Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
EDITOR Kosuke Kurokawa
Energy
Feasibility of
Very Large Scale
Photovoltaic Power
Generation (VLS-PV)
Systems
fromthe
Desert
SUMMARY
Energyfrom
the
Desert
SUMMARY
EDITOR Kosuke Kurokawa
Energy
Feasibility of
Very Large Scale
Photovoltaic Power
Generation (VLS-PV)
Systems
fromthe
Desert
PART THREE: SCENARIO STUDIES AND RECOMMENDATIONS
Published by James & James (Science Publishers) Ltd
8–12 Camden High Street, London, NW1 0JH, UK
© Photovoltaic Power Systems Executive Committee of the
International Energy Agency
The moral right of the author has been asserted.
All rights reserved. No part of this book may be reproduced in any form or by
any means electronic or mechanical, including photocopying, recording or by
any information storage and retrieval system without permission in writing
from the copyright holder and the publisher.
A catalogue record for this book is available from the British Library.
Printed in Hong Kong by H&Y Printing Ltd
Cover image: Horizon Stock Images / Michael Simmons
Neither the authors nor the publisher make any warranty or representation,
expressed or implied, with respect to the information contained in this
publication, or assume any liability with respect to the use of, or damages
resulting from, this information.
Please note: in this publication a comma has been used as a decimal point, according to the
ISO standard adopted by the International Energy Agency.
CHAPTER ELEVEN: CONCLUSIONS OF PART 1 AND PART 2
Contents
Foreword vi
Preface vii
Task VIII Participants viii
COMPREHENSIVE SUMMARY
Objective 1
Background and concept of VLS-PV 1
VLS-PV case studies 1
Scenario studies 2
Understandings 2
R ecommendations 2
EXECUTIVE SUMMARY
A. Background and concept of VLS-PV 3
A.1 World energy issues 3
A.2 Environmental issues 4
A.3 An overview of photovoltaic technology 5A.3.1 Technology trends 5A.3.2 Experiences in operation and maintenance of large-scale PV systems 6A.3.3 Cost trends 6A.3.4 Added values of PV systems 7
A.4 World irradiation database 8
A.5 Concept of VLS-PV system 8A.5.1 Availability of desert area for PV technology 8A.5.2 VLS-PV concept and definition 9A.5.3 Potential of VLS-PV: advantages 10A.5.4 Synthesis in a scenario for the viability of VLS-PV development 10
B. VLS-PV case studies 12
B.1 General information 12
B.2 Preliminary case study of VLS-PV systems in world deserts 12
B.3 Case studies on the Gobi Desert from a life-cycle viewpoint 15
B.4 Case studies on the Sahara Desert 18
B.5 Case studies on the Middle East desert 19
C. Scenario studies and recommendations 21
C.1 Sustainable growth of the VLS-PV system concept 21
C.2 Possible approaches for the future 22
C.3 Financial and organizational sustainability 24
C.4 R ecommendations 25C.4.1 General understandings 25C.4.2 Recommendations on a policy level 26C.4.3 Checklist for specific stakeholders 26
PART THREE: SCENARIO STUDIES AND RECOMMENDATIONS
vi
Foreword
The International Energy Agency's Photovoltaic Power
Systems Programme, IEA PVPS, is pleased to publish this
study on very large-scale photovoltaic (VLS-PV) systems.
VLS-PV systems have been proposed on different
occasions and they may also represent a controversial theme.
The present market focus is indeed on small-scale, dis-
persed stand-alone photovoltaic power systems as well
as small and medium-sized building-integrated grid-
connected photovoltaic power systems. Both applications
have proven large potentials, of which only a very small
fraction has been realized until now. However, in the longer
term, VLS-PV systems may represent a future option for
photovoltaic applications and thereby contribute even more
to the world energy supply.
For the first time, the present study provides a detailed
analysis of all the major issues of such applications. Thanks
to the initiative of Japan, Task VIII of the IEA PVPS
Programme was designed to address these issues in a
comprehensive manner, based on latest scientific and tech-
nological developments and through close international co-
operation of experienced experts from different countries.
The result is the first concrete set of answers to some of the
main questions that have to be addressed in this context.
Experience with today’s technology is used, together with
future projections, to make quantified estimations regard-
ing the relevant technical, economic and environmental
aspects. Besides the specific issues of VLS-PV, the subject
of long-distance high-voltage transmission is also addressed.
This study includes a number of case studies in desert
areas around the world. These case studies have been
carried out in order to investigate the VLS-PV concept
under specific conditions and to identify some of the local
issues that can affect the concept.
I would like to thank the IEA PVPS Task VIII Expert
Group, under the leadership of Prof. K. Kurokawa and Dr
K. Kato, for an excellent contribution to the subject
investigated. The study provides an objective discussion base
for VLS-PV systems. This is very much in line with the
mission of the IEA PVPS Programme, aimed at objective
analysis and information in different technical and non-
technical areas of photovoltaic power systems.
I hope that this study can stimulate the long-term
discussion on the contribution of photovoltaics to the
future energy supply by providing a thorough analysis of
the subject investigated.
Stefan Nowak
Chairman, IEA PVPS Programme
vii
CHAPTER ELEVEN: CONCLUSIONS OF PART 1 AND PART 2
‘It might be a dream, but …’ has been a motive for con-
tinuing our chosen study on Very Large Scale Photovoltaic
Power Generation – VLS-PV. Now, we are confident that
this is not a dream. A desert truly does produce energy.
This report deals with one of the promising recommen-
dations for solving world energy problems in the 21st
century.
This activity first started in 1998 under the umbrella
of IEA Task VI. The new task, Task VIII: ‘Very Large Scale
PV Power Generation Utilizing Desert Areas’, was set up
for feasibility studies in 1999.
To initiate our study, a lot of imagination was required.
It was felt that dreams and imagination are really wel-
come, and that it is worth while to consider things for
future generations, our children and grandchildren.
People have to imagine their lives after 30 or 50 years,
even 100 years, since it requires a longer lead-time to
realize energy technology. In this sense, studies in terms
of VLS-PV include plant design by extending present
technologies as well as discussing basic requirements for PV
energy in the future energy-supplying structure, the social
impact on regions, and the local and global environmental
impact.
It is known that very large deserts in the world have a
large amount of energy-supplying potential. However,
unfortunately, around those deserts, the population is
Preface
generally quite limited. Then, too much power generation
by PV systems becomes worthless. However, world energy
needs will grow larger and larger towards the middle of
the 21st century. In addition, when global environmental
issues are considered, it is felt that future options are lim-
ited. These circumstances became the backbone and
motive force for VLS-PV work.
Finally, all the Task VIII experts wish to thank the IEA
PVPS Executive Committee and the participating coun-
tries of Task VIII for giving them valuable opportunities
for studies.
Prof. Kosuke Kurokawa
Editor
Operating Agent–Alternate, Task VIII
Dr Kazuhiko Kato
Operating Agent, Task VIII
PART THREE: SCENARIO STUDIES AND RECOMMENDATIONS
viii
Kazuhiko Kato, OA
New Energy and Industrial Technology Development Organization (NEDO), Japan
Kosuke Kurokawa, OA–Alternate
Tokyo University of Agriculture and Technology (TUAT), Japan
Isaburo Urabe, Secretary
Photovoltaics Power Generation Technology R esearch Association (PVTEC), Japan
David Collier
Sacramento Municipal Utility District (SMUD), USA
David Faiman
Ben-Gurion University of the Negev, Israel
Keiichi Komoto
Fuji R esearch Institute Corporation (FR IC), Japan
Jesus Garcia Martin
Iberdrola S.A., Brussels Office, Spain
Pietro Menna
General Directorate for Energy and Transport – D2, European Commission, Italy
Kenji Otani
National Institute of Advanced Industrial Science and Technology (AIST), Japan
Alfonso de Julian Palero
Iberdrola, Spain
Fabrizio Paletta
CESI SFR -ER I, Italy
Jinsoo Song
Korea Institute of Energy R esearch (KIER ), Korea
Leendert Verhoef
Verhoef Solar Energy Consultancy, the Netherlands
Peter van der Vleuten
Free Energy International bv, the Netherlands
Namjil Enebish, Observer
Department of Fuel and Energy, Ministry of Infrastructure, Mongolia
Task VIII Participants
1
Comprehensive Summary
Comprehensive summary
OBJECTIVE
The scope of this study is to examine and evaluate the
potential of very large-scale photovoltaic power genera-
tion (VLS-PV) systems (which have a capacity ranging
from several megawatts to gigawatts), by identifying the
key factors that enable VLS-PV system feasibility and
clarifying the benefits of this system’s application to
neighbouring regions, as well as the potential contribution
of system application to protection of the global environ-
ment. R enewable energy utilization in the long term also
will be clarified. Mid- and long-term scenario options for
making VLS-PV systems feasible in some given areas will
be proposed.
In this report, the feasibility and potential for VLS-PV
systems in desert areas are examined. The key factors
for the feasibility of such systems are identified and the
(macro-)economic benefits and the potential contribution
to the global environment are clarified. First the back-
ground of the concept is presented. Then six desert areas
are compared, and three of these are selected for a case
study. Finally, three scenario studies are performed to
ensure sustainability.
BACKGROUND AND CONCEPT OF VLS-PV
A very large-scale PV system is defined as a PV system
ranging from 10 MW up to several gigawatts (0,1–20 km 2
total area) consisting of one plant or an aggregation of
multiple units operating in harmony and distributed in
the same district. These systems should be studied with an
understanding of global energy scenarios, environmental
issues, socio-economic impact, PV technology develop-
ments, desert irradiation and available areas:
• All global energy scenarios project PV to become a
multi-gigawatt generation energy option in the first half
of this century.
• Environmental issues which VLS-PV systems may help
to alleviate are global warming, regional desertification
and local land degradation.
• PV technology is maturing with increasing conversion
efficiencies and decreasing prices per watt. Prices of
1,5 USD/ W are projected for 2010, which would
enable profitable investment and operation of a 100 MW
plant.
• Solar irradiation databases now contain detailed infor-
mation on irradiation in most of the world’s deserts.
• The world’s deserts are so large that covering 50 %
of them with PV would generate 18 times the world
primary energy supply of 1995.
VLS-PV CASE STUDIES
Electr icity generation costs of between 0,09 and
0,11 USD/ kWh are shown, depending mainly on annual
irradiation level (module price 2 USD/ W, interest rate 3 %,
salvage value rate 10 %, depreciation period 30 years).
These costs can come down by a factor of a half to a
quarter by 2010. Plant layouts and introduction scenarios
exist in preliminary versions. I/ O analysis shows that
25 000–30 000 man-years of local jobs for PV module
production are created per 1 km2 of VLS-PV installed.
Other findings of the three case studies (two flat-plate PV
systems and one two-axis tracking concentrator PV) are as
follows:
• The case study in the Gobi Desert describes a VLS-PV
system built of strings of 21 modules combined into
arrays of 250 kW consisting of 100 strings. Two of these
arrays are connected to an inverter of 500 kW. Two
hundred of these sets of two arrays are distributed over
an area of approximately 2 km2. Total requirements forconstruction of the plant based on local module assem-
bly are 848 485 modules, 1 700 tons of concrete for
foundations and 742 tonnes of steel for the array sup-
ports. The life-cycle CO2 emission is around 13 g-C/
kWh, due mainly to manufacturing of the modules andthe array supports.
• In the Sahara case study, several distributed generation
concepts were compared to minimize transmission costs.
A potentially attractive option is 300 dispersed plants of
5 MW PV systems, the total capacity of which is1,5 GW, located along the coast of Northern Africa,
connected to the grid by a single 1–10 km medium-
voltage line. A complete I/ O analysis was also carried
Comprehensive Summary
2
out, resulting in 2 570 induced jobs by the operation ofa 5 MW/ year PV module production facility.
• In the Negev Desert in the Middle East, a 400-sun
concentrator dish of 400 m2 was evaluated. Simulations
indicated that 16,5 % overall system efficiency is
achievable, and an economically attractive operationwith generation costs of less than 0,082 USD/ kWh is
possible.
SCENARIO STUDIES
Three sustainable scenario studies were developed showing
that sustainable local economic growth, sustainable technological–
environmental development and non-technological demonstration
and sustainable financial (stakeholder) support are possible when
a long-term perspective is developed and maintained:
• In the concept of sustainable local economic growth,
the first local PV module production facility has an
annual output of 5 MW. This local production supplies
for the construction of the local VLS-PV system. In
subsequent years, four more 5 MW module production
facilities are brought into operation, so that annually
25 MW is supplied to the local VLS-PV system. After
10–15 years, a module production facility of 50 MW
is put into operation. Every 10 years this facility is
replaced by a more modernized one. Thus after
approximately 40 years a 1,5 GW VLS-PV plant is in
operation, and the local production facility supplies for
replacement. In this way, local employment, and thus
the economy, will grow sustainably.
• To reach the point of a 1 GW system, four intermedi-
ate stages are necessary: R &D stage, pilot stage, dem-
onstration stage, and deployment (commercial) stage.
From stage to stage, the system scale will rise from
2,5 MW to 1 GW, and module and system cost will go
down by a factor of 4. Production will be shifted more
and more to the local economy. Technological issues to
be studied and solved include reliability, power control
and standards. Non-technical items include training,
environmental anti-desertification strategies, industri-
alization and investment attraction. These four stages have
a total duration of 15 years.
• To realize the final commercial stage, a view to financ-
ing distribution is developed for all of the three
previous stages, consisting of direct subsidies, soft loans,
equity, duty reduction, green certificates and tax
advantages. It is clear that direct subsidies will play an
important role in the first three stages (R &D, pilot and
demonstration). Ultimately, in the commercial stage,
enough long-term operating experience and track
record are available to attract both the soft loans and
equity for such a billion-dollar investment.
UNDERSTANDINGS
From the perspective of the global energy situation, global
warming and other environmental issues, as well as from
the case studies and scenarios, it is apparent that VLS-PV
systems can:
• contribute substantially to global energy needs
• become economically and technologically feasible
• contribute considerably to the environment
• contribute considerably to socio-economic development.
RECOM M ENDATIONS
To secure that contribution, a long-term scenario (10–15
years) perspective and consistent policy are necessary on
technological, organizational and financial issues. Action
is required now to unveil the giant potential of VLS-PV
systems in deserts. In such action, the involvement of many
actors is needed. In particular, it is recommended that, on
a policy level:
• national governments and multinational institutions
adopt VLS-PV systems in desert areas as a viable energy
generation option in global, regional and local energy
scenarios;
• the IEA-PVPS community continues Task VIII to
expand the study, refine the R &D and pilot phases,
involve participation by desert experts and financial
experts, and collect further feedback information from
existing PV plants;
• multilateral and national governments of industrialized
countries provide financing to generate feasibility studies
in many desert areas around the world and to imple-
ment the pilot and demonstration phases;
• desert-bound countries (re-)evaluate their deserts not as
potential problem areas but as vast and profitable
(future) resources for sustainable energy production, rec-
ognizing the positive influence on local economic growth,
regional anti-desertification and global warming.
3
Background and Concept of VLS-PV
EXECUTIVE SUMMARY A
Background and concept of
VLS-PV
We are in a new age beyond the 20th century, which was
the age of high-consumption society maintained by a mass
supply of fossil fuels and advances in science and technol-
ogy. But our activities in such a society will have a serious
impact on us, such as in energy security, global environ-
mental issues, population problems, etc. Therefore, it is
necessary to reconstruct a new society with new values
and new lifestyles in order to sustain our world from now
on. Finding solutions for energy and environmental issues
is essential for realizing a sustainable world, since it will
take a long time to develop energy technologies and to
recover from the destruction of the global environment.
R enewable energy such as solar, hydropower, geothermal
and biomass is expected to be the main energy resource in
future. Photovoltaic (PV) technology is one of the most
attractive options of these renewables, and many in the
world have been trying to develop PV technologies for the
long term.
In Part I, the informative introductory part of the whole
report, both global energy and environmental issues,
including the potential of renewable energy sources and
the market trends in PV technology, are reviewed as a
background for this report. General information on PV
technology, such as trends in solar cells and systems, opera-
tion and maintenance experiences, and a case study on
added values of a PV system for utilities, are summarized.
World irradiation data are also important to start a discus-
sion about the potential of VLS-PV systems. In the last
chapter of Part I, the concept of VLS-PV systems, which is
the theme of this report, is introduced.
A.1 WORLD ENERGY ISSUES
The two oil crises in the 1970s made us aware that fossil
fuels are exhaustible and triggered development of
alternative energy resources such as renewable energy.
Nevertheless, most of the primary energy still depends on
fossil fuels, and current utilization of renewables is negli-
gibly small, except for hydropower. According to the IEA
report, generally the total amount of fossil-fuel resources
in the world will not exhaust the energy supply until 2030,
although there are possibilities of a rapid increase in
energy demand, a geographical imbalance between supply
and demand, and temporal and local supply problems. There
is a forecast that the world primary energy supply in 2030
will increase to over 1,5 times as much as that in 2000, as
shown in Figure A.1.
In addition, energy demand in Asian countries will
increase much more than in O ECD countries. Even
beyond 2030, rapid growth in developing countries may
continue further, reflecting the economic gap between the
developing and the industrialized countries. In addition to
Figure A.1 World primary energy supply
by region, 1971–2030. Source: IEA
Executive Summary A
4
the long-term world energy problem, global warming is
another urgent issue because CO2 emissions are caused by
the combustion of fossil fuels (see Figure A.2). As pointed
out at Kyoto CO P-3, simple economic optimization
processes for world energy supply can no longer be
accepted to overcome global warming.
In any consideration of future energy problems, basic
conditions and tendencies may be summarized as follows:
• World energy demands will rapidly expand towards the
middle of this century due to world economic growth
and population increase.
• The sustainable prosperity of human beings can no
longer be expected if global environmental issues are
ignored.
• The share of electrical energy is rising more and more
as a secondary energy form.
• Although the need for nuclear power will increase as a
major option, difficulties in building new plants are
getting more and more notable at the same time.
• Thinking about the long lead-time for the development
of energy technology, it is urgently necessary to seek
new energy ideas applicable for the next generation.
In order to solve global energy and environmental issues,
renewable energy resources are considered to have a large
potential as well as to provide energy conservation,
carbon-lean fuels and CO2 disposal/ recovery. Among the
variety of renewable energy technologies, photovoltaic
(PV) technology is expected to play a key role in the mid-
dle of this century, as reported by Shell International
Petroleum Co. and the G8 R enewable Energy Task Force
(see Table A.1).
The world PV market as well as the world PV system
installation has been growing rapidly for the past several
years. Besides, PV industries in the USA, Europe and
Japan recently established their long-term vision of the PV
market. According to their vision, potential cumulative PV
installation will be in the hundreds of gigawatts in 2030.
A.2 ENVIRONM ENTAL ISSUES
R ecently, great concern about environmental issues, most
of which have been caused by human activities, has spread
throughout the entire world. The environmental impact of
VLS-PV systems may be divided into three categories from
a geographical viewpoint, i.e. global, regional and local
environmental issues, as shown in Figure A.3. The global
environmental issues are matters related to global changes.
R egional issues are trans-boundary environmental issues,
including atmospher ic and water pollution. Local
environmental issues are changes restricted to the local
environment that surrounds the VLS-PV installation site.
The most important phenomenon in this issue may be
desertification and land degradation. Change in micro-
climate is another local environmental issue.
Among environmental issues, global warming is one of
the most important issues because it has a large variety of
impact in various respects. According to the IPCC (Inter-
governmental Panel on Climate Change) Third Assessment
R eport, the global average surface temperature has
increased by (0,6 ± 0,2) °C since the late 19th century. It
is very likely that the period from 1990 to 2000 was the
warmest decade. Also, the global average surface tempera-
ture has been projected to increase by 1,4–5,8 °C between
1990 and 2100. The projected rate of warming is much
Table A.1 Installed global capacity estimated by G8 renewable energy task force (GW)
Coal IGCC Gas FC Bio conv. Bio IGCC Bio FC Small hydro Wind Solar PV Solar thermal Geothermal
2000 0,3 0,3 24,3 0,3 0,1 0,3 12,5 1,0 1,4 6,9
2012 14,3 14,3 34,6 15,7 15,8 18,9 90,5 31,8 9,7 17,4
2020 39,7 35,7 36,7 28,9 28,9 38,8 196,3 118,8 32,6 27,6
2030 142,5 114,0 40,5 68,0 67,5 95,8 554,6 655,8 156,4 49,5
Figure A.2 World primary energy supply and CO2 emissions,
1971–2030. Source: IEA
Figure A.3 Possible environmental issues impacted by
VLS-PV systems
5
Background and Concept of VLS-PV
greater than the observed changes during the 20th cen-
tury, and is very likely to be without precedent at least
during the last 10 000 years.
To mitigate the projected future climate change and
influences, the UN Framework Convention on Climate
Change (UNFCCC) has activated a negotiating process.
In COP-3 held in Kyoto in 1997, the Kyoto Protocol was
adopted and six greenhouse gases (GHGs) have been
designated for reduction by the first commitment period.
In November 2001, CO P-7 was held in Marrakesh,
Morocco. At this conference, the Marrakesh Accords were
adopted, and many have expressed a wish for the Kyoto
Protocol to enter into force in 2002. The finalized Kyoto
rulebook specifies how to measure emissions and reduc-
tions, the degree to which carbon dioxide absorbed by
carbon sinks can be counted towards the Kyoto targets,
how the joint implementation and emissions trading
systems will work, and the rules for ensuring compliance
with commitments. The meeting also adopted the Marra-
kesh Ministerial Declaration as input for the 10th
anniversary of the Convention’s adoption and the ‘R io+10’
World Summit for Sustainable Development (Johannes-
burg, September 2002). The Declaration emphasizes the
contribution that action on climate change can make to
sustainable development and calls for capacity building,
technology innovation and co-operation with the
biodiversity and desertification conventions.
Desertification is the degradation of land in arid, semi-
arid and dry subhumid areas. It occurs because dryland
ecosystems, which cover over one-third of the world’s land
area, are extremely vulnerable to overexploitation and
inappropriate land use. Desertification reduces the land’s
resilience to natural climate variability. Soil, vegetation,
freshwater supplies and other dryland resources tend to
be resilient. They can eventually recover from climatic
disturbances, such as drought, and even from human-
induced impacts, such as overgrazing. When land is
degraded, however, this resilience is greatly weakened. This
has both physical and socio-economic consequences.
Combating desertification is essential to ensuring the
long-term productivity of inhabited drylands. Unfortu-
nately, past efforts at combating desertification have too
often failed, and around the world the problem of land
degradation continues to worsen. R ecognizing the need
for a fresh approach, 179 governments have joined the
UNCCD as of March 2002. The UNCCD promotes
international co-operation in scientific research and
observation, and stresses the need to co-ordinate such
efforts with other related Conventions, in particular those
dealing with climate change and biological diversity.
New technologies and know-how should be developed,
transferred to affected countries, and adapted to local
circumstances. For example, photovoltaic and wind
energy may reduce the consumption of scarce fuelwood
and deforestation. These technologies, however, should also
be environmentally sound, economically viable and socially
acceptable.
VLS-PV systems will be one of the promising tech-
nologies for solving environmental problems. However, if
some projects involving environmentally safe and sound
technology are proposed, we should pay attention not only
to the operation but also to the entire life-cycle, including
production and transportation of components and inci-
dental facilities, construction and decommissioning. For
this purpose, life-cycle assessment (LCA) is a useful approach
and is becoming a general method of evaluating various
technologies. Besides the contribution to reducing gas
emissions such as CO2, projects for developing and intro-
ducing new technologies, such as the Clean Development
Mechanism (CDM), must accompany the sustainable
social and economic development of the region.
A.3 AN OVERVIEW OF PHOTOVOLTAICTECHNOLOGY
A.3.1 Technology trends
PV technology has several specific features such as solar
energy utilization technology, solid-state and static devices,
and decentralized energy systems. The long history of R &D
on solar cells has resulted in a variety of solar cells. Crystal-
line (single-crystalline, polycrystalline) silicon is the most
popular material for making solar cells. In 2001, crystal-
line Si PV modules had approximately 80 % of the market
share.
Mainly because of the lack of sufficient supply of suit-
able silicon material and because of the limited possibili-
ties for further improvements in manufacturing costs for
wafer-based silicon solar cells, much of the worldwide R &D
effort is spent on the development of thin-film solar cells.
Since extensive expertise has been gained with silicon as a
semiconductor material, the first candidates for replacing
wafer-based solar cells use silicon as an active layer. The
most popular thin-film technology today uses amorphous
silicon as the absorber layer; low-cost manufacturing tech-
niques have been designed and amorphous silicon solar
panels are the most cost-effective in the market today.
Multiple cell concepts, using a combination of amorphous
silicon and microcrystalline silicon cells (micromorph
concept), show interesting potentials for increasing solar-
cell efficiencies at relatively low cost. Another group of
thin-film silicon solar cells make use of high-temperature
deposition techniques and grow the silicon thin films on
high-temperature resistant (mostly ceramic) substrates.
Making use of lift-off and transfer techniques, silicon
layers that have been grown on silicon substrates at high
temperatures can be transferred to low-cost substrates and
the original substrate can be re-used. A different approach
using silicon thin films for enhancing the efficiency of a
silicon solar cell is the combination of crystalline silicon
wafers with amorphous silicon cells (hetero-junction cells).
Compound thin-film solar cells using material other than
silicon (CIGS, CdTe) have demonstrated their high
efficiency capability and offer a promising future for this
type of thin-film solar cells. Dye-sensitized and organic
solar cells have potential of low cost; today, their efficiencies
are still and probably will remain low, and the lifetime of
the cells is a major concern. Long-term reliability of thin-
Executive Summary A
6
film solar panels is, as with other types of semiconductors,
very much dependent on the encapsulation.
The general trend for all future design activities will be
to improve the conversion efficiency of the cell, the
simplicity, the throughput and the yield of the production
process, and the long-term reliability of the module. Look-
ing at the present status of R &D, manufacturing and
market penetration of the various technologies, it can be
expected that amorphous silicon will remain the domi-
nant thin-film technology in coming years. In particular,
the combination with microcrystalline silicon offers higher
and more stable efficiency, which is needed in many
applications. The next dominant thin-film technologies may
be polycrystalline compound solar cells, like CIS and CdTe.
Next to that, thin-film silicon cells, either on ceramic ma-
terials or via transfer techniques, may offer the best price/
performance ratio for most applications. For the longer
term, organic cell concepts may also enter the market. In
principle, all the cell concepts mentioned above have the
potential to reach and even pass the 1 USD/ W level. It can
be expected that research activities on all concepts will be
continued and that all concepts, at some time in the future,
will be commercially available. These are all major drivers
towards lower cost per unit of electricity.
A.3.2 Experiences in operation andmaintenance of large-scale PV systems
According to the facts of three projects of SMUD, opera-
tion and maintenance cost of large-scale PV system seems
to be low, less than 1 % of gross total project cost, as shown
in Table A.2.
The long-term reliability of solar cell and modules was
discussed by reviewing long-term data on field exposure
in four regions: Pacific R im, USA, Europe and Negev
Desert. In general, the performance degradation of a
crystalline Si solar-cell module ranges between 0,4 and
2,0 %/ year. In this report, performance degradation was
classified into three levels: typical (0,5 %/ year), severe
(1,0 %/ year), and worst (1,5 %/ year).
A.3.3 Cost trends
Although PV is currently at a disadvantage because of its
high cost, we believe PV has the best long-term potential
because it has the most desirable set of attributes and the
greatest potential for radical reductions in cost. Costs for
the entire system vary widely and depend on a variety of
factors, including system size, location, customer type, grid
connection and technical specifications. For example, for
building-integrated systems (BIPV), the cost of the system
will vary significantly depending on whether the system
is part of a retrofit or is integrated into a new building
structure. Another factor that has been shown to have a
significant effect on prices is the presence of a market stimu-
lation measure, which can have dramatic effects on
demand for equipment in the target sector. The installation
of PV systems for grid-connected applications is increas-
ing year by year, while the grid-connected market must
still depend upon government incentive programmes at
present. The installed cost of grid-connected systems also
varies widely in price. Figure A.4 shows the trends of PV
system and module prices in some countries. Although, in
more recent years, this shows a slight increase in some
markets due to high demand, there appears to be a contin-
ued downward trend.
We need to accelerate that trend. One way to do that is
to step up the scale of the typical PV plant. The largest
plant has a capacity approaching 100 MW/ year. It would
take such a plant, running flat out, 100 years to produce
enough equipment to match the power-generating capac-
ity of one medium-sized combined-cycle gas turbine power
plant. We believe there may be significant economies of
scale to be reaped as we move up to 50–100 MW plants.
Another path towards radically lower costs is technology
step change. The technology in use today is based on
crystalline silicon. This is an inherently material-intensive
technology. It requires batch production methods, and
is now relatively mature. The great hope for the future
lies with thin-film technologies, which are much less
material-intensive and suitable for continuous production
Table A.2 Actual operation and maintenance costs
Project name Total project cost Actual Actual Actual (USD)
(USD) (USD) (USD/kW) / Total project cost
Solarex Residential (329 kW) 2 050 723 6 502 19,76 0,32 %
Sacramento Metropolitan Airport
Solarport (128 kW) 1 324 122 7 500 58,59 0,68 %
Rancho Seco PV-3 Ground-Mounted
Substation System (214 kW) 2 580 008 4 167 19,47 0,25 %
Figure A.4 PV module and system price trends in some
countries
7
Background and Concept of VLS-PV
processes. They offer the potential to shift on to a lower
and steeper learning curve. However, we need to be a little
cautious about predicting when thin film will start to
realize its commercial potential. Both of these routes –
stepping up the scale, and backing the new technology –
carry large risks, both technical and commercial. Taking
bold steps will require a great deal of confidence in the
rapid emergence of a mass market.
Today’s cost of single-crystal and polycrystalline silicon
modules (although proprietary) is such that the present
factory price of 4 USD/ W includes all costs, as well as
marketing and management overheads, for that product
line. N ote that module prices for single-crystal and
polycrystalline silicon have been essentially stable, between
3,75 and 4,15 USD/ W, for nearly 10 years, while manu-
facturing costs have been reduced by over 50 %. Based on
the studies cited and on further analysis, it seems likely
that fully loaded manufacturing costs for a 100 MW
single-crystal silicon module will be 1,40 USD/ W. This
would permit a profitable price of 2,33 USD/ W. Prices
at this level are likely to be required in order to open up
the massive grid-connected and building-integrated
markets. The cast-ingot polycrystalline option continues
to have module costs slightly lower than those of the
single-crystal, allowing this option to offer profitable prices
at the 2 USD/ W level. Thin films and concentrators could
have manufacturing costs that will allow profitable prices
of 1,25 USD/ W. In this forecast, the PV market contin-
ues to grow at 15–25 %. However, in order for this fore-
cast to become a reality, several major events need to
occur. First, the existing subsidized grid-connected
programmes in countries such as Japan, Germany, the
Netherlands and the USA need to stimulate the installa-
tion of quality, reliable systems in sufficient quantities to
stimulate investment in large-volume module manufac-
turing plants. Secondly, continuing decrease in the price
of modules must be realized. There must be profitable
modules below 2 USD/ W by the year 2005 and even
lower prices, approaching 1,5 USD/ W, must occur by
2010. Thirdly, in the transitional phase towards competi-
tive prices, marketing and financing schemes have to be
introduced more widely which will allow the customers
to opt for this solution in spite of costs.
A.3.4 Added values of PV systems
PV technology has unique characteristics different from
those of conventional energy technologies, and additional
values are hidden in PV systems besides their main func-
tion, which is, of course, power generation. Table A.3 shows
a summary of non-energy benefits that can add value to
PV systems. Nowadays, many people are becoming aware
of the additional benefits offered by PV systems. Unfortu-
nately, this awareness does not contribute to the effective
promotion of PV systems since current added values are
not quantitative but qualitative. Thus research activities on
quantitative analysis of this issue should be continued.
There is a case study on the added values of a PV system
for SMUD. The utility benefits evaluated are as follows.
• Energy: avoided marginal cost of system-wide energy
production.
• Capacity: avoided marginal cost of system-wide gen-
eration capacity.
• Distribution: distribution capacity investment deferral.
• Sub-transmission: sub-transmission capacity investment
deferral.
• Bulk transmission: transmission capacity investment
deferral.
• Losses: reduction in electricity losses.
• R EPI: renewable energy production incentive.
• Externalities: value of reduced fossil emissions.
• Green pricing: voluntary monthly contributions from
PV pioneers.
• Fuel price risk mitigation: value of reducing risk from
uncertain gas price projections.
Table A.3 Summary of non-energy benefits that can add value to PV systems
Category Potential values
Electrical kWh generated; kW capacity value; peak generation and load matching value; reduction in demand for ut ility
electricity; power in t imes of emergency; grid support for rural lines; reduced transmission anddistribution losses;
improved grid reliability and resilience; voltage control; smoothing load f luctuations; f iltering harmonics and
reactive power compensation.
Environmental Signif icant net energy generator over its lifet ime; reduced air emissions of part iculates, heavy metals,
CO2, NO
x, SO
x, result ing in lower greenhouse gases; reduced acid rain and lower smog levels; reduced
power station land and water use; reduced impact of urban development; reduced tree clearing for fuel;
reduced nuclear safety risks.
Architectural Substitute building component; mult i-function potential for insulation, water proofing, f ire protection,
w ind protection, acoustic control, daylighting, shading, thermal collection and dissipation; aesthetic appeal
through colour, transparency, non-reflective surfaces; reduced embodied energy of the building;reflection of
electromagnetic waves; reduced building maintenance and roof replacements.
Socio-economic New industries, products and markets; local employment for installat ion and servicing; local choice, resource use
and control; potential for solar breeders; short construction lead-t imes; modularity improves demand matching;
resource diversif ication; reduced fuel imports; reduced price volatility; deferment of large capital outlays for
central generating plant or transmission and distribution line upgrades; urban renewal; rural development; lower
externalit ies (environmental impact, social dislocation, infrastructure requirements) than fossil fuels and nuclear;
reduced fuel transport costs and pollut ion from fossil-fuel use in rural areas; reduced risks of nuclear accidents;
symbol for sustainable development and associated education; potential for international co-operation,
collaboration and long-term aid to developing countries.
Executive Summary A
8
• Service revenues (economic development): net service
revenues from local PV manufacturing plant (result of
economic development efforts).
Table A.4 is an estimation result of utility benefits of fixed
PV systems.
A.4 WORLD IRRADIATION DATABASE
Irradiation data are important to start a discussion about
the potential of VLS-PV systems. The Japan Weather Asso-
ciation (JWA) collected irradiation and air temperature
data during 1989 and 1991 from every meteorological
organization in the world. Data items are monthly means
of global irradiation, monthly means of ambient air tem-
perature, and monthly means of snow depth. The data were
collected from 150 countries, and data from 1 601 sites
throughout the world are available. Monthly global irra-
diation was estimated from monthly sunshine duration
where there were no irradiation data.
The Negev R adiation Survey, which was established in
the 1980s by the Israel Ministry of National Infrastruc-
tures, monitors the following meteorological parameters
at nine stations in the Negev Desert: normal direct beam
irradiance, global horizontal irradiance, ambient tem-
perature, humidity ratio, wind speed, and wind direction.
The data are available from the Ben-Gurion National
Solar Energy Centre, in the form of a CD-ROM, which
contains a set of Typical Meteorological Year (TMY) files
(updated every three years) together with all previous years
of actual data for each site.
Besides these, there are a variety of worldwide databases
of solar energy resources. Table A.5 shows the name and
website address for some of these.
A.5 CONCEPT OF VLS-PV SYSTEM
A.5.1 Availability of desert area forPV technology
Solar energy is low-density energy by nature. To utilize it
on a large scale, a massive land area is necessary. However,
one-third of the land surface of the Earth is covered by
very dry deserts, as shown in Figure A.5. High-level inso-
lation and large spaces exist. It is estimated that if a very
small part of these areas, say 4 %, were used for the instal-
lation of PV systems, the annual energy production would
equal world energy consumption.
A rough estimation was made to examine the potential
of desert under the assumption of a 50 % space factor for
installing PV modules on the desert surface as the first
evaluation. The total electricity production becomes
Table A.4 Estimation result of ut ility benefits of f ixed PV systems (USD/kW, 1996)
Benefits Bulk transmission Sub-transmission Primary voltage Secondary voltage
Service revenues 708 708 708 708
REPI 221 221 221 221
Externalit ies 324 327 338 340
Fuel price risk 192 194 200 201
Green pricing 0 0 44 44
Distribution 0 0 0 117
Sub-transmission 0 0 39 39
Bulk transmission 0 15 16 16
Generation capacity 296 300 314 315
Energy 768 775 800 805
Total 2 509 2 540 2 680 2 806
Table A.5 Examples of world irradiation database
Name Website address
Ground observation
1. Negev Radiation Survey http://www.bgu.ac.il/solar
2. WRDC solar radiation and radiation balance data http://wrdc-mgo.nrel.gov/
3. BSRN: Baseline Surface Radiation Network http://bsrn.ethz.ch/
4. NOAA NCDC GLOBALSOD http://www.ncdc.noaa.gov/
5. METEONORM 2000 (commercial product) http://www.meteotest.ch/
Satellite-derived data
6. SeaWiFS surface solar irradiance http://www.giss.nasa.gov/data/seaw ifs/
7. LaRC Surface Solar Energy dataset (SSE) http://eosweb.larc.nasa.gov/sse/
8. ISCCP datasets http://isccp.giss.nasa.gov/isccp.html
Figure A.5 World deserts (unit: 104 km2)
9
Background and Concept of VLS-PV
1 942,3 × 103 TWh(= 6,992 × 1021 J = 1,67 × 105 Mtoe),
which means a level almost 18 times as much as the world
primary energy supply, 9 245 Mtoe (107,5 × 103 TWh =
3,871 × 1020 J) in 1995. These are quite hypothetical
values, ignoring the presence of loads near these deserts.
However, at least these indicate high potential as primary
resources for developing districts located in such solar-
energy-rich regions.
Figure A.6 also shows that the Gobi Desert area be-
tween the western part of China and Mongolia can gener-
ate as much electricity as the present world primary
energy supply. In Figure A.7, an image of a VLS-PV
system in a desert area is shown.
A.5.2 VLS-PV concept and definition
Presently, three approaches are under consideration to en-
courage the spread and use of PV systems.
(a) Establish small-scale PV systems that are independ-
ent of each other. There are two scales for such systems:
installing stand-alone, several hundred-watt PV systems for
private dwellings; and installing 2–10 kW systems on the
roofs of dwellings as well as 10–100 kW systems on office
buildings and schools. Both methods are already being used.
The former is used to furnish electrical power in develop-
ing countries, the so-called SHS (solar home system), and
the latter is used in Western countries and in Japan. This
Figure A.6 Solar pyramid
Figure A.7 Image of a VLS-PV system in a desert area
Executive Summary A
10
seems to be used extensively in areas of short- and me-
dium-term importance.
(b) Establish 100–1 000 kW mid-scale PV systems on
unused land on the outskirts of urban areas. The PVPS/
Task VI studied PV plants for this scale of power genera-
tion. Systems of this scale are in practical use in about a
dozen sites in the world at the moment, but are expected
to increase rapidly in the early 21st century. This category
can be extended up to multi-megawatt size.
(c) Establish PV systems larger than 10 MW on vast,
barren, unused lands that enjoy extensive exposure to sun-
light. In such areas, a total of even more than 1 GW of PV
system aggregation can be easily realized. This approach
makes it possible to install quickly a large number of PV
systems. When the cost of generated electrical power is
lowered to a certain level in the future, many more PV
systems will be installed. This may lead to a drastically lower
cost of electricity, creating a positive cycle between cost
and consumption. In addition, this may become one of the
solutions to future energy and environmental problems
across the globe, and ample discussion of this possibility is
believed to be worthwhile.
The third category corresponds to very large-scale PV (VLS-
PV) systems. The definition of VLS-PV may be summa-
rized as follows:
• The size of a VLS-PV system may range from 10 MW
to one or a few gigawatts, consisting of one plant, or an
aggregation of many units that are distributed in the
same district and operate in harmony with each other.
• The amount of electricity generated by VLS-PV
systems can be considered significant for people in the
district, in the nation or in the region.
• VLS-PV systems can be classified according to the fol-
lowing concepts, based on their locations:
• land based (arid to semi-arid, deserts)
• other concept (water-based, lakes, coastal, interna-
tional waters)
• locality options (D.C.: lower, middle, higher income;
large or small countries; OECD countries).
Although VLS-PV systems include water-based options,
in principle, many different types of discussions are
required on this matter. It is not neglected but it is treated
as a future possibility outside the major efforts of this
study.
A.5.3 Potential of VLS-PV: advantages
The advantages of VLS-PV systems are summarized as
follows:
• It is very easy to find land around deserts appropriate
for large energy production by PV systems.
• Deserts and semi-arid lands are, normally, high-
insolation areas.
• The estimated potentials of such areas can easily supply
world energy needs in the middle of the 21st century.
• When large-capacity PV installations are constructed,
step-by-step development is possible through utilizing
the modularity of PV systems. According to regional
energy needs, plant capacity can be increased gradually.
This is an easier approach for developing areas.
• Even very large installations are quickly attainable to
meet existing energy needs.
• R emarkable contributions to the global environment
can be expected.
• When a VLS-PV system is introduced to a certain re-
gion, other types of positive socio-economic impact may
be induced, such as technology transfer to regional PV
industries, new employment and economic growth.
• The VLS-PV approach is expected to have a major,
drastic influence on the ‘chicken-and-egg’ cycle in the
future PV market. If this does not happen, the distance
to VLS-PV systems may become a little far.
These advantages make it a very attractive option, and
worthy of discussion regarding global energy in the 21st
century. The image of this concept is illustrated by Figure
A.8.
A.5.4 Synthesis in a scenario for the viabilityof VLS-PV development
Basic case studies were reported concerning regional
energy supply by VLS-PV systems in desert areas, where
solar energy is abundant. According to this report, the
following scenario is suggested to reach a state of large-
scale PV introduction. First, the bulk systems that have
been installed individually in some locations would be
interconnected with each other by a power network. Then
they would be incorporated with regional electricity
demand growth. Finally, such a district would become a
large power source. This scenario is summarized in the
following stages according to Figure A.9:
1 A stand-alone, bulk system is introduced to supply elec-
tricity for surrounding villages or anti-desertification
facilities in the vicinity of deserts.
2 R emote, isolated networks germinate. Plural systems are
connected by a regional grid. This contributes to load
levelling and the improvement of power fluctuation.
Figure A.8 Global network image
11
Background and Concept of VLS-PV
3 The regional network is connected to a primary trans-
mission line. Generated energy can be supplied to a load
centre and industrial zone. Total use combined with other
power sources and storage becomes important for match-
ing to the demand pattern and the improvement of the
capacity factor of the transmission line. Furthermore,
around the time stage 3 is reached, in the case of a
south-to-north inter-tie, seasonal differences between
Figure A.9 Very large-scale PV system deployment scenario
demand and supply can be adjusted. An east-to-west tie
can shift peak hours.
4 Finally, a global network is developed. Most of the
energy consumed by human beings can be supplied
through solar energy. For this last stage, a breakthrough
in advanced energy transportation will be expected on
a long-term basis, such as superconducting cables, FACTS
(flexible A.C. transmission system), or chemical media.
Executive Summary B
12
EXECUTIVE SUMMARY B
VLS-PV case studies
VLS-PV systems are expected to generate a variety
of advantages and will be one of the most attractive
technologies for our future, particularly from the view-
points of energy and the environment. However, realizing
VLS-PV systems may constitute a long-term project, the
nature of which we have not yet experienced. Therefore,
the capability of VLS-PV systems and the configuration of
each component must be assessed while taking into
account site conditions, regional electricity demand,
system performance, transmission technology or other
alternative options, and concurrent use with other energy
resources.
In Part II, some case studies on VLS-PV systems for
selected regions were undertaken to employ the concepts
of VLS-PV systems, after surveying general information
concerning candidate sites. As case studies, first, introduc-
tory analyses on the generation costs of VLS-PV systems
in world deserts were carried out. Secondly, energy
payback time, CO2 emissions and generation costs for
VLS-PV systems in the Gobi Desert in China were evalu-
ated in detail from a life-cycle point of view. Next, by
assuming the Sahara Desert as the site, a network concept
for a VLS-PV system was discussed and an estimation of
the socio-economic impacts of technology transfer were
analysed. Finally, using a simulation model for the Negev
Desert located in the Middle East, fixed modules, one-axis
tracking modules, two-axis tracking modules and a con-
centration system were summarized as expected technolo-
gies for VLS-PV systems.
B.1 GENERAL INFORM ATION
The deserts that are the most promising sites for VLS-PV
systems cover one-third of the land surface. The distribu-
tion is shown in Figure B.1. Because the degree of the
impact of VLS-PV systems would depend upon the
various conditions of particular regions, major indicators
concerning major regions/ countries with deserts were
investigated. The selected regions/ countries were China,
India, the Middle East, North Africa, Mexico and Australia.
Although the economic state of these countries (except
for Australia) is lower than the world average, it has been
growing every year. Particularly, the growth in China and
India is remarkable. With economic growth, energy con-
sumption is increasing, most of which has depended upon
fossil fuels for the commercial and industrial sectors. The
trends for electricity were almost the same. In China, In-
dia and Australia, more than 75 % of the total electricity is
generated by coal, while in the Middle East, North Africa
and Mexico, oil and gas are the main resources for gener-
ating electricity. However, the candidate site is not limited
to only one desert. That is to say, it may be concluded that
all those deserts have the possibility to be candidate sites
for VLS-PV systems.
As the methodologies for case studies, we focused on
life-cycle assessment and I/ O analysis. The former is a method
for making environmental decisions, and is becoming in-
creasingly popular in environmental policies. The latter is
a method for estimating economic effects using an inter-
industry table. These are effective methods to evaluate the
impacts of VLS-PV systems. The former is applied in a
case study on the Gobi Desert, and the latter is applied in
a case study on the Sahara Desert focusing on socio-
economic impact of VLS-PV systems.
B.2 PRELIM INARY CASE STUDY OF VLS-PVSYSTEM S IN WORLD DESERTS
To make a rough sketch of VLS-PV systems in desert areas
and to investigate their economic feasibility, a preliminary
case study was carried out. It was assumed that VLS-PV
systems each with a 1 GW capacity would be installed in
the six major deserts of the world, as shown in Figure B.2.
It was supposed that a 1 GW VLS-PV system, which is
an aggregation of ten 100 MW PV systems with flat-plate
fixed array structures, would be installed in each desert.
Figure B.3 shows conceptual images of a 1 GW VLS-PV
system. Assuming that the power output from a VLS-PV
system would be transmitted to a given load centre,
construction of 110 kV transmission lines would be taken
into account. Though the transmission lines depend upon
distance from the load centre to the VLS-PV system, a
distance of 100 km was employed for all deserts to avoid
complicated evaluation in this study.
13
VLS-PV Case Studies
Figure B.1 Aridity zones of the world.
Source: World Atlas of Desertif ication (UNEP, 1992)
Figure B.2 The six deserts used in this case study: (1) desert name, (2) reference point, (3) area, (4) annual average
ambient temperature, (5) annual horizontal global irradiation
Figure B.3 Conceptual image of a 1 GW VLS-PV system
Executive Summary B
14
To calculate the annual power generation of the
VLS-PV systems, cell temperature factors, load match-
ing factors, efficiency deviation factors and inverter mis-
match factors were taken into account in calculating the
performance ratio (PR ) for each installation site. The
annual average in-plane irradiation was estimated from
the annual global horizontal irradiation using a method
for separating into direct and scattered radiation known
as the Liu–Jordan model.
Initial costs, consisting of system component costs,
transportation costs of the system components, system
construction costs, and annual operation and maintenance
(O&M) costs, were calculated in order to estimate the
generation costs of VLS-PV systems installed in the six
world deserts. No land cost was taken into account in this
study, and cost data in Japanese yen were converted to US
dollars at the (recent) exchange rate of 120 JPY/ USD.
Based on estimates of the initial cost and the annual
O&M cost, the total annual costs of 100 MW PV systems
installed in the six deserts were calculated assuming an
annual interest rate of 3 %, a salvage value rate of 10 %, a
depreciation period of 30 years, and an annual property
tax rate of 1,4 %. An annual overhead expense of 5 % of
annual O&M costs was also taken into account. The gen-
eration costs are shown in Table B.1. The lowest generation
costs were estimated when the array tilt angle was 20°
independent of PV module price, except for the case of
the Gobi Desert, where a tilt angle of 30° had the cheapest
generation cost. The generation costs at a PV module price
of 1 USD/ W, which range from 5,2 to 8,4 US cents/ kWh,
are roughly one-third as great as those at a PV module
price of 4 USD/ W.
Figure B.4 represents the best estimates of generation
costs for each desert as a function of annual global hori-
Table B.1 Generation cost of 100 MW PV system (US cents/kWh)
Sahara Negev Thar Sonoran Great Sandy Gobi
Nema Ouarzazate
Module price =
4 USD/W
Tilt angle =
10º 14,8 18,5 20,6 17,8 18,4 19,1 19,1
Tilt angle =
20º 14,7 17,9 20,0 17,2 17,9 18,8 18,1
Tilt angle =
30º 15,1 17,9 20,4 17,3 18,0 19,4 17,6
Tilt angle =
40º 16,1 18,3 21,3 17,9 18,7 20,5 17,6
Module price =
3 USD/W
Tilt angle =
10º 11,6 14,5 16,6 14,0 14,5 15,5 15,0
Tilt angle =
20º 11,5 14,0 16,1 13,6 14,1 15,4 14,2
Tilt angle =
30º 11,8 14,0 16,5 13,7 14,2 15,9 13,8
Tilt angle =
40º 12,7 14,4 17,3 14,3 14,8 16,8 13,8
Module price =
2 USD/W
Tilt angle =
10º 8,4 10,5 12,6 10,4 10,6 12,0 10,8
Tilt angle =
20º 8,4 10,2 12,3 10,0 10,3 11,9 10,3
Tilt angle =
30º 8,6 10,2 12,7 10,2 10,5 12,4 10,0
Tilt angle =
40º 9,3 10,6 13,4 10,7 11,0 13,2 10,0
Module price =
1 USD/W
Tilt angle =
10º 5,2 6,5 8,6 6,6 6,7 8,5 6,7
Tilt angle =
20º 5,2 6,3 8,4 6,4 6,5 8,4 6,3
Tilt angle =
30º 5,4 6,4 8,8 6,6 6,7 8,8 6,2
Tilt angle =
40º 5,8 6,7 9,5 7,1 7,2 9,5 6,2
Figure B.4 Best estimates of generation cost for each desert as a function of annual global horizontal irradiation
15
VLS-PV Case Studies
zontal irradiation. With the exception of the Negev Desert
and the Great Sandy Desert, in which the generation costs
are relatively higher because of high wages, the level of
generation costs of a 100 MW PV system are roughly
the same. Though the generation costs decrease gently
according to the increase in annual irradiation, even the
generation cost for the Gobi Desert, which has much less
annual irradiation than the Sahara Desert, is on a level
with that of the Sahara. Electricity from VLS-PV systems
in these deserts would not be so cheap when the PV mod-
ule price is expensive (such as at 4 USD/ W), but the cost
of the electricity will become economic even with the
proven system technologies employed in this study when
the PV module price is reduced to a level of 1 USD/ W.
The current market price of PV modules is not low enough
for the realization of VLS-PV systems, but it is expected
that PV module prices will decrease rapidly with the growth
of the PV market. Therefore, VLS-PV systems in desert
areas will be economically feasible in the near future.
B.3 CASE STUDIES ON THE GOBI DESERTFROM A LIFE-CYCLE VIEWPOINT
As shown previously, the introduction of VLS-PV systems
in desert areas seems to be attractive from an economic
point of view when PV modules are produced at a low
price level, even though existing PV system technology is
adopted. But we must pay attention not only to the eco-
nomic aspect but also to the energy and environmental
aspects, since PV systems consume a lot of energy at their
production stage and therefore emit carbon dioxide (CO2)
indirectly, as a result. Therefore, the feasibility of VLS-PV
systems was evaluated in depth from a life-cycle view-
point by means of life-cycle analysis (LCA).
The Gobi Desert was chosen as the installation site of
VLS-PV systems for LCA in this study. This desert, which
lies in both China and Mongolia, is around 1,3 × 106 km2
in size and is located between 40°N and 45°N. Installation
of the VLS-PV systems in the Gobi Desert has some ad-
vantages: it is a stone desert rather than sand, and a utility
grid exists relatively close to the desert. In this study, it was
assumed that the 100 MW VLS-PV system would be in-
stalled in the Gobi Desert on the Chinese side.
To execute LCA, a life-cycle framework of the VLS-PV
system has to be prepared. Figure B.5 gives an image of
the life-cycle framework of the VLS-PV system in this
study. It was supposed that array support structures, trans-
mission towers and foundations for the array support struc-
tures and the transmission towers would be produced in
China and that other system components would be manu-
factured in Japan. All the components are transported to
some installation site near Hoh-hot in the Gobi Desert by
marine and/ or land transport. Land transport is also taken
into consideration. Land cost is not considered, but land
preparation was considered here.
In this study, a south-facing fixed flat array structure
was employed and the array tilt angle was given as a
variable parameter (10°, 20°, 30°, 40°). Both PV module
price and inverter price were also dealt with as variable
parameters. System performance ratio (PR ) was assumed
to be 0,78 by consideration of operation temperature, cell
temperature factor, load matching factor, efficiency
deviation factor and inverter mismatch factor (= 0,90). It
should be noted that the efficiency deviation factor
involves long-term performance degradation (0,5 %/ year)
as well as short-term surface degradation by soil (= 0,95).
The number of PV modules in a string was taken to be
21 by consideration of the Voc
of the PV module and the
D.C. voltage of the inverter. Then the rated output from
one string is 2,52 kW. Accordingly a 250 kW PV array
requires 100 strings. Two of these 250 kW PV arrays
located north and south in parallel form the 500 kW
system with a 500 kW inverter and a 6,6 kV/ 500 V trans-
former.
Figure B.6 illustrates an example of the field layout for
such a 100 MW VLS-PV system with a 30° tilt angle. It
was assumed that array supports were made of zinc-plated
stainless steel (SS400), and the thickness of several types of
steel material were chosen according to stress analysis
assuming that the wind velocity is 42 m/ s, based upon the
design standard of structural steel by the Japanese Society
of Architecture. A cubic foundation made of concrete was
used. Its dimension was decided in accordance with the
design standard of support structures for power transmission
Figure B.5 Life-cycle framework of the case studyFigure B.6 Example of f ield layout for 100 MW VLS-PV
system (30° t ilt angle) (unit: m)
Executive Summary B
16
by the Institute of Electrical Engineering in Japan. Taking
into account Japanese experience in civil engineering
and the local labour situation in China, local labour re-
quirement was also estimated for system construction such
as PV module installation, array support installation, pro-
duction and installation of foundations, cable installation,
and installation of common apparatus. Table B.2 shows a
summary of requirements to construct a 100 MW
VLS-PV system in the Gobi Desert in China.
Labour cost for the operation was estimated based on
the assumption of a 100 MW VLS-PV system that was in
service 24 hours a day by nine persons working in shifts.
The annual labour cost for electrical engineering was
assumed for these operators. Maintenance cost was also
calculated based on actual results of a PVUSA project; that
is, the cost of repair parts was 0,084 %/ year of the total
construction cost and labour for maintenance was one
person per year.
Figure B.7 shows the results of the generation cost of the
100 MW PV system. Differences in the annual cost due to
PV module price resulted in differences in these genera-
tion costs. Though the least annual cost was obtained at the
least array tilt angle for any tilt angle, the minimum
generation cost appeared at around 30° due to the in-
crease in annual power generation as the array tilt angle
increased. The generation cost stays at a high level, around
18 US cents/ kWh (just less than the current consumer price
for residential sectors in Japan), when the PV module price
is 4 USD/ W. But it decreases remarkably to less than
7,0 US cents/ kWh (close to the current electricity tariff
in China) if the PV module price goes down to 1 USD/ W.
Figure B.8 represents the results of total primary
energy requirement and energy payback time (EPT). EPT
was estimated assuming that electricity from the PV
system would replace utility power in China where
recent conversion efficiency is around 33 %. As shown in
these figures, the best EPT was obtained at 20° array tilt
angle, and BOS components made of steel and concrete
(such as array supports, transmission lines, foundations
and troughs) contributed much to both energy require-
ments because these materials consume a great deal of
energy to produce in China. Transportation also uses
a certain amount of energy. Nevertheless, EPT resulted
in a very low level. This suggests that the total energy
requirement throughout the life-cycle of the PV system
(considering production and transportation of system
components, system construction, operation and mainte-
nance) can be recovered in a short period much less than
its lifetime. Therefore VLS-PV is useful for energy
resource savings.
Figure B.9 shows the results of life-cycle CO2 emissions
and life-cycle CO2 emission rate of the 100 MW PV sys-
tem, assuming 30-year operation periods. Discussion of
these results is the same as for the total primary energy
requirement and the EPT. Considering the CO2 emission
rate of existing coal-fired power plants, about 300g-C/
kWh, the life-cycle CO2 emission rate of a 100 MW PV
system is much lower. So the VLS-PV system in desert
Table B.2 Summary of total requirements for a 100 MW VLS-PV system in the Gobi Desert
Item Unit 10º 20º 30º 40º
Material requirement
PV modulea piece 848 485 848 485 848 485 848 485
Array support structurea ton 8 291 8 606 9 658 10 763
Foundationa m3 46 487 46 487 69 391 98 801
Cablea 600 V CV 2 mm2 (single core) km 1 178 1 364 1 434 1 499
600 V CV 8 mm2 (double core) km 173 173 173 173
600 V CV 60 mm2 (single core) km 67 – – –
600 V CV 100 mm2 (single core) km – 88 106 122
6,6 kV CV-T 22 mm2 km 21 27 33 37
6,6 kV CV 200 mm2 (single core) km 38 38 38 38
110 kV CV 150 mm2 (single core) km 11 13 14 15
Trougha m3 35 235 37 450 39 406 41 037
Common apparatus
Inverter (w ith transformer)a set 202 202 202 202
6,6 kV capacitorb set 202 202 202 202
6,6 kV GIS set 4 4 4 4
110 kV/6.6kV transformerb set 5 5 5 5
110 kV GIS set 4 4 4 4
2,4 MVA capacitor set 1 1 1 1
Common power board set 1 1 1 1
Transportation
Heavy oil consumption ton 145 145 147 148
Diesel oil consumption kl 6 101 6 261 7 941 10 031
Transmission
Cable 110 kV TACSR 410 mm2 km 134 134 134 134
A.C. 70 mm2 km 16,7 16,7 16,7 16,7
Pylon (steel) ton 742 742 742 742
Foundation ton 1 715 1 715 1 715 1 715
Construction
Diesel oil consumption kl 128 170 207 238
Labour requirement man-year 2 711 2 752 2 831 2 911
a99 % of construction yield is considered.bSpare sets are included.
17
VLS-PV Case Studies
Figure B.7 Generation cost of a 100 MW PV system
Figure B.8 Total primary energy (TPE) requirement and EPT of a 100 MW PV system
Figure B.9 Life-cycle CO2 emissions and life-cycle CO
2 emission rate of a 100 MW PV
system
Executive Summary B
18
areas is a very effective energy technology for preventing
global warming.
B.4 CASE STUDIES ON THE SAHARA DESERT
It is necessary to build a concept for supplying the elec-
tricity that VLS-PV generates, and the supply of such
electricity may contribute to regional development.
Additionally, VLS-PV may induce some economic impacts,
such as an employment effect. A network concept for
introducing VLS-PV in the Sahara Desert and the
expected socio-economic impact of the technology
transfer of PV module fabrication were discussed.
A transmission system devoted to the exploitation of
remote energy resources has to be designed to minimize
transmission costs, while respecting reliability and
environmental requirements. Transmission costs depend on
the transmission distances and the hours of yearly utiliza-
tion. From these viewpoints, the transmission costs were
analysed for three cases: (1) a 1,5 GW centralized PV power
plant plus 300–900 km of transmission line; (2) 1,5 GW
produced by 30 PV plants of 50 MW; and (3) 1,5 GW
produced by 300 PV plants of 5 MW. The third case
produced the most attractive results. Each of these plants
should cover an area of approximately 10 ha (0,1 km2),
and the power would be typically delivered through single
A.C. MV lines (for example, 20 kV). In this case, the PV
plants would be distributed within the coastal strip of North
African countries, placed less than 10 km from the HV/
MV substations and the distribution networks that feed
the loads. When assuming 5 km as a transmission distance,
the transmission cost would range from 3,7 to 6,2 USD/
MWh, depending upon yearly utilization of VLS-PV, as
shown in Figure B.10.
Additionally, having a variety of technology transfers is
very important for the sustainable expansion of VLS-PV,
and the transfer of PV manufacturing facilities may bring
about the stimulation of various economic activities as well
as the establishment of a local PV industry. To grasp such
impacts quantitatively, a technical analysis of an industrial
initiative in the photovoltaic sector and evaluation of the
socio-economic impacts of the PV demand in terms of
gross domestic production and job creation were carried
out by the I/ O analysis method. When assuming the trans-
fer of a facility with the capacity of 5 MW/ year, it has
been made clear that the local availability of cells (Case L)
brings very different returns on investment in the local
economy, and the induced production increases from
1,4 times to 3,5 times the expenditure, as shown in Figure
B.11 and Table B.3. The induced job creation involved
Figure B.10 Case of small PV systems along w ith
netw ork
Figure B.11 Necessary expenditure and induced production (MUSD)
19
VLS-PV Case Studies
2 570 employees (Case L), while on the other hand, in the
case of not assuming the availability of local cell produc-
tion (Case I), the induced job creation involved 489
employees.
Besides the economic effects of manufacturing, the
availability of PV systems contributes to support social and
economic development of the region that is more
environmentally sound. To perform technology transfer
effectively, clear knowledge of the needs of, as well as the
potential benefits to, the local population is required.
However, it is expected in the future that VLS-PV will
be reinforced year by year with operating PV module
facilities in the region, and that the electricity generated
by VLS-PV will be able to supply global areas through the
Mediterranean Network. As a result, an electricity-for-
technology exchange scheme may be initially set up.
B.5 CASE STUDIES ON THEM IDDLE EAST DESERT
There are certain types of PV systems considered for
constructing VLS-PV systems. In addition to the fixed-
module VLS-PV, the use of sun-tracking non-concentrator
and concentrator PV systems is expected. The relative
performances – which involved static PV modules
(oriented facing south, with tilt angle equalling geographic
latitude), one-axis tracking modules (having a horizontal
axis in the N–S direction), two-axis tracking modules, and
a 400× point-focus concentrator PV system – are addressed
and the potential economic benefits of employing highly
concentrated solar radiation as an energy source for PV
cells were considered. As a practical site, the Negev Desert
was chosen, because the Negev is located at a truly repre-
sentative ‘point’ among the principal deserts of the Middle
East and has produced a wealth of documented detailed
meteorological data.
Computer simulations were carried out, using a typical
meteorological year (TMY) dataset for a specific Negev
site, Sede Boqer. At Sede Boqer, a 25 m diameter multi-
purpose solar concentrator operating at a solar concentra-
tion of 400×, as shown in Figure B.12, already exists.
Simulations have indicated that, in a typical Middle
Eastern desert, 8,5 % total system efficiency from a
conventional static PV system, 10,7 % effective system
efficiency for a one-axis sun-tracking system, and 11,8 %
effective system efficiency for a two-axis tracking system
are to be expected, where all three system types employ
identical, polycrystalline Si PV modules. However, using
a dense array of Si concentrator PV cells in a 400-sun
point-focus system, the simulations have indicated that
16,5 % total system efficiency (17,2 % effective system
efficiency) may be attainable if the cells are actively cooled
so as to remain at a fixed temperature of 60 °C. Here,
effective system efficiency was defined as the total annual
A.C. energy output divided by the annual global irradi-
ance that would be received by a static system of similar
aperture area, irrespective of the type of PV system that
was being discussed (i.e. one-axis, two-axis, or concen-
trator).
R egarding the prospects for a concentrated VLS-PV
plant, it was concluded that a single 1 m2 concentrator PV
module exposed to a light flux of 400 suns (where 1 sun is
Table B.3 Induced impacts of transferring a PV module manufacturing facility
Total induced Value added Job creation
(1 000 USD) (1 000 USD) (man-years)
I L I L I L
1 Photovoltaic 16 294 16 294 1 485 1 485 87 87
6 Misc. petroleum and coal products 205 1 248 160 975 23 138
7 Petroleum refineries 271 1 612 53 315 8 45
8 Electricity and water 335 1 492 85 377 12 53
18 Metals smelt ing and pressing 323 4 477 113 1 573 16 223
19 Fabricated metal products 301 1 082 113 406 16 58
20 Non-electrical machinery 44 599 18 248 3 35
22 Electrical and electronic equipment 501 16 350 170 5 567 24 791
24 Chemicals 1 039 3 718 318 1 138 45 162
25 Rubber and plastics 656 1 210 217 400 31 57
28 Commerce and transport 195 1 244 111 709 21 132
31 Insurance 500 539 157 169 28 30
32 Other services 648 2 326 415 1 492 73 262
Others 947 5 389 446 2 317 103 497
Total 22 259 57 581 3 862 17 099 489 2 570Induced production coeff icient 1,36 3,53
Figure B.12 The PETAL (Photon Energy Transformation and
Astrophysics Laboratory) 400 m2 aperture parabolic dish
reflector at Sede Boqer (the square screen at its focal point is
1 m x 1 m in size)
Executive Summary B
20
here defined as 1 000 W/ m2) would produce nearly 100 kW
of electric power. Table B.4 compares a number of area-
related output parameters of interest for all four types of
systems.
The estimation of the cost of a 30 MW turnkey project
was approximately 136 500 USD per concentrator (CPV)
unit, where in a typical meteorological year each unit would
generate 154 000 kWh of A.C. electricity at Sede Boqer.
When assuming 30-year financing, the electricity would
work out to 0,045 USD/ kWh in the case of 3 % interest
Table B.4 Comparison of predicted area-related performance parameters for various VLS-PV systems at Sede Boqer
Static 30° t ilt One-axis tracking Two-axis tracking Concentrator (CPV)
System yield (kWh ⋅ kW -1 ⋅ y-1) 1 644a 2 071a 2 279a 1 754b
Yield per PV module area (kWh ⋅ m -2 ⋅ y-1) 189 238 262 154 000
Yield per 400 m2 light capture area (kWh⋅y-1) 75 600 95 200 104 800 154 000
Land area/light capture area 2,89 3,42c 7,90d 7,90d
Yield per land area (kWh ⋅ m -2 ⋅ y-1) 65,4 69,6 33,2 48,7
aSolarex MSX64 modules.bModified SunPower Heda 303 cells.cRancho Seco plant.dHesperia Lugo plant.
and to 0,064 USD/ kWh in the case of 6 % interest. By
considering annual O&M costs to be 2 % of the capital
cost, 0,018 USD/ kWh would be added to the electricity
costs given above.
There is a wealth of hardware and performance data
available for non-concentrator PV systems for validation,
while the experimental situation is sparse for concentrated
PV systems. However, it might be concluded that the
economics of a concentrator VLS-PV plant could turn out
to be attractive.
21
Scenario Studies and Recommendations
EXECUTIVE SUMMARY C
Scenario studies and
recommendations
Through Parts I and II, it was suggested that the VLS-PV
system would be an attractive energy source in the 21st
century. However, the long-term sustainable operation of
VLS-PV systems must be discussed considering local ben-
efits to be brought about by introduction and expansion
of the VLS-PV system. Then the step-by-step enlargement
of the PV system might be an effective way to prevent
financial, technological and environmental risks caused by
its rapid development. In addition, it is expected that this
activity will be continued with properly allotted efforts for
further quantitative discussion and necessary evaluation of
VLS-PV to improve our knowledge, to overcome its
defects and to establish an international network with other
interested people. In Part III, based on the generalized
understandings from Parts I and II, scenario studies were
carried out and ‘recommendations’ to stakeholders as
conclusions were described.
In the scenario studies, a concept for the sustainable
growth of VLS-PV was discussed, which included both
the long-term economic aspects and the life-cycle point
of view, and a development scenario assuming actual stages
was proposed. Further, the financial and organizational
sustainability on proposed stage was discussed.
Finally, in order to propose mid- and long- term
scenario options that would enable the feasibility of
VLS-PV, recommendations for considerable stakeholders
were given to realize such long-term targets gradually.
C.1 SUSTAINABLE GROWTH OF THEVLS-PV SYSTEM CONCEPT
VLS-PV has a huge generating power capacity and it
will be more feasible to enhance the capacity gradually.
Therefore, for the introduction of VLS-PV, a develop-
ment scheme for sustainable growth is needed. Considering
the economic aspects of VLS-PV is also important for a
sustainable initiative.
The domestic production of PV modules is one of the
most important issues for the successful introduction of
VLS-PV. As an example, a conceptual scheme of PV
module manufacture through technology transfer to the
region, as shown in Figure C.1, was considered. PV
modules produced at the facilities will be installed in desert
areas as part of a centralized system.
The power-generating capacity of the system will be
reinforced yearly with operating PV module facilities and
a VLS-PV system will be developed. Figure C.2 shows the
sustainable scheme for VLS-PV development, which
supposes that the capacity of VLS-PV will be over 1 GW
in 28 years, and will reach 1,5 GW in 43 years. With the
replacement of PV modules and facilities, and with
operating facilities, the VLS-PV will be a sustainable power
plant. Further, when a variety of VLS-PV components are
produced near the VLS-PV and waste management, like
recycling, is introduced, ‘scrap and build’ for VLS-PV will
be realized, as shown in Figure C.3.
In the economic analysis, the generation cost for VLS-
PV was estimated to be around 3–5 US cents/ kWh for
1,5 GW. However, to obtain long-term economic benefits,
providing advantageous incentives will be needed in the
first stage. Further, for deploying domestic/ regional manu-
facturing of VLS-PV system components, it is necessary
to build a financial mechanism for investing in facility
operation, not only investment for constructing the facility.
Some organizational/ institutional support will be indispen-
sable and this will contribute not only to profitability in the
long term but also to successful technology transfer.
Figure C.1 Conceptual view of a sustainable, technology
transfer scheme
Executive Summary C
22
C.2 POSSIBLE APPROACHES FOR THE FUTURE
The VLS-PV scheme will be a project that has not been
experienced before. Therefore, to realize VLS-PV it is
necessary to identify issues that should be solved and to
discuss a practical development scenario. Focusing on the
technical development, a basic concept for VLS-PV devel-
opment, which consisted of the following four stages, was
proposed. Although the capacity of the first PV system
was set at 25 MW, R&D stage (S-0) was assumed as the
first stage to verify the basic characteristics of the PV sys-
tem.
• S-0: R &D stage (four years)
• PV system: 5 × 500 kW research system
• Price of PV module: 4 USD/ W
Figure C.2 Sustainable scheme for VLS-PV development
Figure C.3 Example of a concept for sustainable growth of VLS-PV
23
Scenario Studies and Recommendations
• PV module: import from overseas
• Inverter: import from overseas
• S-1: Pilot stage (three years)
• PV system: 25 MW pilot system
• Price of PV module: 3 USD/ W
• PV module: import from overseas
• Inverter: import from overseas
• S-2: Demonstration stage (three years)
• PV system: 100 MW large-scale system
• Price of PV module: 2 USD/ W
• PV module: domestic/ regional production
• Inverter: import from overseas
• S-3: Deployment stage (five years)
• PV system: around 1 GW VLS-PV system with
energy network
• Price of PV module: 1 USD/ W
• PV module: domestic/ regional production
• Inverter: domestic/ regional production
To develop VLS-PV, there are many technical and non-
technical aspects that should be considered in each stage.
These are summarized in Table C.1.
S-0: R&D stage (four years)
Five 500 kW PV systems will be constructed and operated
to verify the basic characteristics of the PV system in a
desert area. The reliability of VLS-PV in a desert area and
the requirements for grid connection will be mainly
examined and investigated as technical issues. Conditions
for site selection, planning of co-operation frameworks,
including training engineers, and funding schemes will be
investigated as non-technical issues.
S-1: Pilot stage (three years)
A 25 MW PV system will be constructed and operated to
evaluate and verify preliminary characteristics of a large-
scale PV system. Technical issues here are of a higher level
and shift to concentrated and grid-connected PV systems,
for building VLS-PV technical standards. PV module
facilities will be constructed and operated although the
PV modules constructed would be imported. PV module
production will be introduced in the next stage. Further,
development for preventing desertification, such as
vegetation and plantations, will also be started at this stage.
S-2: Demonstrat ion stage (three years)
A 100 MW PV system will be constructed and operated
to research methods of grid-connected operation and
maintenance when VLS-PV actually takes on part of
the local power supply. The knowledge, on connecting
VLS-PV to the existing grid line, obtained at this stage
will be technical standards for deploying VLS-PV. Non-
technical issues will also advance for industrialization. Mass
production of PV modules will be carried out and BOS
production on-site will be started towards a deployment
stage.
S-3: Deployment stage (f ive years)
A 1 GW PV system will be operated to verify the capability
of VLS-PV as a power source. Although the technologies
for generating and supplying electricity will be nearly
completed, for deployment of VLS-PV in the future, some
options such as demand control, electricity storage and
component recycling will be required. These will contrib-
ute to building the concept of the solar breeder, which is
similar to ‘scrap and build’ shown in Figure C.3, and some
business plans for VLS-PV will be proposed.
The implementation of VLS-PV will activate the world PV
industries in a wide range of technologies involving a vast
range from solar-cell production to system construction.
However, to achieve the final stage, the previous stages
from S-0 to S-2 are important, and the developments in
each stage should be carried out steadily.
Table C.1 Summary of the VLS-PV development scenario
Sub-stage
Technical issues Non-technical issues
S-0: Scale of system: 5 x 500 MW • Examination of the reliability of • Site selection for VLS-PV based on
R&D stage Module cost: 4 USD/W a PV system in a desert area various condit ions
Module: import from overseas • Examination of the required • Project planning, including training
Inverter: import from overseas ability of a PV system for grid engineers and funding
connection
S-1: Scale of system: 25 MW • Development of the methods of • Development of the area around
pilot stage Module cost: 3 USD/W O&M for VLS-PV VLS-PV to prevent desert if ication
Module: import from overseas • Examination of the control of • Training engineers for PV module
Inverter: import from overseas power supply from a PV system production on-site
to grid line
S-2: Scale of system: 100 MW • Development of the technical • Training engineers for mass production
demonstration stage Module cost: 2 USD/W standards for O&M of VLS-PV, of PV modules and for BOS production
Module: domestic/regional including grid connection on-site
production • Preparation for industrialization by
Inverter: import from overseas private investment
S-3: Scale of system: 1 GW • Building the concept of ‘solar breeder’ from the viewpoint of technical and
deployment stage Module cost: 1 USD/W non-technical issues
Module: domestic/regional
production
Inverter: domestic/regional
production
Executive Summary C
24
C.3 FINANCIAL AND ORGANIZATIONALSUSTAINABILITY
The proposed scenario for the development and introduc-
tion of very large-scale PV systems in deserts has basically
four stages: R &D, pilot, demonstration and deployment
(commercial) stages. The characteristics of these stages range
from theoretical to technical, i.e. through the techno-
economic, socio-economic and purely commercial
characteristics. Each stage of growth has its own charac-
teristics and cost structure.
From a viewpoint of the financial scenario, the feasibil-
ity stage should be settled before the R &D stage. The
estimated investment levels for these phases range from
1–2 MUSD for the feasibility stage to 4 000 MUSD for
the commercial stage.
An indicative portfolio of funding sources for each stage
is identified. Since the first two stages are not supposed
to be commercial, but are theoretical and experimental,
no further exploitation or return on investment (ROI)
calculation is undertaken. At this moment, the costs and
funding arrangements of the commercial stage can only
be estimated. The third stage (the demonstration stage)
should generate cost and income details for a full invest-
ment proposal for such a large plant.
There are six potential sources of financing the invest-
ment. In Table C.2, a first estimate of possible contribu-
tions from these sources is given:
• Direct subsidies may be provided for demonstration,
experimental, export promotion, or development
co-operation reasons by governmental bodies. The closer
a given situation is to being commercial, the lower the
direct subsidies that are expected to be granted.
• The provision of soft loans and green money may be
dr iven by similar motives, but they can also be
provided by private capital. The loan money should
increase as the project becomes more commercial to
leverage the ROI for the shareholders.
• Equity and in-kind contributions are investments by
the shareholders of the project. Examples of in-kind
contributions are office housing and free management
services.
• Import duties may be exempted or reduced to stimulate
the uptake of new or renewable energy technologies in
a particular country.
• Green certificate buy-off may constitute an up-front
contribution of a utility that subsidizes the project and
receives green certificates in return.
• Other instances may be profit tax advantages of inves-
tors regarding the project.
Basically, all net investment costs, interest and profits should
be recovered through exploitation of the plant. The net
investment is the investment after subtracting subsidies and
fiscal advantages. There are four recognized sources of
income during the exploitation stage:
• electricity power sales
• opportunity costs, to be explained later
• green certificates, not to be double-counted with a
possible up-front investment
• tax incentives, such as reduced VAT and exemption
from pollution taxes.
In Table C.3, an overview of the income and recurring
costs from the exploitation is given.
The feasibility stage is easily supported when applying
to national or multinational governmental organizations.
The size and novelty of the project is expected to gear
sufficient interest to achieve the involvement of the World
Bank, the EU, and the respective national governments of
interested OECD countries. There are no exploitation costs
or income at this stage. At a cost of around 30–40 MUSD,
this R &D/ pilot project would be a project of a relatively
large size for individual governments to bear, but not for
two or more governments or multilateral organizations. As
Table C.2 Example of contribution towards investment by various sources of co-funding in the different stages of the
introduction of VLS-PV
Source Direct subsidies (Soft) loans Equity and Import duty Green cert if icate Others, such Totala
including green in-kind reduction buy-off and as profit tax
Stage money JI funds advantages
1. Feasibility 75 % 0 % 15 % – – 10 % 100 %
2. R&D/pilot 50 % 30 % 10 % 10 % – – 100 %
3. Demonstration 25 % 30 % 15 % 10 % 15 % 10 % >100 %
4. Deployment/
commercial 5 % 65 % 15 % 10 % 10 % 10 % >100 %
aRedundancy of funding is necessary to reduce risks.
Table C.3 Estimated income as a percentage of total recurring costs after subsidy of the different stages of the introduction
of VLS-PV
Source of funding Electricity Opportunity Green Tax Others Total
Stage costs cert if icates incentives
1. Feasibility – – – – – –
2. R&D/pilot 50 % – 30 % 20 % – 100 %
3. Demonstration 30–50 % 0–17 % 18 % 0–30 % – 48–115 %
4. Deployment/
commercial 50 % 10 % 20 % 20 % – 100 %
25
Scenario Studies and Recommendations
it has interesting technical and social aspects, there will be
multiple instruments to apply for funding. The strongly
reduced investment by heavy subsidies will enable the
electrical power to be sold favourably. Thus electricity
accounts for 50 % in the income of the plant. Other sources
of income are green certificate values and tax incentives.
The subsidy for the cost and financing of a 100 MW
demonstration plant will be reduced. The exploitation could
be economically attractive, depending on several assump-
tions. The first and most important are the value of green
certificates and the value of so-called opportunity costs.
These opportunity costs are costs avoided by certain
companies or increased income for such companies, due
to the existence of the VLS-PV project. The deployment/
commercial stage will have to benefit from reduced costs
of PV modules and increased cost of power and of green
certificates. However, it may be too early to give more
details regarding such a 1 GW plant.
It is recommended to make a full-scale feasibility study
for an R &D project and a 100 MW demonstration plant.
This feasibility study should identify targets and location,
and fully secure funding sources and electricity outlets for
both stages. Without funding identified and secured for
the 100 MW demonstration plant, the R &D stage should
not be implemented.
C.4 RECOM M ENDATIONS
As an overall conclusion of this work, recommendations
are given here to realize long-term targets based upon the
results of the studies performed in the IEA Task VIII. The
adoption of VLS-PV will require four steps, as shown in
Figure C.4:
1. Absorbing the concept of VLS-PV in a desert environ-
ment
2. Considering a long-term scenario approach
3. Positioning yourself in terms of your strategy
4. Making an action plan and allocating resources
In this report, concrete information on VLS-PV is given,
so the first two steps can be taken into consideration.
The generalized understandings and recommendations
on a policy level give direction to those who consider the
adoption process. To support those willing to consider the
third and fourth steps, an initial checklist is given.
C.4.1 General understandings
Based on this report, the considered stakeholders may
recognize the following valuable findings.
VLS-PV can contribute substantially to global energy needs
• The world’s deserts are so large that covering 50 % of
them with PV units would generate 18 times the
primary energy supply of 1995.
• All global energy scenarios project solar PV energy to
develop into a multi-gigawatt energy generation
option in the first half of this century.
VLS-PV can become economically and technologically
feasible
• Electricity generation costs are between 0,09 and 0,11
USD/ kWh, depending mainly on annual irradiation
levels (with module price 2 USD/ W, interest rate 3 %,
salvage value rate 10 %, depreciation period 30 years).
These costs can come down by a factor of 2–3 by the
year 2010.
• The PV technology is maturing with increasing
conversion efficiencies and decreasing prices per watt;
projected prices of 1,5 USD/ W around the year 2010
would enable profitable investment and operation for a
100 MW PV plant.
• Solar irradiation databases now contain detailed infor-
mation on irradiation in most of the world’s deserts.
VLS-PV can contribute considerably to the environment
• The life-cycle CO2 emission is as low as 13 g-C/ kWh;
this is mainly due to the module production and the
array support. This should be compared with the value
of 200 g-C/ kWh for just the fuel component of
conventional fossil-burning power plants.
• The environmental issues for which VLS-PV may
provide a solution are global warming, regional
desertification and local land degradation.
VLS-PV can contribute considerably to socio-economic
development
• Plant layouts and introduction scenarios are available
in preliminary versions. I/ O analysis concluded that
25 000–30 000 man-years of local jobs for PV module
production will be created per 1 km2 of VLS-PV
installed.
VLS-PV development needs a long-term view and
consistent policy
• To reach the level of a 1 GW system, four intermediate
stages are recommended: R &D stage, pilot stage, dem-
Figure C.4 Flowchart for recommendation
Executive Summary C
26
onstration stage, and deployment (commercial) stage.
From stage to stage, the system scale will rise from
2,5 MW to 1 GW, the module and system cost will go
down by a factor of 4, and manufacturing will be shifted
more and more to the local economy.
• In the concept of sustainable local economic growth,
the first local PV module manufacturing facility has an
annual output of 5 MW. This local production provides
for construction of the local VLS-PV system. In subse-
quent years, four more 5 MW module manufacturing
facilities are brought into operation, so that annually
25 MW is supplied to the local VLS-PV system. After
10–15 years, a module production facility of 50 MW is
put into operation. Every 10 years this facility will be
replaced by a more modernized one. Thus after
approximately 40 years a 1,5 GW VLS-PV power
station will be in operation, and the local manufactur-
ing facility will supply for replacement. In this way,
local employment, and thus the economy, will grow
sustainably.
• To realize the final commercial stage, a view to financ-
ing distribution has been developed for all of the three
previous stages, consisting of direct subsidies, soft loans,
equity, duty reduction, green certificates and tax
advantages. It is clear that direct subsidies will play an
important role in the first stage.
C.4.2 Recommendations on a policy level
From the global energy situation, global warming and
other environmental issues, as well as from the case studies
and scenarios, it can be concluded that VLS-PV systems
will have a positive impact. To secure that contribution, a
long-term scenario (10–15 years) on technological,
organizational and financial issues will be necessary.
Action now is necessary to unveil the giant potential of
VLS-PV in deserts. In such action, involvement of many
actors is welcome. In particular, the following are recom-
mended on a policy level:
• National governments and multinational institutions
adopt VLS-PV in desert areas as a viable energy
generation option in global, regional and local energy
scenarios.
• The IEA PVPS community continues Task VIII for
expanding the study, refining the R &D and pilot stages,
involving the participation by desert experts and
financial experts, and collecting further feedback infor-
mation from existing PV plants.
• Multilateral and national governments of industrialized
countries provide financing to generate feasibility studies
in many desert areas around the world and to imple-
ment the pilot and demonstration phases.
• Desert-bound countries (re-)evaluate their deserts not
as potential problem areas but as vast and profitable
(future) resources for sustainable energy production. The
positive influence on local economic growth, regional
anti-desertification and global warming should be
recognized.
C.4.3 Checklist for specific stakeholders
To decision-makers in industrialized countries
You obviously have a long-term view of the world energy
market trends and the need to provide a national energy
outlook.
• Have you considered the future possibility of VLS-PV
for your industries, which may become major enter-
prises controlling the world energy market?
• Do you have a step-by-step plan for R &D to make
good use of the extensive capabilities in photovoltaic
technology when the world energy problem arrives?
• Do you have a view to initiate, continue and extend
bi- or multilateral international collaboration with
those developing countries which have abundant solar
energy?
• Do you have funds available for R &D or pilot
programmes with training courses to introduce PV tech-
nology into developing regions, especially around deserts
as a first stage of a consistent step-by-step approach?
• Do you have strategies in place to maintain regional
sustainability and to consider a moderate technology
transfer scenario when planning the further develop-
ment of developing countries?
• Have you considered using your influence to mobilize
multilateral institutions to stimulate VLS-PV?
To decision-makers in developing countries
You obviously are aware of the coming world energy
problem in 20–30 years.
• Did you include solar PV energy as one of the most
favourable renewable energy options when national
master plans for energy supplies were discussed?
• Have you considered the opportunity that your country
will be able to export PV energy to neighbouring
regions and that new jobs will be brought to your
people?
• Are you aware of the fact that PV technology has
already proven itself to be a cost-competitive energy
source for rural electrification and is still being improved
very rapidly? In particular, are you aware that it is
especially effective for stabilizing rural lives?
• Have you considered a regional development plan that
utilizes abundant electricity production and vast lands?
• Have you settled on a step-by-step, long-term approach
that starts with solar home systems or mini-grids as the
first stage and finally reaches VLS-PV in 20–30 years?
• Do you have a plan to cultivate and gradually raise a
domestic PV specialists’ society from an early stage to a
developed stage?
• Have you already asked for support from the variety of
financial institutions you can utilize?
To decision-makers in oil-export ing countries
You obviously are aware of the fact that many oil-export-
ing countries around desert areas also have an everlasting
natural resource: solar energy.
27
Scenario Studies and Recommendations
• Are you aware that you can export PV energy to neigh-
bouring regions as well?
• Do you know that PV technology has already been
proven as a cost-competitive energy source for rural
electrification and is still being improved rapidly?
• Did you develop a long-term view of the future world
energy market and your strategy including the new level
of photovoltaic power plants and industries? Are you
aware that it will bring you opportunities for high-tech
industries and new jobs?
• Can you confirm the study results that a 100 MW PV
power plant will be economically attractive in an oil-
exporting country? Have you discovered good condi-
tions in interest rates, the value of green certificates and
the value of opportunity benefits from oil savings?
• Have you decided to invest in the development of the
world photovoltaic business?
• Did you choose an appropriate scale for starting
towards VLS-PV?
To f inancing institut ions and banks
You are presumably aware of the fact that the market
potential for VLS-PV amounts to 2 billion people world-
wide.
• Are you aware of the Task VIII study results that show
the size of indicative investment levels for the 100 MW
demonstration stage and the 1 GW deployment stage
corresponds to 500 and 4 000 MUSD respectively? Do
you consider this much different from the magnitude of
hydropower or infrastructure projects in a budgetary
sense?
• Do you respect the following funding scenario study
for a 100 MW demonstration stage and a 1 GW
deployment stage? They are economically attractive in
some cases, assuming that 30–65 % of total investment is
met by soft loans with 4 % interest. Another portion is
expected to come partially from subsidy, equity, tax
reduction, etc.
• Can you positively support a full-scale feasibility study
for a pilot project and for a 100 MW demonstration
plant as a continuation of the Task VIII? This will iden-
tify targets and locations and will secure the funding
sources and electricity outlets for both stages.
• Can you support the pilot stage and the 100 MW
demonstration stage according to the results of this
study?
• Could you consider a low-interest soft loan on a long-
term basis for the initiation of VLS-PV system projects
around desert areas?
To PV industry associat ions and mult inational industries
You are obviously aware of possibilities for future market
growth in southern countries.
• Are you aware of the future possibility of VLS-PV for
PV industries? They may become major enterprises
controlling the world energy market.
• Are you confident that the photovoltaic technology and
market will become competitive on a worldwide level
within 20 years?
• Can you ensure that the prices for solar PV energy will
be reduced by a factor of a half to a quarter within the
next decade?
• Can you support and invest in local industries to take
off according to the technology transfer scenario?
To PV specialists and the academic community
You know that fundamental research will generate new
seed technologies for VLS-PV.
• Can you confirm expected directions such as very high-
efficiency PV cells, high-concentration optics, organic
polymer PV cells, chemical energy transportation
media like hydrogen or methanol, superconducting
power transmission and so on?
• Did you formulate and assist a PV specialist society in
developing countries in co-operation with top leaders
in those countries?
• Will you join our continuing work, seeking the realiza-
tion of VLS-PV systems? Expected work items may
include more precise case studies for specific sites
and funding, proposals for R &D co-operation plans,
other possibilities in technological variety, resource
evaluation, additional value analysis and so on.
To power ut ilit ies
You have clearly recognized that the world energy
market structure will change very drastically in the near
future.
• Can you confirm business opportunities in photovoltaics
within the next decades?
• Can you confirm that a power transmission scenario is
possible according to our study results? Additional tie-
line construction of less than 100 km, for connecting
VLS-PV through existing national power grids to a load
centre, will raise the electricity price by less than 1 US
cent/ kWh. One example is a transmission operation in
co-operation with coal-burning power stations located
on a colliery.
• Are you ready to invest in photovoltaic industries and
foster technological societies with a long-term view for
the future world energy market?
To the Internat ional Energy Agency
You are clearly aware that the diversification of energy
resources and the development of alternative energy are
essential for overcoming the world energy problems within
the next decades.
• Can you confirm our view that solar PV energy is one
of the most favourable options for future electricity
production?
• Can you confirm your continuous support of the IEA
PVPS Implementing Agreement on the basis of the long-
term world energy outlook?
Executive Summary C
28
• Would you support our idea about multilateral activities
between IEA member countries and developing countries?
• Can you organize the higher level of IEA PVPS activi-
ties including demonstration projects for VLS-PV?
• Do you want to support a full-scale feasibility study
corresponding to a pilot project and a 100 MW dem-
onstration plant? This will identify targets and location,
and fully secure funding sources and electricity outlets
for both stages.
• Can you support and enhance the continuing work in
the IEA PVPS Task VIII? Expected work items are to be:
• more precise case studies for specific sites including
detailed local conditions and funding sources as well
as demand application,
• proposals for the first or second stage of co-operation
plans to be submitted to financial institutions,
• comprehensive evaluation of other possibilities of a
technological variety such as tracking, concentrator
and advanced PV cells,
• resource evaluation of VLS-PV by means of remote
sensing technology,
• investigation of additional effects of VLS-PV on the
global environment such as global warming and
desertification,
• expansion of evaluating approaches to other types of
PV mass applications in the 21st century, including
value analysis in the economy, environment, socio-
economy and others.
The world’s deserts are sufficiently large that, in theory, covering a fraction of their landmass with PV systems could
generate many times the current primary global energy supply. Moreover, the energy produced is from solar radiation
– a clean and renewable source – hence such systems would have the potential to contribute massively to the
protection of the global environment.
Energy from the Desert is an extensive and high-level international study, representing the accumulated research of
the world experts involved in Task VIII of the IEA PVPS Programme. This Summary highlights the principal findings of
the full report (available separately).
To date, the market focus for photovoltaics has been on small to medium, stand-alone or building-integrated power
systems, which have proven, but as yet not realized, the great potential of this technology. Energy from the Desert
evaluates the feasibility, potential and global benefits of very large scale photovoltaic power generation (VLS-PV)
systems deployed in desert areas and each generating from 10MW to several gigawatts.
The study details the background and concept of VLS-PV, maps out a development path towards the realization of
VLS-PV systems, and provides firm recommendations to achieve long-term targets, based on the findings of the IEA
Task VIII experts. Critical aspects examined are:
• photovoltaic technologies, systems design and plant operation
• finance, cost-benefits and profitability
• impact on and benefit to global, regional and local environment
• policy-level and investment issues
Energy from the Desert is the first study to provide a concrete set of answers to the questions that must be addressed
in order to secure and exploit the potential for VLS-PV technology and its global benefits. It will be invaluable to
government, energy planners, policy makers, utilities and international organizations assessing the potential for this
technology, PV systems manufacturers and infrastructure providers wishing to develop this new market and
consultants, scientists, researchers and engineers involved in the field.
THE EDITOR
Energy from the Desert is edited by Professor Kosuke Kurokawa, Operating Agent-Alternate, IEA Task VIII with
contributions from a panel of fourteen acknowledged international experts from eight countries. Professor Kurokawa
has 30 years’ experience in energy systems technology including HVDC transmission and solar photovoltaics. He is
currently engaged in researching a wide variety of photovoltaics systems concepts from small AC modules to very
large scale PV systems at the Tokyo University of Agriculture and Technology (TUAT).
Energy from the Desert
James & James (Science Publishers) Ltd
8-12 Camden High Street, London NW1 0JH, UK
www.jxj.com