Field Construction Engineering Aspects of Bridge Construction
Virginia Tech Construction Engineering Conference
Creating Bridges As Art®
Thomas DeHaven, P.E.Executive Vice President -Figg Bridge Inspection, Inc.
October 1, 2010
CABLE STAYED BRIDGES
ARCHESRAIL BRIDGES
LONG SPAN BRIDGESENVIRONMENTAL BRIDGES LONG BRIDGES OVER WATER
URBAN BRIDGES
Today’s presentation will focus on what the construction engineer can do to help deliver a
successful bridge project
10/18/2010
2
Two Types of Relationships
Work for Owner Design/Bid/Build
Work for Contractor
Creating Bridges As Art®
MINNESOTA NEW YORKDELAWARE VIRGINIA
Work for ContractorDesign/Build
Work for Owner Design/Bid/Build
C&D Canal Bridge Delaware
Smart Road BridgeVirginia
Varina-Enon BridgeVirginia
C&D Canal Bridge, Delaware 1994 - 750’ Main Span
10/18/2010
3
C&D Canal Bridge Delaware
Assistant Resident Engineer
Office Engineer
3 Field engineers at the site
2 Field engineers at the casting facility 230 miles away
Casting Yard Inspectors
Field Construction Engineering
Anticipate issues and solve them before they impact the project
Monitor all aspects of geometry control
Review contractor submittals
Monitor stressing of all PT including cable-stays (2 million pounds of force!)
C&D Canal Bridge, DelawarePrecast concrete delta frames to reduce cost and shorten the construction schedule.
10/18/2010
4
Pick Weights
Weight of equipment on deck & movement of loads
Precast PiersStep by step operations to
assemble a 100’ tall pier in a day
Cantilever ConstructionBalance loads during each step
of operation
Stressing Forces for vertical post-tensioning
Place pier segment first
Support conditions and rendundancy
C&D Canal Street Bridge, Delaware Span-by-span erection
Delivery and support of each segment
Weight of equipment on cantilever with geometry control and stay stressing
C&D Canal Bridge, DelawareConstruction Engineering examines ways to build over navigable waterways
Keep ships moving at all times
10/18/2010
5
C&D Canal Bridge, Delaware Opened in 19949 Design Awards
135’ Max
472’
Smart Road Bridge, Blacksburg, Virginia
Concrete segmental variable depth bridge Balanced cantilever construction
Smart Road Bridge, VirginiaNative materials along with flowing shapes create functional sculpture
10/18/2010
6
Out of balance superstructure load is taken in the pier
Smart Road Bridge, Virginia Balanced Cantilever Construction
Geometry control engineered to connect cantilevers accurately
Smart Road Bridge, Virginia Balanced Cantilever Construction
Smart Road Bridge, Virginia Geometry Control Critical
10/18/2010
7
Smart Road Bridge, VirginiaCompleted in 20019 Design Awards
Work for Contractor Design/Build
I-35W Bridge Minnesota
Penobscot Narrows BridgeMaine
JFK AirTrainNew York
I-35W BridgeMinneapolis, Minnesota
504 Ft. Main Span
10/18/2010
8
I-35W BridgeMinneapolis, Minnesota
Opened Sept. 18, 2008 - 5 a.m.
Design/Build in 11 months
Flatiron/Manson Joint Venture
10 lane Interstate over the Mississippi River
FIGG Led the Engineering Team and managed the local consultants
Construction engineering included casting procedure, erection analysis & quality insurance inspection
Minnesota Workers Built This Bridge
The bridge design relied heavily on Minnesota workers and resources
Equivalent of 400 full-time employeesemployees (vast majority local)
Local subcontractors, local materials
A Strategy for Safety and Speed
2-3 shifts day and night, including all holidays except Christmas Day
Zero lost time incidents
10/18/2010
9
Curing procedures for cold weather
February 15, 2008Pier Construction
Formwork is field engineered
Casting yard on south approach roadway
January 27, 2008
Long Line Precasting
Working from previous segments move bulkhead forward
Place rebar cage and place concrete for bottom slab and webs
Field engineering includes inspection of reinforcing and post-tensioning for quality assurance
10/18/2010
10
Spans Over Land Completed May 31, 2008
Precast Segment Erection 1st precast cantilever segment - May 25, 2008
Last SegmentJuly 10, 2008120 precast segments were erected in 45 days
10/18/2010
11
Vibrating Wire Strain Gauge with Temperature Reading
Linear Potentiometer
Accelerometer
Chloride Penetration Sensor
Fiber Optic Cables
A Smart BridgeSensors for Structural Behavior
323 Sensors
Triggers bridge's anti-icing system
Real-time data will assist with managing operations
Fiber optic cables collect data over longer lengths to determinedeformations and correlate other sensors
Partnership between Mn/DOT, FHWA, University of Minnesota
Three-dimensional integrated drawings, like this one, were color coded to indicate the exact location of such elements and simplify construction.
I-35W BridgeMinneapolis, Minnesota
I-35W BridgeMinneapolis, Minnesota
Open September 18, 2008 - 5am
10/18/2010
12
Port Authority New York/New Jersey9 Miles AirTrain JFK, New York
JFK AirTrain, New York
Design/Build with Koch Skanska, Slattery Skanska, Bayshore and STV
$1.2 Billion total, $100 M Bridges
Longest Precast Segmental Bridge in the U.S. - 9 Miles, 461 Spans
5,408 Precast Segments
Completed August 2001 (21 months - almost 2 months ahead of schedule)
Van Wyke Expressway - 160,000 vehicles per dayAirTrain JFK, New York
10/18/2010
13
AirTrain JFK, New York
Completed 12,144’ in 11 Months within 8’ Median of Congested Van Wyck Expressway
4 Sets of Erection trusses
8 Spans @ 110’ Every Week
AirTrain JFK, New York
AirTrain JFK, New York
Create median for elevated structure in existing right-of-way
7’-8”
10/18/2010
14
Equipment designed like a kit-of-parts and color coded for ease of use
AirTrain JFK, New YorkConstruction engineering included design of erection equipment
AirTrain JFK, New YorkPrecise precast geometry control at the site ensured exact alignment
AirTrain JFK, New YorkPre-engineering segment placement saved valuable time
10/18/2010
15
Winner of 13 Design AwardsAirTrain JFK, New York
Qualities of a successful construction engineer
Common Sense
Good communication skills
Flexible, team player
Focused on common goals
Proactive
Schedule driven
Quality conscious
Quick thinker, creative
The New I-35W Bridge book
The full story of construction and field construction
engineering
All conference participants will receive a copy