantages Disadvantages
Georadar
- few traffic perturbation
- Continuous measures
- good efficiency
- more and more used
- interpretation difficulties
(relationship between soil
property and radarwave)
- subjective cleanliness
criteria
(visual observation required)
Boring
-Easy interpretation (direct
relationship between
property and granulometry)
- objective cleanliness
criteria
(optional visual observation)
- Substantial traffic
perturbation (necessary traffic
interruption)
- Discontinuous measures
(need extrapolation)
- bad efficiency
- archaic system
02.10.2012 Strategisch plan Bascooup 22
Ballast renewal - Conclusion
The decision process for ballast renewal remains a
difficult thing, it is not a direct safety related process and
often gets less priority;
Several criteria can be used :
Age of ballast;
Rate of track geometry degradation;
Visual examination;
Geotechnical analysis : borings, georadar,…
A linear asset management tool is needed ( track
geometry, borings, georadar, …).
But what are the good criterias ? I hope this seminar can
help us to determine the best technical and economical
methods .
I wish you good and fruitful discussions.