37
LD-450 5/12/09 DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET Pre-Advertisement Conference Design Changes 4/14/2014 Authored By: Chaz Weaver, PE, MEM Responsible for Pages: All Project Description RTE 81 - INTERCHANGE MODIFICATION, EXIT 310 From: 0.546 miles S of Rt.37 To: 0.513 miles N of Rt. 37 Project UPC No.: 75881 VDOT Materials Division Staunton District Geotechnical Engineering

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

LD-450 5/12/09

DEPARTMENT OF TRANSPORTATION

DIVISION: MATERIALS

REPORT COVER SHEET

Pre-Advertisement Conference Design Changes 4/14/2014

Authored By: Chaz Weaver, PE, MEM

Responsible for Pages: All

Project Description RTE 81 - INTERCHANGE MODIFICATION, EXIT 310

From: 0.546 miles S of Rt.37 To: 0.513 miles N of Rt. 37 Project UPC No.: 75881

VDOT Materials Division Staunton District

Geotechnical Engineering

chaz.weaver
Seal
Page 2: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

DEPARTMENT OF TRANSPORTATION 811 Commerce Road

Staunton, VA 24401-9029 www.VirginiaDOT.org

WE KEEP VIRGINIA MOVING

Charles A. Kilpatrick, P.E. Commissioner

April 14, 2014 MEMORANDUM TO: Scott Alexander, PE

Project Manager FROM: Chaz Weaver, PE, MEM District Materials Engineer SUBJECT: Design Changes at PAC Review The intent of this memorandum is to document the design changes required by Staunton Materials Section, in contrast to those proposed by GeoConcepts in their Final Soil Survey Report of July 26, 2013. Several plan sheets provided for the Pre-Advertisement Conference (PAC) included proposed pavement structures and asphalt pavement mixes not in concurrence with the current Materials Division Manual of Instructions. The report noted above is the third version of such, and it was determined not in the best interests of the Department nor the project schedule to continue redacting this report for the many and various errors and omissions contained therein. Staunton Materials Section’s plan review comments for the PAC meeting included, but were not limited to (see attached combined review comments):

1. Changing the temporary pavement design to eliminate expensive surface asphalt mix. The comment requested SM-12.5A be changed to less expensive IM-19.0A. (Comment #9)

2. Using current version of Note G-6 (provided). GeoConcepts will review their pavement design and slope stability analyses to determine the minimum required CBR value. They will also determine and list areas where unsuitable material is expected. Project soils are acceptable as stormwater management basin embankment material, which should be noted. (Comment #160)

3. Adding binder type to SMA asphalt mixes. The consultant omitted “(70-22)” after “SMA-12.5” and “SMA-19.0” – which would have led to issues during bidding and construction. (Comment #168)

Page 3: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

4. Change Inset E to Superpave asphalt mixes in lieu of SMA. Crossovers do not require these expensive mix types. (Comment #170)

5. Changing full-depth reconstruction of sections of US 11 and US 37 to full-depth widening and mill/replace or overlay. Northwest Regional Operations requested this change to eliminate critical maintenance of traffic issues, to which Staunton Materials Section agrees. (Comment #173)

6. Changing Ramp E to Ramps F and G pavement designs for consistency. This pavement structure (Inset C) is sufficient for Ramp E also, and this change will simplify both the plan sheet and construction operations. (Comment #178)

7. Deleting extraneous materials in entrance details. Aggregate No. 21A and SM-9.5D aren’t used anywhere else on the project. A “D” mix is not suitable for entrances. (Comment #179)

8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due to highly plastic subgrade soils and relatively thin pavement structures, geotextile was required to limit contamination of the aggregate subbase. (Comment #180)

9. Adding geotextile under asphalt path. Discussed during the meeting, geotextile directly below asphalt will reduce edge cracking. (Comment #181)

10. Adding leveling course and using SM-9.5AL. Staunton Materials Section agrees with Construction’s request for additional asphalt quantities to allow a leveling course where needed to provide smooth transitions – this will improve the overall rideability and aesthetics of the project. An “L” (limestone) mix may be used to reduce costs, as this layer will not be subjected to long-term traffic. (Comment #189)

11. Reviewing stormwater management basin slope design(s). Staunton Hydraulics will determine whether impounding water with a roadway embankment is allowable. GeoConcepts will further analyze the Ramp D embankment as a critical slope, per Materials Division Manual of Instructions (not provided in Final Soil Survey Report). (Comment #200)

12. Adding concrete cradle to double 48” pipes on Sheet 2H(14). Despite the consultant’s objections, this basin will be subjected to several drawdown events, and should be designed accordingly. (Comment #209)

13. Reviewing expected settlement under box culverts on Sheets 2M(2) and 2M(4). GeoConcepts did not provide any calculations, discussion or recommendations regarding structures under these relatively large fills. (Comment #230)

14. Correcting undercut locations and/or depths shown in cross-section sheets. Consultant will correct undercut shown to reflect GeoConcepts’ intent in the Final Soil Survey Report. Subgrade undercut is not necessary (or desired) as select material will be used.

The remainder of Staunton Materials Section’s comments were semantic, cosmetic or minor in nature and should not require sign and seal; however, all comments are attached. If you have any questions or concerns, please let me know.

Page 4: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Constructability Review Comments 2-Apr-14

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

1 1 L&DComplete Federal Job Number info for C- and D- number

phasesWill complete.

2 1 L&D Denote the RW Revision date on the Rev. Table Will denote.

3 1 SurveyWill this project be advertised under the new 2014 Road

and Bridge Specifications?Item to be discussed.

Verify P11 Temporary Easement requirements (as shown Temporary Easement to be removed,

Pre-Advertisement Conference

I-81 Exit 310 Interchange Modification Frederick County

0081-034-127 UPC 75881

4 1C L&D Verify P11 Temporary Easement requirements (as shown

on Sht 12)

Temporary Easement to be removed,

LD-36 form and revised sheets to be

provided.

5 1c SurveyThere is a right of way data sheet. Will there be Right of

way plan sheets?

They are included on the RW plan

sheets. Will add to PAC plans.

6 1D Environmental The Revision data sheet was not included.

Revision data sheet submitted on

3/7/14, will submit updated sheets as

needed.

7 1F SurveyVDOT surveyors will rename the traverse table and add the

elevations for the points listed.

Noted, please inform design consultant

when change is made.

8 1F(1) Survey

The surveyor for the Engineering consulting firm should

provide the coordinate x,y, and z values for the control

points than they set for this project and the traverse

It is our understanding that adequate

coordinate information has been

provided for control points in the

between the points. A description of the type of monument

set must accompany the coordinate value.

supplemental survey area. Please

clarify which areas are in question.

9 1K(1) Materials

Temporary Pavement Design Table: Change SM-12.5A

layers to IM-19.0A. Delete BM-25.0A layers on Tasker

Road and Hillandale Lane. (Provided in 8/13/2013 geotech

report review).

Will revise temporary pavement layers.

Change Table 18 in Final Geotechnical

Report as well? Note: No IM-19.0A

called out in any other typical sections.

10 1K(1) MaterialsPhase 1: "Temporary Pavement Roadway" is not shown in

MOT plans.

Will add "Temporary Pavement

Roadway" to MOT plans for Phase 1.

11 1K(1) MaterialsPhase 1A: MOT plans do not show temporary pavement

along I-81.

Temporary pavement shown in plan

view [see example in sheet 1L(7)], will

add detail for temporary pavement along 11 1K(1) Materials

along I-81. add detail for temporary pavement along

I-81.

12 1K(1) MaterialsPhase 1C: Is "temporary roadway" term correct? MOT

plans show minor widening.

Will revise description to temporary

pavement. Phase 1A, Note 4 to be

corrected as well.

13 1K(1) Operations

Provide a barrier warrant analysis for all proposed barrier.

Based on the anticipated short durations of some of the

phases group II channelizing devices may be more

appropriate.

Volkert will assess all locations where

barrier is shown to determine if Group II

channelizing devices would be more

appropriate.

Page 1 of 34

Page 5: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

14 1K(1) Operations

Include a note indicating that permanent signage will need

to be installed throughout various phases once new traffic

patterns have been established at the discretion of the Area

Construction Engineer and the Work Zone Safety

Coordinator

Will comply.

15 1K(1) Operations Phase 1A Note #3 - Please provide more detail Will comply.

16 1K(1) OperationsProvide Durations, Incentives and Disincentives for

individual phasesWill comply.

17 1K(1) Operations

New Tasker Road is utilized during Phase 1C and Phase

1D detours, however the sequence of construction states

that the contractor shall open New Tasker Road during

Phase 2. Please clarify.

Will clarify opening of New Tasker

Road.

Phase 2. Please clarify.

18 1K(1) Operations

Include a note that all construction access points need to be

coordinated with and approved by the Area Construction

Engineer and the Work Zone Safety Coordinator.

Will comply.

19 1K(2) OperationsGeneral Note #1 - Confirm that this does not contradict the

detour plansWill confirm there is no conflict.

20 1K(2) Operations

General Note #6 - Contractor shall notify the "Traffic

Operations Center" and not the Regional Operations

Maintenance Manager

Will comply.

21 1K(2) OperationsGeneral Note #7 - Is this referring to the existing traffic

signal installation plans?Will clarify

22 1K(2) Operations Remove General Note #11 - This is covered in the WAPM Will comply.22 1K(2) Operations Remove General Note #11 - This is covered in the WAPM Will comply.

23 1K(2) OperationsGeneral Note #12 - Replace "construction" with "any phase

or traffic shift".Will comply.

24 1K(2) Operations General Note #13 - Address how this will be accomplished Will comply.

25 1K(2) Operations Remove General Note #16 - This is covered in the WAPM Will comply.

26 1K(2) Operations Remove General Note #19 - This is covered in the WAPM Will comply.

27 1K(2) Operations

Construction Note #1 - Confirm allowable work hours and

verify why we are restricting night work? Is there a noise

ordinance in Winchester? 9-3 lane closures?

Will confirm allowable work hours.

28 1K(2) OperationsConstruction Note #3 - address how this will be

accomplishedWill address.

29 1K(2) OperationsConstruction Note #5 - Revise to include "payment is

incidental to other work"Will comply.

30 1K(2) OperationsAdd a note indicating that signal timing adjustments will be

the responsibility of the contractorWill comply.

31 1K(2) OperationsInclude notes regarding the eradication of existing striping.

Consider showing on plan sheets for individual phases.Will comply.

Page 2 of 34

Page 6: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

32 1K(2) Construction

Holiday Restriction under Construction Notes needs to be

changed to the following: No work operations which restrict

roadway capacity shall be permitted on Sundays or from

12:00 PM the day before a holiday until 12:00 PM the day

after a holiday. If a holiday occurs on a Saturday or Sunday,

the restrictions shall apply from 12:00 PM the Friday before

the holiday until 12:00 PM the Monday after the holiday.

These operations include but are not limited to flagging

operations, temporary road or lane closures, installation or

removal of traffic barrier service, staging of construction removal of traffic barrier service, staging of construction

vehicles within a travel way and entry or exit of slow moving

construction vehicles to or from the work area. Otherwise,

no work operations which restrict roadway capacity beyond

that shown on the plans shall be permitted without

permission from the Engineer for the Holidays as shown per

section 108.02 of the Road and Bridge Specifications.

33 1K(2) Construction

Special Event Restrictions needs to be added under

Construction Notes: This note needs to be specific to the

Annual Apple Blossom Festival which is held in Winchester

each year. No work should be performed during this festival 33 1K(2) Construction

period which would result in impacts to the traffic patterns,

i.e. lane closures or restrictions, flagging operations, etc.,

due to the extremely heavy traffic volumes which are

experienced during the week of the Apple Blossom Festival.

34 1K(2) Construction

The following note needs to be added to the Sequence of

Construction (SOC) Notes: At the end of each day no more

than 2 inches grade difference between travel lanes or at

the edge of the travel lanes will be allowed during

construction. Any grade difference greater than 2 inches

will require an approximate 6:1 wedge be installed for the

Safety and protection of vehicular traffic. The cost of

placing, furnishing and removing the wedge shall be

Will comply.

placing, furnishing and removing the wedge shall be

included in cost of other items.

35 1K(2) Construction

The following note needs to be added to the Sequence of

Construction (SOC) Notes: The Contractor shall replace

damaged impact attenuators immediately after damage is

incurred, not to exceed 24 hours from the time damage is

incurred. Replacement of damaged Attenuators will be

included in the price for the attenuator.

Will comply.

Page 3 of 34

Page 7: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

36 1K(2) Construction

The following note needs to be added to the Sequence of

Construction (SOC) Notes: All traffic Barrier and impact

attenuators shall be installed to maintain sight distance

requirements at all intersections and entrances during

construction unless otherwise directed by the Engineer.

Will comply.

37 1K(2) Construction

The following note needs to be added to the Sequence of

Construction (SOC) Notes: When proceeding from one

phase of construction to another phase any existing or

construction pavement markings that conflict with the new

traffic pattern shall be eradicated and re-striped accordingly.

Will comply.

traffic pattern shall be eradicated and re-striped accordingly.

38 1K(2) Construction

The following note needs to be added to the Sequence of

Construction (SOC) Notes: The contractor shall install a

temporary pavement patch over utility and drainage pipe

trenches in paved roadways and/or shoulder areas.

Temporary surface patch shall consist of Asphalt Concrete

Base Course BM-25.0A installed at a minimum 4"

thickness. Asphalt for temporary patches shall be included

in the price bid for related utilities and drainage pipes.

Will comply.

The following note needs to be added to the Sequence of

Construction (SOC) Notes: All Flagging operations shall be

conducted as per the 2011 Virginia Work Area Protection 39 1K(2) Construction

conducted as per the 2011 Virginia Work Area Protection

Manual. The cost of the required shadow vehicle shall be

included in the price bid for other items in the contract and

no additional compensation for this item will be made.

Will comply.

40 1K(2) Construction

The following note needs to be added to the Sequence of

Construction (SOC) Notes: In accordance with the Work

Area Protection Manual, the contractor shall provide a light

source to illuminate the flagging stations during night time

flagging operations. The flagger stations shall be illuminated

at night by a light source producing a minimum of 5 foot

candles (50 lux). Separate payment will not be made for

providing a light source. The cost thereof shall be included

Will comply.

providing a light source. The cost thereof shall be included

in the price of Flagger Service.

41 1K(3) OperationsProvide a note regarding signal timing adjustments for

existing Route 11 signals during detourWill comply.

42 1K(3) OperationsShould the Legend and hatched area represent Phase 1C

construction?Yes, will correct.

Page 4 of 34

Page 8: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

43 1K(3) Operations

Confirm ramp from Rt 11 to Rt 37 South can handle the

volume of the detoured traffic. Also, a traffic signal may be

considered for Ramp G at Tasker. Provide analysis.

Synchro analyses indicate that the Rt

11/Rt 37 SB ramp would maintain

adequate levels of service during the

Phase 1B detour.

44 1K(3) OperationsRoute 37 is a state primary route, not a U.S. route. Revise

the route shields accordingly.Will comply.

The Phase 1C RT 37 EB Extended at Relocated Tasker

Road intersection analysis is incomplete. It failed to take

into account the unusual Lane Utilization Factor resulting

from the dominant NB LT movement at the intersection 450

feet north. I calculated a Lane Utilization Factor of 0.62 for SimTraffic analyses was beyond the

scope of the completed analyses. This 45 1K(3) Operations

feet north. I calculated a Lane Utilization Factor of 0.62 for

the NB Thru movement at RT 37 EB Extended and

Relocated Tasker Road. This will not change anything in

the Synchro Analysis Worksheet because it is a

macroscopic adjustment. However, running SimTraffic will

show that this unbalanced flow will cause significant

backups for the EB LT movement.

scope of the completed analyses. This

issue should be discussed further with

VDOT.

46 1K(4) OperationsRoute 37 is a state primary route, not a U.S. route. Revise

the route shields accordingly.Will comply.

47 1K(4) OperationsShould the Legend and hatched area represent Phase 1D

construction?Yes, will correct.

48 1K(4) OperationsAll type III barricades should be aligned perpendicular to the

closed roadway sectionsWill comply.

49 1K(4) Operations

Confirm ramp from Rt 11 to Rt 37 South can handle the

volume of the detoured traffic. Also, a traffic signal may be

considered for Ramp G at Tasker. Provide analysis.

Synchro analyses indicate that the Rt

11/Rt 37 SB ramp would maintain

adequate levels of service during the

Phase 1B detour.

50 1L(1) Operations

Barrier along Tasker Rd must meet flare rate requirements.

Ensure that barrier does not impede line of sight looking

northeast.

Will comply.

51 1L(1) Operations

Include notes in the Temporary Traffic Control Plan Sheets

that indicate the contractor is responsible for maintaining

access to all commercial and private entrances during

construction

Will comply.

52 1L(1) OperationsInclude a note indicating that asphalt section will need to be

in place prior to the end of each working shift.Will comply.52 1L(1) Operations

in place prior to the end of each working shift.Will comply.

53 1L(1) Operations

Ensure all left shoulder widening along I-81 will match

existing 2% cross slope of existing section and additional

shoulder grading will be required as work progresses.

Will review and revise if necessary.

54 1L(3) Materials Provide temporary pavement design note. Will comply.

55 1L(6) Operations A right shoulder closed ahead sign will be required Will comply.

56 1L(6) OperationsAddress construction access issues for work to be

performed in Phase 1AWill comply.

Page 5 of 34

Page 9: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

57 1L(6) Operations When is existing striping eradication addressed?Will add notes to address existing

striping eradication.

58 1L(6) Operations Barrier flare rate along I-81 is minimum 22:1.1-81 posted speed limit is 65 mph so a

barrier flare rate of 20:1 was used.

59 1L(6) Operations1' shy line must be to the face of the barrier, not the

centerline.

Will revise typical section to show this

correctly.

60 1L(6) OperationsProvide dimension from the edge line to the edge of the

shoulder widening for each direction of I-81.Will comply.

61 1L(7) Operations Barrier flare rate along I-81 is minimum 22:1.1-81 posted speed limit is 65 mph so a

barrier flare rate of 20:1 was used.barrier flare rate of 20:1 was used.

62 1L(7) Operations

Show traffic control for temporary pavement along Ramps A

and D to be constructed in this phase. Cross slope of

shoulder widening should match existing 2% cross slope of

existing ramps. Provide guidance for conditions left during

non-working hours.

Will provide traffic control for temporary

pavement. Will review slope of shoulder

widening and revise if necessary. Will

provide guidance for conditions left

during non-working hours.

63 1L(8) Operations

Show traffic control for temporary pavement along Rt 37 to

be constructed in this phase. Cross slope of shoulder

widening should match existing 2% cross slope of Route 37.

Provide barrier warrant analysis. Provide guidance for

conditions left during non-working hours.

Will provide traffic control for temporary

pavement. Will review slope of shoulder

widening and revise if necessary. Will

provide guidance for conditions left

during non-working hours.

64 1L(9) Operations Barrier flare rate along I-81 is minimum 22:1.1-81 posted speed limit is 65 mph so a

barrier flare rate of 20:1 was used.

65 1L(11) Operations

Construction same location same location as existing

guardrail. Recommend gr-9 on each side of entrance with

Type III barricades. Eliminate barrier but ramps need to be

at grade once guardrail is modified.

Barrier is needed since full depth

construction is occurring at this location.

66 1L(12) Operations Barrier radius questionable especially down at Route 11. Will modify barrier radius.

67 1L(12) Operations Ensure stop sign is in place at end of ramp E at Rt. 11We have verified the existence of the

stop sign in place in the field.An impact attenuator is not needed

68 1L(12) OperationsVerify impact attenuator is not required on south end of

barrier along Route 11.

An impact attenuator is not needed

since the is a median between the

barrier and traffic from the opposing

direction.69 1L(12) Operations Provide Section B-B for Route 11. Will comply.

Page 6 of 34

Page 10: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

70 1L(12) Operations

Show traffic control for temporary pavement along Route 11

to be constructed in this phase. Cross slope of shoulder

widening should match existing 2% cross slope of existing

ramps. Provide guidance for conditions left during non-

working hours.

Will provide traffic control for temporary

pavement. Will review slope of shoulder

widening and revise if necessary. Will

provide guidance for conditions left

during non-working hours.

71 1L(13) Operations Proposed route signs should be shown on the signing plan.

These are not proposed signs, these are

temporary signs needed due to the

construction restricting left turns on

sheet 1L(15).

Lane drop layout. Recommend pulling lane closure back to This was considered during the design

72 1L(14) Operations

Lane drop layout. Recommend pulling lane closure back to

south and then allow openings for turn lanes instead

splitting traffic.

This was considered during the design

of the TMP but there was not adequate

space available for this to occur.

73 1L(15) Operations

There was no analysis performed at the stop controlled RT

37 WB to RT 11 NB “slip ramp”. During Phases 1C and 1E,

RT 11 NB is reduced to one lane at its intersection with the

slip ramp. This constriction will reduce the number of

available gaps for right turning vehicles off the slip ramp.

There is the potential for slip ramp backups to extend all the

way back to RT 37. This analysis needs to be performed,

at least for Phases 1C and 1E.

Synchro analysis shows the stop

controlled Rt 37 Slip ramp at Rt. 11 can

accommodate detoured traffic.

Since the geometry is different from

74 1L(15) OperationsRemove Left Lane Closed Ahead and replace with a Curve

sign with a Max safe speed plaque.

existing, we determined that the current

signs best notify drivers of the geometry

change. A max safe speed plaque can

be added.75 1L(15) Operations Existing marking across ramp to be eradicated Noted.

76 1L(15) Operations Install a "no Left Turn" sign on Ramp E Will comply.

77 1L(15) OperationsInstall a One Way sign on Route 11 for ramp traffic to go

South only.Will comply.

78 1L(15) OperationsVerify Wrong way signs are already in place on Route 11

North of Ramp E

We have verified the existence of these

signs in place in the field.

79 1L(15) Operations Remove ramp closed with type III on northbound Route 11 Will comply.

80 1L(16) Operations Install a shift sign on south bound Route 11 Will comply.80 1L(16) Operations Install a shift sign on south bound Route 11 Will comply.

81 1L(17) Materials

Add temporary pavement note (referencing Table 1, Sheet

IK(1)) - same for Sheets IL(20), IM(4), 1M(5), 1P(2) and

1P(4).

Will comply.

82 1L(17) Operations Remove barrier in crossover. Place Type III barricades Will comply.

83 1L(17) Operations Barrier warrants due to small amount of work.Barrier is needed since full depth

construction is occurring.

84 1L(17) Operations Construction access due to barrier flared back and in placeWill ensure construction access due to

barrier flare.

Page 7 of 34

Page 11: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

85 1L(17) Operations Add left shoulder closed signage on Route 11 northbound Will comply.

86 1L(17) Operations No left turn sign shall remain from previous phases Will comply.

87 1L(17) Operations Remove "RWA" on Ramp EThe "Road Work Ahead" sign is

necessary according to the VAWAPM.

88 1L(17) OperationsRemove Left Lane Closed Ahead and replace with a Curve

sign with a Max safe speed plaque.

Since the geometry is different from

existing, we determined that the current

signs best notify drivers of the geometry

change. A max safe speed plaque can

be added.The flare rate was shortened due to

89 1L(17) Operations If barrier remains 5:1 flare rate is not to standardThe flare rate was shortened due to

geometry constraints.

90 1L(19) Operations Arrow board at beginning of taper. Will comply.

91 1L(20) Operations Barrier warrant for the trench widening? Clarification is needed. Should be

discussed with VDOT.

92 1L(20) OperationsHeading southbound on Rte 11 create right turn lane and

keep one through lane until south of ramp C.

Clarification is needed. Should be

discussed with VDOT.

93 1L(20) Operations

Pull the Barrels creating the nose for Ramp C at the end

down further towards Route 11 to guide vehicles to make

right turn until striping is installed.

Will comply.

94 1L(20) OperationsRemove LLCA replace with curve sign with max safe speed

plaque

Since the geometry is different from

existing, we determined that the current

signs best notify drivers of the geometry 94 1L(20) Operationsplaque

signs best notify drivers of the geometry

change. A max safe speed plaque can

be added.

95 1L(20) Operations Install a "no Left Turn" sign at bottom on Ramp ELeft turns are permitted; this lane is a

shared left-thru-right turn lane.

96 1L(20) Operations Should be Ramp E instead of C. Will comply.

97 1L(20) Operations Stop sign at bottom of Ramp E Will comply.

98 1L(20) Operations Remove RWA signs on Ramp E The "Road Work Ahead" sign is

necessary according to the VAWAPM.

99 1M(1) Operations Capacity Issue on I-81 NB ramp due to right turn only

This ramp is not right turn only. There is

one left-turn lane and one right-turn

lane.100 1M(1) Operations Realign Type III barricade Will comply.100 1M(1) Operations Realign Type III barricade Will comply.

101 1M(2) Operations Realign Type III barricade Will comply.

102 1M(2) OperationsAdd group II's along shoulder in areas where the new road

alignment occursWill comply.

103 1M(2) OperationsTypical for Hillandale shows a 12 median. Is this a striped

median? There is no median on this sheet.

104 1M(2) OperationsTie in for new/old Hillandale Lane. Is this just getting

overlaid with asphalt only?This tie-in will occur via asphalt overlay.

105 1M(3) OperationsClarify when ramps G and F and new Tasker Road is

constructed and open to trafficWill clarify.

Page 8 of 34

Page 12: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

106 1M(4) Operations Address construction access for Phase 2 construction Will comply.

107 1M(4) Operations Provide cross section B-B for ramp F Will comply.

108 1M(4) Operationsadditional lane width is preferred due to additional traffic

and truck traffic during detour

The space required to do the work does

not allow for additional lane width in this

area.

109 1M(4) OperationsRefer to WAPM TTC-20 for lane closure with barrier for

pavement marking requirements, markers, etc. Will comply.

110 1M(5) Operations Provide R4-7 sign in Rt 37 median NB and SB at I-81 ramps Will comply.

111 1M(5) Operations Provide LT lanes on Rt 37 for I-81 Will comply.

Will comply. It does not appear that 112 1M(5) Operations

Contractor shall provide signal timing plans for I-81 NB off

ramp signal. Will signal head adjustments be required?

Will comply. It does not appear that

signal head adjustments will be

required.

113 1M(5) Operations

The proposal to restrict the bridges over I-81 to a single

lane in each direction (in Phase 2) will not work

operationally. The signals will operate at 150% of capacity

and will both have LOS F. The intersection with the I-81

Northbound ramps has over 5 minutes of delay on all

approaches. The intersection with the I-81 Southbound

ramp has delays exceeding 12 minutes for the off-ramp. In

both cases, traffic will be backing up onto the freeway.

This issued need to be discussed with

VDOT.

114 1M(6) Operations Verify barrier flare meets standards. Will comply.114 1M(6) Operations Verify barrier flare meets standards. Will comply.

115 1M(6) OperationsAddress construction access issues for work to be

performed in Phase 2Will comply.

116 1M(6) OperationsProvide cross section B-B for Rt 37 just south of Ramps A

and BWill comply.

117 1M(6) OperationsRemove Road Closed sign on barricade on Rt 37 SB that is

behind barrierWill comply.

118 1M(7) Operations Remove W9-3L, R4-V7R, W4-2L and G20-2 signs Clarification is needed. Should be

discussed with VDOT.

119 1N(2) Operations11' lanes may present a problem with over width permits.

Please address.Should be discussed with VDOT.

120 1N(2) Operations Remove G20-2 signThe "End Road Work" sign is necessary

according to the VAWAPM.

121 1N(2) OperationsProvide cross section B-B for Rt 37 just south of Ramps C

and DWill comply.

122 1N(2) OperationsBarrier flare rate seems inadequate. Address connection

with existing guardrail.

This was designed in accordance with

the 45 mph posted speed limit.

According to the VAWAPM 14:1 is

correct for 45 mph.

Page 9 of 34

Page 13: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

123 1N(3) Operations

Phase 3 has Route 37 westbound as one lane, and

eastbound as two lanes, over I-81. However, the AM peak

period has LOS F at the I-81 northbound intersection with

4.5 minutes or more of delay for both Route 37 westbound

(from Tasker Road) and the I-81 northbound exit ramp.

Should be discussed with VDOT.

124 1N(5) Operations Arrow board at beginning of taper for ALL lane closures. Will comply.

125 1N(5) OperationsRevise taper to provide access to commercial entrance

across from Rt 37 rampsWill comply.

126 1N(6) Operations Provide R4-7 in median of Ramp E at Rt 11 Will comply.

The lane drop was put in place to 127 1N(6) Operations

Explain reason for lane marking shift along Route 11 NB in

front of Ramp E.

The lane drop was put in place to

accommodate the work on the shoulder

and a portion of the road.

128 1P(1) Operations Ensure lane shift on I-81 is in accordance with TTC-40 Will comply.

129 1P(1) OperationsExist open E5-2 sign should be approximately 650' prior to

ramp openingWill comply.

130 1P(2) Operations Add W4-1R sign for Ramp A onto I-81 SB Will comply.

131 1P(2) Operations Barrier flare rate seems inadequate. Will review and revise if necessary.

132 1P(2) Operations

Provide PCMS along Ramp A to address short merge onto I-

81 SB. Yield ahead and yield signs should also be

installed.

Will comply.

133 1P(2) Operations Barrier flare rate inadequate I-81 NB and SB Will review and revise if necessary.133 1P(2) Operations Barrier flare rate inadequate I-81 NB and SB Will review and revise if necessary.

134 1P(2) Operations Address barrier connection on I-81 NBClarification is needed. Should be

discussed with VDOT.

135 1P(3) OperationsRoad closed sign on 37 NB can be removed since it is

behind barrierWill comply.

136 1P(3) Operations Construction access for Rt 37 SB during phase 4Clarification is needed. Should be

discussed with VDOT.

137 1P(3) Operations

Phase 4 again has Route 37 at only a single lane in each

direction over I-81. This is not workable because there is

not enough capacity for I-81 north to Route 37 west.

Should be discussed with VDOT.

138 1P(4) OperationsAddress barrier connection on I-81 SB (If barrier is

necessary)

Clarification is needed. Should be

discussed with VDOT.Provide PCMS along Ramp A to address short merge onto I-

139 1P(4) Operations

Provide PCMS along Ramp A to address short merge onto I-

81 NB. Yield ahead and yield signs should also be

installed.

Will comply.

140 1P(4) Operations Barrier flare rate for I-81 SB ramp is inadequateClarification is needed. Should be

discussed with VDOT.

141 1P(5) OperationsExist open E5-2 sign should be approximately 650' prior to

ramp openingWill comply.

142 1P(5) Operations Remove extra arrows in left lane of I-81 NB and SB Will comply.

143 1P(6) Operations R4-7 signs in median of Rt 37 NB and SB Will comply.

Page 10 of 34

Page 14: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

144 1P(6) OperationsRt 37 NB approaching Ramp C delineate single through

lane with edgeline prior to creating right turn laneWill comply.

145 1P(6) OperationsEnsure all permanent lane drop signs and markings are in

place for Ramp CWill ensure.

146 1P(6) OperationsAnalyze the storage capacity of the Route 37 SB Left Turn

Lane onto Ramp C

Analyses have been provided for the left-

turn lane of Rt 37 SB/EB ramp under

Phases 4/5 traffic analyses.

147 1P(7) Operations Clarify when Rt 37 off ramp was taken out of service Will clarify.

148 1P(7) Operations Remove End Road Work signThe "End Road Work" sign is necessary

148 1P(7) Operations Remove End Road Work signThe "End Road Work" sign is necessary

according to the VAWAPM.

149 1P(7) Operations Barrier flare rate at Ramp A inadequate Will review and revise if necessary.

150 1P(7) OperationsEnsure all permanent lane drop signs and markings are in

place for Ramp AWill ensure.

151 1Q(2) Operations Remove End Road Work signThe "End Road Work" sign is necessary

according to the VAWAPM.

152 1Q(3) OperationsAddress construction access for Phase 5 construction (only

access appears to be in dual turn lanes).Will address.

153 1Q(3) Operations

Phase 5 again has Route 37 at only a single lane in each

direction over I-81. This is not workable because there is Should be discussed with VDOT.153 1Q(3) Operations direction over I-81. This is not workable because there is

not enough capacity for I-81 north to Route 37 west.

Should be discussed with VDOT.

154 1Q(4) Operations Remove End Road Work signThe "End Road Work" sign is necessary

according to the VAWAPM.

155 1Q(5) OperationsProvide Arrow Board and the beginning of taper for lane

closure.Will comply.

156 1Q(5) OperationsConsider closing left lane Rt 37 SB prior to ramp from Rt 11

to avoid merging from both directions at same locationWill review and revise if necessary.

157 1Q(5) Operations

If left lane is closed prior to Rt 11 ramp, relocate W4-2L

signs and remove Keep Right and Left Lane Closed Ahead

signs from Ramp

Will review and revise if necessary.

signs from Ramp

158 2 Construction

General Notes, under Pavement: Add the following note:

Asphalt leveling shall be performed prior to placement of

the surface layer of asphalt at the direction of the engineer.

Asphalt Concrete Ty. SM-9.5A shall be used for leveling

application.

Will add note. Heading to be "Note:".

SM-9.5A is not used in any proposed

roadway sections, should SM-12.5A be

used instead?

159 2 Materials Delete Note G-2 (FI). Will delete note.

Page 11 of 34

Page 15: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

160 2 MaterialsUse new Note G-6 and Pavement Tie-In Notes (attached).

Discuss minimum CBR value.

Will revised Note G-6 and add

Pavement Tie-In Notes. Minimum CBR

value of 5 called for in Final

Geotechnical Report, should different

value be used?161 2 Materials Add Controlled Blasting Note (attached). Will add note.

162 2 Survey

Note I - 10 should read "Standard RM-2 Right of way

monuments shall be set by the contractor." Matches

Summary sheet 2E1.

The note will be adjusted as requested.

The utility backfill requirements are different than the

standard PB-1. Revise the fourth note under MATERIALS Will revised note, should utility pipe

163 2 Utilities

standard PB-1. Revise the fourth note under MATERIALS

to reflect this and refer the reader to the utility bedding and

backfill detail located on sheet 39(19). Also note that this

shall be included in the price of the pipe and shall not be

measured and paid separately.

Will revised note, should utility pipe

backfill discussion be at the beginning or

end of fourth note?

164 2 ConstructionA note needs to be added on Sheet 2 pertaining to

Controlled Blasting Operations.Will add note, see response to item 160.

165 2A ConstructionTypical Sections I-81. Guardrail Typical drawing needs to

be added to this Typical Sheet.Will add guardrail typical section.

166 2A L&D Verify Note 1Note 1 will be deleted, see comment

178 and response.

167 2A L&D Detail rail sections as necessary (all typicals)Will add guardrail typicals to all relevant

typical sections.

168 2A Materials

Change "SMA-12.5" to "SMA-12.5(70-22)" and change

"SMA-19.0" to "SMA-19.0(70-22)." Same for Sheets 2B,

2B(1), 2B(2), 2B(3) and 2B(4).

Will revise pavement material callout.

169 2A Materials Insets C and G appear to be exactly the same.Inset G to be deleted, NBL I-81 to note

"See Inset D or Inset C".

170 2A MaterialsChange Inset E to SM-12.5A and IM-19.0A (i.e. not SMA

mixes).

Will revise Inset E. Should 2" of BM-

25.0A be used instead of 2" of IM-

19.0A? No IM-19.0A called out in any

other typical sections.

171 2A MaterialsDelete Notes 1, 4 and 5. Same for Sheets 2B, 2B(1), 2B(2),

2B(3) and 2B(4).Will delete notes 1, 4, and 5.

Is the I-81 Left shoulder widening temporary pavement

No, left should widening will be

permanent when placed for Phase 1

172 2A Operations

Is the I-81 Left shoulder widening temporary pavement

being removed and replaced with the permanent typical

section?

permanent when placed for Phase 1

MOT purposes. Is note needed on

sheet 2A for clarification? Sheet 1K(1)

does not call this temporary pavement.

173 2A OperationsConsider modifying structural section to reduce construction

time in work that has to be done under traffic

To discuss, is this in reference to left

shoulder widening in particular?

Page 12 of 34

Page 16: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

174 2B Materials

Upper right typical section: Move UD-4 to edge of full-depth

shoulder or stop surface course at end of intermediate

layer.

Provide clarity, UD-4 edge is currently

lined up with edge of full-depth shoulder.

175 2B(1) Materials

Route 37 with Guardrail Detail: Where do these dimensions

start, what are the pavement layers required and why isn't

shoulder full-depth pavement? Same for Sheet 2B.

Will add dimension start point. Full-

depth pavement will be used, will add

callout for Inset A. UD-4 will be shown

at correct place.176 2B(3) Materials Add "2:1 max" to middle typical sections. Will add label.

177 2B(3) MaterialsUpper right typical section: Move UD-4 to edge of full-depth

shoulder.

Provide clarity, UD-4 edge is currently

lined up with edge of full-depth shoulder.

Will revise Ramp E pavement layers. 178 2B(3) Materials

Change Ramp E to Ramps F and G pavement design (Inset

C) for consistency.

Will revise Ramp E pavement layers.

Change Table 17 in Final Geotechnical

Report as well?

179 2B(4) MaterialsEntrances: Delete "21A or" and "or SM-9.5D." Change "BM-

25.0" to "BM-25.0A."Will delete or correct pavement callouts.

180 2B(4) MaterialsTasker Road and Hillandale Lane: Add subgrade

stabilization geotextile under Aggregate No. 21B layer.

Will add subgrade stabilization

geotextile.

181 2B(4) Materials Inset F does not appear to be used on this sheet.Inset F used on upper right Hillandale

Lane typical section.

182 2B(4) ConstructionTypical Sections Tasker Road. Guardrail Typical drawing

needs to be added to this Typical Section.Will add guardrail typical section.

Show sawcut (full-depth) at joint between existing and 183 2C Materials

Show sawcut (full-depth) at joint between existing and

proposed pavement. Same for Sheets 2C(1) and 2C(3).Will add sawcut label.

184 2C(2) Construction

Interchange Gore Areas, Ramp B Exit Ramp from I-81

S.B.L. Dotting for new Full Depth Pavement is not shown on

this sheet.

Will add dotting for new full depth

pavement.

185 2C(2) Construction

Interchange Gore Areas, Ramp B Exit Ramp from I-81

S.B.L. Cross Hatching for Mill & Overlay is not shown on

this sheet.

Will add cross hatching.

186 2C(2) Materials Show cross-hatching. will add cross hatching.

187 2D L&D There are a number of areas where road fills overlap SWM

fills; ensure quantities aren't double counted

SWM fills in overlap areas are based

upon the assumption that projected

roadway slopes are in place. Volumes

are not overlapped. are not overlapped.

188 2D, 2E L&D There are many quantities that are missing and/or don't

add up; verify totalsWill correct quantities and verify totals.

Page 13 of 34

Page 17: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

189 2E Construction

Pavement Summary Sheet:The Area Construction Engineer

would like to request the addition of 2,000 Tons of Asphalt

Concrete Type SM-9.5A asphalt material which will be used

for a leveling course, if required, in transition areas and

phase construction tie-in areas before placement operations

of the surface layer of asphalt.

To discuss location on summary sheet.

Will add 2,000 tons of Asphalt Concrete

Type SM-9.5A.

190 2E Materials Add "(70-22)" to SMA quantities.Will add "(70-22)" to SMA quantities

description.

191 2E Materials Delete 7" No. 21B and 8" BM-25.0D columns. Will delete unused columns.

To discuss. Type III Barricades are

192 2E(1) ConstructionType III Barricades (8' Wide) are shown in two different

columns in the Incidental Summary Sheet.

To discuss. Type III Barricades are

used in maintenance of traffic for

temporary installation and on sheets

36(9) for permanent installation.

193 2E(1) ConstructionField Office Type II is currently shown in the Incidental

Summary. Field Office needs to be changed to a Type I.Will revise to Field Office Type I.

194 2E(1) Construction

Incidental Summary: Numbers in various columns on this

sheet do not total up correctly to match the totals which are

now shown.

Will correct quantities and verify totals.

195 2E(1) Construction

Incidental Summary: Item # 13600 Impact Attenuation Unit.

A total of 24 Each are shown in the Total Column, but none

are shown by Plan Sheet locations in the table above the

Item is used for maintenance of traffic.

No permanent impact attenuators are

proposed.are shown by Plan Sheet locations in the table above the

totals. proposed.

196 2G L&D Should "Final Design Stage" be checked? Yes. Design stage will be corrected.

197 2H Materials

Change "Soil or Low Permeability Liner" to "Low

Permeability Liner (See Special Provision)." Same for

Sheets 2H(5), 2H(8), 2H(15), 2H(19) and 2H(23).

The note will be adjusted as requested.

Under Note 3, it indicates to "See plan view for locations

and Planting Schedule". While a rudimentary "Plant List" is

provided for this SWM Pond, more details need to be

provided such as number of plants, plant sizes, watering

schedule, etc. Reference attachment sent from Scott

Alexander to Tim Glickman on 9/23/2013. For the ensuing

A landscaping detail for the aquatic

benches will be added to the 2H (SWM

Detail) series which provide greater

construction detail as requested. Note

that the plantings associated with 198 2H Roadside Mgmt.

Alexander to Tim Glickman on 9/23/2013. For the ensuing

Aquatic Bench Summary & Notes, change any reference in

the General Notes from Landscape Architect to District

Roadside Manager, the planting season should be from

November 1 through March 15, reference the table below

for watering requirements, eliminate 2-year establishment

for SWM pond plantings, and place the summary sheet at

the beginning of the "H" series.

that the plantings associated with

aquatic benches will be Zone 1 and 2

submergent and emergent container

plants or stems. typically these are

specified in a stem per square footage

basis without specific planting locations.

Page 14 of 34

Page 18: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

199 2H Roadside Mgmt.Exact planting locations, including spacing, need to be

shown on the plan view of the SWM pond.

we propose to add a typical planting

detail to identify a reasonable cluster of

the plants within the aquatic bench.

Outfall slope should be 3:1 maximum. No critical slope

stability analysis was provided for Ramp D. Have DCR

Outfall from 6-9 proposes rip rap

channel protection of the ditch out

following existing topography. Because

the existing slopes in this area are

greater than 3:1 would require

substantial additional clearing, grading

and potential utility conflict for reduction.

200 2H(1) Materials

stability analysis was provided for Ramp D. Have DCR

requirements (impoundment structure) been verified? (FI

and RoW) Same for Sheets 2H(5) Access Road and

2H(24) Hillandale Lane.

and potential utility conflict for reduction.

(2H(5)) -The access road side slope is a

temporary condition (pending phase III

loop) separated from the impoundment

by more than 60'. 2H(24)- The 2:1

slopes in this section are for the

roadway section and should not be a

consideration for pond stability or

maintenance.

201 2H(1) Materials

Use direct term in lieu of "Proposed Grade" unless the

elevations and slope ratios shown are only suggestions to

the contractor. Same for Sheets 2H(5), 2H(8), 2H(14),

The "Proposed Grade" line represents

the finished grade profile at the section

lines shown and matches the contour

lines in the detail sheet. Please clarify if the contractor. Same for Sheets 2H(5), 2H(8), 2H(14),

2H(16), 2H(20), 2H(24), 2M(2) and 2M(4).

lines in the detail sheet. Please clarify if

specific nomenclature revision is

requested.

202 2H(1) Materials Profile C-C: Add concrete cradle to 24" pipe.

culvert 14-3 to 6-5 is an inflow culvert

above the forebay and should not

require cradle. The layout and sizing is

intended to support/work with future

phase III loop.

A landscaping detail for the aquatic

benches will be added to the 2H (SWM

Detail) series which provide greater

203 2H(4) Roadside Mgmt.Exact planting locations, including spacing, need to be

shown on the plan view of the SWM pond.

Detail) series which provide greater

construction detail as requested. Note

that the plantings associated with

aquatic benches will be Zone 1 and 2

submergent and emergent container

plants or stems. typically these are

specified in a stem per square footage

basis without specific planting locations.

Page 15 of 34

Page 19: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

204 2H(5) Roadside Mgmt. Same comment as Item No. 2

we propose to add a typical planting

detail to identify a reasonable cluster of

the plants within the aquatic bench.

205 2H(8) MaterialsThere appear to be contour lines missing in the area of

Ramp B.

Additional contour/spot elevations will be

added to clarify fill (represented in the

profile) in this area.

206 2H(8) Roadside Mgmt. Same comment as Item No. 2

we propose to add a typical planting

detail to identify a reasonable cluster of

the plants within the aquatic bench.the plants within the aquatic bench.

207 2H(8) Roadside Mgmt.Exact planting locations, including spacing, need to be

shown on the plan view of the SWM pond.

A landscaping detail for the aquatic

benches will be added to the 2H (SWM

Detail) series which provide greater

construction detail as requested. Note

that the plantings associated with

aquatic benches will be Zone 1 and 2

submergent and emergent container

plants or stems. typically these are

specified in a stem per square footage

basis without specific planting locations.

208 2H(12) Roadside Mgmt.

Under Note 3, it references plant locations & a planting

schedule. NO plants are to be planted in this SWM pond as

it is a Detention Basin. References to planting should be

removed to avoid confusion.

Agreed- note will be deleted.

209 2H(14) Materials Add concrete cradle to double 48" pipes.

The cradle appears to be unnecessary

because there is no drawdown

operation for this pond. However, a

cradle will be added if requested.

210 2H(15) Roadside Mgmt.

Under Note 3, it references plant locations & a planting

schedule. NO plants are indicated to be planted in this

SWM pond. References to planting should be removed to Agreed- note will be deleted.

SWM pond. References to planting should be removed to

avoid confusion.

211 2H(19) Roadside Mgmt. Same comment as Item No. 2

we propose to add a typical planting

detail to identify a reasonable cluster of

the plants within the aquatic bench.

Page 16 of 34

Page 20: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

212 2H(19) Roadside Mgmt.Exact planting locations, including spacing, need to be

shown on the plan view of the SWM pond.

A landscaping detail for the aquatic

benches will be added to the 2H (SWM

Detail) series which provide greater

construction detail as requested. Note

that the plantings associated with

aquatic benches will be Zone 1 and 2

submergent and emergent container

plants or stems. typically these are

specified in a stem per square footage

basis without specific planting locations.

213 2H(23) Roadside Mgmt. Same comment as Item No. 2

we propose to add a typical planting

detail to identify a reasonable cluster of

the plants within the aquatic bench.

214 2H(23) Roadside Mgmt.Exact planting locations, including spacing, need to be

shown on the plan view of the SWM pond.

A landscaping detail for the aquatic

benches will be added to the 2H (SWM

Detail) series which provide greater

construction detail as requested. Note

that the plantings associated with

aquatic benches will be Zone 1 and 2

submergent and emergent container

plants or stems. typically these are

specified in a stem per square footage

basis without specific planting locations.

215 2J(1) L & D

Section IV, Note 8: Even though detention basin 18C-1 is

not a WQ BMP it should still be listed as a permanent SWM

facility.

The WQN only pond 18C-1 will be

added to note 8 as requested.

216 2J(2) L & D

Section VI: detention basin 18C-1 must be listed as a

permanent BMP (include treatment acres for detention). A

note can be added to indicate that this basin is for Water

Quantity treatment, not for Water Quality.

Notation will be added to Section VI as

requested.

SWPPP sheet lists six (6) permanent BMP's but the plans Pond 18C-1 will be added to the table

217 2J(2) Roadside Mgmt.

SWPPP sheet lists six (6) permanent BMP's but the plans

show seven (7) permanent BMP's. It appears 18C-1 is

missing.

Pond 18C-1 will be added to the table

with notation as "quantity only"

218 2K Environmental

Notes E-5 and E-9 have the stream names spelled

incorrectly. You have Opequon creek and Hodge Run. The

correct stream names are Opequon Creek and Hoge Run.

Please correct here and anywhere else that you have the

streams named incorrectly.

The stream name spelling will be

corrected.

219 2K L & DNote E-12.2; complete the reference to "Standard Drawings

sheet XXX" with actual page numbers.The page numbers will be added.

Page 17 of 34

Page 21: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

220 2K(2) Environmental

No temporary stream diversion is shown for the stream that

flows from the pond located at the matchline to the inside of

the culvert near between SB Sta. 124-125. Temporary

stream diversion or pump around will be required to work in

the dry prior to the extension of the existing pipe.

Given the contributing area, temporary

diversion does not appear to be required

to extend the culvert upstream because

the extension follows the existing stream

alignment.

221 2K(2) Environmental

Ensure that the outlet ditch (or whatever that wide fuzzy line

is that goes from 5-2 to the stream edge) does not go below

OHW of the stream, because no impacts were shown at this

location in the permit application.

The rip rap outlet ditch is shown ending

at the existing channel. Notation can be

added for clarity.

The rip rap outlet ditch is shown ending 222 2K(2) Environmental

Ensure that the outlet ditch that goes from 6-9 to near the

stream at the outlet does not go below OHW of the stream.

The rip rap outlet ditch is shown ending

at the existing channel. Notation can be

added for clarity.

223 2K(3) Environmental

No temporary stream diversion is shown for the pipe

extension at stream near Sta. 162. Temporary stream

diversion or pump around will be required to work in the dry

prior to the extension of the existing pipe.

Given the contributing area and

proximity to existing inlet #128,

temporary diversion does not appear to

be required to extend the culvert

downstream because the extension

follows the existing stream alignment.

224 2K(6) Environmental

You show the temporary stream diversion for the culvert at

about St. 31+25 but none for the pipe at Sta. 33+25. The

pipe installation will also require a stream diversion in order

A temporary diversion within the

construction limits can be provided as

requested. The existing channel is pipe installation will also require a stream diversion in order

to work in the dry. connected to the box culvert SCC within

the construction area.

225 2K(7) Environmental

Temporary stream diversion is needed for the stream that

flows from near station 15 of the Hillandale Road stationing

to the upstream end of the 60 inch pipe east of the pond.

The diversion ditch shown does not connect to the little

stream at the upper end. Also the diversion ditch around the

pond does not connect with the little stream and it should be

designed so that it does connect with the stream at both the

upper and lower ends as the contractor will be required to

install a proper stream diversion prior to working in the

stream.

Clarification is requested for this

comment to adjust the SCC. Current

plan elevations for the SCC mimic the

ultimate ditch and adequately drain

existing contributing areas. The existing

pond and connection at the outlet of the

60" culvert will be clarified.

226 2K(8) EnvironmentalCrossing at Sta. 162 will also need some temporary

diversion during construction.

The plan does not propose upstream

extension of the culvert at this location

please clarify.

227 2K(9) Environmental

If the temporary SCC #1 is to function also as stream

diversion during construction, it should be polyethene lined

similar to the EC-12.

Polyethene lining will be specified in this

location as requested.

Page 18 of 34

Page 22: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

228 2K(10) EnvironmentalTemporary stream diversion will be needed for the stream

just inside Ramp E near the matchline with 2K(9).

In this location the existing channel is

retained and protected by silt fence until

the final channel with rip rap is installed.

No diversion is needed.

229 2M ConstructionSTR. # 12-1: 12' x 6' Box Culvert. Detail sheets need to be

included for this structure.Will provide detail sheets for box culvert.

230 2M(2) MaterialsWill expected settlement (~40' fill) affect box culvert? Same

for Sheet 2M(4) - ~53' fill.

Geotechnical assessment will be

provided to verify support for the box

culvert fills.

231 2M(3) ConstructionSTR. # 28-6: Double 8' x 8' Box Culvert. Detail sheets need

to be included for this structure. Will provide detail sheets for box culvert.231 2M(3) Construction

to be included for this structure. Will provide detail sheets for box culvert.

232 2R Construction

Underdrain Summary: Total for UD-2 Underdrain, 908 L.F.

is shown under total of UD-3 Underdrain in table. The 908

LF needs to be moved one cell to the left.

The UD-2 quantity will be corrected.

233 2S Materials Add "See pipe backfill note, Sheet 2." Will add note.

234 3 MaterialsCross-hatch paved shoulder as new construction (FI +

RoW). Same for all sheets.

Will cross-hatch paved shoulder as new

construction on all applicable plan

sheets.

235 4 EnvironmentalThe stream is missing that comes out of that pond and goes

into 4-1 (the 48 inch corrugated steel pipe.

The survey file has been revised to

show the stream line per environmental

documents. Updated files will reflect the

stream.stream.

236 4 MaterialsShow sawcut at all joints between existing and proposed

pavements. Same for all sheets.

Will add sawcut label between existing

and proposed pavements on all

applicable plan sheets.

237 4 Operations

Show the sight distance triangle in each direction on Tasker

Rd. Consider Left Turn Lane into the Frederick County

Sanitation Authority entrance.

Evaluating addition of left turn lane into

Frederick County Sanitation Authority

entrance. Sight distance triangle can be

provided in a separate document.

238 5 Environmental

Nothing was included in the permit application for any

structures located in the stream at this location (ref.

drainage str. 5-1 which is some kind of a grate). Is this

really needed? We will have to add it to the permit . Prefer it

Due to fill and slope requirements

associated with widening, the existing

open connection requires a grate drop 238 5 Environmental

really needed? We will have to add it to the permit . Prefer it

be removed and that the typ. Ditch D simple end before

arriving at the stream OHW elevation.

open connection requires a grate drop

inlet as shown.

239 5 L&D Ensure grading at northern end of Pond 26 allows vehicular

passage to the old Tasker roadbed/utility access grading

The pond access turnaround will be

lengthened/graded as needed for

temporary access to the roadbed.

Page 19 of 34

Page 23: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

240 5 Utilities

Provide a stabilized access around pond 26 and down the

embankment to the old Tasker roadbed/utility access drive

at mainline sta 130+90 right.

Request clarification for access area

location. A culvert entrance at the I-81

shoulder is provided at 130+90. Pond

access will be modified as requested.

241 6 Materials

Move northbound UD-4 to edge of proposed pavement.

Please note that this area is not shown in typical sections,

Sheets 2A or 2B(3). Can't see northbound UD-4 south of

Sta. 136+00.

UD-4 will be adjusted/ added as

requested

242 6 MaterialsShow identify northbound lanes sawcut south of existing

label for clarity.Will add additional sawcut label.

Is restoration of natural contours desirable at existing Ramp 243 7 L&D

Is restoration of natural contours desirable at existing Ramp

A/B termini (discuss w/ Materials)?To discuss.

244 9 MaterialsShow sawcut along joint between pavement demolition and

existing pavement/proposed overlay. Same for all sheets.

Will add sawcut label between

pavement demolition and existing

pavement/proposed overlay on all

applicable plan sheets.

245 20 MaterialsTypical section (Sheet 2B) shows Ud-2 under median.

Same for Sheet 21.

UD-2 is shown at the median in this

area. No UD is provided at station

44+00 to west because median ditch is

provided.

246 24 MaterialsAdd UD-2 under MS-2 median per typical section Sheet

2B(2).

UD-2 will be added to the median

transition area (to existing) and outlet at

24-2.

247 25 MaterialsChange CD-2 to UD-4 at Sta. 19+75 (CD-2 does not include

pipe).The label will be corrected.

248 25 MaterialsAdd UD-2 under MS-2 median. Please note that there is no

typical section for Sta. 18+00 to Sta. 22+00.UD-2 will added as requested.

249 25 MaterialsAdd CD-2 at Sta. 20+75 northbound and Sta. 20+25

southbound. (FI)CD-2 will be added as requested.

250 26 Materials Label CD-2 at Sta. 14+75. Label will be added.

251 29 Materials Delete CD-2 at Sta. 34+00. CD-2 will be deleted as requested.

252 29 OperationsConsider keeping Tasker NB a single lane all the way to

Hillandale Drive.

Tasker NB is kept as single through lane

per the pavement marking plan, lane

arrows will be corrected if needed. Lane

arrows show final long term 252 29 Operations

Hillandale Drive. arrows show final long term

configuration. Please see sheet 38(8)

for clarification.

253 30 OperationsConsider keeping Tasker SB a single lane from Hillandale

to Ramp G

Tasker SB is kept a single through lane

per the pavement marking plan, lane

arrows will be corrected if needed. Lane

arrows show final long term

configuration. Please see sheet 38(8)

for clarification.

Page 20 of 34

Page 24: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

254 31 OperationsConsider additional R-O-W at NW quadrant of Hillandale

and Tasker intersection for sight distance requirements

To discuss. Developer may be able to

provide sight distance easement when

Tasker is extended. This may not be

needed until such time.

255 33B(1) MaterialsAdd expected foundation types (VDOT R&B Standard PB-

1) per final soil survey report. Same for Sheets 33B(2-4).

Please provide clarification.

Geotechnical recommendations are not

provided for all pipes. Per VDM 15-2

this has not been required.

STR. # 12-1: 12' x 6' Box Culvert. Note: Material Aggregate Revised drainage descriptions identify

256 33B(1) Construction

STR. # 12-1: 12' x 6' Box Culvert. Note: Material Aggregate

(along Section # 4). Where is Section # 4 of this Box Culvert

shown? Clarify.

Revised drainage descriptions identify

station range for clarification of section 4

(undercut) location.

257 33B(1) Construction

STR # 12-1 Single 12' x 6' Box Culvert: Bedding Material

Aggr. # 57 is shown to be installed at a depth of (18"

Bottom). A total of 78.3 C.Y. of 57 is shown for this

installation. These numbers need to be revised if the intent

is to place 18" depth of #57 stone under the total 669' of

Box Culvert.

The #57 is located only in the section 4

station range.

25833B(1) thru

33B(4)Construction

Various Pipes in the Drainage Details call for Undercut

Excavation. Included are pipes over 48" in diameter in

which any Undercut should be included in Minor Structure

The undercut excavation for pipes

greater than 48" has been included as

minor structure excavation. For the pipe

lower than 48", it continues to be Excavation.

lower than 48", it continues to be

labelled as undercut excavation.

25933B(1) thru

33B(4)Construction

Pipe cover depths shown in the Drainage Details are not

accurate when compared to amount of fill material over

pipes to achieve finished grade elevations.

Cover depths have been reviewed and

adjusted as needed.

26033B(1) thru

33B(4)Construction

Minor Structure Excavation quantities are not correct for the

Box Culvert installations and the pipes with a diameter

greater than 48".

Minor Structure Excavation quantities

have been updated as required per prior

correspondence.

261 33B(2) Environmental

Do the drainage structures associated with the 60 inch

storm sewer pipe add up to the 390 ft. long structure that

was submitted in the permit application?

Total length for the pipe in the permit will

be revised to 396 to account for

structure deductions in the drainage

descriptions.descriptions.

262 33B(3) Environmental

The 60 pipe drainage structure 28-8 states 264 ft. long

pipe. When the permit application was submitted, the

sketches provided by Volkert stated the pipe would be 266

ft. long. This was updated from 264 ft. to 266 ft. at the last

minute. So either the drainage note in the plan is wrong, or

the structure description in the permit sketch is wrong.

The drainage descriptions will be

updated to reflect 266'.

Page 21 of 34

Page 25: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

263 36(1) OperationsUnder General Notes; Note 4 - revise the last line to state

"…and approved by the NWRO Construction Engineer."Will revise note

264 36(1) Operations

Under Definition of Types - Signs "WB-1" and "WB-2" are

not standard VDOT Signs. These should be changed to

SSP-VA and SSP-VIA. Please verify that all sign types are

in accordance with the VDOT Road and Bridge standards

and revise plan sheets accordingly.

Will revise WB-1 and WB-2 notes

265 36(1) Operations

Under General Notes - Add a Note stating "Except for the

Exit Gore Signs, all Type VA and VIA signs shall be

installed behind the ditchline on all I-81 mainline and ramp Will add note265 36(1) Operations

installed behind the ditchline on all I-81 mainline and ramp

locations".

Will add note

266 36(1) Operations

Under General Notes - Add a note stating "All work

involving Travel Services Signing (Logo Signs) shall be

coordinated through Mr. Rick Burgess at 804-225-4903."

Will add note

267 36(1) Operations Graphical scale incorrect on entire sheet 36 series Will revise graphical scale

268 36(2) L&D Establish 35mphNB/45mphSB speed limit on Tasker

around STA 10+00 (subject to NWRO)

Did someone do a speed study or

evaluation? Or are we just to use the

design speed?

269 36(2) Operations

Sign plans do not include layouts of special design signs

such as the "Exit 1 Mile", Point of Turn and directional guide

Signs. These should be included in the plans on Sheets Will add detail sheets for guide signs.

Signs. These should be included in the plans on Sheets

36(2) through 32(16).

270 36(2) Operations

Sign plans do not include the relocation existing or

installation of new mile post signs along I-81. Please

include in the plans on Sheets 36(2) through 32(16).

Will add mile post signs.

271 36(3) Operations

Check horizontal alignment and queue lengths for the

advisory speed sign on the off-ramp. 25 MPH may be too

slow because the plans show a 50 MPH design for the first

curve on the exit ramp.

Will evaluate design speeds and

determine appropriate advisory speed

limits.

272 36(3) OperationsSign 3.06/158 - Logo Sign panel design does not conform

to Figure 2J-1 and 2J-2 in the MUTCD. Please correct.

Per discussion with Jason Newcomb

with VDOT LOGO sign program, the

existing sign is to be reused. Will revise

the plans to remove the proposed sign

and relocate existing.and relocate existing.

273 36(3) OperationsNeed to include a One Way sign (R6-1R) on the

southbound I-81 median at station 130+00 +/-.Will Add sign.

274 36(3) OperationsNeed to include a One Way sign (R6-1L) on the right side of

the southbound on-ramp at station 23+50 +/-.Will add sign

275 36(4) OperationsSign definition symbols include "SRP-1" but this label is not

in the sign type definitions. Please revise.Will revised sign type label

Page 22 of 34

Page 26: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

276 36(5) Operations

Check horizontal alignment and queue lengths for the

advisory speed sign on the off-ramp. 25 MPH may be too

slow because the plans show a 50 MPH design for the first

curve on the exit ramp.

Will evaluate design speeds on ramps

and determine appropriate advisory

speed limits.

277 36(5) OperationsSign 5.06/162 - Logo Sign panel design does not conform

to Figure 2J-1 and 2J-2 in the MUTCD. Please correct.

Per discussion with Jason Newcomb

with VDOT LOGO sign program, the

existing sign is to be reused. Will revise

the plans to remove the proposed sign

and relocate existing.

278 36(5) OperationsNeed to include a One Way sign (R6-1L) on the right side of

the on-ramp at station 22+50+/-.Will add sign278 36(5) Operations

the on-ramp at station 22+50+/-.Will add sign

279 36(5) OperationsNeed to include a One Way sign (R6-1R) on the northbound

I-81 median at station 155+00 +/-.Will add sign

280 36(8) Operations

At the T-intersection with Ramp G and Tasker Road,

remove the chevron alignment signs and replace with a two-

direction large arrow sign (W1-7, 60x30). Put the route sign

assembly above the two-direction large arrow sign. (Refer to

2009 MUTCD section 2C.09, paragraph 7.)

Will revise.

281 36(8) Operations Remove the STOP signs (if a traffic signal is installed).Has a signal warrant study been

completed by VDOT?

282 36(8) Operations

Install a turn sign (W1-1, 36x36) and a 10 MPH advisory

speed plaque (W13-1P, 24x24) facing traffic on northbound Will add sign282 36(8) Operations speed plaque (W13-1P, 24x24) facing traffic on northbound

Tasker Road at station 43+00.00

Will add sign

283 36(8) OperationsInstall symbolic RIGHT LANE ENDS sign (W4-2) on

northbound Tasker Road at approx. station 44+00.00Will add sign

284 36(8) OperationsAdd SIGNAL AHEAD symbol sign (W3-3) on both sides of

the one-way Ramp H in advance of the I-81 intersection

Will evaluate sight distances and add

signal ahead sign if applicable.

285 36(8) Operations

Add SIGNAL AHEAD symbol sign (W3-3) or STOP AHEAD

symbol sign (W3-1) on both sides of one-way Ramp G

(Route 37 approaching Tasker Road) as appropriate

Will evaluate sight distances and add

signal ahead sign if applicable.

Revise interchange approach guide signs on westbound Guide signage will be added as a part of

286 36(8) Operations

Revise interchange approach guide signs on westbound

Route 37 to meet the requirements of MUTCD figure 2D-13.

Signs currently shown on the sign plan may be inadequate.

Guide signage will be added as a part of

the Route 37 Extension UPC No:85972,

VDOT Project Number 0037-034-707,

P101

287 36(8) Operations

Add turn lane use signs on the Ramp G toward Tasker

Road to indicate that the left lane turns left and the right

lane turns right,

Will add sign

Page 23 of 34

Page 27: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

288 36(8) OperationsPlans include Cardinal Direction on the secondary route

shields. Recommend they be removed as th

Comment appears to be clipped.

Unclear what reviewer intends. Cardinal

direction panels were added based on

guidance from VA MUTCD Figure 2D-

6(VA) and Section 2D.29(10). The

direction panels give guidance we feel is

necessary.

289 36(9) Operations

Remove the STOP signs. (There is no need to stop at that

location. Right now, it is not an intersection and there are no

conflicting movements.)

Will remove signs 9.05 and 9.02

290 36(9) OperationsAt station 17+00.00, install a turn sign (W1-1, 36x35) with a

10 MPH advisory speed plaque (W13-1), 24x24)Will add sign

291 36(9) Operations

Remove the ONE WAY sign. Replace it with a one-direction

large arrow sign (W1-6R, 60x30) and put the South 624 -->

sign assembly above it.

Will remove and replace sign panels

292 36(9) Operations

Install a one-direction large arrow sign (W1-6L, 60x30) in

front of the Type 3 barricade facing northbound Tasker

Road

The R/W is directly behind the sidewalk

on the west side of Tasker Road where

the one-way sign would need to be

installed. The sign is 60" wide, so

additional R/W will be required for the

sign placement.

293 36(9) OperationsInstall a DEAD END sign (W14-1, 36x36) facing northbound

Route 847 relocated at approx. Sta. 12+00 Rt.Will add sign

294 36(9) Operations

Guide signs, if possible, should be placed before the off-

ramp splits from the single lane into the three lanes for the

turning movements.

Will add guide signs where feasible.

295 36(9) Operations

Hillandale Road is proposed to have a speed limit of 35

MPH. However, the plan set indicates a 30 MPH design

speed. Hillandale Rd is currently unposted. A speed study

will need to be completed.

To be discussed.

296 36(9) OperationsDelete Signs 9.07/144 and 9.08/141 as this is the

intersection of two secondary roads.

Route sign assemblies were added

based on guidance from VA MUTCD

Section 2D.29(10). Will remove signs intersection of two secondary roads. Section 2D.29(10). Will remove signs

9.07 and 9.08

297 36(9) OperationsSigns 9.07/176 and 9.03/178 should be replaced with M1-

V3aB with single arrows.

Will remove sign 9.07. Will revise 9.04

sign (believe the reviewer intended this

sign instead of 9.03) to a M1-3Va series

sign.

298 36(9) Operations

Plans indicate signs 9.05/116 and 9.06/116 are to be quite

large in size. Are both signs necessary? Rte. 847 carries

approximately 500 vehicles per day (2012).

Will remove signs

Page 24 of 34

Page 28: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

299 36(9) OperationsSign 9.02/109 - Do we want/need a Stop sign at this

location?Will remove signs

300 36(10) Operations

Remove all LEFT LANE MUST TURN LEFT and RIGHT

LANE MUST TURN RIGHT signs. Replace them with the

signs that show the full lane configuration on the exit ramp.

There should be at least one sign showing the full lane

configuration on each side of the road.

Will replace signs

301 36(10) Operations

Place all WRONG WAY signs on the back side of other

signs on the exit ramps. Do not mount WRONG WAY signs

on their own posts if this can be avoided.

Will place sign panels on as few post as

possible

302 36(10) OperationsAdd SIGNAL AHEAD symbol sign (W3-3) on both sides of

the exit ramp

Will evaluate sight distances and add

signal ahead sign if applicable.

303 36(10) Operations

Guide signs, if possible, should be placed before the off-

ramp splits from the single lane into the four lanes for the

turning movements.

Will add guide signs where feasible.

304 36(10) OperationsSigns for the existing Through Truck Restriction need to be

included.Will add truck restriction signs.

305 36(10) OperationsSign 10.19/159 - Logo Sign panel design does not conform

to Figure 2J-1 and 2J-2 in the MUTCD. Please correct.

Per discussion with Jason Newcomb

with VDOT LOGO sign program, the

existing sign is to be reused. Will revise

the plans to remove the proposed sign

and relocate existing.and relocate existing.

306 36(10) Operations

There is an existing sign and route shield assembly [North

37/To 11/To West 50/To North 522] on sheet 36(4) at the

northbound ramp intersection with Route 37 that is not on

the new plan sheet. This needs to be included.

Sign panel assembly will be added

307 36(10) OperationsOne Way signs for the intersection of Route 37 and the

northbound ramps have not been included. Please revise.

Will add one-way sign planes to 10.14

and 10.15

308 36(11) Operations

Remove all LEFT LANE MUST TURN LEFT and RIGHT

LANE MUST TURN RIGHT signs. Replace them with the

signs that show the full lane configuration on the exit ramp.

There should be at least one sign showing the full lane

Will replace signs

There should be at least one sign showing the full lane

configuration on each side of the road.

309 36(11) Operations

The Virginia Logos signs for Lodging and Food on

northbound/westbound Route 37, approaching the Route 11

exit, should have angled arrows pointing to the right.

Per discussion with Jason Newcomb at

VA LOGOs we will remove proposed

sign and will reuse existing sign

310 36(11) Operations

Place all WRONG WAY signs on the back side of other

signs on the exit ramps. Do not mount WRONG WAY signs

on their own posts if this can be avoided.

Will place sign panels on as few post as

possible

Page 25 of 34

Page 29: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

311 36(11) OperationsAdd SIGNAL AHEAD symbol sign (W3-3) on both sides of

the exit ramp

Will evaluate sight distances and add

signal ahead sign if applicable.

312 36(11) OperationsSigns for the existing Through Truck Restriction need to be

included.Will add signs

313 36(11) Operations

Signs 11.23/167 & 11.24/168 - Logo Sign panel design

does not conform to Figure 2J-1 and 2J-2 in the MUTCD.

Please correct.

Per discussion with Jason Newcomb at

VA LOGOs we will remove proposed

sign and will reuse existing sign

314 36(11) Operations

Sign 11.08/133 - Route shields in the assembly are

reversed. Rte. 37 should be on the left side and Rte. 742

should be on the right side of the assembly.

Will update sign 11.08

should be on the right side of the assembly.

315 36(11) OperationsNeed to include One Way signs on the post of sign

11.01/104.Sign panels will be added

316 36(11) OperationsShould we also include signs directing motorists to Rte. 11

from the southbound off ramp?Will add sign panels to sign 11.11

317 36(12) Operations

Remove all LEFT LANE MUST TURN LEFT and RIGHT

LANE MUST TURN RIGHT signs. Replace them with the

signs that show the full lane configuration on the exit ramp.

There should be at least one sign showing the full lane

configuration on each side of the road.

Will replace signs

318 36(12) Operations

Place all WRONG WAY signs on the back side of other

signs on the exit ramps. Do not mount WRONG WAY signs Will place sign panels on as few post as

possibleon their own posts if this can be avoided.

possible

319 36(12) Operations

Add two SIGNAL AHEAD symbol signs (W3-3) on both

sides of eastbound Route 37 in advance of the I-81

interchange (if there are none already and if the existing

signs, if any, are removed).

Will evaluate sight distances and add

signal ahead sign if applicable.

320 36(12) OperationsRoute 11 is a US route, not a state primary. Revise the

route shields accordingly.Will update panels on 12.04 and12.05

321 36(12) Operations

Signs 12.19/170 & 12.20/171 - Logo Sign panel design

does not conform to Figure 2J-1 and 2J-2 in the MUTCD.

Please correct.

Per discussion with Jason Newcomb at

VA LOGOs we will remove proposed

sign and will reuse existing sign

Revise interchange approach guide signs on westbound

Route 37 to meet the requirements of MUTCD figure 2D-13 Will evaluate existing Exit 310 1 mile

322 36(13) Operations

Route 37 to meet the requirements of MUTCD figure 2D-13

(if the existing overhead signage is not to remain in place).

This is not clear from the plan set whether the existing

signage will remain in place or not.

Will evaluate existing Exit 310 1 mile

advance sign to determine if guide sign

needs to be updated.

Page 26 of 34

Page 30: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

323 36(16) Operations

Sign Schedule Plan Sheets [Sheets 36(16) - 36(19)] call for

Route Shield panels to be oversized (36 inches in height).

Please reduce to the standard size of 24 inches in height.

Should also review other signs on the plans to verify they

are not calling for a larger size than what is needed.

Will reduce all route shields and

accessory signs to regular height in

entire plan set

324 36(16) Operations

Sign Schedule Plan Sheets [Sheets 36(16) - 36(19)] - Sign

Structure number should reference the standard sign

structure type in the VDOT Road and Bridge Standards.

Will add standard sign structure type

Do not include Cardinal direction panels on Secondary Cardinal direction panels were added

325 36(16) OperationsDo not include Cardinal direction panels on Secondary

Route Shields. [Sheets 36(16) - 36(19)]

Cardinal direction panels were added

based on guidance from VA MUTCD

Figure 2D-6(VA) and Section 2D.29(10).

326 36(16) OperationsCoordinate with the Sign Shop on the route sign

assemblies.

This should be discussed with VDOT. It

is not clear as to the need for

coordination with the sign shop with

regards to the route sign assemblies.

327 36(16) OperationsSign 12.16/103 - Message does not match sign shown on

sheet 36(12).Will update sign panel

328 36(17) OperationsSigns 3.04/149, 5.03/149 are shown to be 36"x36". Since

these are on the mainline of I-81 please revise to 48"x48".Will update sign panel

329 36(17) OperationsSigns 10.21/146, 11.26/146, 10.20/147 & 11.25/147 should

be 48"x48".Will update sign panel

330 37(1) Operations

The RT 37 EB Extended at Relocated Tasker Road

intersection should be signalized. The construction plans

currently have it un-signalized with the EB approach stop

controlled. Need to add series of sheets for signal at 37 and

Tasker Road

Has a signal warrant study been

completed by VDOT?

331 37(1) Operations

The Traffic Signal General Notes 26-28 refer to serial

radios. These should be Ethernet radios. We are sending

an Ethernet radio spec to Mike True for inclusion.

Will revise to ethernet.

Note 2 - Define requirements for a “qualified

representative”. This should preferably be a signal timing

332 37(1) Operations

representative”. This should preferably be a signal timing

engineer with experience in inputting timings into the

controller, watching and monitoring traffic conditions in the

field, and being able to make adjustments in the field as

necessary to accommodate smooth traffic flow.

Note changed to "qualified traffic

engineer."

Page 27 of 34

Page 31: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

333 37(1) Operations

Contractor shall be responsible for changing vehicle

clearance intervals, phasings, and signal timing plans for

any phase of construction that impacts a signalized

intersection. All changes shall be approved by the NWRO

Regional Signal Operations Engineer prior to switching

construction phases. Contractor shall submit the timing

plans for the various construction phases to the NWRO

Regional Signal Operations Engineer one month in advance

of the construction phase beginning to provide time for

adequate review and comment. Clearance interval timings

shall be signed and stamped by a Virginia licensed

Will add note

shall be signed and stamped by a Virginia licensed

professional engineer. This language needs to be

incorporated into the contract documents and construction

plans

334 37(1) Operations

There needs to be a response time requirement for any

maintenance or repairs to the signals and changes to the

signal timings. In addition, there should be some recourse

for VDOT if the response time is not met. This language

also needs to be incorporated into the contract documents

and construction plans

Will add general notes.

335 37(1) Operations Note 1 - add "and NWRO Regional Signal Specifications". Will change note

336 37(1) OperationsNote 3 - revise to state the VDOT NWRO Construction

Engineer will review the pole locations.Will change note

337 37(1) OperationsNote 9 - What is the intent of this note? Recommend

deleting.Will clarify note

338 37(1) Operations Note 12 - Revise to specify solid aluminum backplates. Will change note

339 37(1) Operations Note 17 - Is this note needed? Recommend it be deleted. Will clarify note

340 37(1) OperationsNote 20 - revise last line to read "…installed in accordance

with VDOT Road and Bridge Standards unless…"Will change note

341 37(1) OperationsNote 21 - Recommend the electrical service have three (3)

twenty (20) Amp breakers.Will change note

twenty (20) Amp breakers.

342 37(1) OperationsNote 25 - Revise to state "Cabinet shall be as specified in

the NWRO Regional Signal Specifications."Will change note

343 37(1) OperationsNote 27 - Revise to state "Radio Network Address to be set

as directed by the NWRO Signal Timings Engineer."Will change note

344 37(1) OperationsNote 28 - Revise to state "Controller System Address to be

set as directed by the NWRO Signal Timings Engineer."Will change note

Page 28 of 34

Page 32: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

345 37(2) Operations Item 51030 - Missing quantity for Int. Rte. 37/NB Ramps.Quantity is correct. Intersection has

master controller.

346 37(2) Operations

Items 51337 & 51347 - Are theses needed since non-

standard mast arm poles are being specified? This would

agree with the NWRO Signal Specifications. Recommend

51337 & 51347 be deleted.

Will revise quantities

347 37(3) OperationsSigns S-1 and S-2 (no left turn, no right turn) should be

36x36Will change sign panel size

348 37(3) Operations

Need to include 4 - 2" Conduits for electrical service,

communications, and traffic camera. This will need to be

coordinated through with the right of Way and Utilities Will revise quantities348 37(3) Operations

coordinated through with the right of Way and Utilities

section.

Will revise quantities

349 37(3) Operations

Need to include 1-3" Conduit and 2-2" Conduits from the

signal cabinet to the existing traffic camera on the northeast

corner of the I-81 overpass.

Will add conduit

350 37(4) Operations

Is it intended to allow right-turns on red at this intersection?

If so, then Signal head 4B (with the right arrows) should

NOT use a right-turn red arrow indication.

Will revise signal heads for right turns.

351 37(4) OperationsSigns S-1 and S-2 (no left turn, no right turn) should be

36x36Will change sign panel size

Protected/permissive left turn signal with CIRCULAR

GREEN should NOT be placed directly above the left turn Signal head alignment was changed to

lane center, based on previous review

352 37(5) Operations

GREEN should NOT be placed directly above the left turn

lane. It should be placed above the lane line between the

left-turn lane and the through lane. If the

protected/permissive left turn signal is to be mounted over

the left turn lane or in the median, then the flashing yellow

arrow should be used in accordance with MUTCD section

4D.13, paragraph 9.

lane center, based on previous review

comment dated 01/27/2014 from Mike

True: "Signal heads on the plans do not

appear to be centered over the lanes

they govern." Will relocate 5-section

heads to lane line extended.

353 37(5) Operations

Is it intended to allow right-turns on red at this intersection?

If so, then Signal head 4 (with the right arrows) should NOT

use a right-turn red arrow indication. If not, then the red

arrow is OK, but the 10-second delay detection should be

removed.

Will revise signal heads for right turns.

354 37(5) OperationsSignal head 5 should be centered on the lane line between

the left turn lane and the left-most thru lane of Rte. 11.

Signal head alignment was changed to

lane center, based on previous review

comment dated 01/27/2014 from Mike

True: "Signal heads on the plans do not

appear to be centered over the lanes

they govern." Will relocate 5-section

heads to lane line extended.

Page 29 of 34

Page 33: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

355 37(5) OperationsSignal head 4 can be revised to provide a red ball indication

to permit right turns on red from the Rte. 37 off ramp.Will revise signal head

356 37(6) Operations

Recommend reducing the overall size of this sign; 11 feet

by 2 feet is rather large. Recommend redesigning in

accordance with TE-311 to provide 8" and 6" lettering and a

more appropriate size sign panel.

Will redesign sign

357 38(1) Operations

There is no mention anywhere in the pavement marking

plans about the retroreflective snowplowable raised

pavement markings (reflectors). Ensure that the retroflective Added notes about plowable raised 357 38(1) Operations

pavement markings (reflectors). Ensure that the retroflective

snowplowable raised pavement markings are installed

according to the requirements of the Virginia MUTCD

Supplement, section 3B.11

Added notes about plowable raised

pavement markings

358 38(1) Operations Graphical scale incorrect on entire sheet 38 series Will revise graphical scale

359 38(7) OperationsAdd a turn lane into the driveway and revise the "median"

pavement markings accordingly.

Need to coordinate with roadway design

-- current road width is 24' for 2-lane

road.

360 38(8) Operations

Use a wide dotted pavement marking instead of the normal

lane line marking on Ramp G. This is needed to better

differentiate the left turn lane from the right turn lane.

Will revise pavement markings

361 38(9) Operations The "median" on Hillandale Road should be striped out. Will revise pavement markings361 38(9) Operations The "median" on Hillandale Road should be striped out. Will revise pavement markings

362 38(9) Operations

The "intersection" of Tasker and Hillandale Road has only

two of three legs only. For now, it is a temporary sharp turn

and the double yellow centerline striping should be carried

through the intersection.

Will revise intersection markings

363 38(9) OperationsRemove the stop bars at the "intersection" (temporary sharp

turn) at Tasker and HillandaleWill revise intersection markings

364 38(9) Operations

Are two handicap ramps necessary for NW quadrant of

Tasker/Hillandale intersection? Confirm layout meets ADA

requirements.

Need to coordinate with roadway

design.

365 38(12) Operations

Route 11 SB striping should provide dedicated right turn

lane onto Route 37 WB ramp and carry one through lane

past the ramp before becoming two through lanes

Will revise right/through arrow to right

turn only arrow and revise lane

configuration in signal plan, Sheet 37(5).past the ramp before becoming two through lanes configuration in signal plan, Sheet 37(5).

366 39-4 Construction

The Utility drawings denotes Drainage STR. # 26-10. This

structure # needs to be changed to STR. 4-5 to match the

construction plan sheet #4.

Will revise structure number.

Page 30 of 34

Page 34: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

367 40(1) Roadside Mgmt.

The Plant Schedule on sheet 40(2) should be moved to this

sheet, along with deleting the "Fertilizer and Mulch" insert

and the planting details on sheet 40(2) (both of which are

covered in the Road & Bridge Standards). Reference

attachment sent from Scott Alexander to Tim Glickman on

9/23/2013.

Will revise. Will transfer information to

remain into one sheet. Will remove

items as described.

368 40(1) Roadside Mgmt.

Under General Notes, a note after #1 should be added

indicating which version of the Road & Bridge Standards

shall be followed.

Will revise.

369 40(1) Roadside Mgmt.

Under General Notes #3, the planting season is incorrectly

shown as March 15 through October 15. It should read

October 15 through March 15.

Will revise.

October 15 through March 15.

370 Contract Materials

Ensure that the following are included in the proposal:

SPCN for Pipe Backfill, SPCN for Embankments, SP for

Controlled Vibration, SP for Aggregate Density

Requirements, SP for Contractor Quality Control of

Aggregates and Select Material, SP for Low Permeability

Liners and SP for Select Material. These have been

provided via Mr. Alexander's folder.

Should be discussed with VDOT.

371 General L&D MOT challenges may dictate PR budget within CEI.To discuss, can add to CEI budget per

VDOT direction.

372 General LandscapeAn establishment period for the L construction needs to be

determined. Regular or 2 year?

Currently, plans call for an additional 2

year establishment period.determined. Regular or 2 year? year establishment period.

373 General LandscapeLandscape Architect of record for construction needs to be

determined; ideally designer.

Currently VDOT Landscape architect.

Current contract is only for design.

374 General Landscape

Inspections for soils, installation, and plant materials need

to be emphasized in the L summary so they will be included

in TRNSPRT and bids.

Will revise.

375 General Landscape

Maintenance for the planting establishment (waterings,

mulch, trash, and vegetative controls, etc.) need to be

refined on the summary so that the Regional L.A. can

provide the proper Special Provisions document to the

designer for editing.

Special Provision for additional plant

establishment was provided. See

SECTION 605 PLANTING (2 Year

Establishment Period).

To discuss. Old record drawings were

376 General MaterialsPlease follow-up regarding I-81 shoulder depth issue. Were

GPR or additional borings performed? (RoW)

To discuss. Old record drawings were

provided and showed inadequate

shoulder pavement depth. No additional

borings were performed.

377 General Materials Provide final soil survey report in digital format.Will provide pdf of final soil survey

report.

Page 31 of 34

Page 35: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

378 General Operations

Coordinate the work so that construction does not occur

concurrently with the project at I-81 Exit 317 (UPC 94847),

nor with the project on Route 277 (UPC 18003).

A note shall be added to the plans

instructing the Contractor to coordinate

construction activities with the I-81 Exit

317 and Rt 277 projects.

379 General OperationsCheck the spelling of Hillandale Road and be consistent

with the spelling on all plan sheets.

Will check spelling. Note: Hillandale

Lane is correct name of road.

380 General OperationsConsider wide load permits for Rt 37. Rt 37 lane width is

reduced to 11' in multiple phases.Should be discussed with VDOT.

381 General Operations

Show temporary pavement markings and all traffic control

devices (including traffic signals) on the temporary traffic Will comply.381 General Operations devices (including traffic signals) on the temporary traffic

control plans

Will comply.

382 General Operations

There are no Phase 1D Synchro Analysis Worksheets in

Appendix A (or maybe it is mislabeled as Phase 1C, and

Phase 1C is mislabeled as Phase 1B).

Will provide.

383 General Operations

Phases 2 and 3 reduce the RT 37 EB and WB movements

across I-81 to one lane each. All approaches will be

significantly over capacity in the AM and PM peak periods

(and probably throughout the day as well). All stakeholders

need to be aware that these reductions will create massive

delays. Reducing the EB LT movement onto I-81 NB to a This suggestion will be considered and

discussed with VDOT.single thru-left lane in particular will cause delays. One

suggestion is to route RT 37 EB -> I-81 NB left turn vehicles

thru the I-81 NB Ramp signal in the EB direction, U-turn at

Relocated Tasker Road and turn right onto I-81 NB. This

will require additional detour plans to be in place.

discussed with VDOT.

Page 32 of 34

Page 36: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

384 General Operations

During Phases 2-5, there is at least one I-81 Off-Ramp with

a LOS F in the AM or PM peak. A LOS F indicated the

movement is over capacity and in effect, will have an

infinitely increasing queue. If that is the case, it will be near

impossible to prevent queues from reaching the interstate.

The TMP does not provide any mitigation measures to

prevent that. This needs to be changed. The TMP and the

TTC Plans must incorporate very specific requirements on

what to do if queues start get close to the interstate on

either of the ramps. This is a major safety concern.

Preventing traffic from queuing back onto the interstate is

Should be discussed with VDOT.

Preventing traffic from queuing back onto the interstate is

important for NWRO to address and alleviate under normal

traffic operational conditions. We expect the contractor to

do the same during construction. The contractor shall be

responsible to not allow this to happen and shall provide

plans to prevent this from happening. These requirements

need to be incorporated into the contract documents and

construction plans.

385 General Operations

The TMP did not analyze vehicle queuing during any

construction phase. This needs to be done to identify and

mitigate the effects of queue spillback, inadequate turn lane

storage, and most importantly queuing on the I-81 off ramps storage, and most importantly queuing on the I-81 off ramps

reaching the interstate.

386 General Operations

The Contractor needs to submit copies of all the Synchro

files used in the TMP. This is necessary for review and will

be a valuable tool for VDOT during construction.

Will provide.

387 General Operations

Tasker Road design speed is shown as 40 MPH with a

posted speed limit of 35. Existing speed limit is posted as

45 MPH. A speed study will need to be completed to justify

this reduction.

Should be discussed with VDOT.

388 General LandscapeThe design Landscape Architect needs to be included in

invitations to the PAC.

Design team will coordinate with design

Landscape Architect before PAC

meeting to discuss outstanding issues.

Separate meeting/ conference call can invitations to the PAC.

Separate meeting/ conference call can

be set up if needed.

389

Special

Provision

For Section

605 Planting

Construction

Recommend a 1 year establishment period to avoid

unnecessary administrative cost and burden to the

Department in replacement of the 2 year establishment

period as shown in the Special Provision.

To discuss. See Item 371. Currently,

plans call for an additional 2 year

establishment period.

Page 33 of 34

Page 37: DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS … · 2014. 12. 11. · 8. Adding subgrade stabilization geotextile under Tasker Road and Hillandale Lane pavement structures. Due

Item Sheet No. Section Combined Comments Responses Meeting Resolutions

390 X149-156 MaterialsPer final soil survey report, this 4:1 slope could be steeper

(and reduce right-of-way costs).

4:1 slope is used under Future Route 37

extension from sta. 39+00 to 42+50 and

is already within proposed right of way.

2:1 slope could be used from sta. 42+50

(X154) to 45+00 (X156) to reduce

proposed temporary construction

easement for slopes. Note: The right of

way is proffered land from the

developer.

391 X47-49 MaterialsDon't show new pavement on bridge. Same for Sheets X56-

57.Will remove new pavement on bridge.391 X47-49 Materials

57.Will remove new pavement on bridge.

392 X56 Materials Label slopes. Will label slopes.

393 X70-75 Materials Comment missing.

394 X84 Materials2:1 slope is taller than 10' (see final soil survey report).

Same for Sheet X86.Will correct to 2.5:1 slope.

395 X90-95 MaterialsIs this undercut necessary? Explain need/method of

undercut. Same throughout cross-section sheets.

To discuss. Undercut called for in final

soil survey report, p. 25, based on

expected consolidation settlement.

Page 34 of 34