The GNWT Action Plan – The Levelton Report Jan 18, 2011 Yellowknife 1

Deh Cho Bridge Project

Embed Size (px)

DESCRIPTION

Deh Cho Bridge Project. The GNWT Action Plan – The Levelton Report Jan 18, 2011 Yellowknife. Presentation - Aim. To present the Project Team’s plan of action in response to the recently completed Levelton Report which was an audit on the Phase 1 works. - PowerPoint PPT Presentation

Citation preview

Page 1: Deh Cho Bridge Project

The GNWT Action Plan –

The Levelton Report

Jan 18, 2011 Yellowknife

1

Page 2: Deh Cho Bridge Project

Presentation - AimTo present the Project Team’s plan of action in response

to the recently completed Levelton Report which was an audit on the Phase 1 works.

2

Page 3: Deh Cho Bridge Project

Presentation Agenda BackgroundAim of the ReportScopeFindingsRecommendationsActions PlannedConclusion Questions

3

Page 4: Deh Cho Bridge Project

Audit Background Phase 1 all works completed prior to 31 March 2010

under the DCBCPhase 2 all works under the GNWT Technical issues (design), fabrication, constructionQuality control (QC) and quality assurance (QA)Due diligence dictated the GNWT review and understand

what had taken place in Phase 1Levelton Consultants assigned the role and commenced

April/May 2010 and completed 30 Nov 2010Audit employed interviews/documentation

review/inspections to complete the audit.

4

Page 5: Deh Cho Bridge Project

Aim/Scope of the Audit Aim : To assure the GNWT that the “in place” works were

constructed to standard and that all phase 2 works would be based on quality works.

Scope:Confirm continuity of design responsibility;Confirm all issues raised in Ph 1 addressed;Confirm fabrication and construction QC/QA followed and

certifiedConfirm general compliance with the contract and specsIdentify issues required to close off the Phase 1 works

5

Page 6: Deh Cho Bridge Project

Findings and Recommendations (1) Findings divided into 6 main categoriesSection 6 of the Report details the formal

recommendations. Some further notes in the main body of the report which

are germane to the Project.GNWT has grouped the recommendations where they

make sense and where one has a direct impact on the other.

Due to the audit process- the GNWT has taken action concurrently to the review and has already completed some recommendations, with others well underway.

6

Page 7: Deh Cho Bridge Project

Findings and Recommendations (2) Nothing found in Phase 1 that impacts the safety of the work

to date or that would affect construction of Phase 2Deficiencies were found in Phase 1 document control which,

given further time and research, may be remediedRecommendation that Phase 1 works be accepted upon

completion of the recommendationsGWNT has accepted the Levelton Report and has the resources

and time available to address all the recommendations.Our main priority remains to complete the project safely and

to a high standard.

7

Page 8: Deh Cho Bridge Project

8

Page 9: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

1 Phase 1 QC/QA

Develop, implement and monitor a QA/QC and document control program

In place and operating

On going monitoring with regular meetings and checks

9

Page 10: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

2a Design Ensure proper design responsibility established

Design continuity review in progress

Initial report due end Jan 2011.Complete by end Feb 2011

10

Page 11: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

2b Design Infinity to confirm all design issues raised by the GNWT addressed

Infinity will confirm this

Initial report due end Jan 2011.Complete by end Feb 2011

11

Page 12: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

2c Design Fracture critical and dimensional tolerances

Confirm documents

Completed in Phase 2 works

12

Page 13: Deh Cho Bridge Project

Actions Planned Ser

Element Recommendation

Action Notes

3a Alignment of piers

Outstanding issues to alignment be addressed

Independent survey of the piers confirm they are in the exact location they should be

Completed by Sub Arctic Survey summer of 2010

13

Page 14: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

3b Pier 3 S Top of footing to be examined in the area of the suspected depression

Expert firms who have this expertise are being contacted. Work to be tendered.

Must be done in ice free time. Can be done concurrent to already planned works.

14

Page 15: Deh Cho Bridge Project

15

Page 16: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

3c Constr Pier 2S

Resolved - Infinity to confirm this issue does not impact future works

GNWT will include this into the design review

Draft report due end Jan 2011.Final report due end Feb 2011

16

Page 17: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

3d Concrete Elms

Concrete Elems for Piers 1-4 N accepted

No action required

Completed

17

Page 18: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

4a Complete QC gaps at the AIS Plant

The turnover packages produced by AIS to be reviewed

Current QC team to review the packages

Ongoing. Review due end Feb 2011

18

Page 19: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

4b Review Geocon’s Reports (55)

Current QC team to review these QC documents to determine further action required

Current QC Team to review and provide comment

Ongoing. Review due by end Fen 2011

19

Page 20: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

4d Steel Elms- QC gaps

Qualified firm to conduct further review and testing to allow them to extend their certification

Ensure testing and reviews of components that were not fully documented in the QCprocess

Testing to take place in Mar 2011 and completed by end Apr 2011

20

Page 21: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

5c Scour Rock

Scour rock materials and placement be reviewed by a qualified consultant

Review completed and plan in place to remediate the situation

Review took place in Oct 2010. Plan submitted in Oct 2010.Work to commence summer of 2011 completed by 2012.

21

Page 22: Deh Cho Bridge Project

Actions Planned Ser Element Recommendatio

nAction Notes

6 Earthwork

Continue with remediation works currently underway with EBA certification

Phase 1 works corrected and approaches ready for launch.

Phase 1 completed.Phase 2 to commence spring 2011.

22

Page 23: Deh Cho Bridge Project

Summary of Conclusions

Levelton and Associated Engineering recommend the GNWT accept the works of Phase 1 provided recommendations are followed.

The GNWT and the Project Team accepts the report and will actively pursue all the recommendations to their successful completion.

There are sufficient resources to successfully address all the recommendations

23

Page 24: Deh Cho Bridge Project

Questions

24