LD-450 5/12/09
DEPARTMENT OF TRANSPORTATION
DIVISION: MATERIALS
REPORT COVER SHEET
Pre-Advertisement Conference Design Changes 4/14/2014
Authored By: Chaz Weaver, PE, MEM
Responsible for Pages: All
Project Description RTE 81 - INTERCHANGE MODIFICATION, EXIT 310
From: 0.546 miles S of Rt.37 To: 0.513 miles N of Rt. 37 Project UPC No.: 75881
VDOT Materials Division Staunton District
Geotechnical Engineering
DEPARTMENT OF TRANSPORTATION 811 Commerce Road
Staunton, VA 24401-9029 www.VirginiaDOT.org
WE KEEP VIRGINIA MOVING
Charles A. Kilpatrick, P.E. Commissioner
April 14, 2014 MEMORANDUM TO: Scott Alexander, PE
Project Manager FROM: Chaz Weaver, PE, MEM District Materials Engineer SUBJECT: Design Changes at PAC Review The intent of this memorandum is to document the design changes required by Staunton Materials Section, in contrast to those proposed by GeoConcepts in their Final Soil Survey Report of July 26, 2013. Several plan sheets provided for the Pre-Advertisement Conference (PAC) included proposed pavement structures and asphalt pavement mixes not in concurrence with the current Materials Division Manual of Instructions. The report noted above is the third version of such, and it was determined not in the best interests of the Department nor the project schedule to continue redacting this report for the many and various errors and omissions contained therein. Staunton Materials Section’s plan review comments for the PAC meeting included, but were not limited to (see attached combined review comments):
1. Changing the temporary pavement design to eliminate expensive surface asphalt mix. The comment requested SM-12.5A be changed to less expensive IM-19.0A. (Comment #9)
2. Using current version of Note G-6 (provided). GeoConcepts will review their pavement design and slope stability analyses to determine the minimum required CBR value. They will also determine and list areas where unsuitable material is expected. Project soils are acceptable as stormwater management basin embankment material, which should be noted. (Comment #160)
3. Adding binder type to SMA asphalt mixes. The consultant omitted “(70-22)” after “SMA-12.5” and “SMA-19.0” – which would have led to issues during bidding and construction. (Comment #168)
4. Change Inset E to Superpave asphalt mixes in lieu of SMA. Crossovers do not require these expensive mix types. (Comment #170)
5. Changing full-depth reconstruction of sections of US 11 and US 37 to full-depth widening and mill/replace or overlay. Northwest Regional Operations requested this change to eliminate critical maintenance of traffic issues, to which Staunton Materials Section agrees. (Comment #173)
6. Changing Ramp E to Ramps F and G pavement designs for consistency. This pavement structure (Inset C) is sufficient for Ramp E also, and this change will simplify both the plan sheet and construction operations. (Comment #178)
7. Deleting extraneous materials in entrance details. Aggregate No. 21A and SM-9.5D aren’t used anywhere else on the project. A “D” mix is not suitable for entrances. (Comment #179)
8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due to highly plastic subgrade soils and relatively thin pavement structures, geotextile was required to limit contamination of the aggregate subbase. (Comment #180)
9. Adding geotextile under asphalt path. Discussed during the meeting, geotextile directly below asphalt will reduce edge cracking. (Comment #181)
10. Adding leveling course and using SM-9.5AL. Staunton Materials Section agrees with Construction’s request for additional asphalt quantities to allow a leveling course where needed to provide smooth transitions – this will improve the overall rideability and aesthetics of the project. An “L” (limestone) mix may be used to reduce costs, as this layer will not be subjected to long-term traffic. (Comment #189)
11. Reviewing stormwater management basin slope design(s). Staunton Hydraulics will determine whether impounding water with a roadway embankment is allowable. GeoConcepts will further analyze the Ramp D embankment as a critical slope, per Materials Division Manual of Instructions (not provided in Final Soil Survey Report). (Comment #200)
12. Adding concrete cradle to double 48” pipes on Sheet 2H(14). Despite the consultant’s objections, this basin will be subjected to several drawdown events, and should be designed accordingly. (Comment #209)
13. Reviewing expected settlement under box culverts on Sheets 2M(2) and 2M(4). GeoConcepts did not provide any calculations, discussion or recommendations regarding structures under these relatively large fills. (Comment #230)
14. Correcting undercut locations and/or depths shown in cross-section sheets. Consultant will correct undercut shown to reflect GeoConcepts’ intent in the Final Soil Survey Report. Subgrade undercut is not necessary (or desired) as select material will be used.
The remainder of Staunton Materials Section’s comments were semantic, cosmetic or minor in nature and should not require sign and seal; however, all comments are attached. If you have any questions or concerns, please let me know.
Constructability Review Comments 2-Apr-14
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
1 1 L&DComplete Federal Job Number info for C- and D- number
phasesWill complete.
2 1 L&D Denote the RW Revision date on the Rev. Table Will denote.
3 1 SurveyWill this project be advertised under the new 2014 Road
and Bridge Specifications?Item to be discussed.
Verify P11 Temporary Easement requirements (as shown Temporary Easement to be removed,
Pre-Advertisement Conference
I-81 Exit 310 Interchange Modification Frederick County
0081-034-127 UPC 75881
4 1C L&D Verify P11 Temporary Easement requirements (as shown
on Sht 12)
Temporary Easement to be removed,
LD-36 form and revised sheets to be
provided.
5 1c SurveyThere is a right of way data sheet. Will there be Right of
way plan sheets?
They are included on the RW plan
sheets. Will add to PAC plans.
6 1D Environmental The Revision data sheet was not included.
Revision data sheet submitted on
3/7/14, will submit updated sheets as
needed.
7 1F SurveyVDOT surveyors will rename the traverse table and add the
elevations for the points listed.
Noted, please inform design consultant
when change is made.
8 1F(1) Survey
The surveyor for the Engineering consulting firm should
provide the coordinate x,y, and z values for the control
points than they set for this project and the traverse
It is our understanding that adequate
coordinate information has been
provided for control points in the
between the points. A description of the type of monument
set must accompany the coordinate value.
supplemental survey area. Please
clarify which areas are in question.
9 1K(1) Materials
Temporary Pavement Design Table: Change SM-12.5A
layers to IM-19.0A. Delete BM-25.0A layers on Tasker
Road and Hillandale Lane. (Provided in 8/13/2013 geotech
report review).
Will revise temporary pavement layers.
Change Table 18 in Final Geotechnical
Report as well? Note: No IM-19.0A
called out in any other typical sections.
10 1K(1) MaterialsPhase 1: "Temporary Pavement Roadway" is not shown in
MOT plans.
Will add "Temporary Pavement
Roadway" to MOT plans for Phase 1.
11 1K(1) MaterialsPhase 1A: MOT plans do not show temporary pavement
along I-81.
Temporary pavement shown in plan
view [see example in sheet 1L(7)], will
add detail for temporary pavement along 11 1K(1) Materials
along I-81. add detail for temporary pavement along
I-81.
12 1K(1) MaterialsPhase 1C: Is "temporary roadway" term correct? MOT
plans show minor widening.
Will revise description to temporary
pavement. Phase 1A, Note 4 to be
corrected as well.
13 1K(1) Operations
Provide a barrier warrant analysis for all proposed barrier.
Based on the anticipated short durations of some of the
phases group II channelizing devices may be more
appropriate.
Volkert will assess all locations where
barrier is shown to determine if Group II
channelizing devices would be more
appropriate.
Page 1 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
14 1K(1) Operations
Include a note indicating that permanent signage will need
to be installed throughout various phases once new traffic
patterns have been established at the discretion of the Area
Construction Engineer and the Work Zone Safety
Coordinator
Will comply.
15 1K(1) Operations Phase 1A Note #3 - Please provide more detail Will comply.
16 1K(1) OperationsProvide Durations, Incentives and Disincentives for
individual phasesWill comply.
17 1K(1) Operations
New Tasker Road is utilized during Phase 1C and Phase
1D detours, however the sequence of construction states
that the contractor shall open New Tasker Road during
Phase 2. Please clarify.
Will clarify opening of New Tasker
Road.
Phase 2. Please clarify.
18 1K(1) Operations
Include a note that all construction access points need to be
coordinated with and approved by the Area Construction
Engineer and the Work Zone Safety Coordinator.
Will comply.
19 1K(2) OperationsGeneral Note #1 - Confirm that this does not contradict the
detour plansWill confirm there is no conflict.
20 1K(2) Operations
General Note #6 - Contractor shall notify the "Traffic
Operations Center" and not the Regional Operations
Maintenance Manager
Will comply.
21 1K(2) OperationsGeneral Note #7 - Is this referring to the existing traffic
signal installation plans?Will clarify
22 1K(2) Operations Remove General Note #11 - This is covered in the WAPM Will comply.22 1K(2) Operations Remove General Note #11 - This is covered in the WAPM Will comply.
23 1K(2) OperationsGeneral Note #12 - Replace "construction" with "any phase
or traffic shift".Will comply.
24 1K(2) Operations General Note #13 - Address how this will be accomplished Will comply.
25 1K(2) Operations Remove General Note #16 - This is covered in the WAPM Will comply.
26 1K(2) Operations Remove General Note #19 - This is covered in the WAPM Will comply.
27 1K(2) Operations
Construction Note #1 - Confirm allowable work hours and
verify why we are restricting night work? Is there a noise
ordinance in Winchester? 9-3 lane closures?
Will confirm allowable work hours.
28 1K(2) OperationsConstruction Note #3 - address how this will be
accomplishedWill address.
29 1K(2) OperationsConstruction Note #5 - Revise to include "payment is
incidental to other work"Will comply.
30 1K(2) OperationsAdd a note indicating that signal timing adjustments will be
the responsibility of the contractorWill comply.
31 1K(2) OperationsInclude notes regarding the eradication of existing striping.
Consider showing on plan sheets for individual phases.Will comply.
Page 2 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
32 1K(2) Construction
Holiday Restriction under Construction Notes needs to be
changed to the following: No work operations which restrict
roadway capacity shall be permitted on Sundays or from
12:00 PM the day before a holiday until 12:00 PM the day
after a holiday. If a holiday occurs on a Saturday or Sunday,
the restrictions shall apply from 12:00 PM the Friday before
the holiday until 12:00 PM the Monday after the holiday.
These operations include but are not limited to flagging
operations, temporary road or lane closures, installation or
removal of traffic barrier service, staging of construction removal of traffic barrier service, staging of construction
vehicles within a travel way and entry or exit of slow moving
construction vehicles to or from the work area. Otherwise,
no work operations which restrict roadway capacity beyond
that shown on the plans shall be permitted without
permission from the Engineer for the Holidays as shown per
section 108.02 of the Road and Bridge Specifications.
33 1K(2) Construction
Special Event Restrictions needs to be added under
Construction Notes: This note needs to be specific to the
Annual Apple Blossom Festival which is held in Winchester
each year. No work should be performed during this festival 33 1K(2) Construction
period which would result in impacts to the traffic patterns,
i.e. lane closures or restrictions, flagging operations, etc.,
due to the extremely heavy traffic volumes which are
experienced during the week of the Apple Blossom Festival.
34 1K(2) Construction
The following note needs to be added to the Sequence of
Construction (SOC) Notes: At the end of each day no more
than 2 inches grade difference between travel lanes or at
the edge of the travel lanes will be allowed during
construction. Any grade difference greater than 2 inches
will require an approximate 6:1 wedge be installed for the
Safety and protection of vehicular traffic. The cost of
placing, furnishing and removing the wedge shall be
Will comply.
placing, furnishing and removing the wedge shall be
included in cost of other items.
35 1K(2) Construction
The following note needs to be added to the Sequence of
Construction (SOC) Notes: The Contractor shall replace
damaged impact attenuators immediately after damage is
incurred, not to exceed 24 hours from the time damage is
incurred. Replacement of damaged Attenuators will be
included in the price for the attenuator.
Will comply.
Page 3 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
36 1K(2) Construction
The following note needs to be added to the Sequence of
Construction (SOC) Notes: All traffic Barrier and impact
attenuators shall be installed to maintain sight distance
requirements at all intersections and entrances during
construction unless otherwise directed by the Engineer.
Will comply.
37 1K(2) Construction
The following note needs to be added to the Sequence of
Construction (SOC) Notes: When proceeding from one
phase of construction to another phase any existing or
construction pavement markings that conflict with the new
traffic pattern shall be eradicated and re-striped accordingly.
Will comply.
traffic pattern shall be eradicated and re-striped accordingly.
38 1K(2) Construction
The following note needs to be added to the Sequence of
Construction (SOC) Notes: The contractor shall install a
temporary pavement patch over utility and drainage pipe
trenches in paved roadways and/or shoulder areas.
Temporary surface patch shall consist of Asphalt Concrete
Base Course BM-25.0A installed at a minimum 4"
thickness. Asphalt for temporary patches shall be included
in the price bid for related utilities and drainage pipes.
Will comply.
The following note needs to be added to the Sequence of
Construction (SOC) Notes: All Flagging operations shall be
conducted as per the 2011 Virginia Work Area Protection 39 1K(2) Construction
conducted as per the 2011 Virginia Work Area Protection
Manual. The cost of the required shadow vehicle shall be
included in the price bid for other items in the contract and
no additional compensation for this item will be made.
Will comply.
40 1K(2) Construction
The following note needs to be added to the Sequence of
Construction (SOC) Notes: In accordance with the Work
Area Protection Manual, the contractor shall provide a light
source to illuminate the flagging stations during night time
flagging operations. The flagger stations shall be illuminated
at night by a light source producing a minimum of 5 foot
candles (50 lux). Separate payment will not be made for
providing a light source. The cost thereof shall be included
Will comply.
providing a light source. The cost thereof shall be included
in the price of Flagger Service.
41 1K(3) OperationsProvide a note regarding signal timing adjustments for
existing Route 11 signals during detourWill comply.
42 1K(3) OperationsShould the Legend and hatched area represent Phase 1C
construction?Yes, will correct.
Page 4 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
43 1K(3) Operations
Confirm ramp from Rt 11 to Rt 37 South can handle the
volume of the detoured traffic. Also, a traffic signal may be
considered for Ramp G at Tasker. Provide analysis.
Synchro analyses indicate that the Rt
11/Rt 37 SB ramp would maintain
adequate levels of service during the
Phase 1B detour.
44 1K(3) OperationsRoute 37 is a state primary route, not a U.S. route. Revise
the route shields accordingly.Will comply.
The Phase 1C RT 37 EB Extended at Relocated Tasker
Road intersection analysis is incomplete. It failed to take
into account the unusual Lane Utilization Factor resulting
from the dominant NB LT movement at the intersection 450
feet north. I calculated a Lane Utilization Factor of 0.62 for SimTraffic analyses was beyond the
scope of the completed analyses. This 45 1K(3) Operations
feet north. I calculated a Lane Utilization Factor of 0.62 for
the NB Thru movement at RT 37 EB Extended and
Relocated Tasker Road. This will not change anything in
the Synchro Analysis Worksheet because it is a
macroscopic adjustment. However, running SimTraffic will
show that this unbalanced flow will cause significant
backups for the EB LT movement.
scope of the completed analyses. This
issue should be discussed further with
VDOT.
46 1K(4) OperationsRoute 37 is a state primary route, not a U.S. route. Revise
the route shields accordingly.Will comply.
47 1K(4) OperationsShould the Legend and hatched area represent Phase 1D
construction?Yes, will correct.
48 1K(4) OperationsAll type III barricades should be aligned perpendicular to the
closed roadway sectionsWill comply.
49 1K(4) Operations
Confirm ramp from Rt 11 to Rt 37 South can handle the
volume of the detoured traffic. Also, a traffic signal may be
considered for Ramp G at Tasker. Provide analysis.
Synchro analyses indicate that the Rt
11/Rt 37 SB ramp would maintain
adequate levels of service during the
Phase 1B detour.
50 1L(1) Operations
Barrier along Tasker Rd must meet flare rate requirements.
Ensure that barrier does not impede line of sight looking
northeast.
Will comply.
51 1L(1) Operations
Include notes in the Temporary Traffic Control Plan Sheets
that indicate the contractor is responsible for maintaining
access to all commercial and private entrances during
construction
Will comply.
52 1L(1) OperationsInclude a note indicating that asphalt section will need to be
in place prior to the end of each working shift.Will comply.52 1L(1) Operations
in place prior to the end of each working shift.Will comply.
53 1L(1) Operations
Ensure all left shoulder widening along I-81 will match
existing 2% cross slope of existing section and additional
shoulder grading will be required as work progresses.
Will review and revise if necessary.
54 1L(3) Materials Provide temporary pavement design note. Will comply.
55 1L(6) Operations A right shoulder closed ahead sign will be required Will comply.
56 1L(6) OperationsAddress construction access issues for work to be
performed in Phase 1AWill comply.
Page 5 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
57 1L(6) Operations When is existing striping eradication addressed?Will add notes to address existing
striping eradication.
58 1L(6) Operations Barrier flare rate along I-81 is minimum 22:1.1-81 posted speed limit is 65 mph so a
barrier flare rate of 20:1 was used.
59 1L(6) Operations1' shy line must be to the face of the barrier, not the
centerline.
Will revise typical section to show this
correctly.
60 1L(6) OperationsProvide dimension from the edge line to the edge of the
shoulder widening for each direction of I-81.Will comply.
61 1L(7) Operations Barrier flare rate along I-81 is minimum 22:1.1-81 posted speed limit is 65 mph so a
barrier flare rate of 20:1 was used.barrier flare rate of 20:1 was used.
62 1L(7) Operations
Show traffic control for temporary pavement along Ramps A
and D to be constructed in this phase. Cross slope of
shoulder widening should match existing 2% cross slope of
existing ramps. Provide guidance for conditions left during
non-working hours.
Will provide traffic control for temporary
pavement. Will review slope of shoulder
widening and revise if necessary. Will
provide guidance for conditions left
during non-working hours.
63 1L(8) Operations
Show traffic control for temporary pavement along Rt 37 to
be constructed in this phase. Cross slope of shoulder
widening should match existing 2% cross slope of Route 37.
Provide barrier warrant analysis. Provide guidance for
conditions left during non-working hours.
Will provide traffic control for temporary
pavement. Will review slope of shoulder
widening and revise if necessary. Will
provide guidance for conditions left
during non-working hours.
64 1L(9) Operations Barrier flare rate along I-81 is minimum 22:1.1-81 posted speed limit is 65 mph so a
barrier flare rate of 20:1 was used.
65 1L(11) Operations
Construction same location same location as existing
guardrail. Recommend gr-9 on each side of entrance with
Type III barricades. Eliminate barrier but ramps need to be
at grade once guardrail is modified.
Barrier is needed since full depth
construction is occurring at this location.
66 1L(12) Operations Barrier radius questionable especially down at Route 11. Will modify barrier radius.
67 1L(12) Operations Ensure stop sign is in place at end of ramp E at Rt. 11We have verified the existence of the
stop sign in place in the field.An impact attenuator is not needed
68 1L(12) OperationsVerify impact attenuator is not required on south end of
barrier along Route 11.
An impact attenuator is not needed
since the is a median between the
barrier and traffic from the opposing
direction.69 1L(12) Operations Provide Section B-B for Route 11. Will comply.
Page 6 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
70 1L(12) Operations
Show traffic control for temporary pavement along Route 11
to be constructed in this phase. Cross slope of shoulder
widening should match existing 2% cross slope of existing
ramps. Provide guidance for conditions left during non-
working hours.
Will provide traffic control for temporary
pavement. Will review slope of shoulder
widening and revise if necessary. Will
provide guidance for conditions left
during non-working hours.
71 1L(13) Operations Proposed route signs should be shown on the signing plan.
These are not proposed signs, these are
temporary signs needed due to the
construction restricting left turns on
sheet 1L(15).
Lane drop layout. Recommend pulling lane closure back to This was considered during the design
72 1L(14) Operations
Lane drop layout. Recommend pulling lane closure back to
south and then allow openings for turn lanes instead
splitting traffic.
This was considered during the design
of the TMP but there was not adequate
space available for this to occur.
73 1L(15) Operations
There was no analysis performed at the stop controlled RT
37 WB to RT 11 NB “slip ramp”. During Phases 1C and 1E,
RT 11 NB is reduced to one lane at its intersection with the
slip ramp. This constriction will reduce the number of
available gaps for right turning vehicles off the slip ramp.
There is the potential for slip ramp backups to extend all the
way back to RT 37. This analysis needs to be performed,
at least for Phases 1C and 1E.
Synchro analysis shows the stop
controlled Rt 37 Slip ramp at Rt. 11 can
accommodate detoured traffic.
Since the geometry is different from
74 1L(15) OperationsRemove Left Lane Closed Ahead and replace with a Curve
sign with a Max safe speed plaque.
existing, we determined that the current
signs best notify drivers of the geometry
change. A max safe speed plaque can
be added.75 1L(15) Operations Existing marking across ramp to be eradicated Noted.
76 1L(15) Operations Install a "no Left Turn" sign on Ramp E Will comply.
77 1L(15) OperationsInstall a One Way sign on Route 11 for ramp traffic to go
South only.Will comply.
78 1L(15) OperationsVerify Wrong way signs are already in place on Route 11
North of Ramp E
We have verified the existence of these
signs in place in the field.
79 1L(15) Operations Remove ramp closed with type III on northbound Route 11 Will comply.
80 1L(16) Operations Install a shift sign on south bound Route 11 Will comply.80 1L(16) Operations Install a shift sign on south bound Route 11 Will comply.
81 1L(17) Materials
Add temporary pavement note (referencing Table 1, Sheet
IK(1)) - same for Sheets IL(20), IM(4), 1M(5), 1P(2) and
1P(4).
Will comply.
82 1L(17) Operations Remove barrier in crossover. Place Type III barricades Will comply.
83 1L(17) Operations Barrier warrants due to small amount of work.Barrier is needed since full depth
construction is occurring.
84 1L(17) Operations Construction access due to barrier flared back and in placeWill ensure construction access due to
barrier flare.
Page 7 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
85 1L(17) Operations Add left shoulder closed signage on Route 11 northbound Will comply.
86 1L(17) Operations No left turn sign shall remain from previous phases Will comply.
87 1L(17) Operations Remove "RWA" on Ramp EThe "Road Work Ahead" sign is
necessary according to the VAWAPM.
88 1L(17) OperationsRemove Left Lane Closed Ahead and replace with a Curve
sign with a Max safe speed plaque.
Since the geometry is different from
existing, we determined that the current
signs best notify drivers of the geometry
change. A max safe speed plaque can
be added.The flare rate was shortened due to
89 1L(17) Operations If barrier remains 5:1 flare rate is not to standardThe flare rate was shortened due to
geometry constraints.
90 1L(19) Operations Arrow board at beginning of taper. Will comply.
91 1L(20) Operations Barrier warrant for the trench widening? Clarification is needed. Should be
discussed with VDOT.
92 1L(20) OperationsHeading southbound on Rte 11 create right turn lane and
keep one through lane until south of ramp C.
Clarification is needed. Should be
discussed with VDOT.
93 1L(20) Operations
Pull the Barrels creating the nose for Ramp C at the end
down further towards Route 11 to guide vehicles to make
right turn until striping is installed.
Will comply.
94 1L(20) OperationsRemove LLCA replace with curve sign with max safe speed
plaque
Since the geometry is different from
existing, we determined that the current
signs best notify drivers of the geometry 94 1L(20) Operationsplaque
signs best notify drivers of the geometry
change. A max safe speed plaque can
be added.
95 1L(20) Operations Install a "no Left Turn" sign at bottom on Ramp ELeft turns are permitted; this lane is a
shared left-thru-right turn lane.
96 1L(20) Operations Should be Ramp E instead of C. Will comply.
97 1L(20) Operations Stop sign at bottom of Ramp E Will comply.
98 1L(20) Operations Remove RWA signs on Ramp E The "Road Work Ahead" sign is
necessary according to the VAWAPM.
99 1M(1) Operations Capacity Issue on I-81 NB ramp due to right turn only
This ramp is not right turn only. There is
one left-turn lane and one right-turn
lane.100 1M(1) Operations Realign Type III barricade Will comply.100 1M(1) Operations Realign Type III barricade Will comply.
101 1M(2) Operations Realign Type III barricade Will comply.
102 1M(2) OperationsAdd group II's along shoulder in areas where the new road
alignment occursWill comply.
103 1M(2) OperationsTypical for Hillandale shows a 12 median. Is this a striped
median? There is no median on this sheet.
104 1M(2) OperationsTie in for new/old Hillandale Lane. Is this just getting
overlaid with asphalt only?This tie-in will occur via asphalt overlay.
105 1M(3) OperationsClarify when ramps G and F and new Tasker Road is
constructed and open to trafficWill clarify.
Page 8 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
106 1M(4) Operations Address construction access for Phase 2 construction Will comply.
107 1M(4) Operations Provide cross section B-B for ramp F Will comply.
108 1M(4) Operationsadditional lane width is preferred due to additional traffic
and truck traffic during detour
The space required to do the work does
not allow for additional lane width in this
area.
109 1M(4) OperationsRefer to WAPM TTC-20 for lane closure with barrier for
pavement marking requirements, markers, etc. Will comply.
110 1M(5) Operations Provide R4-7 sign in Rt 37 median NB and SB at I-81 ramps Will comply.
111 1M(5) Operations Provide LT lanes on Rt 37 for I-81 Will comply.
Will comply. It does not appear that 112 1M(5) Operations
Contractor shall provide signal timing plans for I-81 NB off
ramp signal. Will signal head adjustments be required?
Will comply. It does not appear that
signal head adjustments will be
required.
113 1M(5) Operations
The proposal to restrict the bridges over I-81 to a single
lane in each direction (in Phase 2) will not work
operationally. The signals will operate at 150% of capacity
and will both have LOS F. The intersection with the I-81
Northbound ramps has over 5 minutes of delay on all
approaches. The intersection with the I-81 Southbound
ramp has delays exceeding 12 minutes for the off-ramp. In
both cases, traffic will be backing up onto the freeway.
This issued need to be discussed with
VDOT.
114 1M(6) Operations Verify barrier flare meets standards. Will comply.114 1M(6) Operations Verify barrier flare meets standards. Will comply.
115 1M(6) OperationsAddress construction access issues for work to be
performed in Phase 2Will comply.
116 1M(6) OperationsProvide cross section B-B for Rt 37 just south of Ramps A
and BWill comply.
117 1M(6) OperationsRemove Road Closed sign on barricade on Rt 37 SB that is
behind barrierWill comply.
118 1M(7) Operations Remove W9-3L, R4-V7R, W4-2L and G20-2 signs Clarification is needed. Should be
discussed with VDOT.
119 1N(2) Operations11' lanes may present a problem with over width permits.
Please address.Should be discussed with VDOT.
120 1N(2) Operations Remove G20-2 signThe "End Road Work" sign is necessary
according to the VAWAPM.
121 1N(2) OperationsProvide cross section B-B for Rt 37 just south of Ramps C
and DWill comply.
122 1N(2) OperationsBarrier flare rate seems inadequate. Address connection
with existing guardrail.
This was designed in accordance with
the 45 mph posted speed limit.
According to the VAWAPM 14:1 is
correct for 45 mph.
Page 9 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
123 1N(3) Operations
Phase 3 has Route 37 westbound as one lane, and
eastbound as two lanes, over I-81. However, the AM peak
period has LOS F at the I-81 northbound intersection with
4.5 minutes or more of delay for both Route 37 westbound
(from Tasker Road) and the I-81 northbound exit ramp.
Should be discussed with VDOT.
124 1N(5) Operations Arrow board at beginning of taper for ALL lane closures. Will comply.
125 1N(5) OperationsRevise taper to provide access to commercial entrance
across from Rt 37 rampsWill comply.
126 1N(6) Operations Provide R4-7 in median of Ramp E at Rt 11 Will comply.
The lane drop was put in place to 127 1N(6) Operations
Explain reason for lane marking shift along Route 11 NB in
front of Ramp E.
The lane drop was put in place to
accommodate the work on the shoulder
and a portion of the road.
128 1P(1) Operations Ensure lane shift on I-81 is in accordance with TTC-40 Will comply.
129 1P(1) OperationsExist open E5-2 sign should be approximately 650' prior to
ramp openingWill comply.
130 1P(2) Operations Add W4-1R sign for Ramp A onto I-81 SB Will comply.
131 1P(2) Operations Barrier flare rate seems inadequate. Will review and revise if necessary.
132 1P(2) Operations
Provide PCMS along Ramp A to address short merge onto I-
81 SB. Yield ahead and yield signs should also be
installed.
Will comply.
133 1P(2) Operations Barrier flare rate inadequate I-81 NB and SB Will review and revise if necessary.133 1P(2) Operations Barrier flare rate inadequate I-81 NB and SB Will review and revise if necessary.
134 1P(2) Operations Address barrier connection on I-81 NBClarification is needed. Should be
discussed with VDOT.
135 1P(3) OperationsRoad closed sign on 37 NB can be removed since it is
behind barrierWill comply.
136 1P(3) Operations Construction access for Rt 37 SB during phase 4Clarification is needed. Should be
discussed with VDOT.
137 1P(3) Operations
Phase 4 again has Route 37 at only a single lane in each
direction over I-81. This is not workable because there is
not enough capacity for I-81 north to Route 37 west.
Should be discussed with VDOT.
138 1P(4) OperationsAddress barrier connection on I-81 SB (If barrier is
necessary)
Clarification is needed. Should be
discussed with VDOT.Provide PCMS along Ramp A to address short merge onto I-
139 1P(4) Operations
Provide PCMS along Ramp A to address short merge onto I-
81 NB. Yield ahead and yield signs should also be
installed.
Will comply.
140 1P(4) Operations Barrier flare rate for I-81 SB ramp is inadequateClarification is needed. Should be
discussed with VDOT.
141 1P(5) OperationsExist open E5-2 sign should be approximately 650' prior to
ramp openingWill comply.
142 1P(5) Operations Remove extra arrows in left lane of I-81 NB and SB Will comply.
143 1P(6) Operations R4-7 signs in median of Rt 37 NB and SB Will comply.
Page 10 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
144 1P(6) OperationsRt 37 NB approaching Ramp C delineate single through
lane with edgeline prior to creating right turn laneWill comply.
145 1P(6) OperationsEnsure all permanent lane drop signs and markings are in
place for Ramp CWill ensure.
146 1P(6) OperationsAnalyze the storage capacity of the Route 37 SB Left Turn
Lane onto Ramp C
Analyses have been provided for the left-
turn lane of Rt 37 SB/EB ramp under
Phases 4/5 traffic analyses.
147 1P(7) Operations Clarify when Rt 37 off ramp was taken out of service Will clarify.
148 1P(7) Operations Remove End Road Work signThe "End Road Work" sign is necessary
148 1P(7) Operations Remove End Road Work signThe "End Road Work" sign is necessary
according to the VAWAPM.
149 1P(7) Operations Barrier flare rate at Ramp A inadequate Will review and revise if necessary.
150 1P(7) OperationsEnsure all permanent lane drop signs and markings are in
place for Ramp AWill ensure.
151 1Q(2) Operations Remove End Road Work signThe "End Road Work" sign is necessary
according to the VAWAPM.
152 1Q(3) OperationsAddress construction access for Phase 5 construction (only
access appears to be in dual turn lanes).Will address.
153 1Q(3) Operations
Phase 5 again has Route 37 at only a single lane in each
direction over I-81. This is not workable because there is Should be discussed with VDOT.153 1Q(3) Operations direction over I-81. This is not workable because there is
not enough capacity for I-81 north to Route 37 west.
Should be discussed with VDOT.
154 1Q(4) Operations Remove End Road Work signThe "End Road Work" sign is necessary
according to the VAWAPM.
155 1Q(5) OperationsProvide Arrow Board and the beginning of taper for lane
closure.Will comply.
156 1Q(5) OperationsConsider closing left lane Rt 37 SB prior to ramp from Rt 11
to avoid merging from both directions at same locationWill review and revise if necessary.
157 1Q(5) Operations
If left lane is closed prior to Rt 11 ramp, relocate W4-2L
signs and remove Keep Right and Left Lane Closed Ahead
signs from Ramp
Will review and revise if necessary.
signs from Ramp
158 2 Construction
General Notes, under Pavement: Add the following note:
Asphalt leveling shall be performed prior to placement of
the surface layer of asphalt at the direction of the engineer.
Asphalt Concrete Ty. SM-9.5A shall be used for leveling
application.
Will add note. Heading to be "Note:".
SM-9.5A is not used in any proposed
roadway sections, should SM-12.5A be
used instead?
159 2 Materials Delete Note G-2 (FI). Will delete note.
Page 11 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
160 2 MaterialsUse new Note G-6 and Pavement Tie-In Notes (attached).
Discuss minimum CBR value.
Will revised Note G-6 and add
Pavement Tie-In Notes. Minimum CBR
value of 5 called for in Final
Geotechnical Report, should different
value be used?161 2 Materials Add Controlled Blasting Note (attached). Will add note.
162 2 Survey
Note I - 10 should read "Standard RM-2 Right of way
monuments shall be set by the contractor." Matches
Summary sheet 2E1.
The note will be adjusted as requested.
The utility backfill requirements are different than the
standard PB-1. Revise the fourth note under MATERIALS Will revised note, should utility pipe
163 2 Utilities
standard PB-1. Revise the fourth note under MATERIALS
to reflect this and refer the reader to the utility bedding and
backfill detail located on sheet 39(19). Also note that this
shall be included in the price of the pipe and shall not be
measured and paid separately.
Will revised note, should utility pipe
backfill discussion be at the beginning or
end of fourth note?
164 2 ConstructionA note needs to be added on Sheet 2 pertaining to
Controlled Blasting Operations.Will add note, see response to item 160.
165 2A ConstructionTypical Sections I-81. Guardrail Typical drawing needs to
be added to this Typical Sheet.Will add guardrail typical section.
166 2A L&D Verify Note 1Note 1 will be deleted, see comment
178 and response.
167 2A L&D Detail rail sections as necessary (all typicals)Will add guardrail typicals to all relevant
typical sections.
168 2A Materials
Change "SMA-12.5" to "SMA-12.5(70-22)" and change
"SMA-19.0" to "SMA-19.0(70-22)." Same for Sheets 2B,
2B(1), 2B(2), 2B(3) and 2B(4).
Will revise pavement material callout.
169 2A Materials Insets C and G appear to be exactly the same.Inset G to be deleted, NBL I-81 to note
"See Inset D or Inset C".
170 2A MaterialsChange Inset E to SM-12.5A and IM-19.0A (i.e. not SMA
mixes).
Will revise Inset E. Should 2" of BM-
25.0A be used instead of 2" of IM-
19.0A? No IM-19.0A called out in any
other typical sections.
171 2A MaterialsDelete Notes 1, 4 and 5. Same for Sheets 2B, 2B(1), 2B(2),
2B(3) and 2B(4).Will delete notes 1, 4, and 5.
Is the I-81 Left shoulder widening temporary pavement
No, left should widening will be
permanent when placed for Phase 1
172 2A Operations
Is the I-81 Left shoulder widening temporary pavement
being removed and replaced with the permanent typical
section?
permanent when placed for Phase 1
MOT purposes. Is note needed on
sheet 2A for clarification? Sheet 1K(1)
does not call this temporary pavement.
173 2A OperationsConsider modifying structural section to reduce construction
time in work that has to be done under traffic
To discuss, is this in reference to left
shoulder widening in particular?
Page 12 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
174 2B Materials
Upper right typical section: Move UD-4 to edge of full-depth
shoulder or stop surface course at end of intermediate
layer.
Provide clarity, UD-4 edge is currently
lined up with edge of full-depth shoulder.
175 2B(1) Materials
Route 37 with Guardrail Detail: Where do these dimensions
start, what are the pavement layers required and why isn't
shoulder full-depth pavement? Same for Sheet 2B.
Will add dimension start point. Full-
depth pavement will be used, will add
callout for Inset A. UD-4 will be shown
at correct place.176 2B(3) Materials Add "2:1 max" to middle typical sections. Will add label.
177 2B(3) MaterialsUpper right typical section: Move UD-4 to edge of full-depth
shoulder.
Provide clarity, UD-4 edge is currently
lined up with edge of full-depth shoulder.
Will revise Ramp E pavement layers. 178 2B(3) Materials
Change Ramp E to Ramps F and G pavement design (Inset
C) for consistency.
Will revise Ramp E pavement layers.
Change Table 17 in Final Geotechnical
Report as well?
179 2B(4) MaterialsEntrances: Delete "21A or" and "or SM-9.5D." Change "BM-
25.0" to "BM-25.0A."Will delete or correct pavement callouts.
180 2B(4) MaterialsTasker Road and Hillandale Lane: Add subgrade
stabilization geotextile under Aggregate No. 21B layer.
Will add subgrade stabilization
geotextile.
181 2B(4) Materials Inset F does not appear to be used on this sheet.Inset F used on upper right Hillandale
Lane typical section.
182 2B(4) ConstructionTypical Sections Tasker Road. Guardrail Typical drawing
needs to be added to this Typical Section.Will add guardrail typical section.
Show sawcut (full-depth) at joint between existing and 183 2C Materials
Show sawcut (full-depth) at joint between existing and
proposed pavement. Same for Sheets 2C(1) and 2C(3).Will add sawcut label.
184 2C(2) Construction
Interchange Gore Areas, Ramp B Exit Ramp from I-81
S.B.L. Dotting for new Full Depth Pavement is not shown on
this sheet.
Will add dotting for new full depth
pavement.
185 2C(2) Construction
Interchange Gore Areas, Ramp B Exit Ramp from I-81
S.B.L. Cross Hatching for Mill & Overlay is not shown on
this sheet.
Will add cross hatching.
186 2C(2) Materials Show cross-hatching. will add cross hatching.
187 2D L&D There are a number of areas where road fills overlap SWM
fills; ensure quantities aren't double counted
SWM fills in overlap areas are based
upon the assumption that projected
roadway slopes are in place. Volumes
are not overlapped. are not overlapped.
188 2D, 2E L&D There are many quantities that are missing and/or don't
add up; verify totalsWill correct quantities and verify totals.
Page 13 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
189 2E Construction
Pavement Summary Sheet:The Area Construction Engineer
would like to request the addition of 2,000 Tons of Asphalt
Concrete Type SM-9.5A asphalt material which will be used
for a leveling course, if required, in transition areas and
phase construction tie-in areas before placement operations
of the surface layer of asphalt.
To discuss location on summary sheet.
Will add 2,000 tons of Asphalt Concrete
Type SM-9.5A.
190 2E Materials Add "(70-22)" to SMA quantities.Will add "(70-22)" to SMA quantities
description.
191 2E Materials Delete 7" No. 21B and 8" BM-25.0D columns. Will delete unused columns.
To discuss. Type III Barricades are
192 2E(1) ConstructionType III Barricades (8' Wide) are shown in two different
columns in the Incidental Summary Sheet.
To discuss. Type III Barricades are
used in maintenance of traffic for
temporary installation and on sheets
36(9) for permanent installation.
193 2E(1) ConstructionField Office Type II is currently shown in the Incidental
Summary. Field Office needs to be changed to a Type I.Will revise to Field Office Type I.
194 2E(1) Construction
Incidental Summary: Numbers in various columns on this
sheet do not total up correctly to match the totals which are
now shown.
Will correct quantities and verify totals.
195 2E(1) Construction
Incidental Summary: Item # 13600 Impact Attenuation Unit.
A total of 24 Each are shown in the Total Column, but none
are shown by Plan Sheet locations in the table above the
Item is used for maintenance of traffic.
No permanent impact attenuators are
proposed.are shown by Plan Sheet locations in the table above the
totals. proposed.
196 2G L&D Should "Final Design Stage" be checked? Yes. Design stage will be corrected.
197 2H Materials
Change "Soil or Low Permeability Liner" to "Low
Permeability Liner (See Special Provision)." Same for
Sheets 2H(5), 2H(8), 2H(15), 2H(19) and 2H(23).
The note will be adjusted as requested.
Under Note 3, it indicates to "See plan view for locations
and Planting Schedule". While a rudimentary "Plant List" is
provided for this SWM Pond, more details need to be
provided such as number of plants, plant sizes, watering
schedule, etc. Reference attachment sent from Scott
Alexander to Tim Glickman on 9/23/2013. For the ensuing
A landscaping detail for the aquatic
benches will be added to the 2H (SWM
Detail) series which provide greater
construction detail as requested. Note
that the plantings associated with 198 2H Roadside Mgmt.
Alexander to Tim Glickman on 9/23/2013. For the ensuing
Aquatic Bench Summary & Notes, change any reference in
the General Notes from Landscape Architect to District
Roadside Manager, the planting season should be from
November 1 through March 15, reference the table below
for watering requirements, eliminate 2-year establishment
for SWM pond plantings, and place the summary sheet at
the beginning of the "H" series.
that the plantings associated with
aquatic benches will be Zone 1 and 2
submergent and emergent container
plants or stems. typically these are
specified in a stem per square footage
basis without specific planting locations.
Page 14 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
199 2H Roadside Mgmt.Exact planting locations, including spacing, need to be
shown on the plan view of the SWM pond.
we propose to add a typical planting
detail to identify a reasonable cluster of
the plants within the aquatic bench.
Outfall slope should be 3:1 maximum. No critical slope
stability analysis was provided for Ramp D. Have DCR
Outfall from 6-9 proposes rip rap
channel protection of the ditch out
following existing topography. Because
the existing slopes in this area are
greater than 3:1 would require
substantial additional clearing, grading
and potential utility conflict for reduction.
200 2H(1) Materials
stability analysis was provided for Ramp D. Have DCR
requirements (impoundment structure) been verified? (FI
and RoW) Same for Sheets 2H(5) Access Road and
2H(24) Hillandale Lane.
and potential utility conflict for reduction.
(2H(5)) -The access road side slope is a
temporary condition (pending phase III
loop) separated from the impoundment
by more than 60'. 2H(24)- The 2:1
slopes in this section are for the
roadway section and should not be a
consideration for pond stability or
maintenance.
201 2H(1) Materials
Use direct term in lieu of "Proposed Grade" unless the
elevations and slope ratios shown are only suggestions to
the contractor. Same for Sheets 2H(5), 2H(8), 2H(14),
The "Proposed Grade" line represents
the finished grade profile at the section
lines shown and matches the contour
lines in the detail sheet. Please clarify if the contractor. Same for Sheets 2H(5), 2H(8), 2H(14),
2H(16), 2H(20), 2H(24), 2M(2) and 2M(4).
lines in the detail sheet. Please clarify if
specific nomenclature revision is
requested.
202 2H(1) Materials Profile C-C: Add concrete cradle to 24" pipe.
culvert 14-3 to 6-5 is an inflow culvert
above the forebay and should not
require cradle. The layout and sizing is
intended to support/work with future
phase III loop.
A landscaping detail for the aquatic
benches will be added to the 2H (SWM
Detail) series which provide greater
203 2H(4) Roadside Mgmt.Exact planting locations, including spacing, need to be
shown on the plan view of the SWM pond.
Detail) series which provide greater
construction detail as requested. Note
that the plantings associated with
aquatic benches will be Zone 1 and 2
submergent and emergent container
plants or stems. typically these are
specified in a stem per square footage
basis without specific planting locations.
Page 15 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
204 2H(5) Roadside Mgmt. Same comment as Item No. 2
we propose to add a typical planting
detail to identify a reasonable cluster of
the plants within the aquatic bench.
205 2H(8) MaterialsThere appear to be contour lines missing in the area of
Ramp B.
Additional contour/spot elevations will be
added to clarify fill (represented in the
profile) in this area.
206 2H(8) Roadside Mgmt. Same comment as Item No. 2
we propose to add a typical planting
detail to identify a reasonable cluster of
the plants within the aquatic bench.the plants within the aquatic bench.
207 2H(8) Roadside Mgmt.Exact planting locations, including spacing, need to be
shown on the plan view of the SWM pond.
A landscaping detail for the aquatic
benches will be added to the 2H (SWM
Detail) series which provide greater
construction detail as requested. Note
that the plantings associated with
aquatic benches will be Zone 1 and 2
submergent and emergent container
plants or stems. typically these are
specified in a stem per square footage
basis without specific planting locations.
208 2H(12) Roadside Mgmt.
Under Note 3, it references plant locations & a planting
schedule. NO plants are to be planted in this SWM pond as
it is a Detention Basin. References to planting should be
removed to avoid confusion.
Agreed- note will be deleted.
209 2H(14) Materials Add concrete cradle to double 48" pipes.
The cradle appears to be unnecessary
because there is no drawdown
operation for this pond. However, a
cradle will be added if requested.
210 2H(15) Roadside Mgmt.
Under Note 3, it references plant locations & a planting
schedule. NO plants are indicated to be planted in this
SWM pond. References to planting should be removed to Agreed- note will be deleted.
SWM pond. References to planting should be removed to
avoid confusion.
211 2H(19) Roadside Mgmt. Same comment as Item No. 2
we propose to add a typical planting
detail to identify a reasonable cluster of
the plants within the aquatic bench.
Page 16 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
212 2H(19) Roadside Mgmt.Exact planting locations, including spacing, need to be
shown on the plan view of the SWM pond.
A landscaping detail for the aquatic
benches will be added to the 2H (SWM
Detail) series which provide greater
construction detail as requested. Note
that the plantings associated with
aquatic benches will be Zone 1 and 2
submergent and emergent container
plants or stems. typically these are
specified in a stem per square footage
basis without specific planting locations.
213 2H(23) Roadside Mgmt. Same comment as Item No. 2
we propose to add a typical planting
detail to identify a reasonable cluster of
the plants within the aquatic bench.
214 2H(23) Roadside Mgmt.Exact planting locations, including spacing, need to be
shown on the plan view of the SWM pond.
A landscaping detail for the aquatic
benches will be added to the 2H (SWM
Detail) series which provide greater
construction detail as requested. Note
that the plantings associated with
aquatic benches will be Zone 1 and 2
submergent and emergent container
plants or stems. typically these are
specified in a stem per square footage
basis without specific planting locations.
215 2J(1) L & D
Section IV, Note 8: Even though detention basin 18C-1 is
not a WQ BMP it should still be listed as a permanent SWM
facility.
The WQN only pond 18C-1 will be
added to note 8 as requested.
216 2J(2) L & D
Section VI: detention basin 18C-1 must be listed as a
permanent BMP (include treatment acres for detention). A
note can be added to indicate that this basin is for Water
Quantity treatment, not for Water Quality.
Notation will be added to Section VI as
requested.
SWPPP sheet lists six (6) permanent BMP's but the plans Pond 18C-1 will be added to the table
217 2J(2) Roadside Mgmt.
SWPPP sheet lists six (6) permanent BMP's but the plans
show seven (7) permanent BMP's. It appears 18C-1 is
missing.
Pond 18C-1 will be added to the table
with notation as "quantity only"
218 2K Environmental
Notes E-5 and E-9 have the stream names spelled
incorrectly. You have Opequon creek and Hodge Run. The
correct stream names are Opequon Creek and Hoge Run.
Please correct here and anywhere else that you have the
streams named incorrectly.
The stream name spelling will be
corrected.
219 2K L & DNote E-12.2; complete the reference to "Standard Drawings
sheet XXX" with actual page numbers.The page numbers will be added.
Page 17 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
220 2K(2) Environmental
No temporary stream diversion is shown for the stream that
flows from the pond located at the matchline to the inside of
the culvert near between SB Sta. 124-125. Temporary
stream diversion or pump around will be required to work in
the dry prior to the extension of the existing pipe.
Given the contributing area, temporary
diversion does not appear to be required
to extend the culvert upstream because
the extension follows the existing stream
alignment.
221 2K(2) Environmental
Ensure that the outlet ditch (or whatever that wide fuzzy line
is that goes from 5-2 to the stream edge) does not go below
OHW of the stream, because no impacts were shown at this
location in the permit application.
The rip rap outlet ditch is shown ending
at the existing channel. Notation can be
added for clarity.
The rip rap outlet ditch is shown ending 222 2K(2) Environmental
Ensure that the outlet ditch that goes from 6-9 to near the
stream at the outlet does not go below OHW of the stream.
The rip rap outlet ditch is shown ending
at the existing channel. Notation can be
added for clarity.
223 2K(3) Environmental
No temporary stream diversion is shown for the pipe
extension at stream near Sta. 162. Temporary stream
diversion or pump around will be required to work in the dry
prior to the extension of the existing pipe.
Given the contributing area and
proximity to existing inlet #128,
temporary diversion does not appear to
be required to extend the culvert
downstream because the extension
follows the existing stream alignment.
224 2K(6) Environmental
You show the temporary stream diversion for the culvert at
about St. 31+25 but none for the pipe at Sta. 33+25. The
pipe installation will also require a stream diversion in order
A temporary diversion within the
construction limits can be provided as
requested. The existing channel is pipe installation will also require a stream diversion in order
to work in the dry. connected to the box culvert SCC within
the construction area.
225 2K(7) Environmental
Temporary stream diversion is needed for the stream that
flows from near station 15 of the Hillandale Road stationing
to the upstream end of the 60 inch pipe east of the pond.
The diversion ditch shown does not connect to the little
stream at the upper end. Also the diversion ditch around the
pond does not connect with the little stream and it should be
designed so that it does connect with the stream at both the
upper and lower ends as the contractor will be required to
install a proper stream diversion prior to working in the
stream.
Clarification is requested for this
comment to adjust the SCC. Current
plan elevations for the SCC mimic the
ultimate ditch and adequately drain
existing contributing areas. The existing
pond and connection at the outlet of the
60" culvert will be clarified.
226 2K(8) EnvironmentalCrossing at Sta. 162 will also need some temporary
diversion during construction.
The plan does not propose upstream
extension of the culvert at this location
please clarify.
227 2K(9) Environmental
If the temporary SCC #1 is to function also as stream
diversion during construction, it should be polyethene lined
similar to the EC-12.
Polyethene lining will be specified in this
location as requested.
Page 18 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
228 2K(10) EnvironmentalTemporary stream diversion will be needed for the stream
just inside Ramp E near the matchline with 2K(9).
In this location the existing channel is
retained and protected by silt fence until
the final channel with rip rap is installed.
No diversion is needed.
229 2M ConstructionSTR. # 12-1: 12' x 6' Box Culvert. Detail sheets need to be
included for this structure.Will provide detail sheets for box culvert.
230 2M(2) MaterialsWill expected settlement (~40' fill) affect box culvert? Same
for Sheet 2M(4) - ~53' fill.
Geotechnical assessment will be
provided to verify support for the box
culvert fills.
231 2M(3) ConstructionSTR. # 28-6: Double 8' x 8' Box Culvert. Detail sheets need
to be included for this structure. Will provide detail sheets for box culvert.231 2M(3) Construction
to be included for this structure. Will provide detail sheets for box culvert.
232 2R Construction
Underdrain Summary: Total for UD-2 Underdrain, 908 L.F.
is shown under total of UD-3 Underdrain in table. The 908
LF needs to be moved one cell to the left.
The UD-2 quantity will be corrected.
233 2S Materials Add "See pipe backfill note, Sheet 2." Will add note.
234 3 MaterialsCross-hatch paved shoulder as new construction (FI +
RoW). Same for all sheets.
Will cross-hatch paved shoulder as new
construction on all applicable plan
sheets.
235 4 EnvironmentalThe stream is missing that comes out of that pond and goes
into 4-1 (the 48 inch corrugated steel pipe.
The survey file has been revised to
show the stream line per environmental
documents. Updated files will reflect the
stream.stream.
236 4 MaterialsShow sawcut at all joints between existing and proposed
pavements. Same for all sheets.
Will add sawcut label between existing
and proposed pavements on all
applicable plan sheets.
237 4 Operations
Show the sight distance triangle in each direction on Tasker
Rd. Consider Left Turn Lane into the Frederick County
Sanitation Authority entrance.
Evaluating addition of left turn lane into
Frederick County Sanitation Authority
entrance. Sight distance triangle can be
provided in a separate document.
238 5 Environmental
Nothing was included in the permit application for any
structures located in the stream at this location (ref.
drainage str. 5-1 which is some kind of a grate). Is this
really needed? We will have to add it to the permit . Prefer it
Due to fill and slope requirements
associated with widening, the existing
open connection requires a grate drop 238 5 Environmental
really needed? We will have to add it to the permit . Prefer it
be removed and that the typ. Ditch D simple end before
arriving at the stream OHW elevation.
open connection requires a grate drop
inlet as shown.
239 5 L&D Ensure grading at northern end of Pond 26 allows vehicular
passage to the old Tasker roadbed/utility access grading
The pond access turnaround will be
lengthened/graded as needed for
temporary access to the roadbed.
Page 19 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
240 5 Utilities
Provide a stabilized access around pond 26 and down the
embankment to the old Tasker roadbed/utility access drive
at mainline sta 130+90 right.
Request clarification for access area
location. A culvert entrance at the I-81
shoulder is provided at 130+90. Pond
access will be modified as requested.
241 6 Materials
Move northbound UD-4 to edge of proposed pavement.
Please note that this area is not shown in typical sections,
Sheets 2A or 2B(3). Can't see northbound UD-4 south of
Sta. 136+00.
UD-4 will be adjusted/ added as
requested
242 6 MaterialsShow identify northbound lanes sawcut south of existing
label for clarity.Will add additional sawcut label.
Is restoration of natural contours desirable at existing Ramp 243 7 L&D
Is restoration of natural contours desirable at existing Ramp
A/B termini (discuss w/ Materials)?To discuss.
244 9 MaterialsShow sawcut along joint between pavement demolition and
existing pavement/proposed overlay. Same for all sheets.
Will add sawcut label between
pavement demolition and existing
pavement/proposed overlay on all
applicable plan sheets.
245 20 MaterialsTypical section (Sheet 2B) shows Ud-2 under median.
Same for Sheet 21.
UD-2 is shown at the median in this
area. No UD is provided at station
44+00 to west because median ditch is
provided.
246 24 MaterialsAdd UD-2 under MS-2 median per typical section Sheet
2B(2).
UD-2 will be added to the median
transition area (to existing) and outlet at
24-2.
247 25 MaterialsChange CD-2 to UD-4 at Sta. 19+75 (CD-2 does not include
pipe).The label will be corrected.
248 25 MaterialsAdd UD-2 under MS-2 median. Please note that there is no
typical section for Sta. 18+00 to Sta. 22+00.UD-2 will added as requested.
249 25 MaterialsAdd CD-2 at Sta. 20+75 northbound and Sta. 20+25
southbound. (FI)CD-2 will be added as requested.
250 26 Materials Label CD-2 at Sta. 14+75. Label will be added.
251 29 Materials Delete CD-2 at Sta. 34+00. CD-2 will be deleted as requested.
252 29 OperationsConsider keeping Tasker NB a single lane all the way to
Hillandale Drive.
Tasker NB is kept as single through lane
per the pavement marking plan, lane
arrows will be corrected if needed. Lane
arrows show final long term 252 29 Operations
Hillandale Drive. arrows show final long term
configuration. Please see sheet 38(8)
for clarification.
253 30 OperationsConsider keeping Tasker SB a single lane from Hillandale
to Ramp G
Tasker SB is kept a single through lane
per the pavement marking plan, lane
arrows will be corrected if needed. Lane
arrows show final long term
configuration. Please see sheet 38(8)
for clarification.
Page 20 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
254 31 OperationsConsider additional R-O-W at NW quadrant of Hillandale
and Tasker intersection for sight distance requirements
To discuss. Developer may be able to
provide sight distance easement when
Tasker is extended. This may not be
needed until such time.
255 33B(1) MaterialsAdd expected foundation types (VDOT R&B Standard PB-
1) per final soil survey report. Same for Sheets 33B(2-4).
Please provide clarification.
Geotechnical recommendations are not
provided for all pipes. Per VDM 15-2
this has not been required.
STR. # 12-1: 12' x 6' Box Culvert. Note: Material Aggregate Revised drainage descriptions identify
256 33B(1) Construction
STR. # 12-1: 12' x 6' Box Culvert. Note: Material Aggregate
(along Section # 4). Where is Section # 4 of this Box Culvert
shown? Clarify.
Revised drainage descriptions identify
station range for clarification of section 4
(undercut) location.
257 33B(1) Construction
STR # 12-1 Single 12' x 6' Box Culvert: Bedding Material
Aggr. # 57 is shown to be installed at a depth of (18"
Bottom). A total of 78.3 C.Y. of 57 is shown for this
installation. These numbers need to be revised if the intent
is to place 18" depth of #57 stone under the total 669' of
Box Culvert.
The #57 is located only in the section 4
station range.
25833B(1) thru
33B(4)Construction
Various Pipes in the Drainage Details call for Undercut
Excavation. Included are pipes over 48" in diameter in
which any Undercut should be included in Minor Structure
The undercut excavation for pipes
greater than 48" has been included as
minor structure excavation. For the pipe
lower than 48", it continues to be Excavation.
lower than 48", it continues to be
labelled as undercut excavation.
25933B(1) thru
33B(4)Construction
Pipe cover depths shown in the Drainage Details are not
accurate when compared to amount of fill material over
pipes to achieve finished grade elevations.
Cover depths have been reviewed and
adjusted as needed.
26033B(1) thru
33B(4)Construction
Minor Structure Excavation quantities are not correct for the
Box Culvert installations and the pipes with a diameter
greater than 48".
Minor Structure Excavation quantities
have been updated as required per prior
correspondence.
261 33B(2) Environmental
Do the drainage structures associated with the 60 inch
storm sewer pipe add up to the 390 ft. long structure that
was submitted in the permit application?
Total length for the pipe in the permit will
be revised to 396 to account for
structure deductions in the drainage
descriptions.descriptions.
262 33B(3) Environmental
The 60 pipe drainage structure 28-8 states 264 ft. long
pipe. When the permit application was submitted, the
sketches provided by Volkert stated the pipe would be 266
ft. long. This was updated from 264 ft. to 266 ft. at the last
minute. So either the drainage note in the plan is wrong, or
the structure description in the permit sketch is wrong.
The drainage descriptions will be
updated to reflect 266'.
Page 21 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
263 36(1) OperationsUnder General Notes; Note 4 - revise the last line to state
"…and approved by the NWRO Construction Engineer."Will revise note
264 36(1) Operations
Under Definition of Types - Signs "WB-1" and "WB-2" are
not standard VDOT Signs. These should be changed to
SSP-VA and SSP-VIA. Please verify that all sign types are
in accordance with the VDOT Road and Bridge standards
and revise plan sheets accordingly.
Will revise WB-1 and WB-2 notes
265 36(1) Operations
Under General Notes - Add a Note stating "Except for the
Exit Gore Signs, all Type VA and VIA signs shall be
installed behind the ditchline on all I-81 mainline and ramp Will add note265 36(1) Operations
installed behind the ditchline on all I-81 mainline and ramp
locations".
Will add note
266 36(1) Operations
Under General Notes - Add a note stating "All work
involving Travel Services Signing (Logo Signs) shall be
coordinated through Mr. Rick Burgess at 804-225-4903."
Will add note
267 36(1) Operations Graphical scale incorrect on entire sheet 36 series Will revise graphical scale
268 36(2) L&D Establish 35mphNB/45mphSB speed limit on Tasker
around STA 10+00 (subject to NWRO)
Did someone do a speed study or
evaluation? Or are we just to use the
design speed?
269 36(2) Operations
Sign plans do not include layouts of special design signs
such as the "Exit 1 Mile", Point of Turn and directional guide
Signs. These should be included in the plans on Sheets Will add detail sheets for guide signs.
Signs. These should be included in the plans on Sheets
36(2) through 32(16).
270 36(2) Operations
Sign plans do not include the relocation existing or
installation of new mile post signs along I-81. Please
include in the plans on Sheets 36(2) through 32(16).
Will add mile post signs.
271 36(3) Operations
Check horizontal alignment and queue lengths for the
advisory speed sign on the off-ramp. 25 MPH may be too
slow because the plans show a 50 MPH design for the first
curve on the exit ramp.
Will evaluate design speeds and
determine appropriate advisory speed
limits.
272 36(3) OperationsSign 3.06/158 - Logo Sign panel design does not conform
to Figure 2J-1 and 2J-2 in the MUTCD. Please correct.
Per discussion with Jason Newcomb
with VDOT LOGO sign program, the
existing sign is to be reused. Will revise
the plans to remove the proposed sign
and relocate existing.and relocate existing.
273 36(3) OperationsNeed to include a One Way sign (R6-1R) on the
southbound I-81 median at station 130+00 +/-.Will Add sign.
274 36(3) OperationsNeed to include a One Way sign (R6-1L) on the right side of
the southbound on-ramp at station 23+50 +/-.Will add sign
275 36(4) OperationsSign definition symbols include "SRP-1" but this label is not
in the sign type definitions. Please revise.Will revised sign type label
Page 22 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
276 36(5) Operations
Check horizontal alignment and queue lengths for the
advisory speed sign on the off-ramp. 25 MPH may be too
slow because the plans show a 50 MPH design for the first
curve on the exit ramp.
Will evaluate design speeds on ramps
and determine appropriate advisory
speed limits.
277 36(5) OperationsSign 5.06/162 - Logo Sign panel design does not conform
to Figure 2J-1 and 2J-2 in the MUTCD. Please correct.
Per discussion with Jason Newcomb
with VDOT LOGO sign program, the
existing sign is to be reused. Will revise
the plans to remove the proposed sign
and relocate existing.
278 36(5) OperationsNeed to include a One Way sign (R6-1L) on the right side of
the on-ramp at station 22+50+/-.Will add sign278 36(5) Operations
the on-ramp at station 22+50+/-.Will add sign
279 36(5) OperationsNeed to include a One Way sign (R6-1R) on the northbound
I-81 median at station 155+00 +/-.Will add sign
280 36(8) Operations
At the T-intersection with Ramp G and Tasker Road,
remove the chevron alignment signs and replace with a two-
direction large arrow sign (W1-7, 60x30). Put the route sign
assembly above the two-direction large arrow sign. (Refer to
2009 MUTCD section 2C.09, paragraph 7.)
Will revise.
281 36(8) Operations Remove the STOP signs (if a traffic signal is installed).Has a signal warrant study been
completed by VDOT?
282 36(8) Operations
Install a turn sign (W1-1, 36x36) and a 10 MPH advisory
speed plaque (W13-1P, 24x24) facing traffic on northbound Will add sign282 36(8) Operations speed plaque (W13-1P, 24x24) facing traffic on northbound
Tasker Road at station 43+00.00
Will add sign
283 36(8) OperationsInstall symbolic RIGHT LANE ENDS sign (W4-2) on
northbound Tasker Road at approx. station 44+00.00Will add sign
284 36(8) OperationsAdd SIGNAL AHEAD symbol sign (W3-3) on both sides of
the one-way Ramp H in advance of the I-81 intersection
Will evaluate sight distances and add
signal ahead sign if applicable.
285 36(8) Operations
Add SIGNAL AHEAD symbol sign (W3-3) or STOP AHEAD
symbol sign (W3-1) on both sides of one-way Ramp G
(Route 37 approaching Tasker Road) as appropriate
Will evaluate sight distances and add
signal ahead sign if applicable.
Revise interchange approach guide signs on westbound Guide signage will be added as a part of
286 36(8) Operations
Revise interchange approach guide signs on westbound
Route 37 to meet the requirements of MUTCD figure 2D-13.
Signs currently shown on the sign plan may be inadequate.
Guide signage will be added as a part of
the Route 37 Extension UPC No:85972,
VDOT Project Number 0037-034-707,
P101
287 36(8) Operations
Add turn lane use signs on the Ramp G toward Tasker
Road to indicate that the left lane turns left and the right
lane turns right,
Will add sign
Page 23 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
288 36(8) OperationsPlans include Cardinal Direction on the secondary route
shields. Recommend they be removed as th
Comment appears to be clipped.
Unclear what reviewer intends. Cardinal
direction panels were added based on
guidance from VA MUTCD Figure 2D-
6(VA) and Section 2D.29(10). The
direction panels give guidance we feel is
necessary.
289 36(9) Operations
Remove the STOP signs. (There is no need to stop at that
location. Right now, it is not an intersection and there are no
conflicting movements.)
Will remove signs 9.05 and 9.02
290 36(9) OperationsAt station 17+00.00, install a turn sign (W1-1, 36x35) with a
10 MPH advisory speed plaque (W13-1), 24x24)Will add sign
291 36(9) Operations
Remove the ONE WAY sign. Replace it with a one-direction
large arrow sign (W1-6R, 60x30) and put the South 624 -->
sign assembly above it.
Will remove and replace sign panels
292 36(9) Operations
Install a one-direction large arrow sign (W1-6L, 60x30) in
front of the Type 3 barricade facing northbound Tasker
Road
The R/W is directly behind the sidewalk
on the west side of Tasker Road where
the one-way sign would need to be
installed. The sign is 60" wide, so
additional R/W will be required for the
sign placement.
293 36(9) OperationsInstall a DEAD END sign (W14-1, 36x36) facing northbound
Route 847 relocated at approx. Sta. 12+00 Rt.Will add sign
294 36(9) Operations
Guide signs, if possible, should be placed before the off-
ramp splits from the single lane into the three lanes for the
turning movements.
Will add guide signs where feasible.
295 36(9) Operations
Hillandale Road is proposed to have a speed limit of 35
MPH. However, the plan set indicates a 30 MPH design
speed. Hillandale Rd is currently unposted. A speed study
will need to be completed.
To be discussed.
296 36(9) OperationsDelete Signs 9.07/144 and 9.08/141 as this is the
intersection of two secondary roads.
Route sign assemblies were added
based on guidance from VA MUTCD
Section 2D.29(10). Will remove signs intersection of two secondary roads. Section 2D.29(10). Will remove signs
9.07 and 9.08
297 36(9) OperationsSigns 9.07/176 and 9.03/178 should be replaced with M1-
V3aB with single arrows.
Will remove sign 9.07. Will revise 9.04
sign (believe the reviewer intended this
sign instead of 9.03) to a M1-3Va series
sign.
298 36(9) Operations
Plans indicate signs 9.05/116 and 9.06/116 are to be quite
large in size. Are both signs necessary? Rte. 847 carries
approximately 500 vehicles per day (2012).
Will remove signs
Page 24 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
299 36(9) OperationsSign 9.02/109 - Do we want/need a Stop sign at this
location?Will remove signs
300 36(10) Operations
Remove all LEFT LANE MUST TURN LEFT and RIGHT
LANE MUST TURN RIGHT signs. Replace them with the
signs that show the full lane configuration on the exit ramp.
There should be at least one sign showing the full lane
configuration on each side of the road.
Will replace signs
301 36(10) Operations
Place all WRONG WAY signs on the back side of other
signs on the exit ramps. Do not mount WRONG WAY signs
on their own posts if this can be avoided.
Will place sign panels on as few post as
possible
302 36(10) OperationsAdd SIGNAL AHEAD symbol sign (W3-3) on both sides of
the exit ramp
Will evaluate sight distances and add
signal ahead sign if applicable.
303 36(10) Operations
Guide signs, if possible, should be placed before the off-
ramp splits from the single lane into the four lanes for the
turning movements.
Will add guide signs where feasible.
304 36(10) OperationsSigns for the existing Through Truck Restriction need to be
included.Will add truck restriction signs.
305 36(10) OperationsSign 10.19/159 - Logo Sign panel design does not conform
to Figure 2J-1 and 2J-2 in the MUTCD. Please correct.
Per discussion with Jason Newcomb
with VDOT LOGO sign program, the
existing sign is to be reused. Will revise
the plans to remove the proposed sign
and relocate existing.and relocate existing.
306 36(10) Operations
There is an existing sign and route shield assembly [North
37/To 11/To West 50/To North 522] on sheet 36(4) at the
northbound ramp intersection with Route 37 that is not on
the new plan sheet. This needs to be included.
Sign panel assembly will be added
307 36(10) OperationsOne Way signs for the intersection of Route 37 and the
northbound ramps have not been included. Please revise.
Will add one-way sign planes to 10.14
and 10.15
308 36(11) Operations
Remove all LEFT LANE MUST TURN LEFT and RIGHT
LANE MUST TURN RIGHT signs. Replace them with the
signs that show the full lane configuration on the exit ramp.
There should be at least one sign showing the full lane
Will replace signs
There should be at least one sign showing the full lane
configuration on each side of the road.
309 36(11) Operations
The Virginia Logos signs for Lodging and Food on
northbound/westbound Route 37, approaching the Route 11
exit, should have angled arrows pointing to the right.
Per discussion with Jason Newcomb at
VA LOGOs we will remove proposed
sign and will reuse existing sign
310 36(11) Operations
Place all WRONG WAY signs on the back side of other
signs on the exit ramps. Do not mount WRONG WAY signs
on their own posts if this can be avoided.
Will place sign panels on as few post as
possible
Page 25 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
311 36(11) OperationsAdd SIGNAL AHEAD symbol sign (W3-3) on both sides of
the exit ramp
Will evaluate sight distances and add
signal ahead sign if applicable.
312 36(11) OperationsSigns for the existing Through Truck Restriction need to be
included.Will add signs
313 36(11) Operations
Signs 11.23/167 & 11.24/168 - Logo Sign panel design
does not conform to Figure 2J-1 and 2J-2 in the MUTCD.
Please correct.
Per discussion with Jason Newcomb at
VA LOGOs we will remove proposed
sign and will reuse existing sign
314 36(11) Operations
Sign 11.08/133 - Route shields in the assembly are
reversed. Rte. 37 should be on the left side and Rte. 742
should be on the right side of the assembly.
Will update sign 11.08
should be on the right side of the assembly.
315 36(11) OperationsNeed to include One Way signs on the post of sign
11.01/104.Sign panels will be added
316 36(11) OperationsShould we also include signs directing motorists to Rte. 11
from the southbound off ramp?Will add sign panels to sign 11.11
317 36(12) Operations
Remove all LEFT LANE MUST TURN LEFT and RIGHT
LANE MUST TURN RIGHT signs. Replace them with the
signs that show the full lane configuration on the exit ramp.
There should be at least one sign showing the full lane
configuration on each side of the road.
Will replace signs
318 36(12) Operations
Place all WRONG WAY signs on the back side of other
signs on the exit ramps. Do not mount WRONG WAY signs Will place sign panels on as few post as
possibleon their own posts if this can be avoided.
possible
319 36(12) Operations
Add two SIGNAL AHEAD symbol signs (W3-3) on both
sides of eastbound Route 37 in advance of the I-81
interchange (if there are none already and if the existing
signs, if any, are removed).
Will evaluate sight distances and add
signal ahead sign if applicable.
320 36(12) OperationsRoute 11 is a US route, not a state primary. Revise the
route shields accordingly.Will update panels on 12.04 and12.05
321 36(12) Operations
Signs 12.19/170 & 12.20/171 - Logo Sign panel design
does not conform to Figure 2J-1 and 2J-2 in the MUTCD.
Please correct.
Per discussion with Jason Newcomb at
VA LOGOs we will remove proposed
sign and will reuse existing sign
Revise interchange approach guide signs on westbound
Route 37 to meet the requirements of MUTCD figure 2D-13 Will evaluate existing Exit 310 1 mile
322 36(13) Operations
Route 37 to meet the requirements of MUTCD figure 2D-13
(if the existing overhead signage is not to remain in place).
This is not clear from the plan set whether the existing
signage will remain in place or not.
Will evaluate existing Exit 310 1 mile
advance sign to determine if guide sign
needs to be updated.
Page 26 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
323 36(16) Operations
Sign Schedule Plan Sheets [Sheets 36(16) - 36(19)] call for
Route Shield panels to be oversized (36 inches in height).
Please reduce to the standard size of 24 inches in height.
Should also review other signs on the plans to verify they
are not calling for a larger size than what is needed.
Will reduce all route shields and
accessory signs to regular height in
entire plan set
324 36(16) Operations
Sign Schedule Plan Sheets [Sheets 36(16) - 36(19)] - Sign
Structure number should reference the standard sign
structure type in the VDOT Road and Bridge Standards.
Will add standard sign structure type
Do not include Cardinal direction panels on Secondary Cardinal direction panels were added
325 36(16) OperationsDo not include Cardinal direction panels on Secondary
Route Shields. [Sheets 36(16) - 36(19)]
Cardinal direction panels were added
based on guidance from VA MUTCD
Figure 2D-6(VA) and Section 2D.29(10).
326 36(16) OperationsCoordinate with the Sign Shop on the route sign
assemblies.
This should be discussed with VDOT. It
is not clear as to the need for
coordination with the sign shop with
regards to the route sign assemblies.
327 36(16) OperationsSign 12.16/103 - Message does not match sign shown on
sheet 36(12).Will update sign panel
328 36(17) OperationsSigns 3.04/149, 5.03/149 are shown to be 36"x36". Since
these are on the mainline of I-81 please revise to 48"x48".Will update sign panel
329 36(17) OperationsSigns 10.21/146, 11.26/146, 10.20/147 & 11.25/147 should
be 48"x48".Will update sign panel
330 37(1) Operations
The RT 37 EB Extended at Relocated Tasker Road
intersection should be signalized. The construction plans
currently have it un-signalized with the EB approach stop
controlled. Need to add series of sheets for signal at 37 and
Tasker Road
Has a signal warrant study been
completed by VDOT?
331 37(1) Operations
The Traffic Signal General Notes 26-28 refer to serial
radios. These should be Ethernet radios. We are sending
an Ethernet radio spec to Mike True for inclusion.
Will revise to ethernet.
Note 2 - Define requirements for a “qualified
representative”. This should preferably be a signal timing
332 37(1) Operations
representative”. This should preferably be a signal timing
engineer with experience in inputting timings into the
controller, watching and monitoring traffic conditions in the
field, and being able to make adjustments in the field as
necessary to accommodate smooth traffic flow.
Note changed to "qualified traffic
engineer."
Page 27 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
333 37(1) Operations
Contractor shall be responsible for changing vehicle
clearance intervals, phasings, and signal timing plans for
any phase of construction that impacts a signalized
intersection. All changes shall be approved by the NWRO
Regional Signal Operations Engineer prior to switching
construction phases. Contractor shall submit the timing
plans for the various construction phases to the NWRO
Regional Signal Operations Engineer one month in advance
of the construction phase beginning to provide time for
adequate review and comment. Clearance interval timings
shall be signed and stamped by a Virginia licensed
Will add note
shall be signed and stamped by a Virginia licensed
professional engineer. This language needs to be
incorporated into the contract documents and construction
plans
334 37(1) Operations
There needs to be a response time requirement for any
maintenance or repairs to the signals and changes to the
signal timings. In addition, there should be some recourse
for VDOT if the response time is not met. This language
also needs to be incorporated into the contract documents
and construction plans
Will add general notes.
335 37(1) Operations Note 1 - add "and NWRO Regional Signal Specifications". Will change note
336 37(1) OperationsNote 3 - revise to state the VDOT NWRO Construction
Engineer will review the pole locations.Will change note
337 37(1) OperationsNote 9 - What is the intent of this note? Recommend
deleting.Will clarify note
338 37(1) Operations Note 12 - Revise to specify solid aluminum backplates. Will change note
339 37(1) Operations Note 17 - Is this note needed? Recommend it be deleted. Will clarify note
340 37(1) OperationsNote 20 - revise last line to read "…installed in accordance
with VDOT Road and Bridge Standards unless…"Will change note
341 37(1) OperationsNote 21 - Recommend the electrical service have three (3)
twenty (20) Amp breakers.Will change note
twenty (20) Amp breakers.
342 37(1) OperationsNote 25 - Revise to state "Cabinet shall be as specified in
the NWRO Regional Signal Specifications."Will change note
343 37(1) OperationsNote 27 - Revise to state "Radio Network Address to be set
as directed by the NWRO Signal Timings Engineer."Will change note
344 37(1) OperationsNote 28 - Revise to state "Controller System Address to be
set as directed by the NWRO Signal Timings Engineer."Will change note
Page 28 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
345 37(2) Operations Item 51030 - Missing quantity for Int. Rte. 37/NB Ramps.Quantity is correct. Intersection has
master controller.
346 37(2) Operations
Items 51337 & 51347 - Are theses needed since non-
standard mast arm poles are being specified? This would
agree with the NWRO Signal Specifications. Recommend
51337 & 51347 be deleted.
Will revise quantities
347 37(3) OperationsSigns S-1 and S-2 (no left turn, no right turn) should be
36x36Will change sign panel size
348 37(3) Operations
Need to include 4 - 2" Conduits for electrical service,
communications, and traffic camera. This will need to be
coordinated through with the right of Way and Utilities Will revise quantities348 37(3) Operations
coordinated through with the right of Way and Utilities
section.
Will revise quantities
349 37(3) Operations
Need to include 1-3" Conduit and 2-2" Conduits from the
signal cabinet to the existing traffic camera on the northeast
corner of the I-81 overpass.
Will add conduit
350 37(4) Operations
Is it intended to allow right-turns on red at this intersection?
If so, then Signal head 4B (with the right arrows) should
NOT use a right-turn red arrow indication.
Will revise signal heads for right turns.
351 37(4) OperationsSigns S-1 and S-2 (no left turn, no right turn) should be
36x36Will change sign panel size
Protected/permissive left turn signal with CIRCULAR
GREEN should NOT be placed directly above the left turn Signal head alignment was changed to
lane center, based on previous review
352 37(5) Operations
GREEN should NOT be placed directly above the left turn
lane. It should be placed above the lane line between the
left-turn lane and the through lane. If the
protected/permissive left turn signal is to be mounted over
the left turn lane or in the median, then the flashing yellow
arrow should be used in accordance with MUTCD section
4D.13, paragraph 9.
lane center, based on previous review
comment dated 01/27/2014 from Mike
True: "Signal heads on the plans do not
appear to be centered over the lanes
they govern." Will relocate 5-section
heads to lane line extended.
353 37(5) Operations
Is it intended to allow right-turns on red at this intersection?
If so, then Signal head 4 (with the right arrows) should NOT
use a right-turn red arrow indication. If not, then the red
arrow is OK, but the 10-second delay detection should be
removed.
Will revise signal heads for right turns.
354 37(5) OperationsSignal head 5 should be centered on the lane line between
the left turn lane and the left-most thru lane of Rte. 11.
Signal head alignment was changed to
lane center, based on previous review
comment dated 01/27/2014 from Mike
True: "Signal heads on the plans do not
appear to be centered over the lanes
they govern." Will relocate 5-section
heads to lane line extended.
Page 29 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
355 37(5) OperationsSignal head 4 can be revised to provide a red ball indication
to permit right turns on red from the Rte. 37 off ramp.Will revise signal head
356 37(6) Operations
Recommend reducing the overall size of this sign; 11 feet
by 2 feet is rather large. Recommend redesigning in
accordance with TE-311 to provide 8" and 6" lettering and a
more appropriate size sign panel.
Will redesign sign
357 38(1) Operations
There is no mention anywhere in the pavement marking
plans about the retroreflective snowplowable raised
pavement markings (reflectors). Ensure that the retroflective Added notes about plowable raised 357 38(1) Operations
pavement markings (reflectors). Ensure that the retroflective
snowplowable raised pavement markings are installed
according to the requirements of the Virginia MUTCD
Supplement, section 3B.11
Added notes about plowable raised
pavement markings
358 38(1) Operations Graphical scale incorrect on entire sheet 38 series Will revise graphical scale
359 38(7) OperationsAdd a turn lane into the driveway and revise the "median"
pavement markings accordingly.
Need to coordinate with roadway design
-- current road width is 24' for 2-lane
road.
360 38(8) Operations
Use a wide dotted pavement marking instead of the normal
lane line marking on Ramp G. This is needed to better
differentiate the left turn lane from the right turn lane.
Will revise pavement markings
361 38(9) Operations The "median" on Hillandale Road should be striped out. Will revise pavement markings361 38(9) Operations The "median" on Hillandale Road should be striped out. Will revise pavement markings
362 38(9) Operations
The "intersection" of Tasker and Hillandale Road has only
two of three legs only. For now, it is a temporary sharp turn
and the double yellow centerline striping should be carried
through the intersection.
Will revise intersection markings
363 38(9) OperationsRemove the stop bars at the "intersection" (temporary sharp
turn) at Tasker and HillandaleWill revise intersection markings
364 38(9) Operations
Are two handicap ramps necessary for NW quadrant of
Tasker/Hillandale intersection? Confirm layout meets ADA
requirements.
Need to coordinate with roadway
design.
365 38(12) Operations
Route 11 SB striping should provide dedicated right turn
lane onto Route 37 WB ramp and carry one through lane
past the ramp before becoming two through lanes
Will revise right/through arrow to right
turn only arrow and revise lane
configuration in signal plan, Sheet 37(5).past the ramp before becoming two through lanes configuration in signal plan, Sheet 37(5).
366 39-4 Construction
The Utility drawings denotes Drainage STR. # 26-10. This
structure # needs to be changed to STR. 4-5 to match the
construction plan sheet #4.
Will revise structure number.
Page 30 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
367 40(1) Roadside Mgmt.
The Plant Schedule on sheet 40(2) should be moved to this
sheet, along with deleting the "Fertilizer and Mulch" insert
and the planting details on sheet 40(2) (both of which are
covered in the Road & Bridge Standards). Reference
attachment sent from Scott Alexander to Tim Glickman on
9/23/2013.
Will revise. Will transfer information to
remain into one sheet. Will remove
items as described.
368 40(1) Roadside Mgmt.
Under General Notes, a note after #1 should be added
indicating which version of the Road & Bridge Standards
shall be followed.
Will revise.
369 40(1) Roadside Mgmt.
Under General Notes #3, the planting season is incorrectly
shown as March 15 through October 15. It should read
October 15 through March 15.
Will revise.
October 15 through March 15.
370 Contract Materials
Ensure that the following are included in the proposal:
SPCN for Pipe Backfill, SPCN for Embankments, SP for
Controlled Vibration, SP for Aggregate Density
Requirements, SP for Contractor Quality Control of
Aggregates and Select Material, SP for Low Permeability
Liners and SP for Select Material. These have been
provided via Mr. Alexander's folder.
Should be discussed with VDOT.
371 General L&D MOT challenges may dictate PR budget within CEI.To discuss, can add to CEI budget per
VDOT direction.
372 General LandscapeAn establishment period for the L construction needs to be
determined. Regular or 2 year?
Currently, plans call for an additional 2
year establishment period.determined. Regular or 2 year? year establishment period.
373 General LandscapeLandscape Architect of record for construction needs to be
determined; ideally designer.
Currently VDOT Landscape architect.
Current contract is only for design.
374 General Landscape
Inspections for soils, installation, and plant materials need
to be emphasized in the L summary so they will be included
in TRNSPRT and bids.
Will revise.
375 General Landscape
Maintenance for the planting establishment (waterings,
mulch, trash, and vegetative controls, etc.) need to be
refined on the summary so that the Regional L.A. can
provide the proper Special Provisions document to the
designer for editing.
Special Provision for additional plant
establishment was provided. See
SECTION 605 PLANTING (2 Year
Establishment Period).
To discuss. Old record drawings were
376 General MaterialsPlease follow-up regarding I-81 shoulder depth issue. Were
GPR or additional borings performed? (RoW)
To discuss. Old record drawings were
provided and showed inadequate
shoulder pavement depth. No additional
borings were performed.
377 General Materials Provide final soil survey report in digital format.Will provide pdf of final soil survey
report.
Page 31 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
378 General Operations
Coordinate the work so that construction does not occur
concurrently with the project at I-81 Exit 317 (UPC 94847),
nor with the project on Route 277 (UPC 18003).
A note shall be added to the plans
instructing the Contractor to coordinate
construction activities with the I-81 Exit
317 and Rt 277 projects.
379 General OperationsCheck the spelling of Hillandale Road and be consistent
with the spelling on all plan sheets.
Will check spelling. Note: Hillandale
Lane is correct name of road.
380 General OperationsConsider wide load permits for Rt 37. Rt 37 lane width is
reduced to 11' in multiple phases.Should be discussed with VDOT.
381 General Operations
Show temporary pavement markings and all traffic control
devices (including traffic signals) on the temporary traffic Will comply.381 General Operations devices (including traffic signals) on the temporary traffic
control plans
Will comply.
382 General Operations
There are no Phase 1D Synchro Analysis Worksheets in
Appendix A (or maybe it is mislabeled as Phase 1C, and
Phase 1C is mislabeled as Phase 1B).
Will provide.
383 General Operations
Phases 2 and 3 reduce the RT 37 EB and WB movements
across I-81 to one lane each. All approaches will be
significantly over capacity in the AM and PM peak periods
(and probably throughout the day as well). All stakeholders
need to be aware that these reductions will create massive
delays. Reducing the EB LT movement onto I-81 NB to a This suggestion will be considered and
discussed with VDOT.single thru-left lane in particular will cause delays. One
suggestion is to route RT 37 EB -> I-81 NB left turn vehicles
thru the I-81 NB Ramp signal in the EB direction, U-turn at
Relocated Tasker Road and turn right onto I-81 NB. This
will require additional detour plans to be in place.
discussed with VDOT.
Page 32 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
384 General Operations
During Phases 2-5, there is at least one I-81 Off-Ramp with
a LOS F in the AM or PM peak. A LOS F indicated the
movement is over capacity and in effect, will have an
infinitely increasing queue. If that is the case, it will be near
impossible to prevent queues from reaching the interstate.
The TMP does not provide any mitigation measures to
prevent that. This needs to be changed. The TMP and the
TTC Plans must incorporate very specific requirements on
what to do if queues start get close to the interstate on
either of the ramps. This is a major safety concern.
Preventing traffic from queuing back onto the interstate is
Should be discussed with VDOT.
Preventing traffic from queuing back onto the interstate is
important for NWRO to address and alleviate under normal
traffic operational conditions. We expect the contractor to
do the same during construction. The contractor shall be
responsible to not allow this to happen and shall provide
plans to prevent this from happening. These requirements
need to be incorporated into the contract documents and
construction plans.
385 General Operations
The TMP did not analyze vehicle queuing during any
construction phase. This needs to be done to identify and
mitigate the effects of queue spillback, inadequate turn lane
storage, and most importantly queuing on the I-81 off ramps storage, and most importantly queuing on the I-81 off ramps
reaching the interstate.
386 General Operations
The Contractor needs to submit copies of all the Synchro
files used in the TMP. This is necessary for review and will
be a valuable tool for VDOT during construction.
Will provide.
387 General Operations
Tasker Road design speed is shown as 40 MPH with a
posted speed limit of 35. Existing speed limit is posted as
45 MPH. A speed study will need to be completed to justify
this reduction.
Should be discussed with VDOT.
388 General LandscapeThe design Landscape Architect needs to be included in
invitations to the PAC.
Design team will coordinate with design
Landscape Architect before PAC
meeting to discuss outstanding issues.
Separate meeting/ conference call can invitations to the PAC.
Separate meeting/ conference call can
be set up if needed.
389
Special
Provision
For Section
605 Planting
Construction
Recommend a 1 year establishment period to avoid
unnecessary administrative cost and burden to the
Department in replacement of the 2 year establishment
period as shown in the Special Provision.
To discuss. See Item 371. Currently,
plans call for an additional 2 year
establishment period.
Page 33 of 34
Item Sheet No. Section Combined Comments Responses Meeting Resolutions
390 X149-156 MaterialsPer final soil survey report, this 4:1 slope could be steeper
(and reduce right-of-way costs).
4:1 slope is used under Future Route 37
extension from sta. 39+00 to 42+50 and
is already within proposed right of way.
2:1 slope could be used from sta. 42+50
(X154) to 45+00 (X156) to reduce
proposed temporary construction
easement for slopes. Note: The right of
way is proffered land from the
developer.
391 X47-49 MaterialsDon't show new pavement on bridge. Same for Sheets X56-
57.Will remove new pavement on bridge.391 X47-49 Materials
57.Will remove new pavement on bridge.
392 X56 Materials Label slopes. Will label slopes.
393 X70-75 Materials Comment missing.
394 X84 Materials2:1 slope is taller than 10' (see final soil survey report).
Same for Sheet X86.Will correct to 2.5:1 slope.
395 X90-95 MaterialsIs this undercut necessary? Explain need/method of
undercut. Same throughout cross-section sheets.
To discuss. Undercut called for in final
soil survey report, p. 25, based on
expected consolidation settlement.
Page 34 of 34