19
Delay, Disruption Delay, Disruption and Acceleration and Acceleration Michael J.R. Kremer Contract Management in Contract Management in International Construction International Construction Beijing, April 28, 2009 Beijing, April 28, 2009

Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Embed Size (px)

Citation preview

Page 1: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Delay, Disruption and AccelerationAcceleration

Michael J.R. Kremer

Contract Management in Contract Management in International ConstructionInternational Construction

Beijing, April 28, 2009Beijing, April 28, 2009

Page 2: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 2

1. Introduction1. Introduction

Time is of essence in basically every construction project

Yet, delays of some sort are general rule, rather than the exception

Consequence: claims for extension of time, issue of acceleration

Therefore, closer look to: What are the obligations as to time in general? When and how does acceleration become relevant?

Page 3: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 3

2. Contractor‘s obligations as to time2. Contractor‘s obligations as to time

Modern construction contracts typically foresee three separate, but inter-related express obligations:

First obligation: Contractor to complete works by certain date or within specified period; possibly with stage or sectional completion obligation

Second obligation: Contractor to progress the works regularly and diligently

Third obligation: Contractor to prepare and work to an accepted program (work schedule)

Page 4: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 4

2.1 2.1 First obligation: specific date/periodFirst obligation: specific date/period

In case of “period for completion”, identification of “commencement date” as well as periods crucial

e.g.: x months from the “Commencement Date” clarification of “days” and “weeks”

If no date or period foreseen: obligation to complete “by a reasonable time”

Standard form contracts regularly provide for express obligation

Page 5: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 5

2.1 2.1 First obligation: specific date/period (cont’d)First obligation: specific date/period (cont’d)

Effect of specific date of completion typically no qualification as of the essence clauses for extension of time or liquidated damages

prevent such interpretation Specific date of completion of little assistance in

management of the project Employer wants to take action early to avoid late

completion stage or sectional completion obligations and

liquidated damages give only limited recourse

Page 6: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 6

2.2 2.2 Second obligation: “progress regularly”Second obligation: “progress regularly”

If specific date for completion agreed, no “implied” second obligation

Contractor has right to plan, execute and progress the works

severe evidential difficulties for Employer Therefore: express obligation (regularly included

in standard form contracts)

Page 7: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 7

2.2 2.2 Second obligation: “progress regularly” (cont’d)Second obligation: “progress regularly” (cont’d)

Effect of express obligation to proceed regularly and diligently

“Proceed continuously, industriously and efficiently with appropriate resources so as to progress steadily towards completion substantially in accordance with the contract.”

Contractor may not slow down even if ahead in time schedule

Employer may have remedy of damages, even if completed in time, if Employer can show “loss”

Page 8: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 8

2.3 2.3 Third obligation: programThird obligation: program

“program/work schedule” no legal term Requires basic information of activities or operation

with a list of dates for commencement and completion of respective activities

Types of programs: Bar Chart Network Program Line of

Balance

Page 9: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 9

2.3 2.3 Third obligation: program (cont’d)Third obligation: program (cont’d)

Potential roles of the program: Monitor role:

- milestone program- progress program- prediction program

Dynamic role- management program- compensation program

Page 10: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 10

3. Employer‘s obligations as to time3. Employer‘s obligations as to time

Completion of obligations specified in the contract e.g. supply information, provide material, execution

of certain pre-condition works, permits, appointment of engineer etc.

- at times specified in program- or reasonable times with regard to execution of works

Typically no obligation to comply with approved program, rather obligation not to hinder Contractor

implied obligation not to hinder implied obligation to cooperate

Page 11: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 11

4. Acceleration4. Acceleration

What does the term mean? What is the benchmark? Basically, tow situations relating to the overall

works: Contractor is required to finish earlier than the

contractual date- variation of the contract, i.e. constructive order/change order- constructive acceleration

Contractor is likely to complete later than the contractual completion date

- acceleration to reduce delays

Page 12: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 12

4.1 Constructive acceleration4.1 Constructive acceleration

typical example for constructive acceleration claim:

Equipment procured by Employer from a third-party is delivered late. Contractor’s words are delayed. Contractor applies for Extension of Time (EOT). Interim assessment of the Engineer denies EOT; final review still pending. Employer presses Contractor to increase resources to make up for the delay.

Page 13: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 13

4.1 Constructive acceleration (cont’d)4.1 Constructive acceleration (cont’d)

Contractor‘s stark choice: Continue in hope to prove EOT or “accept” to be in

default temporarily and take steps to mitigate Nature of problem: contract’s EOT procedures

and contractor’s “temporary default” Conclusion: Constructive acceleration claim

presents significant legal difficulties; claim for disruption may be possible with fewer legal difficulties

Page 14: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 14

4.2 4.2 Acceleration to reduce delaysAcceleration to reduce delays

The issue of right or obligation to reduce the effect of qualifying delays may arise in three ways:

- Contractor’s may have right to choose how to deal with a qualifying delay and whether to accelerate or not and to recovery on the basis of this right;

- Contractor may be entitled to EOT and any associated loss only to the extent that he has mitigated the effect of the delays;

- Contractor may be under an obligation to progress the works including an express obligation to mitigate delays and the failure to do so prevents remedies of EOT/associated losses.

Page 15: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 15

4.2 4.2 Acceleration to reduce delays (cont’d)Acceleration to reduce delays (cont’d)

Mitigation of delay by acceleration? Contractor reacts to the qualifying delay

- most contracts provide for EOT provisions and express terms for agreement for acceleration

- generally no right of contractor to accelerate and recover costs (except if “constructive order”)

- “reasonabless”-argument Contractor does not react to the qualifying delay

- Generally no obligation where EOT provisions apply Mitigation by managing delay?

obligation to re-plan recourses and activities obligation to progress “regularly & diligently” includes

managing of effects of delay

Page 16: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 16

4.3 Obligation to accelerate?4.3 Obligation to accelerate?

Differentiation by reason for delay: Delay not caused by Contractor, i.e. entitled to EOT

- no obligation; only by means of separate agreement Delay caused by Contractor:

- in principle no obligation (discretion of contractor in regard of his own culpable delay)

- contract may provide power to order Contractor to adopt acceleration measures

“Indirect” obligation Contractor must weigh costs of acceleration, chance of

recovery against liquidated damages potentially levied against him

Page 17: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 17

4.4 Entitlement to acceleration4.4 Entitlement to acceleration

Contractor may perceive commercial advantage to accelerate; generally only bound by completion date

Generally no obligation of the Employer to co-operate

Exception: entitlement of acceleration provided in the contract and bound to program

Page 18: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Delay, Disruption and Acceleration · April 2009 18

5. Conclusion5. Conclusion

Time is of the essence in construction projects The effort of planning, negotiating and drafting

does not end at providing sophisticated terms for the event of delays by

finding a realistic completion date, incorporating EOT provisions and delay related

liquidated damages Instead, the same though and sophistication

should be put in addressing delays in terms of acceleration, rather than only dealing with them in terms of EOT and liquidated damages.

Page 19: Delay, Disruption and Acceleration Michael J.R. Kremer Contract Management in International Construction Beijing, April 28, 2009

Clifford Chance, Königsallee 59, 40215 Düsseldorf, Germany

© Clifford Chance 2009

Clifford Chance Partnerschaftsgesellschaft von Rechtsanwälten, Wirtschaftsprüfern, Steuerberatern und Solicitors · Sitz: Frankfurt am Main · AG Frankfurt am Main PR 1000

www.cliffordchance.com

Delay, Disruption and Delay, Disruption and AccelerationAcceleration

#960898

ContractContract Management in Management in International ConstructionInternational Construction

Beijing, April 28, 2009Beijing, April 28, 2009