    System Process DocumentDefining a Reason for a Resource Capacity Change

    Department

    Responsibility/Role

    File Name 27761529.docRevision

    Document Generation Date 18/01/2010 09:35:00

    Date Modified 1/18/2010 09:35:00 AM

    Last Changed by

    Status

    Defining a Reason for a Resource Capacity Change

    Trigger:

    Concept

    The resource capacity change reasons list of values are defined as lookups. Lookup codes must be

    decided upon and defined during the implementation process.

    You can assign a reason for a resource capacity change in the Capacity Changes page by

    selecting the reason from the list of values. You can define the reasons for this list of values in the

    Resource Capacity Change Reasons page.

    In this topic, you will define a reason for a resource capacity change.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/18/2010 09:35:00 AM Page 1

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    2/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Procedure

    Step Action

    1. Begin by navigating to the Resource Capacity Change Reasons page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/18/2010 09:35:00 AM

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    3/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/18/2010 09:35:00 AM Page 3

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    4/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    3. Click the vertical scrollbar.

    Step Action

    4. Click the Resource Capacity Change Reasons link.

    Page 4 Last changed on: 1/18/2010 09:35:00 AM

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    5/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    5. Use the Resource Capacity Change Reasons page to assign reasons for a resource

    capacity change.

    Last changed on: 1/18/2010 09:35:00 AM Page 5

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    6/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    6. Click in the Code field.

    Step Action

    7. Enter the desired information into the Code field. Enter "10".

    Page 6 Last changed on: 1/18/2010 09:35:00 AM

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    7/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    8. Click in the Lookup Code Meaning field.

    Last changed on: 1/18/2010 09:35:00 AM Page 7

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    8/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    9. Enter the desired information into the Lookup Code Meaning field. Enter

    "Mechanical Fault".

    Step Action

    10. Click in the Lookup Code Description field.

    Page 8 Last changed on: 1/18/2010 09:35:00 AM

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    9/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    11. Enter the desired information into the Lookup Code Description field. Enter

    "Mechanical Fault".

    Last changed on: 1/18/2010 09:35:00 AM Page 9

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    10/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    12. The Tag field enables you to categorize lookup values.

    Click in the Tag field.

    Step Action

    13. Enter the desired information into the Tag field. Enter "101".

    Page 10 Last changed on: 1/18/2010 09:35:00 AM

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    11/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    14. The Effective From Date defaults as the system date, but you can update this date.

    Last changed on: 1/18/2010 09:35:00 AM Page 11

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    12/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    15. Enter a Effective To Date to indicate an expiration of the code.

    Click in the To field.

    Step Action

    16. Enter the desired information into the To field. Enter "31-OCT-2008".

    Page 12 Last changed on: 1/18/2010 09:35:00 AM

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    13/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    17. Use the Enabled check box to enable this code for Bills of Material.

    Last changed on: 1/18/2010 09:35:00 AM Page 13

  • 8/14/2019 Defining a Reason for a Resource Capacity Change_SPD

    14/14

    System Process DocumentDefining a Reason for a Resource Capacity Change

    Step Action

    18. Click the Save button.

    Step Action

    19. You have completed the Defining a Reason for a Resource Capacity Change

    procedure.End of Procedure.

    Page 14 Last changed on: 1/18/2010 09:35:00 AM