64
DECOMMISSIONING EXPERIENCE IN SPAIN Manuel Rodríguez Silva ISPRA, July 2011

DECOMMISSIONING EXPERIENCE IN SPAIN2011.radioactivewastemanagement.org/download/14 - RODRIGUEZ.pdf · cajon de hormigÓn pretensado 2. reactor 3. superficie soporte 4. ... decommissioning

Embed Size (px)

Citation preview

DECOMMISSIONING EXPERIENCE IN

SPAIN

Manuel Rodríguez Silva ISPRA, July 2011

2

DECOMMISSIONING EXPERIENCE IN SPAIN

•Enresa •RW Management Plan

• Enresa’s Fund

•El Cabril

Decommissioning responsibility

Financial aspects

Disposal facilities for:

- LLW

- ILW

- VLLW

- HLW

- Graphite

•On selection / construction

• Green field Final site required

Strategy: The Spanish Scenario

3

DECOMMISSIONING EXPERIENCE IN SPAIN

JOSE CABRERA

2010 / 2016

PIMIC

2006 / 2010

VANDELLÓS 1

1998 / 2003

DECOMMISSIONIG PROJECTS IN SPAIN

4

DECOMMISSIONING EXPERIENCE IN SPAIN

DECOMMISSIONIG PROJECTS IN SPAIN

Madrid. PIMIC (CIEMAT) -Project length: 2006-2011 -Reactor type: Research Reactor & reprocessing facilities -Status: Site Restoration

Madrid

Guadalajara

Tarragona

Tarragona. VANDELLOS 1 NPP -Project length: 1998-2003 -Reactor type: GCR -E. Power: 460 Mw -Status: On dormancy

Guadalajara. JOSE CABRERA NPP (ZORITA) -Project length: 2010-2016 -Reactor type: PWR -E. Power: 160 Mw -Status: Preparatory activities / Conventional dismantling

5

DECOMMISSIONING EXPERIENCE IN SPAIN

15

16

79 10

8

1

12

13

2

3

4

6 5

14

11

LEYENDA 1. CAJON DE HORMIGÓN PRETENSADO 2. REACTOR 3. SUPERFICIE SOPORTE 4. CAMBIADOR 5. SOPLANTE 6. TUNEL DE VENTILACIÓN EN PARADA 7. TURBINA 8. CONDENSADOR 9. ALTERNADOR 10. TRANSFORMADOR 11. DISPOSITIVO PRINCIPAL DE MANUTENCIÓN ( DPM ) 12. MANUTENCIÓN DE ELEMENTOS COMBUSTIBLES 13. PISCINAS 14. TOMA DE AGUA DE MAR DE REFRIGERACIÓN 15. ESTACIÓN DE BOMBEO 16. EVACUACIÓN DEL AGUA DE MAR DE REFRIGERACIÓN

Vandellòs I

6

DECOMMISSIONING EXPERIENCE IN SPAIN

Vandellós I

7

DECOMMISSIONING EXPERIENCE IN SPAIN

Decommissioning activities in Spain: PIMIC (I)

NUCLEAR REACTOR

REPROCESSING PILOT PLANT

LIQUID WASTE TREATMENT

BUILDING

LIQUID WASTE STORAGE

BUILDING

8

DECOMMISSIONING EXPERIENCE IN SPAIN

PIMIC Project (CIEMAT)

9

DECOMMISSIONING EXPERIENCE IN SPAIN

Type: Westinghouse - 1-Loop PWR

Net Electrical Power: 160 MWe

Net Thermal Power: 510 MWth

Fuel Elements: 69 – 14x14

Fuel Type: UO2 – enrichment 3,6% (U-235)

Mass UO2 (core) 20,76 t

Control Rod (Banks): 17

Reactor Vessel (Diameter): 2,82 m

Reactor Vessel (Height without Head): 5,87 m

NSSS (Diameter): 70 cm

Containment:

Reinforced concrete + Stainless Steel Head

Spent Fuel Pool:

In Containment

Final cooling:

Tajo River

INSTALLATION MAIN DESIGN DATA

José Cabrera NPP (Zorita)

10

DECOMMISSIONING EXPERIENCE IN SPAIN

CONSTRUCTION WORKS

José Cabrera NPP (Zorita)

11

DECOMMISSIONING EXPERIENCE IN SPAIN

DISMANTLING OF THE REACTOR VESSEL & INTERNAL ELEMENTS

MAIN CHALLENGE

SPANISH DECOMMISSIONING

APPROACH

13

DECOMMISSIONING EXPERIENCE IN SPAIN

DECOMMISSIONING VISION

Inputs Outputs Transformation process

+ + RESOURCES MATERIALS

1

2 3 4

5 6

DISMANTLING is not only DEMOLITION, but an INDUSTRIAL

PROCESS

1 2 3 4 5 6

14

DECOMMISSIONING EXPERIENCE IN SPAIN

DECOMMISSIONING VISION

Inputs Outputs Transformation process

+ + RESOURCES MATERIALS

1

2 3 4

5 6

DISMANTLING is not only DEMOLITION, but an INDUSTRIAL

PROCESS

1 2 3 4 5 6

15

DECOMMISSIONING EXPERIENCE IN SPAIN

Characterization

Modifications

Disassemblies

Demolitions

Site restoration

Materials Management

DECOMMISSIONING MAIN STEPS

16

DECOMMISSIONING EXPERIENCE IN SPAIN

CHARACTERIZATION

DECOMMISSIONING PHASES: DESCRIPTION AND EXAMPLES

18

DECOMMISSIONING EXPERIENCE IN SPAIN

OBJECTIVES:

Identification of the types of wastes to be generated (both

radioactive and conventional)

Quantification of the volumes of each of the waste categories

Isotopic Vectors corresponding to the existing radioactive waste

streams (Key for the determination of activity by measuring the

gamma emitters involved)

Planning of operational radiological protection

INITIAL CHARACTERIZATION

19

DECOMMISSIONING EXPERIENCE IN SPAIN

linked

To a Data Base: Physical and Radiological Inventory for José

Cabrera NPP Dismantling Project

INITIAL CHARACTERIZATION

20

DECOMMISSIONING EXPERIENCE IN SPAIN

MATERIAL Activity (Bq) Impacted Mass (kg)

Activation Contamination Total Activation Contamination Total

Steel 1,9E+16 1,3E+12 1,9E+16 1,8E+05 2,5E+06 2,7E+06

Concrete 4,8E+13 4,5E+12 5,3E+13 3,3E+05 5,9E+07 5,9E+07

Scraps iron 1,1E+09 1,1E+09 5,2E+04 5,2E+04

Electric Cables 5,4E+09 5,4E+09 9,4E+04 9,4E+04

Isolations 2,6E+09 2,6E+09 8,2E+03 8,2E+03

PVC & others 9,7E+06 9,7E+06 1,4E+06 1,4E+06

TOTAL 1,9E+16 5,8E+12 1,9E+16 5,1E+05 6,3E+07 6,4E+07

CHARACTERIZATION (José Cabrera NPP Radological Inventory)

21

DECOMMISSIONING EXPERIENCE IN SPAIN

CHARACTERIZATION

PIMIC Radiological characterization campaign

22

DECOMMISSIONING EXPERIENCE IN SPAIN

Adaptation of plant systems to the needs of decommissioning. The adaptation may be a simplification, a reinforcement or a change of layout, in order to minimize risk, interference and unavailability

MODIFICATIONS: SYSTEMS & FACILITIES

SYSTEMS

-Fire protection.

-Electrical and instrumentation

systems and control

-Ventilation.

-Water

-Surveillance and control, etc.

Adaptation of buildings and infrastructure of the plant to new uses required by the decommissioning:

AUXILIARY FACILITIES

-Access control offices, walkways to

controlled areas.

-Storage areas and waste conditioning.

-Declassification area.

-Radiation Protection Equipment and

Materials Management

23

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: PLANT ADAPTATION (VANDELLÓS 1 NPP)

Checkpoint

Fuel tank

Portable ventilation unit

Modular Laundry Controlled area access

24

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: PLANT ADAPTATION (JOSÉ CABRERA NPP)

Electrical System Adaptation

Fire Fight System Conditioning Ventilation System Adaptation

25

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: PLANT ADAPTATION (PIMIC)

Building 11. Initial State Building 11. Final State

26

DECOMMISSIONING EXPERIENCE IN SPAIN

Temporary RadW Store CE-2a/b

CE-2a/b Concrete Filling Area

New Areas for Cutting & Decon

CMT Conditioning Area

Temporary RadW Store

TURBINE BUILDING MODIFICATION & ADAPTATION

PHASE 1.- PREPARATORY ACTIVITIES

27

DECOMMISSIONING EXPERIENCE IN SPAIN

After completion of the preparatory activities, the dismantling of different parts can be started

The removal of radiological systems and components is the core activity of decommissioning projects.

The materials generated should be segregated, characterized and seeded in situ to establish the appropriate management pathway by type.

The minimization of the dose received by workers and the amount of radioactive waste are the main objectives of this phase

3. DISASSEMBLIES

MAIN STEPS: DISASSEMBLIES

28

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DISASSEMBLIES (VANDELLÓS 1 NPP)

Computer Hall

380 V Transformer Hall

5,5 KV Transformer Hall

Relay Hall

29

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DISASSEMBLIES (VANDELLÓS 1 NPP)

30

DECOMMISSIONING EXPERIENCE IN SPAIN

FUEL REPROCESSING INSTALLATION

Decommissioning activities in Spain: PIMIC (II)

REACTOR POND

31

DECOMMISSIONING EXPERIENCE IN SPAIN

Pool Platform

MAIN STEPS: DISASSEMBLIES (PIMIC)

32

DECOMMISSIONING EXPERIENCE IN SPAIN

M1 Cell

MAIN STEPS: DISASSEMBLIES (PIMIC)

33

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DISASSEMBLIES (JOSÉ CABRERA NPP)

Turbine Building Disassembly and

Conditioning

34

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DISASSEMBLIES (JOSÉ CABRERA NPP)

Diesel

Main Transformer

35

DECOMMISSIONING EXPERIENCE IN SPAIN

CORE BARREL LOWER INTERNALS

UPPER INTERNALS

THERMAL SHIELD BAFFLE

REACTOR VESSEL & MAJOR COMPONENTS

FORMERS

REACTOR VESSEL

MAIN STEPS: DISMANTLING of MAJOR RAD COMPONENTS (ZORITA)

36

DECOMMISSIONING EXPERIENCE IN SPAIN

Elevation 621,600

Elevation 604,000

+614,700

Transfer Wire Basket

75 tons Crane

35 tons Crane

32 tons New Crane

CE-2a

Reinforced Bell

TRANSPORT AND WASTE PACKAGING

MAIN STEPS: DISMANTLING of MAJOR RAD COMPONENTS (ZORITA)

37

DECOMMISSIONING EXPERIENCE IN SPAIN

4.1 DECONTAMINATION BUILDING

After removal of radiological components and systems, it´s necessary to

decontaminate walls (walls, floors and ceilings) of the buildings for

subsequent demolition.

4.2 DECLASSIFICATION OF SURFACES

The application of the methodology for the declassification of surfaces

ensures the absence of contamination in the walls of buildings facing

subsequent reuse or demolition.

4.3 DEMOLITION

Once declassified, buildings will be demolished to a depth of 1 meter

below ground level.

The debris are usually crushed for reuse on site as filling material

Declassification measures

Demolition activities

MAIN STEPS: DEMOLITIONS

4. DEMOLITIONS

38

DECOMMISSIONING EXPERIENCE IN SPAIN

Decontamination

Evaporation cell soil characterization

MAIN STEPS: DEMOLITIONS (VANDELLÓS 1 NPP)

Reactor Building Characterization

Decontamination

39

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DEMOLITIONS (VANDELLÓS 1 NPP)

Effluent building demolition

40

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DEMOLITIONS (PIMIC)

Reactor Pool

41

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: DEMOLITIONS (JOSÉ CABRERA NPP)

Cooling Towers

42

DECOMMISSIONING EXPERIENCE IN SPAIN

• The purpose of this activity is to demonstrate

that the radiological content of the site in its

final state satisfies the release criteria.

If necessary, remediation work is carried out

before the final characterization

(decontamination of affected areas).

Site Characterization

MAIN STEPS: SITE RESTORATION

5. SITE RESTORATION

43

DECOMMISSIONING EXPERIENCE IN SPAIN

EXAMPLES: SITE RESTORATION (PIMIC – CONTAMINATED AREA)

44

DECOMMISSIONING EXPERIENCE IN SPAIN

MAIN STEPS: SITE RESTORATION

The material obtained in demolitions is crushed and used in

site restoration works

45

DECOMMISSIONING EXPERIENCE IN SPAIN

OBJECTIVES:

To separate conventional materials from radioactive

wastes.

To control conventional materials and ensure that they

are not contaminated.

To dispatch the materials safely.

MATERIALS MANAGEMENT

46

DECOMMISSIONING EXPERIENCE IN SPAIN

HISTORICAL OPERATING

DATA

1

RADIOMETRIC STUDIES

2

ACTIVE ZONES

CONVENTIONAL ZONES

ACTIVE PARTS P.D.

CLEAN

CONVENCIONAL COMPONENT P.D.

“IN SITU” RADIOLOGICAL

CONTROL

3

+

RADIOACTIVE WASTE

DESTINATION (Administrative control)

EXIT GATE MONITORS

5

CLEARANCE

4

Disassembly & Preparation of MDC handling

Units

YES

Disassembly & preparation

MTC handling unit

EL CABRIL DISPOSAL FACILITY

TRANSPORT

NO CONDITIONING AND PREPARATION FOR

TRANSPORT

6. MATERIALS MANAGEMENT

47

DECOMMISSIONING EXPERIENCE IN SPAIN

43 t

218 t

4.000 t

4.700 t 95.300 t

175 t

MATERIALS MANAGEMENT: EXPECTED QUANTITIES

104.000 tons to manage Only 4% is radiactive All materials have a destination

48

DECOMMISSIONING EXPERIENCE IN SPAIN

MATERIALS MANAGEMENT

49

DECOMMISSIONING EXPERIENCE IN SPAIN

Gestión de materiales convencionales

GESTION DE

MATERIALES

CONVENCIONALES

PROCEDENTES DE

PARTES ACTIVAS

50

DECOMMISSIONING EXPERIENCE IN SPAIN

6. MATERIALS MANAGEMENT

Radiological characterization with Box Counter Transfer of handling units

Loading of clered materials Dispatch of cleared materials

51

DECOMMISSIONING EXPERIENCE IN SPAIN

ZORITA DECOMMISSIONING

SPECIFIC ISSUES RELATED TO THE TRANSFER OF RESPONSIBILITY

52

DECOMMISSIONING EXPERIENCE IN SPAIN

ENRESA`s RESPONSIBILITY

OTHER RESPONSIBILITIES

ENGINEERING

& START UP

OPERATION D&D EXECUTION

PROJECT TRANSITION TO

DECOMMISSIONING

1963

STRATEGY BASIC STUDIES

DOCUMENTATION + EIS

LICENSING

D&D PLANNING

“SETTLE” PLAN

2006 1969

SITE RETURN to the OWNER

ELECTRICAL NET DISCONNECTION

NSSS DECONTAMINATION

SPENT FUEL MANAGEMENT

SPENT FUEL CASKS at the ISFI

TRANSFER of RESPONSIBILITY

(Feb, 11, 2010)

2016 2010

Build up Starting – Jul-65

1st Criticallity – Jun-68

1st Electrical Net Connection – Jul-68

Commercial Status– Oct-69

FIRST NPP IN SPAIN DEVELOPING the SPANISH NUCLEAR INDUSTRY

BASE for TRAINING

TRANSFER OF RESPONSIBILITY TO THE DECOMMISSIONING OPERATOR

53

DECOMMISSIONING EXPERIENCE IN SPAIN

Feb, 11 – 2010 – 12:05h

Feb, 11 – 2010 – 13:03h

TRANSFER OF RESPONSIBILITY TO THE DECOMMISSIONING OPERATOR

54

DECOMMISSIONING EXPERIENCE IN SPAIN

The hand over of responsibility to operate the plant is a complex situation, specific of the spanish framework, that requires plenty of planning and negotiation between the owner and the decommissioning operator (Enresa).

TRANSFER OF RESPONSIBILITY TO THE DECOMMISSIONING OPERATOR

55

DECOMMISSIONING EXPERIENCE IN SPAIN

HAND OVER PREPARATORY ACTIVITIES

1. AGREEMENTS WITH THE OWNER

2. ORGANIZATIONAL DESIGN

3. PROCUREMENT OF SERVICES

TRANSFER OF RESPONSIBILITY TO THE DECOMMISSIONING OPERATOR

56

DECOMMISSIONING EXPERIENCE IN SPAIN

STAKEHOLDERS &

POLICIES

57

DECOMMISSIONING EXPERIENCE IN SPAIN

POLICIES

enresa

Regulatory body

General public

Former operator

•Change of role !

Local institutions

• Safety ! • Radioactive waste !

•No mistakes !

•Local employment ! •Safety !

FACTS, FEARS & EXPECTATIONS

• Sbd.else’s site

58

DECOMMISSIONING EXPERIENCE IN SPAIN

POLICIES

Engineering Project

Decommissioning Viability

Waste Mangt. organization

Policies

• Internal training • Local employment • Communication &

transparency • Safety

59

DECOMMISSIONING EXPERIENCE IN SPAIN

Communication Goal:

To Inform

To neutralize negative opinions and attitudes

Remove false expectations

To Form

COMMUNICATION AS A KEY FACTOR

60

DECOMMISSIONING EXPERIENCE IN SPAIN

CT Mestral Visit

SITE VISIT IN DISMANTLING

PIMIC Visit

61

DECOMMISSIONING EXPERIENCE IN SPAIN

PROFESSIONAL TRAINING

CT Mestral

OIEA Course (PIMIC)

62

DECOMMISSIONING EXPERIENCE IN SPAIN

JOSE CABRERA

2010 / 2016

PIMIC

2006 / 2010

VANDELLÓS 1

1998 / 2003

CONCLUSIONS

Lessons learned

Lessons learned

Lessons learned

Decommissioning is a complex industrial activity, plenty of technical and not technical matters, as we have seen in the previus slides. Our commitment is to constantly review and improve the model we have shown, so that can undertake with solvency our current

and future demands.

. . .

63

DECOMMISSIONING EXPERIENCE IN SPAIN

Thanks for your attention

64

DECOMMISSIONING EXPERIENCE IN SPAIN