44

DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA
Page 2: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

ADDENDUM NO. 1

TO CONTRACT DOCUMENTS FOR: CITY OF NORFOLK DEPARTMENT OF UTILITIES PUMP STATION 23 – PHASE 4 WATER AND SANITARY SEWER REPLACEMENT This addendum forms a part of the contract documents and clarifies the revised documents as stated herein. This addendum must be acknowledged in the space provided in the proposal. Failure to acknowledge shall subject the Bidder to disqualification. Except as may be otherwise described, bidding requirements, materials, and workmanship, for the work described herein, shall conform to all requirements of the original Contract Documents. The following Addendum to the drawings and specifications is made a part of the project, and takes precedence over the section of the specifications in part, as originally written and over the drawings, in part, as originally drawn and/or written. This addendum consists of 43 pages, including this cover sheet.

SPECIFICATIONS: 1. Revised Bid Form (Section 102).

2. Questionnaire (Section 102) – must be submitted with sealed bid.

3. Revised Appendix D – Measurement and Payment: Entire section.

ATTACHMENTS

Minutes of Pre-bid Meeting

Attendance Sheet for Pre-bid Meeting

Drawings (C-02, D-05)

Bid Form (Section 102 pages 14 thru 17)

Questionnaire (Section 102 page 25 thru 29)

Appendix D – Measurement and Payment

END OF ADDENDUM

Page 3: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

1

Hampton Roads Office 2809 S Lynnhaven Rd Suite 350 Virginia Beach, VA 23452 Phone: (757) 497-0490

City of Norfolk PS 23 Service Area, Phase 4 Water and Sewer Replacement

Non Mandatory Pre-Bid Meeting Minutes

Wednesday, June 10, 2015 at 10:00 a.m.

Utilities – Conference Room

1. Leticia opened the meeting @ 10:05 and introduced the project and gave a

background and overview. The project was identified as being a continuation of

Phase 2 along Parkview Avenue primarily replacing water and sewer, connecting

from Densmore Place to Whit Avenue/Pretty Lake Avenue, Marlina Court and

adjacent connections to Redwing Avenue, Inlet Road, and Whit Avenue. She then

stated the last day to submit questions or clarifications was 12:00 noon on Friday,

June 12, 2015 and that any questions would be answered via an Addendum, which

would be published the following Monday, June 15, 2015, by 5:00 P.M.. She said

questions or clarifications should be addressed to her and copied to Alan.

2. The site constraints and challenges were discussed, specifically storage yard.

3. Leticia discussed all bidders must submit the Questionnaire as provided in Section

102 of the specifications with the bid.

4. Leticia discussed the apparent low bidder must complete and submit the American

Iron and Steel documents as provided in Appendix K (Attachment #6-9) of the

specifications prior to Notice to Proceed.

5. Questions from the contractors included:

A. Private property laterals and private property cleanouts are included in the bid

form. Are there any on this phase?

i. Clarification: Not all sewer cleanouts were found in the field during the

survey and design phase therefore a bid item description was added to

the bid form.

B. Are the VSMP permit fees ($2,700) from the City the same as DEQ?

Page 4: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

2

Hampton Roads Office 2809 S Lynnhaven Rd Suite 350 Virginia Beach, VA 23452 Phone: (757) 497-0490

i. Clarification: Yes, the fees are the same. SWPPP is a part of the VSMP

permit.

C. Notes on plans state the trenches for private sewer cannot be left open, no

exceptions. Please clarify since the work must be field verified by a code

inspector prior to backfill.

i. Clarification: Work performed on private property must comply with the

code inspector.

D. Will any additional full depth removal and replacement of pavement be

necessary specifically in areas where the proposed gravity sewer is deep and

less than 10 feet of horizontal separation from the proposed water main?

i. Clarification: Additional full removal and replacement will be necessary.

See revised hatching and note callout on attached Sheet 13 (Drawing

Number D-05). In addition, the limits for milling were revised at the

intersection of Densmore Place/Parkview Avenue.

E. Please confirm the total proposed linear footage of 8-inch gravity sewer.

i. Clarification: Total proposed quantity of 1,637 LF of 8” PVC main is

correct.

F. Please clarify the intent of milling and overlay depth range of 2 to 3 inches.

i. Clarification: Milling and overlay depth revised to 2 inches. See revised

note on attached Sheet 13 (Drawing Number D-05).

G. Please clarify the intent of Miscellaneous Concrete as it may include ADA

ramps, sidewalk, driveways and other concrete not within a specified bid item

number which each have a varying difference in unit cost thus making it difficult

to determine the appropriate unit cost.

i. Clarification: The intent was to include all concrete (except for

remove/replace curb/curb and gutter) work since it is anticipated only a

small portion of curb and gutter, modified valley gutter, and a few

driveway aprons that were to be replaced, and that this item was to cover

Page 5: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

3

Hampton Roads Office 2809 S Lynnhaven Rd Suite 350 Virginia Beach, VA 23452 Phone: (757) 497-0490

those and any other identified during construction. The quantity for this

bid item has been revised and also assigned a fixed unit price.

ii. Additional bid item numbers have been added including a new No. 54

– Concrete Sidewalk Replacement (SY), No. 55 - Residential Driveway

Apron (SY), and No. 56 – Modified Valley Gutter (SY). See attached

revised bid form and Appendix D – Measurement and Payment.

H. Should permanent pavement be included in the Flowable Fill measurement

and payment?

i. Clarification: No, the permanent pavement is quantified in Asphalt

Surface Course (SM-9.5A). The wording “permanent paving” was

removed in the measurement and payment description. See attached

revised Appendix D.

I. Should permanent pavement be included in the Manhole Removal

measurement and payment?

i. Clarification: No, the permanent pavement is quantified in Asphalt

Surface Course (SM-9.5A). The wording “permanent paving” was

removed in the measurement and payment description. See attached

revised Appendix D.

J. The right-of-way permit fee identified for this project appears incorrect based

on $1/SF of disturbed area.

i. Clarification: The right-of-way permit included as note #50 on Sheet 02

(Drawing Number X-01) of $1,100 is accurate and was confirmed with

the Right-of-Way department. The fee calculation of $1/SF multiplied by

the area of disturbance does not apply to City utility projects. This fee is

incidental and will not be paid as separate line item in the contract.

K. Please clarify how pavement demolition is quantified.

i. Clarification: Total width of asphalt for affected area as defined on plans

multiplied by the total length as defined on Sheet 13 (Drawing Number

D-05) multiplied by total inch depth (square yards-inch). The inch-depth

Page 6: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

4

Hampton Roads Office 2809 S Lynnhaven Rd Suite 350 Virginia Beach, VA 23452 Phone: (757) 497-0490

is based on the higher asphalt thickness per boring number per plan

sheet.

L. How is temporary pavement paid?

i. Clarification: Please see Paving Phasing Notes as shown on the

Pavement Phasing Plan and Details on Sheet 13 (Drawing Number D-

05). The Contractor can use 21A or crushed asphalt for trenches to meet

the placement and maintenance of daily temporary patching. Final

pavement is paid by separate bid line item.

M. There are 6” laterals on the job, but no separate line item for them. How does

the contractor get paid for these laterals and larger property line cleanouts?

i. Clarification: There are 6” laterals on this project due to duplex units and

multiple units sharing a single lateral. The laterals and property line

clean outs are to be paid the same regardless of size.

N. Several bid item measurement and payment descriptions include the wording

“placement and maintenance of daily temporary pavement patching.” Please

clarify.

i. Clarification: This phrase was removed from each measurement and

payment section.

6. After no further questions were brought forth, the meeting was adjourned.

7. Action Items:

A. Leticia to send Attachments:

i. Agenda

ii. Attendee sign-in sheet

B. H&S to send to Leticia the following:

i. Minutes from this meeting

ii. Draft Addendum with items noted above

Page 7: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA
Page 8: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

PARKVIEW AVENUE

INSET 1

SEE THIS SHEET

SCALE 1" = 10'

Page 9: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

KINGSTON AVENUE

RE

DW

IN

G

IN

LE

T R

OA

D

MA

RLIN

A C

OU

RT

DE

NS

MO

RE

P

LA

CE

AV

EN

UE

KINGSTON AVENUE

KERSEY AVENUE

PARKVIEW AVENUE

WH

IT

A

VE

NU

E

1S

T B

AY

S

TR

EE

T

E OCEAN VIEW AVENUE

Page 10: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 14 Pump Station 23 Service Area Phase 4 ADDENDUM No. 1 City of Norfolk

III. BID FORM Bids to be opened: Time 3:00 p.m., Wednesday, June 24, 2015, Work to be Completed in: Substantial Completion: 210 Calendar Days Final Completion: 240 Calendar Days Liquidated Damages: One Thousand Dollars and No Cents ($1,000.00)

per calendar day after time for Substantial Completion has expired. Five Hundred Dollars and No Cents ($500.00) per calendar day after time for Final Completion has expired.

Performance Bond: 100% Payment Bond: 100% Bid Security: 5% Contractor and owner recognize that time is of the essence of this agreement and that the owner will suffer financial loss if the work is not completed within the times specified, plus any extensions thereof allowed in accordance with the contract documents. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration preceding the actual loss suffered by the owner if the work is not completed on time. Accordingly, instead of requiring any such proof, owner and contractor agree that as liquidated damages for delay (but not as penalty), contractor shall pay owner One Thousand Dollars and No Cents ($1,000.00) for each calendar day that expires after the time specified for substantial completion until the work is substantially complete. After substantial completion, if contractor shall neglect, refuse, or fail to complete the remaining work within the contract time or any proper extension thereof granted by owner, contractor shall pay owner Five Hundred Dollars and No Cents ($500.00) for each calendar day that expires after the time specified for final completion and readiness for final payment until the work is completed and ready for final payment. If substantial completion is not achieved by the time of final completion then liquidated damages for both substantial and final completion shall run concurrently until substantial completion is achieved. To: Director of Utilities City of Norfolk, Virginia A. BID PRICE OPTION A - LUMP SUM BID “Not Used” OPTION B - COMBINATION LUMP SUM AND UNIT PRICE BID “Not Used”

Page 11: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 15 Pump Station 23 Service Area Phase 4 ADDENDUM No. 1 City of Norfolk

OPTION C - UNIT PRICE BID In compliance with the Bid Documents, titled Pump Station 23 Service Area - Phase 4 Sanitary Sewer and Water Replacement, all Addenda issued to date all of which are part of this Bid, the undersigned hereby proposes to furnish all items including materials, supervision, labor, and equipment in strict accordance with, said Contract Documents, for the sum of:

Item No. Item Description Unit Quantity Eligible/

Ineligible Unit Price Total Price

Water Distribution

1 6" PVC Main LF 266 I $ $

2 8" PVC Main LF 1,967 I $ $

3 6" Gate Valve EA 4 I $ $

4 8" Gate Valve EA 8 I $ $

5 Ductile Iron Fittings EA 41 I $ $

6 Fire Hydrant Assembly EA 4 I $ $

7 6" TS&V EA 4 I $ $

8 Blow-Off Valve EA 1 I $ $

9 3/4" Corporation Stop EA 51 I $ $

10 3/4" Type K Copper (Public) LF 820 I $ $

11 Meter Stop EA 51 I $ $

12 3/4" Type K Copper (Private) LF 50 I $ $

13 Cut & Cap EA 5 I $ $

14 Valve Abandonment EA 8 I $ $

15 New Meter Box EA 51 I $ $

16 Fire Hydrant Assembly Removal EA 2 I $ $

17 Select Backfill CY 750 I $ 35.00 $ 26,250.00

18 Select Bedding, No. 57 Stone Ton 260 I $ 38.00 $ 9,880.00

19 Test Pits (<3' deep) EA 5 I $ $

20 Plumbing Permit Allowance EA 10 I $ 46.92 $ 469.20

21 Plumbing Repair Allowance AL 1 I $ 1,000.00 $ 1,000.00

22 Undercut and Dispose CY 788 I $ $

23 Pavement Demolition SY-IN 15,059 I $ $

24 Aggregate Base Ton 997 I $ $

25 Asphalt Base Course, BM-25 Ton 850 I $ $

26 Asphalt Surface Course, SM-9.5A Ton 425 I $ $

SUBTOTAL WATER SYSTEM IMPROVEMENTS $

Page 12: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 16 Pump Station 23 Service Area Phase 4 ADDENDUM No. 1 City of Norfolk

Item No. Item Description Unit Quantity Eligible/

Ineligible Unit Price Total Price

Sanitary Sewer

27 8" PVC Main LF 1,637 E $ $

28 12" PVC Main LF 448 E $ $

29 Manhole (< 5.99' deep) EA 7 E $ $

30 Manhole (>6' to 8.99' deep) EA 4 E $ $

31 Manhole (> 9' deep) EA 1 E $ $

32 PVC Service Lateral (Public) LF 1,340 E $ $

33 PVC Service Lateral (Private) LF 250 I $ $

34 Property Line Cleanout EA 48 E $ $

35 Private Property Cleanout EA 5 I $ $

36 Plumbing Turnaround EA 2 I $ $

37 Flowable Fill CY 9 E $ $

38 Manhole Removal EA 8 E $ $

39 Main Line Cleanout Removal EA 2 E $ $

40 Main Line Cleanout Abandonment EA 2 E $ $

41 Select Backfill CY 3,570 E $ 35.00 $ 124,950.00

42 Select Bedding, No. 57 Stone Ton 850 E $ 38.00 $ 32,300.00

43 Test Pits (>6' to 9' deep) EA 1 E $ $

44 Test Pits (>9' to 12' deep) EA 2 E $ $

45 Test Pits (>12 ft deep) EA 3 E $ $

46 Plumbing Permit Allowance EA 10 I $ 46.92 $ 469.20

47 Plumbing Repair Allowance AL 1 I $ 1,000.00 $ 1,000.00

48 Undercut and Dispose CY 583 E $ $

49 Pavement Demolition SY-IN 15,059 E $ $

50 Aggregate Base Ton 997 E $ $

51 Asphalt Base Course, BM-25 Ton 850 E $ $

52 Asphalt Surface Course, SM-9.5A Ton 425 E $ $

SUBTOTAL SANITARY SEWER SYSTEM IMPROVEMENTS $

Page 13: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 17 Pump Station 23 Service Area Phase 4 ADDENDUM No. 1 City of Norfolk

Item No. Item Description Unit Quantity Eligible/

Ineligible Unit Price Total Price

Miscellaneous

53 Miscellaneous Concrete CY 100 I $ 300.00 $ 30,000.00

54 Concrete Sidewalk Replacement SY 214 I $ $

55 Residential Driveway Apron SY 134 I $ $

56 Modified Valley Gutter SY 69 I $ $

57 Remove / Replace Curb / Curb & Gutter LF 1,559 I $ $

58 Curb Inlet Removal EA 3 I $ $

59 Stormwater Manhole Removal EA 1 I $ $

60 Stormwater-RCP Removal LF 101 I $ $

61 24" RCP LF 10 I $ $

SUBTOTAL MISCELLANEOUS IMPROVEMENTS $

TOTAL OF ALL PRICES: $

In Words:

Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents. The prices quoted shall include without exception all materials, supervision, labor, equipment, appliances, clean-up, incidental items, applicable sales, use and other taxes, insurance, building permit or fees, and the Contractor's labor, overhead, profit, mobilization and other mark-ups, and in full accordance with the Contract Documents. Include allowance for waste where appropriate. The unit prices shall be maintained throughout the Contract Time. Unit prices shall be used in determining additions or deductions from the total Contract Price in the event of changes due to unforeseen conditions in the Work.

- THE REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK -

Page 14: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 25

Pump Station 23 Service Area Phase 4May 2015City of Norfolk

V. QUESTIONNAIRE

If requested by the Owner, the The following questions shall be answered in full by the Bidder, and returned

to the Owner within 72 hours. and submitted with the signed bid form.

1. Name of Company: __________________________________________________________

Trade Name (if different from Company Name): ___________________________________

Principal Office Address: _____________________________________________________

__________________________________________________________________________

Telephone No(s).: _________________________________________________________

Fax No(s).:_________________________________________________________________

a. If a Corporation, answer the following:

When Incorporated: ____________________________________________________

In What State: ________________________________________________________

Names and Addresses of Directors: ________________________________________

_____________________________________________________________________

_____________________________________________________________________

Names and Addresses of Shareholders: _____________________________________

_____________________________________________________________________

_____________________________________________________________________

b. If an Unincorporated Organization, answer the following:

Date of Organization: __________________________________________________

Names and Addresses of Owners or Members: ______________________________

____________________________________________________________________

____________________________________________________________________

Type and State of Organization: __________________________________________

c. If a Partnership, state whether Partnership is General or Limited:_________________

Names and Addresses of Owners or Partners:

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

Page 15: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 26

Pump Station 23 Service Area Phase 4May 2015City of Norfolk

2. a. How many years has this Bidder been in business as a Contractor under its present business

name?____________________________________________________

b. What are prior names of this Bidder, if any? __________________________________

______________________________________________________________________

3. How many years’ experience in this type of construction work has this Bidder had:

1) As a Contractor _______________ 2) As a Subcontractor _____________

4. Provide a list of uncompleted Contracts at present held by this Bidder (attach supplemental sheet ifnecessary):

Type of PercentageContract Work Amount Completed

________________________ _______________________ ___________ _____________

_______________________ _______________________ ___________ _____________

_______________________ _______________________ ___________ _____________

_______________________ _______________________ ___________ _____________

_______________________ _______________________ ___________ _____________

5. List the Bidder's crew foremen and supervisors proposed for this Project and their years of relatedexperience:

Years of Dates of EmploymentName Experience with Bidder

______________________ _______________________ _____________________

______________________ _______________________ _____________________

______________________ _______________________ _____________________

6. What construction equipment does this Bidder own that is available for the proposed work (attachsupplemental sheet if necessary)?

___________________________________________________________________________

___________________________________________________________________________

___________________________________________________________________________

Page 16: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 27

Pump Station 23 Service Area Phase 4May 2015City of Norfolk

7. Does this Bidder plan to subcontract any part of this work? If so, list name, address, yearsexperience, and type and amount of work to be performed by each subcontractor:

___________________________________________________________________________

___________________________________________________________________________

___________________________________________________________________________

8. Provide a list of projects similar in character and scope to the Work specified under this Contract

which have been successfully completed by this Bidder and proposed subcontractors or employees

with principal roles in this contract during the past three five years (attach supplemental sheet if

necessary).

(The term "completed" means accepted and final payment received from the Owner or authorizedrepresentative).

ContactOwner's Person

Location & Name/ (Name and Date ContractType of Work Address Telephone) Completed Price____________________________________________________________________________________

____________________________________________________________________________________

____________________________________________________________________________________

____________________________________________________________________________________

9. Have you ever performed work for a municipal corporation, local governing body, or similar agencypreviously? (If all such bodies are listed under 8, this question need not be completed).

_________________________________________________________________________________

_________________________________________________________________________________

_________________________________________________________________________________

10. a. Has this Bidder ever failed to complete any work awarded to it? If yes, give name of Owner,name of Bonding Company and circumstances:

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

Page 17: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 28

Pump Station 23 Service Area Phase 4May 2015City of Norfolk

b. Is this Bidder debarred by the Federal Government or by the Commonwealth of Virginia or byany other state, or by any town, city, or county?

Yes _________ No ___________ If yes, please provide details:

_____________________________________________________________________

_____________________________________________________________________

c. Has this Bidder ever had any judgements entered against it for the breach of contract forconstruction? If yes, please provide details:

_____________________________________________________________________

_____________________________________________________________________

d. Give a summary of your financial statement. (List assets and liabilities, use an insert sheet, ifnecessary).

__________________________________________________________________________

__________________________________________________________________________

__________________________________________________________________________

__________________________________________________________________________

___________________________________________________________

11. State approximate largest dollar volume of work performed by this Bidder in one year:

___________________________________________________________________________

12. Give two (2) Banking Institution References:

a. Name: _______________________________________________________________

Address: _____________________________________________________________

Credit Available: ______________________________________________________

b. Name: _______________________________________________________________

Address: _____________________________________________________________

Credit Available: ______________________________________________________

13. List three material suppliers and amount of credit available:

___________________________________ _________________________________

___________________________________ _________________________________

___________________________________ _________________________________

Page 18: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

December 2010 102 - 29

Pump Station 23 Service Area Phase 4May 2015City of Norfolk

14. List insurance coverage and amount (or attach certificate of insurance):

___________________________________ _________________________________Liability-Property

___________________________________ _________________________________Liability-Personal Injury

___________________________________ _________________________________Vehicle and Equipment

___________________________________ _________________________________Other - Identify

15. Bonding reference - List surety company and highest coverage:

___________________________________________________________________________

16. Have you or your authorized representative, personally inspected the location of the proposed Work,and do you have a clear understanding of the requirements of the Bid Documents?

_________________________________________________________________________________

_________________________________________________________________________________

_______________________________________________________________

The undersigned hereby authorizes and consents to any person, firm or corporation to furnish anyinformation requested by the Owner in verification of this statement of contractor's qualifications.Also, if it is the apparent low Bidder, the undersigned hereby agrees to furnish the Owner uponrequest, a complete and current financial statement:

Contractor:____________________________________________________________________

By:__________________________________________________________________________

Title: ______________________

Date: __________________

Page 19: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 1Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

1

Water Distribution

Items 1 & 2: PVC Main:Pipe shall be measured horizontally along the centerline of the main from the centerlineat the point of connection(s), or to the centerline of the plug at dead ends. Paymentshall be made based on the LINEAR FEET of new pipe installed, by size. There shallbe no reduction in linear feet for each valve, tapping sleeve and valve, and ductile ironfitting.

The unit price bid for this item shall be full compensation for the furnishing and installingof new C-900 PVC pipe, complete and in place. Also included in the cost will bestakeout, furnishing of a written cut sheet, dewatering, erosion and sediment control,tree protection, traffic control, excavation, sheeting and/or shoring in accordance withOSHA regulations, clearing, grubbing, grading, care and protection of existing utilitiesand structures, thrust protection, backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is also included. Alsoincluded are cleaning, flushing, testing, disinfecting, neutralization of disinfecting agent,# 10 gauge insulated copper wire and non-metallic marking tape (copper tracer wire willbe checked for continuity at, or prior to final inspection). In areas where new mains areplaced in soil, a minimum of 4” of clean pliable topsoil (submittal required) andvegetation that matches original vegetation in size and species are included. Sawcutting, removal, proper disposal and complete joint-to-joint replacement of: granitecurb, valley gutter and handicap ramps, in-kind, are also included items. With theexception of permanent paving, all right of way restoration and related landscaping shallbe incorporated in this item.

No payment, partial or final, shall be made for any part of a water distribution systemuntil that part of the system has been flushed, tested, disinfected and placed intoservice. Service lines shall be transferred to the new system immediately uponactivation of that system, or when deemed appropriate by the City’s inspector.

Items 3 & 4: Gate Valve:Payment shall be based on the number of EACH new gate valve installed, by size,complete and in place. The unit price bid for this item shall be full compensation for thefurnishing and installing of the new resilient seat gate valve, excavation, fittings and/oraccessories, testing and backfilling. Included in the costs will be the furnishing andplacement of an appropriately sized riser (riser material shall match type of pipeinstalled), an appropriately sized Norfolk standard valve box and lid, set to grade andvalve extension (valve extensions are required if the top of operating nut is more thanfour feet below ground elevation), complete and in place.

Page 20: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 2Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

2

All gate valves in the water system shall be resilient-seat gate valves that open to theright and will be operated (fully opened and fully closed) in the presence of the City’sinspector prior to installation.

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering,erosion and sediment control, tree protection, traffic control, excavation, sheeting and/orshoring in accordance with OSHA regulations, clearing, grubbing, grading, care andprotection of existing utilities and structures, thrust protection, backfilling andcompaction. Additionally the on site properly contained temporary storage and drying oftrench soils is included. Also included are cleaning, flushing, testing, disinfecting, andneutralization of disinfecting agent. In areas where new valves are placed in soil, aminimum of 4” of clean pliable topsoil (submittal required) and vegetation that matchesoriginal vegetation in size and species are included. Saw cutting, removal, properdisposal and complete joint-to-joint replacement of: granite curb, valley gutter andhandicap ramps, in-kind, are also included items. All right of way restoration and relatedlandscaping shall be incorporated in this item.

Note: 6” gate valves used in the fire hydrant assembly are considered to be part of thefire hydrant assembly and will be paid for under that item.

Item 5: Ductile Iron Fittings:Payment shall be based on the number of EACH new ductile iron fitting installed.Fittings included in this bid item are tees (with the exception of tees for fire hydrants,which are included in the fire hydrant assembly pay item), bends, crosses and reducersincluding all accessories, complete and in place. The cost of providing any other itemsthat may be commonly referred to as a fitting shall be included in the cost of the pipe.The unit price bid for this item shall be full compensation for the furnishing and installingof the new ductile iron fittings, complete and in place including MEGA LUGS, or otherapproved restraint methods, and restraint to the proper pipe length.

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering, erosionand sediment control, tree protection, traffic control, excavation, sheeting and/or shoringin accordance with OSHA regulations, clearing, grubbing, grading, care and protectionof existing utilities and structures, thrust protection, backfilling and compaction.Additionally the on site properly contained temporary storage and drying of trench soils isincluded. Also included are cleaning, flushing, testing, disinfecting, and neutralization ofdisinfecting agent. In areas where new fittings are placed in soil, a minimum of 4” of cleanpliable topsoil (submittal required) and vegetation that matches original vegetation in sizeand species are included. Saw cutting, removal, proper disposal and complete joint-to-joint replacement of: granite curb, valley gutter and handicap ramps, in-kind, are alsoincluded items. All right of way restoration and related landscaping shall be incorporatedin this item.

Page 21: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 3Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

3

Item 6: Fire Hydrant Assembly:Payment for this item will be based on the number of EACH new fire hydrant assemblyinstalled. Fire hydrants shall be manufactured within two (2) years of the date of Noticeto Proceed, and shall be in accordance with AWWA Specification C502, latest revision.The fire hydrant shall be installed with MEGA LUG or other approved restraint methods.All valves controlling the fire hydrant shall be resilient seat gate valves and will beinstalled with tie rod assemblies to the main line tee on the water main. The water mainbetween the fire hydrant and the main line tee shall be thickness class 52 ductile iron.

Included in the unit cost of the fire hydrant assembly are all costs of providing andinstalling 4 ½” fire hydrants complete and in place, including MEGA LUGS, or otherapproved restraint methods, all fittings and/or accessories from and including the mainline tee to the hydrant, tie rod restraint and thrust protection, 6” ductile iron main, valve,and tapping sleeve and valve (if required). The contractor shall supply and place aburlap bag or an “out of service” ring on the hydrant until such time as the hydrant isplaced into service. The bag or ring will be promptly removed when the main andhydrant are placed into service.

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering, erosionand sediment control, tree protection, traffic control, excavation, sheeting and/or shoringin accordance with OSHA regulations, clearing, grubbing, grading, care and protection ofexisting utilities and structures, thrust protection, backfilling and compaction. Additionallythe on site properly contained temporary storage and drying of trench soils is included.Also included are cleaning, flushing, testing, disinfecting, and neutralization of disinfectingagent. In areas where new fire hydrant assemblies are placed in soil, a minimum of 4” ofclean pliable topsoil (submittal required) and vegetation that matches original vegetationin size and species are included. Saw cutting, removal, proper disposal and completejoint-to-joint replacement of: granite curb, valley gutter and handicap ramps, in-kind, arealso included items. All right of way restoration and related landscaping shall beincorporated in this item.

Item 7: Tapping Sleeve and Valve:Payment shall be based on the number of EACH new tapping sleeve and valveinstalled, by size, complete and in place. The unit price bid for this item shall be fullcompensation for the furnishing and installing of a new appropriately sized tappingsleeve and resilient seat tapping valve, excavation, fittings and/or accessories, stainlesssteel bolts, testing, tapping and backfilling. Included in the costs will be the furnishingand placement of an appropriately sized riser (riser material shall match type of pipeinstalled), an appropriately sized Norfolk standard valve box and lid, set to grade andvalve extension (valve extensions are required if the top of operating nut is more thanfour feet below ground elevation), complete and in place.

Page 22: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 4Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

4

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering,erosion and sediment control, tree protection, traffic control, excavation, sheeting and/orshoring in accordance with OSHA regulations, clearing, grubbing, grading, care andprotection of existing utilities and structures, thrust protection, backfilling andcompaction. Additionally the on site properly contained temporary storage and drying oftrench soils is included. Also included are cleaning, flushing, testing, disinfecting, andneutralization of disinfecting agent. In areas where new tapping sleeve and valves areplaced in soil, a minimum of 4” of clean pliable topsoil (submittal required) andvegetation that matches original vegetation in size and species are included. Sawcutting, removal, proper disposal and complete joint-to-joint replacement of: granitecurb, valley gutter and handicap ramps, in-kind, are also included items. All right of wayrestoration and related landscaping shall be incorporated in this item.

All valves in the water system will be resilient seat valves that open to the right. Allvalves will be operated (fully opened and fully closed) in the presence of the City’sinspector prior to installation. Prior to tapping, all interior surfaces of the tapping sleeveand valve, and those portions of the tapping machine that will be enclosed when the tapis made, will be thoroughly cleaned and washed with chlorine bleach. The pipe couponwill be retrieved and delivered to the City’s inspector on a daily basis.

Item 8: Blow-Off Valve:Payment for this item will be based on the number of EACH new blow-off valve installedcomplete and in place.

The unit price bid for this item shall be full compensation for the furnishing and installingof the new blow-off valves complete and in place. Included in the costs will be thefurnishing and placement of a standard blow-off valve box and lid, set to grade.

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering, erosionand sediment control, tree protection, traffic control, excavation, sheeting and/or shoringin accordance with OSHA regulations, clearing, grubbing, grading, care and protection ofexisting utilities and structures, backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is included. Also includedare cleaning, flushing, testing, disinfecting, and neutralization of disinfecting agent. Inareas where blow off valves are placed in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are also includeditems. All right of way restoration and related landscaping shall be incorporated in thisitem.

Page 23: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 5Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

5

Item 9: Corporation Stop:Payment for this item will be based on the number of EACH new corporation stopinstalled by size.

The unit price bid for this item shall include all costs of furnishing and installing thecorporation stop complete and in place. This shall include tapping the main by the wettap method, installing the corporation stop and connecting the service line to thecorporation stop.

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering, erosionand sediment control, tree protection, traffic control, excavation, sheeting and/or shoringin accordance with OSHA regulations, clearing, grubbing, grading, care and protection ofexisting utilities and structures, backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is included. Also includedare cleaning and flushing. In areas where new corporation stops are placed in soil, aminimum of 4” of clean pliable topsoil (submittal required) and vegetation that matchesoriginal vegetation in size and species are included. Saw cutting, removal, properdisposal and complete joint-to-joint replacement of: granite curb, valley gutter andhandicap ramps, in-kind, are also included items. All right of way restoration and relatedlandscaping shall be incorporated in this item.

Item 10: Type K Copper (Public):Tubing shall be measured horizontally along the centerline of the service from thecenterline of the main to the meter stop / copper connection. Payment for this item willbe based on the LINEAR FEET of new tubing installed, by size.The unit price bid for this item shall be full compensation for the furnishing and installingof the new copper service lines located within the City’s right of way.

Included in the cost will be stakeout, dewatering, erosion and sediment control, treeprotection, traffic control, excavation, sheeting and/or shoring in accordance with OSHAregulations, clearing, grubbing, grading, care and protection of existing utilities andstructures, boring, jacking or similar approved method, backfilling and compaction.Additionally the on site properly contained temporary storage and drying of trench soilsis included. Also included are cleaning, flushing, testing, disinfecting, and neutralizationof disinfecting agent. In areas where new services are placed in soil, a minimum of 4”of clean pliable topsoil (submittal required) and vegetation that matches originalvegetation in size and species are included. Saw cutting, removal, proper disposal andcomplete joint-to-joint replacement of: granite curb, valley gutter and handicap ramps,in-kind, are also included items. All right of way restoration and related landscapingshall be incorporated in this item.

Note: No open cuts for service lines will be allowed unless authorized by the City’sinspector prior to the service installation.

Page 24: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 6Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

6

Item 11: Meter Stop:Payment for this item will be based on the number of EACH new meter stop / copperconnection installed by size.

The unit price bid for this item shall be full compensation for the furnishing and installingof the new meter stop complete and in place. This shall include, but not be limited toconnecting new meter stops, inspecting the service line on both sides of the meter forlead connections and / or lead pipe.

Included in the cost will be stakeout, furnishing of a written cut sheet, dewatering, erosionand sediment control, tree protection, traffic control, excavation, sheeting and/or shoringin accordance with OSHA regulations, clearing, grubbing, grading, care and protection ofexisting utilities and structures, backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is included. Also includedare cleaning, flushing, testing, disinfecting, and neutralization of disinfecting agent. Inareas where new meter stops are placed in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are also includeditems. All right of way restoration and related landscaping shall be incorporated in thisitem.

Item 12: Type K Copper (Private):Tubing shall be measured horizontally along the centerline of the service from the pointof connection on the private side of the meter to the point of connection at or near thehouse or plumbing turn-around. Payment for this item is based on the LINEAR FEET ofnew tubing installed by size.

The unit price bid for this item shall be full compensation for the furnishing and installingof the new copper tubing, including dewatering, erosion and sediment control, treeprotection, traffic control, excavation, hand digging, root pruning, replacement of brick,stone and faux brick, stone concrete pavers, removal and in-kind replacement offences, decks and vegetation, sheeting and/or shoring in accordance with OSHAregulations, clearing, grubbing, grading, care and protection of existing utilities andstructures, backfilling and compaction. Additionally the on site properly containedtemporary storage and drying of trench soils is included. Also included are cleaning,flushing. In areas where new services are placed in soil, a minimum of 4” of cleanpliable topsoil (submittal required) and vegetation that matches original vegetation insize and species are included. Saw cutting, removal, proper disposal and completejoint-to-joint replacement of: granite curb, valley gutter and handicap ramps, in-kind, arealso included items. All right of way restoration and related landscaping shall beincorporated in this item.

Page 25: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 7Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

7

Additionally, the joint-to-joint removal, proper disposal and replacement in-kind ofconcrete, brick or block walkways, patios or other structures are included in the cost ofthis item.

A licensed plumbing contractor shall perform all plumbing work.No payment shall be made for this item until all landscape restoration work is completeto the satisfaction of the City’s inspector.

Item 13: Cut and Cap:Payment for this item will be based on the number of EACH cut and cap performed. Theunit price bid for this item shall be full compensation for the cutting and removal of aportion of the existing main, MEGA LUGS, tie-rods or other approved restraints,furnishing and installing new pressurized caps on existing water mains within three feetof existing valves and restraint of pressurized caps to valves or other fittings and/oraccessories to remain on the system. The price also includes sealing the adjacent openend of the non-pressurized abandoned main with a brick and mortar plug.

Included in the cost will be stakeout, dewatering, erosion and sediment control, treeprotection, traffic control, excavation, sheeting and/or shoring in accordance with OSHAregulations, clearing, grubbing, grading, care and protection of existing utilities andstructures, thrust protection, backfilling and compaction. Additionally the on site properlycontained temporary storage and drying of trench soils is included. In areas whereexisting mains are cut and capped in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are alsoincluded items. All right of way restoration and related landscaping shall be incorporatedin this item.

Note: The City’s inspector shall verify all cut and caps prior to the contractor placing anybackfill. Any cut and cap excavations that are backfilled prior to verification will be subjectto re-excavation and backfilling by the Contractor at no additional cost to the City. Aftercut and caps have been performed, the Contractor shall assist the City’s inspector inopening hydrants along the abandoned portion of the main to assure that the main hasbeen properly abandoned. Hydrants that become out of service will immediately becovered with a burlap bag or an out of service ring. The contractor will removehydrants within 72 hours of them being placed out of service. Cut and caps willonly be performed during normal working hours (7:00 am to 4:30 pm Mondaythrough Friday), unless directed otherwise by the City’s inspector.

Page 26: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 8Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

8

Item 14: Valve Abandonment:Payment for this item will be based on the number of EACH valve abandoned.

The unit price bid for this item shall be full compensation for the valve abandonment(which shall include fully closing the valve), the removal of the existing valve box and lid,and delivery of the lid to the on site City’s inspector on a daily basis. The removal ofthe valve operating nut and its’ delivery to the on site City’s inspector is requiredon the date of removal. Included in the cost will be dewatering, erosion and sedimentcontrol, tree protection, traffic control, excavation, sheeting and/or shoring inaccordance with OSHA regulations, clearing, grubbing, grading, care and protection ofexisting utilities and structures, thrust protection, backfilling and compaction.Additionally the on site properly contained temporary storage and drying of trench soilsis included. In areas where existing valves are abandoned in soil, a minimum of 4” ofclean pliable topsoil (submittal required) and vegetation that matches original vegetationin size and species are included. Saw cutting, removal, proper disposal and completejoint-to-joint replacement of: granite curb, valley gutter and handicap ramps, in-kind, arealso included items. All right of way restoration and related landscaping shall beincorporated in this item.

Note: The gate valve that controls flow to the fire hydrant assembly will be abandonedas part of the fire hydrant assembly removal and will be paid for under that item.

Item 15: New Meter Box:Payment for this item will be based on the number of EACH new meter box installed.

The unit price bid for this item shall be full compensation for the furnishing and installingof the new Norfolk standard meter box and lid complete and in place, and set to grade.

Included in the cost will be the removal and proper disposal of the existing meter box, treeprotection, traffic control, excavation, hand digging, root pruning, replacement of brick,stone and faux brick, stone concrete pavers, clearing, grubbing, grading, care andprotection of existing utilities and structures, backfilling and compaction. Also includedare bricks to support the meter box and # 57 stone. In areas where meter boxes areplaced in soil, a minimum of 4” of clean pliable topsoil (submittal required) and vegetationthat matches original vegetation in size and species are included. Saw cutting, removal,proper disposal and complete joint-to-joint replacement of: granite curb, valley gutter andhandicap ramps, in-kind, are also included items. All right of way restoration and relatedlandscaping shall be incorporated in this item.

Item 16: Fire Hydrant Assembly Removal:Payment for this item will be based on the number of EACH fire hydrant assemblyremoved.

Page 27: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 9Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

9

The unit price bid for this item shall be full compensation for the fire hydrant assemblyremoval which shall include closing the existing hydrant valve, cutting and capping ofpressurized main segments, valve nut removal and delivery of the nut and valve lid tothe City’s inspector on the date of removal, excavation and the removal of the entire firehydrant and barrel assembly. Note: All hydrants manufactured within 10 years of thedate of the Notice to Proceed, shall be carefully removed in order to insure the intactand undamaged removal of the entire fire hydrant and barrel assembly, safely stored,transported and delivered to the Combined Operations facility located at 1316 BallentineBoulevard. The price also includes sealing the open end of the non-pressurized firehydrant main with a brick and mortar plug.

Included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, sheeting and/or shoring in accordance with OSHAregulations, clearing, grubbing, grading, care and protection of existing utilities andstructures, backfilling and compaction. Additionally the on site properly containedtemporary storage and drying of trench soils is included. In areas where existing firehydrant assemblies are abandoned in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are alsoincluded items. All right of way restoration and related landscaping shall be incorporatedin this item.

Note: The Contractor shall replace fire hydrants that are to be delivered to the City thatare damaged or lost during removal and / or transport, with a new fire hydrant at noadditional cost to the City.

Page 28: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 10Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

10

SANITARY SEWER ITEMS

Items 27 & 28: SDR-26 PVC Main:By size, pipe shall be measured horizontally in LINEAR FEET along the centerline ofthe main from manhole to manhole or from manhole to cleanout, excluding insidemanhole diameter (s) and two feet for the cleanout.

The unit price bid for this item shall be full compensation for furnishing and installingnew PVC (SDR 26) sanitary sewer mains and wyes or other approved connectors,complete and in place. Also included in the cost will be Select Bedding No. 57 stone asper Pipe Bedding Detail, stakeout, furnishing of a written cut sheet, dewatering, erosionand sediment control, tree protection, traffic control, excavation, sheeting and/or shoringin accordance with OSHA regulations, clearing, grubbing, grading, care and protectionof existing utilities and structures, backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is also included. Inareas where new PVC mains are placed in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are alsoincluded items. With the exception of permanent paving, all right of way restoration andrelated landscaping shall be incorporated in this item.

Also included are the by-pass pumping or any other approved method to maintainexisting sewer flow, enclosure of by-pass pump, removal of existing pipe (whererequired), drop connections at existing drop manholes, connections to existing mainsand manholes, reconnection of existing and active service laterals, boring or jacking,testing, and post-installation TV inspection and video recording.

As part of the submittal process, the Contractor shall indicate what method is to be usedto maintain line and grade on the proposed main. The invert elevation of each newlyinstalled sanitary sewer manhole shall be verified in the presence of the City’sinspector prior to continuing with the installation of the sewer main. Thetolerance shall be based on the current HRPDC standards.

Post TV includes: The camera footage counter shall be set to “0.00” at the centerline ofthe beginning manhole frame. The recorded video shall be continuous and uninterruptedfor the pipe segment being examined. The video (videotape and / or DVD, shall include:

ONLY “AMERICAN IRON AND STEEL” PRODUCTS (INCLUDED BUT NOTLIMITED TO MANHOLE AND CLEANOUT CASTINGS) WILL BE PERMITTEDFOR USE ON PROJECTS FUNDED BY THE VIRGINIA CLEAN WATERREVOLVING LOAN FUND (VCWRLF).

Page 29: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 11Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

11

official project title, contracting party (i.e. Norfolk Utilities, NRHA, VDOT, developer),contractor’s name, street name, manhole ID numbers, direction of video and flow, dateand time video was recorded, continuous counter text, pipe size and material, audio andtext call outs of laterals. A written log shall be provided that duplicates the informationfound on the video.

Items 29 - 31: Pre-Cast Manhole:Payment for this item will be based on the number of EACH new pre-cast manhole thatis installed in the specified depth categories. For payment, depth is measured from therim of the manhole casting down to the lowest invert of the pipe that can be measuredwhen the survey rod is held vertically. Unit Cost for manhole will result in a decrease oflinear feet of main based on inside manhole diameter.

The unit price bid for this item shall be full compensation for furnishing and installing therequired Norfolk standard pre-cast manhole, complete and in place. This cost shallinclude an adjustable manhole frame, dust cover, new stainless steel Rainstoppermanhole insert as manufactured by Southwestern Packing & Seals or approved equal,outside drops if needed, connections to the main line sewer and service laterals. Alsoincluded in the cost will be stakeout, furnishing of a written cut sheet, dewatering,erosion and sediment control, tree protection, traffic control, excavation, sheeting and/orshoring in accordance with OSHA regulations, testing, clearing, grubbing, grading, careand protection of existing utilities and structures, backfilling and compaction.Additionally the on site properly contained temporary storage and drying of trench soilsis also included. In areas where new manholes are placed in soil, a minimum of 4” ofclean pliable topsoil (submittal required) and vegetation that matches original vegetationin size and species are included. Saw cutting, removal, proper disposal and completejoint-to-joint replacement of: granite curb, valley gutter and handicap ramps, in-kind, arealso included items. All right of way restoration and related landscaping shall beincorporated in this item. Also included is the by-pass pumping or any other approvedmethod to maintain existing sewer flow, and enclosure of by-pass pump.The invert elevation of each newly installed sanitary sewer manhole shall beverified in the presence of the City’s inspector prior to continuing with theinstallation of the sewer main. The tolerance shall be based on the currentHRPDC standards.

No payment request shall be made for this item until all landscape restoration work iscomplete to the satisfaction of the City’s inspector.

Note: When ordering a pre-cast manhole, an allowance should be made for at least oneadjustment ring below the casting.

Page 30: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 12Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

12

Item 32: PVC Service Lateral (Public):By size, pipe shall be measured horizontally on the ground along the centerline of thelateral from the centerline of the sewer main (inside edge of manhole for lateralsconnected to manholes) to the center of the newly installed property line clean out, or tothe point of connection to the existing lateral. Payment for laterals shall be measuredbased on the LINEAR FEET of new pipe installed, complete and in place. The lateralpipe material shall match the material of the main line.

Included in the cost is furnishing and installing SDR 26 PVC service lateral lines locatedwithin the City’s right of way. This cost shall include the locating of, and connection to,existing service lateral at new or existing manholes, or mains, including approvedsaddles or fittings and/or accessories.

Also included in the cost will be stakeout, furnishing of a written cut sheet, dewatering,erosion and sediment control, tree protection, traffic control, excavation, sheeting and/orshoring in accordance with OSHA regulations, clearing, grubbing, grading, care andprotection of existing utilities and structures, backfilling and compaction. Additionally theon site properly contained temporary storage and drying of trench soils is also included.In areas where new service laterals are placed in soil, a minimum of 4” of clean pliabletopsoil (submittal required) and vegetation that matches original vegetation in size andspecies are included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are alsoincluded items. All right of way restoration and related landscaping shall be incorporatedin this item.

No payment request shall be made for this item until all landscape restoration work iscomplete to the satisfaction of the City’s inspector.

Item 33: PVC Service Lateral (Private):By size, pipe shall be measured horizontally along the centerline of the lateral from thecenterline of the newly installed property line clean out to the point of connection to theexisting lateral, or to within five feet of the building or house. Payment for lateral pipeshall be measured based on the LINEAR FEET of new pipe installed, complete and inplace.

The unit price bid for this item shall be full compensation for furnishing and installingSDR-26 PVC service lateral lines located on private property. This cost shall includethe locating of, and connection to, the existing service or new lateral with approvedfittings and/or accessories and the abandonment or removal of the existing lateral. Alsoincluded in the cost will be stakeout, furnishing of a written cut sheet, dewatering,erosion and sediment control, tree protection, hand digging, root pruning, replacementof brick, faux stone and faux brick, traffic control, excavation, sheeting and/or shoring inaccordance with OSHA regulations, clearing, grubbing, grading, care and protection of

Page 31: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 13Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

13

existing utilities and structures, backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is also included. Inareas where new private service laterals are placed in soil, a minimum of 4” of cleanpliable topsoil (submittal required) and vegetation that matches original vegetation insize and species are included. Saw cutting, removal and in-kind replacement of fences,decks, vegetation, sidewalk, driveway and driveway apron, in-kind, are also includeditems. All restoration and related landscaping shall be incorporated in this item.

Additionally, the joint-to-joint removal, proper disposal and replacement in-kind ofconcrete, brick or block walkways, patios or other structures are included in the cost ofthis item.

A licensed plumbing contractor shall perform all plumbing work.

No payment request shall be made for this item until all landscape restoration work iscomplete to the satisfaction of the City’s inspector.

Item 34: Property Line Cleanout:Payment for this item will be based on the number of EACH new property line cleanout,by size that is installed.

The unit price bid for this item shall be full compensation for furnishing and installing theNorfolk standard property line cleanout, complete and in place. This cost shall includeconnection to the service lateral with approved fittings and/or accessories, riser pipe,frame and lid. The removal of existing property line cleanouts are included in this cost ifthe property line cleanout being removed is within a five foot radius of the newlyinstalled property line cleanout. Also included in the cost will be stakeout, furnishing of awritten cut sheet, dewatering, erosion and sediment control, tree protection, rootpruning, traffic control, excavation, hand digging, sheeting and/or shoring in accordancewith OSHA regulations, clearing, grubbing, grading, care and protection of existingutilities and structures, placement and maintenance of daily temporary pavementpatching backfilling and compaction. Additionally the on site properly containedtemporary storage and drying of trench soils is also included. In areas where a newproperty line cleanout is placed in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are alsoincluded items. All in-kind replacement of fences, decks and vegetation, all restorationand related landscaping shall be incorporated in this item.

Additionally, the joint-to-joint removal, proper disposal and replacement in-kind ofconcrete, brick or block walkways, patios or other structures are included in the cost ofthis item.

Page 32: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 14Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

14

Item 35: Private Property Cleanout:Payment for this item will be based on the number of EACH new private propertycleanout that is installed.

The unit price bid for this item shall be full compensation for furnishing and installing theprivate property cleanout, complete and in place. These private property cleanouts willbe placed at the house, at bends or at any change in direction or as directed by thePlumbing Inspector, in conjunction with the replacement of service laterals on privateproperty. This cost shall include connection to the service lateral with approved fittingsand/or accessories, frame and lid. The removal of existing private property cleanoutsare included in this cost if the private property cleanout being removed is within a fivefoot radius of the newly installed private property cleanout.

Also included in the cost will be dewatering, erosion and sediment control, treeprotection, root pruning, traffic control, excavation, hand digging, sheeting and/orshoring in accordance with OSHA regulations, clearing, grubbing, grading, care andprotection of existing utilities and structures, placement and maintenance of dailytemporary pavement patching backfilling and compaction. Additionally the on siteproperly contained temporary storage and drying of trench soils is also included. Inareas where new private property cleanout is placed in soil, a minimum of 4” of cleanpliable topsoil (submittal required) and vegetation that matches original vegetation insize and species are included. Saw cutting, removal, proper disposal and completejoint-to-joint replacement of: granite curb, valley gutter and handicap ramps, in-kind, arealso included items. In-kind replacement of fences, decks and vegetation, allrestoration and related landscaping shall be incorporated in this item.

Additionally, the joint-to-joint removal, proper disposal and replacement in-kind ofconcrete, brick or block walkways, patios or other structures are included in the cost ofthis item.

Private property cleanouts are to be installed in accordance with the BOCANational Plumbing Code by a licensed plumbing contractor.

No payment request shall be made for this item until all landscape restoration work iscomplete to the satisfaction of the City’s inspector.

Item 36: Plumbing Turnaround:Payment for this item will be based on the number of EACH plumbing turnaround that isperformed.

The unit price bid for this item shall be full compensation for furnishing and installing,complete and in place, all materials necessary to change the direction of the existingsanitary sewer lateral underneath the house and to extend the piping through the

Page 33: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 15Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

15

foundation wall to five feet past the outside wall of the house, or to route the seweraround the house to five feet past the front wall of the house. This pay item includes anyand all repairs to foundation walls. In areas where a new plumbing turn-around isplaced in soil, a minimum of 4” of clean pliable topsoil (submittal required) andvegetation that matches original vegetation in size and species are included.

Plumbing turnarounds are to be installed in accordance with the BOCA NationalPlumbing Code by a licensed plumbing contractor.

No payment request shall be made for this item until all landscape restoration work iscomplete to the satisfaction of the City’s inspector.

Item 37: Flowable Fill:Payment for this item is based on the CUBIC YARDS of flowable fill used as determinedby delivery tickets received at the job site on a daily basis and as calculated. This payitem shall include costs for plugging sewer pipe (s), furnishing and placing flowable fillmaterial (EZ Flow # 40, GRT-11, or approved equal) in pipes to be abandoned in themanner described in the specifications, shown on the Construction Drawings or asdirected by the City’s inspector. Included in the price is excavation, backfilling, temporarypaving, concrete and/or granite curb / curb and gutter, valley gutter, handicap ramps,sidewalk, driveway, and driveway apron replacement in-kind, area restoration and anyother cost not included in any other pay item.

Item 38: Manhole Removal:Payment for this item will be based on the number of EACH manhole that is removed.

The manhole removal pay item shall include all costs associated with the excavation andcomplete removal of all of the brick/mortar or concrete for the entire manhole, down tothe base slab to the satisfaction of the City’s inspector. Any associated pipe entering themanhole to be removed will be cut a minimum of 2 feet from the outside of the manhole.This piping shall be removed as part of this bid item. Pipes that are cut, shall be pluggedand filled with flowable fill. This pay item includes removal of the frame, dust cover andlid, and delivery of the manhole dust cover and lid to the City’s inspector on a daily basis.

Also included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, sheeting and/or shoring in accordance with OSHA regulations,clearing, grubbing, grading, care and protection of existing utilities and structures,backfilling and compaction. Additionally the on site properly contained temporary storageand drying of trench soils is also included. In areas where existing manholes are removedin soil, a minimum of 4” of clean pliable topsoil (submittal required) and vegetation thatmatches original vegetation in size and species are included. Saw cutting of pavementand concrete, the removal, proper disposal and complete joint-to-joint replacement of:

Page 34: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 16Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

16

granite curb, valley gutter and handicap ramps, in-kind, are also included items. With theexception of permanent paving, all right of way restoration and related landscaping shallbe incorporated in this item.

Item 39: Main Line Cleanout Removal:Payment for this item will be based on the number of EACH main line cleanout that isremoved. Cleanouts removed to install new manholes are included in the price of themanhole.

The main line cleanout removal shall include the removal of the existing main linecleanout and lid, removal of 18” of riser pipe (minimum), plugging the open end of theriser, filling with flowable fill, and delivery of the cleanout lid to the City’s inspector on adaily basis.

Also included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, clearing, grubbing, grading, care and protection of existingutilities and structures, backfilling and compaction. Additionally the on site properlycontained temporary storage and drying of trench soils is also included. In areas wheremain line cleanouts are abandoned in soil, a minimum of 4” of clean pliable topsoil(submittal required) and vegetation that matches original vegetation in size and speciesare included. Saw cutting, removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are also includeditems. All right of way restoration and related landscaping shall be incorporated in thisitem.

Item 40: Main Line Cleanout Abandonment:Payment for this item will be based on the number of EACH main line cleanout that isabandoned.

The main line cleanout abandonment pay item shall include all costs of the removal ofthe frame and lid and the top 3 feet (minimum) of the cleanout. Also included is theplugging of the cleanout openings and filling the remainder of the cleanout with flowablefill, compaction and complete restoration of the area to its’ original condition. This payitem includes delivery of the cleanout lid to the City’s inspector on a daily basis.

Also included in the cost will be stakeout, furnishing of a written cut sheet, dewatering,erosion and sediment control, tree protection, traffic control, excavation, sheeting and/orshoring in accordance with OSHA regulations, clearing, grubbing, grading, care andprotection of existing utilities and structures, backfilling and compaction. Additionally theon site properly contained temporary storage and drying of trench soils is also included.In areas where existing mains or services are abandoned in soil, a minimum of 4” of

Page 35: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 17Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

17

clean pliable topsoil (submittal required) and vegetation that matches original vegetationin size and species are included.

There shall be no compensation for cleanouts that are removed in the course ofinstallation of a new and / or replacement service lateral. The cost of such removal andthe delivery of the lid to the City’s inspector shall be included in the cost of the installationof the service lateral.

- REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK -

Page 36: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 18Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

18

MISCELLANEOUS

Items 17 & 41: Select Backfill:Payment for this item will be based upon the material placed in the trench; no paymentwill be made for stored materials. Delivery tickets must be given to the City’sinspector on a daily basis and will NOT be accepted with monthly invoices. Selectbackfill will be measured and paid for by the CUBIC YARD at the established price of$35.00 per CUBIC YARD. This item includes placement and compaction.

The City’s inspector shall approve select backfill such as borrow sand or other commongranular fill hauled to the job site for use.

A delivery ticket shall accompany each load of select backfill material. Each ticket willbe serially numbered, list the company supplying the fill material, truck number of trucksdelivering material, date, size of load, and the project where delivered. In the event amaterial delivery ticket and delivery do not correspond, the City’s inspector may refusethe delivery and / or payment until such conditions are corrected to the satisfaction ofthe City’s inspector. Payment shall include the proper removal, replacement anddisposal of surplus material.

The Contractor shall designate the source of material and provide appropriate data aspart of the submittal process. In the event borrow sand is stored at the project site, it shallbe kept at a completely separate location from native soils which are also stored at theconstruction site.

Items 18 & 42: Select Bedding, No. 57 Stone:Payment for this item, when properly installed for water main, sewer forcemain or asdirected by the City will be based upon the material placed in the trench; no paymentwill be made for stored materials. Delivery tickets must be given to the City’sinspector on a daily basis and will NOT be accepted with monthly invoices. Selectbedding, No. 57 stone, will be measured and paid for by the TON at the establishedprice of $38.00 per ton.

The Contractor shall designate the source of material and provide appropriate data aspart of the submittal process. The City’s inspector shall approve select bedding materialhauled to the job site for use.

Payment will only be made for select bedding used during the installation of pipe workand will not be paid for when in the sole opinion of the City’s inspector, properdewatering methods have not been used. Select bedding required for the installation ofmanholes and hydrants and where otherwise shown on the drawings will not bemeasured for payment as such, its’ costs shall be included in the unit prices bid forthose items.

Page 37: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 19Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

19

A delivery ticket shall accompany each load of select bedding material. Each ticket willbe serially numbered, list the company supplying the fill material, truck number of trucksdelivering material, date, size of load, and the project where delivered. In the event amaterial delivery ticket and delivery do not correspond, the City’s inspector may refusethe delivery and / or payment until such conditions are corrected to the satisfaction of theCity’s inspector. Payment shall include the proper removal, replacement and disposal ofsurplus material.

Items 19 and 43 - 45: Test Pits:Payment for this item will be based on the number of EACH test pit performed that ismade in the specified depth categories. The depth is measured from the lowestauthorized point of the excavation to the top of the ground at the point of excavation.

Included in the unit cost of the test pits are all costs of locating buried utilities orstructures by non-destructive, open cut methods (for the purpose of obtainingelevations) and where directed by the City’s inspector.

Included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, sheeting and/or shoring in accordance with OSHAregulations, clearing, grubbing, grading, care and protection of existing utilities andstructures, backfilling and compaction. Additionally the on site properly containedtemporary storage and drying of trench soils is included. In areas where test pits areplaced in soil, a minimum of 4” of clean pliable topsoil (submittal required) andvegetation that matches original vegetation in size and species are included. Sawcutting, removal, proper disposal and complete joint-to-joint replacement of: granitecurb, valley gutter and handicap ramps, in-kind, are also included items. All right of wayrestoration and related landscaping shall be incorporated in this item.

Any underground utilities, which are uncovered in the normal course ofconstruction, will not be considered as test pits.

Items 20 & 46: Plumbing Permit Allowance:Payment for this item will be based on the number of EACH plumbing permit obtained.The amount of $46.92 is the established price. The cost of the permit is $40.80 plus15% for overhead and profit.

This pay item shall be full reimbursement for all obtained plumbing permits for thereplacement of water or sewer service lines on private property. The Contractor shall bereimbursed for the actual number of permits obtained as evidenced by the permitssubmitted to and approved by the City’s inspector. Permits shall be submitted withmonthly invoices.

Page 38: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 20Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

20

Items 21 & 47: Plumbing Repair Allowance:Payment for this item will be based on the ACTUAL COST of the minor plumbing repairwork on private property plus 15% overhead and profit. Invoices from the plumber mustaccompany the Contractor’s monthly invoice.

A licensed plumbing contractor shall perform all plumbing work.

This pay item shall be full reimbursement for minor plumbing repair work on servicelines on private property. Payment under this item shall be made only when the defect isdetermined to be pre-existing and the City’s inspector has authorized the repair work inwriting prior to execution of the repair work. All necessary landscape restoration shallbe included in the costs.

No payment shall be made for this item until all landscape restoration work is completeto the satisfaction of the City’s inspector.

Items 22 & 48: Undercut and DisposePayment for this item will be based on daily totals in CUBIC YARDS agreed to by theContractor’s superintendent and the City’s inspector. This item shall only be used afterbeing authorized by the City’s inspector. The purpose of this item is to undercut anddispose unstable areas of the roadway outside of pipe trenches during the road rebuildingprocess.

Quantities shall be measured beginning from the bottom of the proposed pavementsection. Replacement materials shall be Select Backfill, Aggregate Base, or nativematerials as approved by the City Inspector.

Included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, sheeting and/or shoring in accordance with OSHA regulations,clearing, grubbing, grading, care and protection of existing utilities and structures,backfilling and compaction. Also included are the Saw cutting, removal, proper disposaland complete joint-to-joint replacement of: granite and concrete curb, curb and gutter,valley gutter, handicap ramps, sidewalk, driveway and driveway apron in kind are alsoincluded items. All right of way restoration, with the exception of permanent pavementreplacement, and all related landscaping shall be incorporated in this item.

Items 23 & 49: Pavement Demolition:Payment for this item shall be for each SQUARE YARD-INCH of asphalt concretepavement or concrete pavement demolished. Pavement shall be demolished/milled asshown on the Contract Drawings, described in the Specifications, or as directed by theCity’s inspector. Pavement milling is included in this pay item.

Page 39: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 21Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

21

The price shall be full compensation for the demolition/milling operation, saw cutting,removal and proper disposal of existing pavement, and for all materials, tools, equipment,and incidentals required to complete the work in its entirety. All demolished/milledmaterial becomes the property of the contractor.

Items 24 & 50: Aggregate Base:Payment for this item will be based upon the DAILY presentation of delivery tickets to theCity’s inspector. Delivery tickets must be given to the City’s inspector on a dailybasis and will NOT be accepted with monthly invoices. The costs shall include thefurnishing and placement of aggregate base material (VDOT No. 21A), or as directed bythe City’s inspector, in conformance with lines, grades and thickness shown on theContract Drawings. Included shall be the cost of sub-grade preparation includingexcavation, grading and sub-grade compaction as specified 21A Aggregate will bemeasured and paid for by the TON. The City’s inspector shall approve in advance 21AAggregate hauled to the job site for replacement unstable areas of the roadway outsideof pipe trenches during the road rebuilding process.

A delivery ticket shall accompany each load of 21A material. Each ticket will be seriallynumbered, list the company supplying the fill material, truck number of trucks deliveringmaterial, date, size of load, and project where delivered. In the event a material deliveryticket and delivery do not correspond, the City’s inspector may refuse the delivery ofpayment until such conditions are corrected to the satisfaction of the City’s inspector.

The Contractor shall designate the source of material and provide appropriate data aspart of the submittal process.

Items 25 & 51: Asphalt Base Course, BM-25:Payment for this item shall be for each TON that is placed as specified, based upon theDAILY presentation of delivery tickets to the City’s inspector. Delivery tickets must begiven to the City’s inspector on a daily basis and will NOT be accepted with monthlyinvoices. Included in the costs shall be the furnishing and placement of the asphalt basecourse B-25 material in conformance to lines, grades and thickness shown on theContract Drawings, as directed by the City’s inspector, or as described in thespecifications. Tack coat is included in the cost of this item. This pay item includesmaterial used as either temporary or permanent pavement.

Items 26 & 52: Asphalt Surface Course, SM-9.5A:Payment for this item shall be for each TON that is placed as specified, based upon theDAILY presentation of delivery tickets to the City’s inspector. Delivery tickets must begiven to the City’s inspector on a daily basis and will NOT be accepted with monthlyinvoices. Included in the costs shall be the furnishing and placement of the asphalt

Page 40: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 22Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

22

surface course SM-9.5 material in conformance to lines, grades and thickness shown onthe Contract Drawings, as directed by the City’s inspector, or as described in thespecifications. Tack coat is included in the cost of this item. This pay item includesmaterial used as either temporary or permanent pavement.

Item 53: Miscellaneous Concrete:Payment for this item shall be for each CUBIC YARD of concrete installed. . The intentof this pay item is to provide compensation for isolated areas of in-kind concretereplacement when not applicable to any other line item. Additional concretereplacement not previously quantified in the project documents shall be agreed to by theContractor’s superintendent and the City’s inspector prior to installation. This pay itemincludes any concrete work not specifically included in an established pay item. Thisitem will be measured and paid for by the CUBIC YARD at the established price of$300.00 per CUBIC YARD.

Included in the price are all costs associated with providing the accurate placement ofconcrete in accordance with Department of Utilities and Public Works specifications.Concrete shall be replaced in-kind from joint-to-joint for each section of replacementwork.

Also included are stakeout, saw cutting of pavement and concrete, excavation, bedding,form work installation and removal, erosion and sediment control, traffic control,concrete removal and proper disposal, clearing, grubbing, grading, care and protectionof existing utilities and structures, and the installation of truncated domes athandicapped ramps. All right of way restoration including associated adjacent pavingand related landscaping is also included.

No payment shall be made for this item until all landscape restoration work is completeto the satisfaction of the City’s inspector.

Item 54: Concrete Sidewalk Replacement:Measurement for this item will be based on the number of SQUARE YARDS of concretethat is placed for a sidewalk to be replaced.

The intent of this pay item is to provide compensation when a sidewalk is to be replacedor installed within the project. All other pay items include the joint to joint replacement ofcurb / curb and gutter as part of their unit prices.

Included in the unit cost of sidewalk are all costs of providing and the accurate placementof concrete, (in compliance with public works specifications), where directed by theEngineer. Expansion joint(s) will be placed in new sections of sidewalk per the details.

Page 41: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 23Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

23

Costs included are excavation, bedding, form work, erosion and sediment control, trafficcontrol, concrete removal and proper disposal, clearing, grubbing, grading, care andprotection of existing utilities and structures. All right of way restoration and relatedlandscaping is also included.

Item 55: Residential Driveway Apron:Measurement for this item will be based on the number of SQUARE YARDS ofconcrete that is placed for the new driveways aprons, by type installed.

Included in the unit cost of driveway aprons are all costs of providing and the accurateplacement of concrete (in accordance with Public Works specifications), where directedby the City’s inspector. Without exception, all driveway aprons will be replaced in-kindfrom joint-to-joint with at least one expansion joint in each section of replacement work.Also included are, stakeout, saw cutting of pavement and concrete, excavation,bedding, form work installation and removal, erosion and sediment control, trafficcontrol, driveway permits, concrete removal and proper disposal, clearing, grubbing,grading, care and protection of existing utilities and structures. All right of wayrestoration including associated adjacent paving and related landscaping is alsoincluded.

Damages to existing driveway apron that was caused by the contractor and was notexpected to be damaged by the construction work shall be replaced at the contractor’sexpense.No payment shall be made for this item until all landscape restoration work is completeto the satisfaction of the City’s inspector.

Item 56: Modified Valley Gutter:Payment for this item shall be for each SQUARE YARD of concrete valley gutter installed.Included in the price are all costs of providing and accurate placement of concrete valleygutter including base preparation in accordance with the Contract Drawings andspecifications, or as directed by the Engineer. Valley gutters shall be constructed using ahigh early strength concrete. The intent of this pay item is to provide compensation whenadditional, in-kind valley gutter work is to be performed within the project. All other payitems include the joint-to-joint replacement of valley gutter as part of their unit prices.Without exception, all valley gutters will be replaced from joint-to-joint. At least oneexpansion joint will be placed in each section of replacement work.

Also included are stakeout, saw cutting of pavement and concrete, excavation, bedding,form work installation and removal, erosion and sediment control, traffic control, concreteremoval and proper disposal, clearing, grubbing, grading, care and protection of existingutilities and structures. All right of way restoration including associated adjacent pavingand related landscaping is also included.

Page 42: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 24Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

24

No payment shall be made for this item until all landscape restoration work is completeto the satisfaction of the Engineer.

Item 57: Remove / Replace Curb / Curb & Gutter:Payment for this item will be based on the number of LINEAR FEET installed.

Included in the unit cost of curb/curb and gutter are all costs of providing and accurateplacement of concrete (in compliance with Public Works specifications), where directedby the City’s inspector. Without exception, all curb / curb and gutter will be replacedfrom joint-to-joint. At least one expansion joint will be placed in each section ofreplacement work.

Also included are stakeout, saw cutting of pavement and concrete, excavation, bedding,form work installation and removal, erosion and sediment control, traffic control,concrete removal and proper disposal, clearing, grubbing, grading, care and protectionof existing utilities and structures. All right of way restoration including associatedadjacent paving and related landscaping is also included.

Damages to existing curb and gutter that was caused by the contractor and was notexpected to be damaged by the construction work shall be replaced at the contractor’sexpense.

No payment shall be made for this item until all landscape restoration work is completeto the satisfaction of the City’s inspector.

Item 58: Curb Inlet Removal:Payment for this item will be based on the number of EACH curb inlet that is removed.

Curb inlet removal shall include the removal of the existing structure and lid, includingcomplete removal of concrete and brick down to the base of the existing structure.

Also included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, clearing, grubbing, grading, care and protection of existingutilities and structures, backfilling and compaction. Additionally the on site properlycontained temporary storage and drying of trench soils is also included. Saw cutting ofpavement and concrete, the removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are also includeditems. All right of way restoration and related landscaping shall be incorporated in thisitem.

Item 59: Stormwater Manhole Removal:Payment for this item will be based on the number of EACH manhole that is removed.

Page 43: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 25Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

25

The manhole removal pay item shall include all costs associated with the excavation andcomplete removal of all of the brick/mortar or concrete for the entire manhole, down tothe base slab to the satisfaction of the City’s inspector. Any associated pipe entering themanhole to be removed will be cut a minimum of 2 feet from the outside of the manhole.This piping shall be removed as part of this bid item. Pipes that are cut, shall be pluggedand filled with flowable fill. This pay item includes removal of the frame, dust cover andlid, and delivery of the manhole dust cover and lid to the City’s inspector on a daily basis.

Also included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, sheeting and/or shoring in accordance with OSHA regulations,clearing, grubbing, grading, care and protection of existing utilities and structures,backfilling and compaction. Additionally the onsite properly contained temporary storageand drying of trench soils is also included. In areas where existing manholes are removedin soil, a minimum of 4” of clean pliable topsoil (submittal required) and vegetation thatmatches original vegetation in size and species are included. Saw cutting of pavementand concrete, the removal, proper disposal and complete joint-to-joint replacement of:granite curb, valley gutter and handicap ramps, in-kind, are also included items.Permanent paving, all right of way restoration and related landscaping shall beincorporated in this item.

Item 60: Stormwater Pipe Removal:Payment for this item will be based on the number of LINEAR FEET of stormwater pipe,by size that is removed.

The unit price bid for this item shall be full removal of existing stormwater pipe asindicated on the contract drawings and agreed to by the Contractor’s superintendentand the City’s inspector. Removal is to be completed prior to the installation ofproposed infrastructure installations.

Also included in the cost will be dewatering, erosion and sediment control, tree protection,traffic control, excavation, clearing, grubbing, grading, care and protection of existingutilities and structures, backfilling and compaction. Additionally the on site properlycontained temporary storage and drying of trench soils is also included. Saw cutting ofpavement and concrete, the removal, proper disposal and complete joint-to-jointreplacement of: granite curb, valley gutter and handicap ramps, in-kind, are also includeditems. All right of way restoration and related landscaping shall be incorporated in thisitem.

Item 61: Storm Sewer Pipe (Reinforced Concrete Pipe):By size, pipe shall be measured horizontally in LINEAR FEET along the centerline of thepipe from structure to structure, excluding structure diameter (s).

Page 44: DEPARTMENT OF UTILITIES - NORFOLK, VIRGINIA

D - 26Pump Station 23 Service Area Phase 4ADDENDUM No. 1City of Norfolk

26

Included in the unit cost is furnishing and installing new storm sewer pipe, complete andin place. Also included in the cost will be Select Bedding No. 57 stone as per Pipe BeddingDetail for storm sewer pipe. Also included are erosion and sediment control, treeprotection, excavation, clearing, grubbing, grading, hand digging, root pruning, by-passpumping or any other approved method to maintain existing storm flow, care andprotection of existing utilities including the offsetting of existing water main as necessary,and structures, temporary pavement and traffic control. Removal of existing pipe (whererequired), connections to existing structure, dewatering, sheeting and / or shoring inaccordance with OSHA regulations, grading, backfilling, compaction and compactiontesting are also included. The removal, proper disposal and complete joint to jointreplacement of: granite and concrete curb, curb and gutter, valley gutter, sidewalk,driveway and driveway apron, in kind are also included items. All right of way restorationand related landscaping shall be incorporated in this item.

END OF SECTION

-REMAINDER OF THIS PAGE LEFT INTENTIONALLY BLANK-