Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
KULeuven Energy Institute
TME Branch
WP EN2018-13
Design and off-design optimization procedure for low-temperature geothermal
organic Rankine cycles
Sarah Van Erdeweghe, Johan Van Bael, Ben Laenen and William D‘haeseleer
TME WORKING PAPER - Energy and Environment Last update: February 2019
An electronic version of the paper may be downloaded from the TME website:
http://www.mech.kuleuven.be/tme/research/
Design and off-design optimization procedure for low-temperaturegeothermal organic Rankine cycles
Sarah Van Erdeweghea,c, Johan Van Baelb,c, Ben Laenenb, William D’haeseleera,c,∗
aUniversity of Leuven (KU Leuven), Applied Mechanics and Energy Conversion Section, Celestijnenlaan 300 - box2421, B-3001 Leuven, Belgium
bFlemish Institute for Technological Research (VITO), Boeretang 200, B-2400 Mol, Belgium
cEnergyVille, Thor Park 8310, B-3600 Genk, Belgium
Abstract
In this paper, a two-step optimization methodology for the design and off-design optimization of
low-temperature (110-150◦C) geothermal organic Rankine cycles (ORCs) is proposed. For the in-
vestigated conditions—which are based on the Belgian situation—we have found that the optimal
ORC design is obtained for design parameter values for the environment temperature and for the
electricity price which are both higher than the respective yearly-averaged values. However, the net
present value is negative (-12.62MEUR) which indicates that the low-temperature (130◦C) geother-
mal electric power plant is not economically attractive for the investigated case. Nevertheless, and
demonstrated by the results of a detailed sensitivity analysis, a low-temperature geothermal power
plant might be economically feasible for geological sites with a higher brine temperature or in a coun-
try with a more favorable economic situation; e.g., with higher electricity prices (∼70EUR/MWh).The novelty of our paper is the development of a thermoeconomic design optimization strategy for
low-temperature geothermal ORCs, accounting for the off-design behavior already in the design
stage. The generic methodology is valid for low-temperature geothermal ORCs (with MW scale
power output) and includes detailed thermodynamic and geometric component models, is based on
hourly data rather than monthly-averaged data and accounts for economics.
Keywords: ORC, geothermal energy, design optimization, off-design performance
∗Corresponding authorEmail address: [email protected] (William D’haeseleer)
Preprint submitted to Applied Energy February 18, 2019
1. Introduction
Geothermal energy is readily available all over the world, as long as one is willing to drill deeply
enough. Nevertheless, the available geothermal source temperature depends on the site-specific
geological conditions. In this work, geothermal source (also called brine) temperatures of 110-150◦C
are considered, which are typical for non-volcanic regions like NW Europe. The organic Rankine
cycle (ORC) is the most appropriate energy conversion cycle to effectuate this low-temperature
heat-to-electricity conversion.
Some relevant thermodynamic and economic studies have already been performed in the literature
and are briefly discussed. Imran et al. [1] have compared the basic, recuperated and regenerative
ORC set-ups 1 for application in a geothermal power plant (160◦C, 5kg/s). A Pareto front solution
has been shown for the specific investment cost (SIC) and the exergy efficiency (ηex)2, as they are
conflicting optimization objectives. The authors have found that the basic ORC has the lowest SIC
for ηex < 45% whereas the regenerative ORC has the lowest SIC for ηex > 45%.
Braimakis et al. [2] have performed a thermoeconomic optimization of the standard and the regen-
erative ORC. Heat source temperatures of 100, 200 and 300◦C and heat source capacities of 100,
500, 1000 and 2000kWth have been considered, representing different energy sources. They have
concluded that the expander type has a dominant role in the economic performance of ORCs. Fur-
thermore, the authors do not recommend the use of a regenerative ORC for geothermal applications,
because the performance benefits are found to be insignificant and the economic competitiveness
inferior.
Astolfi et al. [3] have performed a thermodynamic and thermoeconomic optimization of differ-
ent types of ORCs for application to low- to medium-enthalpy geothermal brines (120 − 180◦C,
1In a recuperated ORC, a heat exchanger (the recuperator) is used the preheat the working fluid before it enters
the economizer/evaporator with the heat of the turbine outlet vapor. In a regenerative ORC, part of the working
fluid mass flow rate is extracted between two turbine stages to preheat the working fluid in direct contact before it
enters the economizer/evaporator.2The exergy efficiency has been based on the flow exergy which is transferred between the brine and the working
fluid in the evaporator. In our case, however, the exergetic plant efficiency is based on the exergy content of the
brine at the production state (so we consider the remaining brine flow exergy at the injection state as a loss for the
system).
2
200kg/s). The authors have found that the supercritical ORC, with a working fluid which has a
critical temperature slightly lower than the brine temperature, leads to the lowest SIC and that
the optimal operating conditions do not depend on the well costs. Furthermore, the results of the
thermoeconomic optimization are significantly different from the thermodynamic optimization re-
sults, which highlights the importance of including economics. For the investigated case, the main
effect of the economic optimization is a reduction of the total plant (-7%) and power block (-16%)
specific costs, even if the net power output decreases.
Fiaschi et al. [4] have compared the ORC, Kalina and CO2 cycles for geothermal heat sources
based on an exergoeconomic analysis. Two cases are considered for the geothermal heat source: a
medium-temperature source of 212◦C and a low-temperature source of 120◦C. The authors have
found that an ORC with R1233zd has the best performance for the medium-temperature source
(approximately 6MW power output) with a levelized cost of electricity (LCOE) of 88.5EUR/MWh.
For the low-temperature source, the Kalina cycle has shown the best performance. The electrical
power output is 22-42% higher than for the ORC and the LCOE is 125EUR/MWh (for a 500kW
power output).
Next to the design optimization, also the off-design performance of (geothermal) ORC plants has
been studied in the literature. Calise et al. [5] have developed an off-design simulation model
for recuperated ORCs powered by medium-temperature heat sources (solar, via diathermic oil at
160◦C, 20kg/s). First, the authors have performed a parameter study to find the optimal values for
the heat exchanger design parameters (tube length, tube number and shell diameter) for the lowest
annualized total cost of the ORC plant. The authors have found that by optimization 3 of the heat
exchangers geometry, the economic benefit, the net power generation and the global efficiency can
be increased with 21.06%, 20.01% and 33.60%, respectively. And second, the off-design performance
has been calculated for a varying source temperature in the range of 155 − 185◦C and a flow ratein the range of 18− 24kg/s. The maximum net power generation of 335.4kW is obtained for a flowrate of 18kg/s and a source temperature of 185◦C, the lowest value of 269.3kW is obtained for a
source temperature of 185◦C and a flow rate of 24kg/s.
Kim et al. [6] have performed an off-design performance analysis for an ORC fueled by waste heat
3The mentioned optimization was rather a parameter search in this case.
3
or residual heat from a combined heat-and-power plant. The authors have concluded that off-design
performance should be taken into account in the performance analysis. They have highlighted a
case for which the ORC design based on the nominal operating conditions would not be economical
because the actual source temperature and flow rate (during off-design) — and hence the electrical
power output — are generally lower than the design values. A pure thermodynamic study has been
performed without taking economics into account.
Hu et al. [7] have developed a model for the design and off-design calculation of a geothermal power
plant (90◦C, 10kg/s). No cost models have been included but the net electrical power output and
the cycle efficiency are used as the indicators. They have concluded that for an increase of the
source flow rate from 3.6kg/s to 14.4kg/s, the cycle efficiency increases from 2.6% to 6.3% and the
net power increases from 16.7kW to 88.7kW. The heat exchanger pressure drop in the design step
is limited to 3%, from which the heat exchanger layout has been calculated.
Astolfi et al. [8] have compared the performance of a dry-cooling system with the novel Emeritus
cooling system for application in a low temperature (120◦C) geothermal ORC. The Emeritus cooling
system is a dry-cooler with additional adiabatic panels and water sprays. The variables of the
optimization procedure are the cooling water temperature at the condenser inlet and the number
and type of heat rejection units. The authors have concluded that the novel Emeritus cooling
system is better than the dry-cooling system for the investigated desert climate and high electricity-
to-water price ratio. However, for mild climates and low electricity prices, the dry-cooling system
might perform better.
Wang et al. [9] have performed an off-design analysis of a solar ORC plant. The ORC has been
designed for the weather conditions on June 21st. As a result, the maximum net power output
occurs in June or September because then the operating conditions are the closest to the design
conditions. The exergy efficiency is the highest in December, and both the net power output and
the exergy efficiency are the lowest in August.
Manente et al. [10] have developed an off-design model for a low-enthalpy geothermal power plant
(100kg/s). The influence on the net power output by a varying heat source temperature (130-180◦C)
and a fluctuating environment temperature (0-30◦C) has been studied. The pump speed, turbine
capacity (using control valves) and the air-flow rate in the condenser are the control variables. The
off-design modeling has been simplified by assuming that the overall heat transfer coefficient only
4
depends on the mass flow rate (by a power law). The authors have concluded that the environment
temperature greatly influences the power output due to the air-cooled system and that the electrical
power output increases with the geothermal source temperature.
Other authors have investigated the design aspects as well as the off-design performance. Lecompte
et al. [11] have developed a thermoeconomic design methodology for an ORC, including off-design
behavior. The methodology has been applied to internal combustion engine waste heat with a
thermal power of 1800 to 3500kW. In a first step, the number of plates and the length of the plate
heat exchangers, and the number of tube rows and the frontal area of the condenser are optimized
together with the operating conditions towards minimal SIC. This is repeated for multiple design
values for the heat source thermal power and the environment temperature. In the second step, the
off-design analysis has been performed for every design point. The off-design results are based on
an hourly waste heat profile and hourly data for the environment temperature over one year. Using
the off-design results, the real SIC has been calculated corresponding to every design point and
the best design point (design values for the waste heat power and the environment temperature) is
indicated.
Petrollese et al. [12] have studied the optimal design of an ORC fueled by solar energy and a thermal
storage tank, considering the off-design performance. Different scenarios are defined based on the
hot fluid mass flow rate and inlet temperature to the ORC, and the environment temperature. In
the first step, a preliminary design of the components is calculated based on the thermodynamic
cycle under design conditions (source conditions: 275◦C, 12kg/s). Then the off-design performance
is calculated for the different scenarios and the respective LCOE is finally calculated (taking into
account the probability of each scenario). The authors have concluded that the different scenarios
should be considered together (a so-called multi-scenario approach) because this results in an ORC
design with the lowest LCOE value. The optimal ORC has a lower performance under design
conditions but is less sensitive to fluctuating heat source and ambient conditions.
Budisulistyo et al. [13] have developed a lifetime design strategy for a geothermal power plant in
New Zealand. The geothermal source temperature and flow rate decline over the plant’s lifetime of
40 years, starting from 131◦C and 200kg/s. The authors have calculated the design of a standard
ORC for the geothermal source conditions in years 1, 7, 15 and 30 and have found that the ORC
design for year 7 (with partly degraded source conditions) shows the best overall performance, with
5
a net present value (NPV) of 6.89MUSD. Furthermore, they have concluded that two types of
adaptations can be made to increase the performance at heat source degradation. The operating
conditions (working fluid flow rate and air flow rate in the condenser) can be adapted or structural
changes can be made such as installing a recuperator at the half-life or down-sizing the preheater
and vaporizer at the half-life.
Usman et al. [14] have compared the performance of an air-cooled and a cooling tower based ORC
for different climate conditions. Two types of geothermal sources have been considered: the first
one has a temperature and flow rate of 130◦C and 9.16kg/s, the second is at a temperature of 145◦C
and has a flow rate of 6.57kg/s. During off-design, the heat sink is controlled to get maximum power
output at different environment conditions. The ORC has been designed for summer conditions
such that it can benefit from larger pressure ratios in winter. The authors have concluded that the
environment conditions have significant effect on the power output. In summer, the drop in power
output can be 62% of its winter capacity. Furthermore, the authors have found that the cooling
tower based ORC is preferable for hot dry regions and that an air-cooled ORC can be implemented
in other climates.
In the aforementioned references, some assumptions have been made regarding the design and/or
thermodynamic cycle: a fixed geometry for the heat exchangers [1, 2, 6] or a fixed heat transfer
area [9], a fixed condenser temperature [1] or cooling water inlet temperature [2, 7], a fixed pinch-
point-temperature difference [1, 7, 8, 13], a fixed degree of superheating [9, 11, 14] and fixed (or
neglected) temperature and/or pressure drops over the heat exchangers [3, 5, 7–9]. However, to
properly calculate the economics of a geothermal ORC, these parameter values should be optimized.
Furthermore, some off-design studies have been based on monthly-averaged data [9, 13, 14] but then
the extreme weather conditions and the corresponding ORC operation are not considered. Note
also that a variety of optimization/simulation tools have been used in the literature: Matlab [1–
3, 7, 9–11, 14], EES [4, 5], Excel/VBA [8], Aspen Plus and EDR [13] and Aspen HYSYS [6]; which
means that there is no clear best tool for this kind of simulations.
In this paper, we propose a novel two-step optimization framework for low-temperature geothermal
ORCs. In the first step, the design of the geothermal ORC is optimized towards maximal NPV. In a
second step, the operating conditions are optimized towards maximal net power output depending
on the real environment conditions during off-design. Finally, the real NPV is calculated, taking the
6
off-design performance—and thereby the real power production—into account. In general the real
NPV differs from the value in the design stage because some parameter assumptions were made,
e.g., for the environment temperature and electricity price. The design which corresponds to the
highest real NPV is the optimal design of the power plant. In our work, the same optimization
framework is used for the design and the off-design optimization steps. The models for the heat
transfer and pressure drop calculations hold for design and off-design conditions. Only for the
turbine modeling, an off-design model for the turbine efficiency calculation has been added. Since
the same computer tool is used for the design and off-design calculations, errors related to the use
of different programming languages are avoided.
The novelties of our paper are multiple. First, the assumptions which are commonly made in the
literature regarding the design or the thermodynamic cycle (as mentioned before) are optimized in
our optimization framework. This results in a more accurate estimation for the thermodynamic
states and for the size and cost of the different components. Furthermore, the correlations used
are valid for multiple working fluids such that a generic (non-linear) optimization tool has been
obtained 4. Also, economics are included since the optimized values of the variables are different
compared to a pure thermodynamic approach [3]. Furthermore, our off-design calculations are
based on hourly data for the environment conditions instead of monthly-averaged values, such
that the extreme operating conditions are taken into account. Together with the use of hourly
data for the electricity price, this might result in large differences in total revenues compared to
the use of monthly-averaged data. And finally, our optimization tool contains detailed models
which are valid for an electrical power output in the MW scale, whereas most of the studies in the
literature (including the study of Lecompte et al. [11], who have followed a similar optimization
approach) consider lower power scales (and use different component models) or do not include
detailed thermoeconomic models. Up to the authors’ knowledge, the implementation of all these
aspects in an economic design optimization tool for low-temperature geothermal ORCs which also
accounts for the off-design performance, has not been proposed in the literature so far.
It is generally known that low-temperature geothermal power plants are hardly economically feasible
4This is in contrast to some papers in the literature (for example in the paper of Astolfi et al. [3]) where a fit of
manufacturer data has been used, but that approach is very case-specific.
7
in NW Europe without some kind of feed-in tariff [15]. Therefore, the first goal of this paper is
to investigate under which (brine, environment and economic) conditions this type of power plant
might become economically attractive. Due to the site-dependency of some model parameters, the
aim is to give trends rather than a single numerical value for the optimization objective, variables
and performance indicators. The second goal is to study the influence of varying environment
conditions during off-design on the net power output, and the impact of fluctuating electricity
prices on the revenues and on the economic feasibility of the power plant. Finally, and based on the
design and off-design results which are obtained by the proposed two-step optimization approach,
the optimal ORC design will be calculated for the investigated conditions.
2. Methodology
2.1. ORC set-up
Standard and recuperated organic Rankine cycles (ORCs) are considered for the electrical power
production. Figure 1a shows a schematic presentation of the recuperated ORC with indication of
the states. The brine, at a temperature Tb,prod and flow rate ṁb, transfers heat to the working fluid
and is injected at a temperature Tb,inj . The working fluid is pumped to a higher pressure (1→ 2),gets subsequently heated in the recuperator (RECUP, 2 → 3), the economizer (ECO, 3 → 4), theevaporator (EVAP, 4 → 5) and the superheater (SUP, 5 → 6), expands over the turbine (6 → 7)which is connected to a generator to produce electrical power, transfers part of its heat in the
recuperator (7→ 8) and is finally condensed back to state 1 to close the cycle. The cooling mediumis air at the environment conditions (Tenv and penv). In the standard ORC, there is no recuperator
and this component is removed from the set-up (state 2 = state 3 and state 7 = state 8). The
corresponding T-s diagram for the reference standard and recuperated ORC is shown in Figure
1b.
Shell-and-tube TEMA E type heat exchangers are used with the brine flowing through the tubes
(which eases the cleaning processes). For the recuperator, the liquid (state 2 → 3) is in the tubes.Furthermore, we assume that the economizer, the evaporator and the superheater have the same
geometry, which will be optimized in the design optimization procedure of Section 3. According
8
(a) Recuperated ORC (b) T-s diagram
Figure 1: Schematic presentation of the recuperated ORC and corresponding T-s diagram for the reference standard
and recuperated cycle. For the standard ORC (without recuperator), state 2 = state 3 and state 7 = state 8.
9
to previous KU Leuven/VITO PhD research [16], a 30◦ tube layout leads to the highest electrical
power output (if all heat exchangers have the same tube layout).
The air-cooled condenser is the most general type of condenser since no water has to be on site
[17]. The considered cooling system is a forced-draft air-cooled condenser (ACC). An A-frame ACC
with flat tubes and corrugated fins has been implemented. Flat tubes are considered because the
pressure drop is lower than for round tubes [18, 19]. The legs of the A-frame make an angle of 60◦
with the horizontal. The considered fins do not have a perpendicular orientation with respect to
each of the legs, but are vertically oriented in order to minimize fouling [19].
A single-stage axial turbine is chosen for the expander. The axial flow turbine is the most often
applied in geothermal power plants with about 80% of the total global capacity installed, followed
by the centripetal turbine (≈ 15%) and the centrifugal radial turbine (< 5%) [17]. A single-stagehas been considered to lower the investment costs [20].
A variable-speed multi-stage centrifugal pump is commonly used in geothermal ORCs [21]. However,
because of the small contribution of the pump power with respect to the power output of the ORC,
a constant pump efficiency has been assumed 5. The same reasoning holds for the fan of the
ACC.
2.2. Thermodynamic models
Table 1 summarizes the models and correlations which have been implemented. The models which
are used in the design optimization step are based on previous PhD work of Walraven [15] 6. The
off-design models are newly implemented, and the optimization procedure has been adapted and
5The mechanical ORC pump power is 6.79% of the mechanical turbine power for the standard cycle and 6.67%
for the recuperated cycle (for the reference parameter values). In absolute numbers, the ORC pump power is
approximately half of the well pumps power. Therefore, the implementation of a more detailed off-design model for
the pump efficiency has only a small impact on the overall economics of the plant. The implementation of a more
detailed model for the pump efficiency might be considered for future work.6The reader is kindly reffered to the PhD work of Walraven [15] for more detailed information regarding the
design models (implementation). Walraven [15] has also found that the Nusselt number which is given in the paper
of Yang [19] is 10 times too big, so we have adapted the equation of the Nu number accordingly. Furthermore, we
have divided the equation for the friction factor by 2, because the correlations of Yang were established for another
type of fins.
10
parameter component correlation
heat transfer and pressure drop shell HEx Bell-Delaware [23–25]
ideal heat transfer and pressure drop single-phase shell HEx Shah et al. [24]
ideal heat transfer and pressure drop two-phase shell HEx Hewitt et al. [23]
friction factor single-phase tube HEx Bhatti and Shah [26]
heat transfer coefficient single-phase tube HEx Petukhov and Popov [27]
heat transfer and friction factor air-side ACC Yang [19]
heat transfer coefficient single-phase wf ACC Gnielinski [28]
friction factor single-phase wf ACC Petukhov and Popov [27]
void fraction two-phase wf ACC CISE [29]
pressure drop two-phase wf ACC Chisholm [30]
heat transfer coefficient two-phase wf ACC Shah [31]
design efficiency turbine Macchi and Perdichizzi [32]
off-design efficiency turbine Keeley [33]
Table 1: Correlations used in the thermodynamic models. The abbreviation wf stands for working fluid.
expanded to be able to perform design as well as off-design optimization calculations. The geometry
of the heat exchangers is modeled following the TEMA standards [22–24].
Detailed thermodynamic models have been implemented for the calculation of pressure drops and
heat transfer coefficients in the heat exchangers and the air-cooled condenser, and a correlation has
been implemented for the turbine design efficiency calculation and for its off-design performance.
More information on the turbine efficiency modeling and off-design behavior is given in Appendix
A. For the heat exchangers and the air-cooled condenser, the same heat transfer and friction factor
correlations hold for the off-design calculations as for the design optimization but the geometry is
fixed.
2.3. Cost models
The correlations for the bare equipment costs (CBE) of all components are summarized in Table 2.
They are based on the heat transfer area A or on the power Ẇ . We assume correction factors to
account for high temperatures (> 100◦C), high pressures (> 7bar) and the need for stainless steel
11
capacity measure size range cost correlation [USD] ref
shell&tube HEx A [m2] 80-4000m2 3.28 104(A/80)0.68 [34]
centr. pump (incl. motor) Ẇ [W ] 4-700kW 9.84 103(Ẇ/4000)0.55 [34]
turbine Ẇ [W ] 0.1-20MW −19000 + 820(Ẇ/1000)0.8 [36]ACC excl. fan A [m2] 200-2000m2 1.56 105(A/200)0.89 [34]
ACC fan incl. motor Ẇ [W ] 50-200kW 1.23 104(Ẇ/50000)0.76 [34]
Table 2: Bare equipment costs. Table is adapted from [15].
in the heat exchangers: fT = 1.6, fp = 1.5 and fM = 1.7 [34]. Furthermore, an installation factor
of fI = 0.6 has been assumed [35]. The equipment cost C thus becomes:
C = CBE (fT fp fM + fI) (1)
The chemical engineering index has been used to convert the costs to 2016-based values and a
conversion factor of EUR− to− USD = 1.2 has been assumed.
2.4. Reference parameter values
Table 3 presents the reference parameter values. The brine is modeled as pure water and the
reference conditions (brine production temperature Tb,prod and pressure pb,prod, brine flow rate ṁb,
well investment costs Iwells and well pumps power Ẇwells) are based on the test parameters for the
geological site of Balmatt (Mol, Belgium) [37]. The economic parameters are the yearly-averaged
constantly assumed electricity price pel [38], yearly electricity price increase del [39], discount rate
dr [40], lifetime L and availability factor N [41]. Furthermore, the cycle parameters are the pump
isentropic efficiency ηp [42], generator and motor mechanical-to-electrical efficiencies ηg and ηm [42,
43], fan efficiency ηf [44], the minimum pinch-point-temperature difference over the heat exchangers
∆Tmin and the minimum degree of superheating ∆Tminsup . Throughout the entire paper, the year
2016 is taken as the reference year. The reference environment conditions (Tenv and penv) are the
average values for Mol in 2016 [45].
7ηf = 60% is the total fan efficiency, which includes the isentropic and mechanical-to-electrical conversion effi-
ciency.
12
Brine & wells [37] Economic [38–41] Environment [45] Cycle [42–44]
Tb,prod = 130◦C pel = 60EUR/MWh Tenv = 10.85◦C ηp = 80%
pb,prod = 40bar del = 1.25%/year penv = 1.02bar ηg = 98%
ṁb = 150kg/s dr = 5% ηm = 98%
Iwells = 15MEUR L = 30years ηf = 60%7
Ẇwells = 500kW N = 90% ∆Tmin = 1◦C = ∆Tminsup
Table 3: Reference parameter values.
2.5. ORC working fluid
Isobutane (R600a) [46] is chosen as the working fluid because of its low environmental impact [47],
high power output and the low cost of hydrocarbons [21, 48]. The thermodynamic and environ-
mental properties of Isobutane are summarized in Table 4.
MW [g/mole] Tcrit [◦C] pcrit [MPa] ODP GWP
Isobutane (R600a) 58.12 134.7 3.63 0 20
Table 4: Thermodynamic and environmental properties of Isobutane (R600a) [47].
3. Design optimization
3.1. Optimization strategy
The net present value (NPV) is considered as the objective and is defined as:
NPV = −Iwells − IORC +L−1∑
i=0
Ẇnetpel(1 + del)iN8760− 0.025IORC
(1 + dr)i(2)
According to the IEA [49], the maintenance costs can be estimated by 2.5% of the ORC investment
costs.
The design of the heat exchangers (shell diameter Dshell, tube diameter Dtube, tube pitch ptube,
baffle cut Bc, length between baffles Lbc) and the air-cooled condenser (height of the fins Hfin,
spacing between the fins Sfin, number of tubes ntube) are optimized together with the operating
13
variable lower bound upper bound variable lower bound upper bound
Dshell [m] 0.3 2 Lbc [m] 0.3 5
Dtube [mm] 5 50 Sfin [mm] 1.14 3.04
ptube/Dtube [-] 1.2 2.5 Hfin [mm] 14.25 23.75
Bc/Dshell [-] 0.25 0.45 ntube [-] 500 10000
T6 [◦C] Tenv + 10◦C min(Tcrit, Tupper) ṁwf/ṁb [-] 0.01 5
T4 [◦C] Tenv min(Tb,prod, Tupper) vair [m/s] 1.5 10
T1 [◦C] Tenv min(Tb,prod, Tupper) � [%] 0.01 90
Table 5: Variable bounds in the optimization procedure, based on [19, 22].
conditions. The operating conditions are the turbine inlet temperature T6, the evaporator inlet
temperature T4, the condenser outlet temperature T1, the working fluid mass flow rate ṁwf , the
air speed vair through the condenser and the recuperator efficiency � (=T7−T8T7−T2 , with reference to
Figure 1) in case of the recuperated ORC. All variable bounds are given in Table 5. The design
variable bounds are based on the TEMA standards [22] for the heat exchangers and comply with
the validity range of the correlations given by Yang [19] for the ACC. Tcrit and Tupper refer to the
critical temperature and the temperature which corresponds to the maximal pressure in the fluid
properties database, respectively.
Some additional structural and operational constraints are set for the optimization problem and
are summarized in Table 6. The constraint on the tube-to-shell ratio of the heat exchangers is
in accordance with the TEMA standards [22]. In addition, a minimal degree of superheating of
∆Tminsup has been assumed to ensure a proper turbine operation. From the well tests at the Balmatt
geological site [37], no problems regarding salt sedimentation are expected around the optimized
values so no constraint has been imposed on the brine injection temperature Tb,inj . The pinch-
point-temperature difference over each of the heat exchangers is higher than the assumed minimal
temperature difference ∆Tmin.
3.2. Flowchart
Figure 2 shows the flowchart of the developed design optimization model. The black values be-
long to the design optimization flowchart. The flowchart will be extended with the red values
14
constraint lower bound upper bound
Dtube/Dshell [-] 0 0.1
LACC [m] 0 15
T6 − T4 [◦C] ∆Tminsup Tupper − TenvT4 − T1 [◦C] 10 2(Tupper − Tenv)Tb,inj [
◦C] 25 Tb,prod
∆Tpinch [◦C] ∆Tmin 100
Table 6: Constraints to the optimization procedure, based on [19, 22].
for the off-design optimization (see Section 4.2). The parameter values for the brine, economic
and environment conditions, the ORC working fluid, some parameter assumptions related to the
cycle modeling and the costs of the wells and the well pumps power are input parameters for the
optimization model (see Tables 3 and 4). The optimization model includes all geometric models,
heat transfer coefficient and pressure drop correlations, the turbine efficiency correlation and the
cost functions as defined in Tables 1 and 2. The objective in the design optimization step is the
NPV, since it takes into account the component costs, the time value of money (as reflected by the
discount rate) and the thermodynamic performance. The variable bounds are set (in Table 5) and
some structural and operational constraints are defined (in Table 6). The results are the optimized
ORC design (geometry of the heat exchangers and the ACC) and optimal operating conditions
(temperatures and flow rates), and the value for the objective function. In a post-processing step,
all other performance indicators can be calculated.
3.3. Model implementation
The thermodynamic and economic models are implemented in Python [50] and the CasADi [51]
optimization framework together with the IpOpt [52] non-linear solver are used for the optimization.
Fluid properties are called from the REFPROP 8.0 database [53].
Concerning the validation/verification of our obtained results, we are confident that our optimiza-
tion results are trustworthy. There are no experimental results available to the authors. Never-
theless, the considered thermoeconomic optimization model is an extension of our thermodynamic
optimization model, which has been discussed and verified against results in the literature in pre-
15
Figure 2: Flowchart of the optimization procedure. Black: design optimization framework, red: extension to the
design optimization framework (black) for off-design calculations.
vious work [54]. The added heat transfer coefficient and pressure drop correlations and the turbine
efficiency model (which were given in Table 1) are commonly used in the field of ORC modeling
and are validated in the literature. We confirm that we stay within the range of validity for each
of the correlations used (optimization bounds in Tables 5 and 6).
3.4. Definition of the performance indicators
The following performance indicators are used:
• Levelized cost of electricity, LCOE =Iwells+IORC+
∑L−1i=0
0.025IORC(1+dr)i
∑L−1i=0
ẆnetN(1+del)i8760
(1+dr)i
;
• Specific investment cost, SIC = Iwells+IORCẆnet
;
• Specific work of the ORC 8, w = Ẇ∗net
ṁwf;
8In the definition of the specific work w, the well pumps power is not included in Ẇ ∗net since w is a property of
the ORC. Note that in the definition of the plant net electrical power output Ẇnet, the well pumps power has been
included.
16
standard recuperator recuperator
shell diameter Dshell [m]
EE
S
0.77 0.77
RE
CU
P
1.05
tube diameter Dtube [mm] 6.00 5.97 5.52
tube pitch ptube [mm] 7.20 7.16 8.69
baffle cut Bc [m] 0.19 0.19 0.26
length between baffles Lbc [m] 3.05 3.15 5.00
fin height Hfin [mm]
AC
C
23.75 23.75
fin spacing Sfin [mm] 3.04 3.04
number of tubes ntube 1060 1066
Table 7: Optimal design of the economizer, evaporator, superheater (called EES), the air-cooled condenser (ACC )
and the recuperator (RECUP) for the reference conditions of Table 3.
standard recuperator standard recuperator
NPV [MEUR] -3.74 -2.81 ηen [%] 11.45 12.44
Ẇnet [MW] 3.11 3.38 ηex [%] 25.12 27.28
w [kJ/kg] 38.91 41.50 Tb,inj [◦C] 73.53 74.52
IORC [MEUR] 11.48 (73.90%) 12.49 (68.28%) � [%] - 71.15
SIC [EUR/kW] 8509.51 8135.71 ηt [%] 89.07 88.86
LCOE [EUR/MWh] 68.20 65.67
Table 8: Design optimization results for the reference conditions of Table 3.
• Energetic cycle efficiency, ηen =Ẇt−Ẇp
Q̇b, with Q̇b = ṁb(hb,prod − hb,inj);
• Exergetic plant efficiency, ηex = ẆnetĖxb,prodwith Ėxb,prod = ṁbexb,prod and exb,prod = hb,prod − henv − Tenv(sb,prod − senv).
3.5. Results for the reference conditions
The T-s diagrams of the optimized standard and recuperated ORCs for the reference conditions
were already shown in Figure 1b. The use of a recuperator leads to a higher cycle efficiency and the
condenser can be cooled at a lower temperature. Furthermore, the optimal design for the reference
parameter values is given in Table 7 and the general results are summarized in Table 8.
17
Both, the standard and the recuperated geothermal ORC are not feasible (NPV < 0) for the
investigated reference conditions without some kind of feed-in tariff. However, the recuperated
ORC has a higher NPV than the standard ORC. Although the total investment costs are higher,
the revenues from the higher electrical power production are higher. This also leads to a lower
specific investment cost for the recuperated cycle and a lower LCOE. The use of a recuperator
leads to a higher cycle efficiency, a higher specific work and a higher brine injection temperature.
But due to the higher pressure ratio over the turbine, the turbine efficiency ηt is slightly lower for
the recuperated ORC. Furthermore, the values between brackets in the row of IORC indicate the
share of the ORC costs which is allocated to the ACC. The cost of the cooling system is the major
investment cost, which is a direct consequence of the low brine temperature and the corresponding
low cycle efficiency. This emphasizes the importance of a good cooling system design since getting
a lower condensing pressure, at given environment conditions, results in a higher electrical power
output.
Note that the working fluid isobutane is a flammable fluid. Therefore, a fire protection system should
be installed. The cost can be estimated as 2 − 5% of the total plant investment costs [55], whichcorresponds to 1 − 2% of the total investment costs (including the drilling costs) for the referenceconditions and a NPV which would be 0.2MEUR to 0.6MEUR less. The fire protection system
cost is rather unpredictable and small compared to the total investment costs, and is therefore not
discussed further in this study.
The LCOE in Table 8 (68.20EUR/MWh for the standard ORC and 65.67EUR/MWh for the recu-
perated cycle) is higher than the assumed electricity price of 60EUR/MWh, which indicates that
a higher electricity price is needed to have break-even (NPV = 0) of the geothermal power plant
at the end of its lifetime. According to the IEA [56], electricity prices higher than 80USD/MWh
(≈ 67EUR/MWh) are possible for the 450 Scenario, which indicates that the low-temperaturegeothermal power plant might become economically competitive in the future. The results of a
detailed sensitivity analysis, including the influence of the electricity price on the NPV and LCOE,
are given in Section 3.6.2 and Figure 4.
18
3.6. Sensitivity analysis
In order to identify the parameters which affect the project feasibility the most, we perform a
sensitivity analysis of the brine, economic and environment parameters on the NPV , the Ẇnet, the
SIC and the LCOE.
3.6.1. Brine conditions
We consider different brine temperatures and mass flow rates and investigate the effect on the
project feasibility. Figure 3 shows the results.
(a) Net present value (NPV) (b) Net electrical power output (Ẇnet)
(c) Levelized cost of electricity (LCOE) (d) Specific investment cost (SIC)
Figure 3: Sensitivity analysis on the design optimization results for different brine conditions, for the standard and
the recuperated ORC. Every bar is the result of a design optimization.
From Figure 3a follows that the NPV increases for both the brine temperature and flow rate, which
19
was expected. Furthermore, we see that for the reference brine temperature of Tb,prod = 130◦C,
the project only becomes feasible for the high flow rate of ṁb = 200kg/s. For the reference brine
flow rate of 150kg/s, the project becomes feasible for a brine production temperature of 140◦C. For
higher temperatures, the project is almost break-even at the lowest flow rate of 100kg/s and has
a positive NPV for higher brine flow rates. Besides, the NPV of the recuperated ORC is always
(slightly) higher than for the standard ORC for all investigated conditions.
Figure 3b shows similar trends for the net electrical power output. The power production of the
optimized cycles increases with the brine production temperature and the brine mass flow rate.
The brine production temperature has the highest impact.
Figures 3c and 3d show that the LCOE and the SIC decrease with Tb,prod and ṁb. Also here,
the brine temperature has the highest impact. The LCOE can be as high as 176EUR/MWh for
the standard ORC and the lowest investigated brine temperature and flow rate. The lowest value
for the LCOE is at Tb,prod = 150◦C and ṁb = 200kg/s and is 41EUR/MWh for the recuperated
cycle. For comparison, the black dashed line indicates the electricity price which was assumed in the
reference scenario. The corresponding highest and lowest values for the SIC are 23,315EUR/kW for
the standard ORC at Tb,prod = 110◦C and ṁb = 100kg/s, and 4,959EUR/kW for the recuperated
ORC Tb,prod = 150◦C and ṁb = 200kg/s.
3.6.2. Economic conditions
Figure 4 shows the sensitivity analysis results of the standard ORC for changing economic parameter
values with respect to their reference values (of Table 3). For the yearly electricity price increase
(del), only the case of a constant electricity price over the entire lifetime (del = 0%) has been
additionally investigated and is indicated with the black arrow in Figures 4a to 4d. The results are
shown for the standard ORC, however similar trends hold for the recuperated cycle.
From Figure 4a follows that, from the economic parameters, the electricity price (pel) and the
availability factor (N) have the highest impact on the NPV, followed by the discount rate (dr),
the investment costs for the drillings (Iwells), the lifetime (L) and the well pumps power (Ẇwells).
If the electricity price would be 50% higher (pel = 90EUR/MWh instead of 60EUR/MWh),
the NPV would be 11.12MEUR instead of -3.74MEUR. This is a difference of almost 15MEUR
and makes the project economically attractive. Remark that NPV = 0 for an electricity price
20
(a) Net present value (NPV) (b) Net electrical power output (Ẇnet)
(c) Levelized cost of electricity (LCOE) (d) Specific investment cost (SIC)
Figure 4: Sensitivity analysis on the design optimization results for different economic and brine conditions, for the
standard ORC. Every point is the result of a design optimization. The legend is shown in Figure 4c. The economic
conditions are the electricity price pel and yearly electricity price increase del, the lifetime L, the availability factor
N , the well investment costs Iwells and the well pumps power Ẇwells. The results for a changing brine temperature
Tb,prod and flow rate ṁb are additionally shown. For every line, the corresponding parameter value is changed whilst
all other parameters are at their reference values of Table 3.
21
of pel = LCOE = 68.20EUR/MWh. From Figure 4b follows that Ẇnet is mostly affected by pel
followed by N , dr and Ẇwells. The electrical power production is not influenced by Iwells because it
is a constant cost which does not depend on the variables of the optimization process. For a higher
pel, more revenues can be received from selling electricity and a more expensive ORC is installed
which generates more power. Figure 4c shows that the LCOE is mostly affected byN and L, followed
by pel (on the negative side), dr and Iwells. In contrast to the electrical power output, the LCOE
depends on the well investment costs. Finally, from Figure 4d follows that the SIC is dominated
by the well costs, since Iwells and IORC are of the same order of magnitude. The electrical power
output strongly depends on the incentive to invest in an efficient (hence more expensive) ORC. For
low values of pel, a cheap ORC will be installed which produces little power. For high values of pel,
a more expensive ORC is installed, but the electrical power production increases as well. Therefore,
the SIC is almost independent of the electricity price for pel > 60EUR/MWh. The same reasoning
holds for the lifetime 9.
In addition to the economic conditions, also the sensitivity towards the brine conditions is included
in Figure 4. The project feasibility mostly depends on the brine conditions (especially the brine
temperature), followed by the electricity price and the availability factor, the discount rate and
the investment costs for the well drillings. The brine conditions are determined by the geological
conditions, but the type of contract for electricity selling, the type of investor (discount rate) and
the maturity of the well drilling company might have a big impact on the overall project feasibility.
Well-considered assumptions have to be made in the design stage of the geothermal project.
Figure 5a shows the impact of the electricity price pel on the project feasibility. For a higher
electricity price, a more efficient ORC can be installed which produces more electricity. The project
becomes feasible for electricity prices higher than 65− 70EUR/MWh (and for reference values forthe other parameters of Table 3), as was already indicated by the results for the LCOE in Table
8. The gray line indicates the difference between the NPV for the recuperated and the standard
ORC. The recuperated ORC has generally a higher NPV, and the difference increases for higher
electricity prices.
9For low values of pel and L, the net electrical power output is too low to compensate for the investment costs
which results in a higher SIC value.
22
(a) NPV as a function of pDel, for TDenv = 10.85
◦C (b) NPV as a function of TDenv, for pDel =
60EUR/MWh
Figure 5: Impact of the design electricity price and the design environment temperature assumptions on the design
NPV value. All other parameter values are at their reference values of Table 3. Every point is the result of a design
optimization. The results for the standard and the recuperated cycle are shown in blue and green dashed lines,
respectively. The gray line indicates the difference between the NPV for the recuperated and the standard ORC
(ordinate scale on the right-hand side).
3.6.3. Environment conditions
Figure 5b shows the impact of the environment temperature on the NPV. If the same installation
would be installed in colder regions, the NPV is higher which could be expected. The opposite
is true for hotter regions. Also here, the recuperated ORC has a slightly higher NPV than the
standard cycle and the difference (gray line) increases for lower environment temperatures.
4. Off-design optimization
4.1. Hourly data for the environment temperature and electricity prices
The off-design analysis is based on hourly data for the environment temperature in Mol and the
wholesale day-ahead electricity prices in Belgium for 2016. The hourly environment temperature is
given in Figure 6a, but our off-design model results are based on the duration curve for Tenv which
23
is shown in Figure 6b 10. Instead of using all 8784 data points (blue line, 8784 hours in 2016), we
reduce this curve to 100 data points (red dashed line) to speed up the calculation time. The 100
data points are defined as the points at 0.5%, 1.5%, . . . , 99.5% of the duration curve for Tenv. This
data reduction leads to the elimination of the extreme values of Tenv (Tmaxenv = 29.04
◦C is used
instead of the real maximum temperature 33.19◦C and Tminenv = −4.28◦C is used instead of the realminimum temperature −8.13◦C). The impact on the annual power production and the NPV isvery small, which will be discussed more in detail in Section 4.4.
Furthermore, the real hourly electricity prices are shown in Figure 6c. The inset is a zoom of the
y-axis to more moderate values. For each of the 100 data points on the duration curve for Tenv
(red dashed line in Figure 6b), the average electricity price is calculated for all hours during the
year which correspond to that environment temperature. The resulting average electricity price for
every data point is shown in Figure 6d.
4.2. Optimization strategy
The same models are used as in the design optimization framework, and the off-design models are
added. Since the design is fixed (the ORC is installed and the investments are made), only the
operational variables are considered in the operational optimization procedure. Some additional
constraints are set for the fixed design geometry and for the off-design operation constraints. In
order to allow convergence, ∆Tmin = 0.75◦C instead of 1◦C in the design optimization. Further-
more, the brine parameters are kept constant at their reference values, which were given in Table
3. In the off-design case, the objective of maximizing the NPV reduces to maximizing the net elec-
trical power output since all investments are made (and do not depend on the operating variables
anymore).
The flowchart of the off-design optimization framework was already given in Figure 2. The changes
with respect to the design optimization framework are indicated in red.
For each of the 100 data points on the reduced duration curve of Tenv (Figure 6b), the off-design
optimization model is run. The optimization results are the operational variables and the net
10The duration curve for Tenv shows for what percentage of the time during a year, the environment temperature
is above a certain value.
24
(a) Hourly environment temperature Tenv (b) Environment temperature duration curve
(c) Hourly electricity price pel (d) Average electricity price pavel for the 100 data
points of the reduced temperature duration curve
Figure 6: Real hourly data and reduced curves (considering 100 data points) for the environment temperature and
electricity price.
25
electrical power output for every data point. Taking the corresponding electricity prices into account
(Figure 6d) and the number of hours that each value of Tenv occurs in the year, the real NPV can
be calculated in a post-processing step.
4.3. Off-design performance for the reference conditions
The optimal design for the standard and the recuperated ORC was already found in Section 3.5
as the result of the design optimization model. Figure 7 shows the off-design optimization model
results for the optimized (reference) ORC design. The optimized working fluid temperatures and
the net electrical power output are shown for each of the 100 data points. First, from Figure 7a it
follows that the turbine inlet temperature is almost constant for all values of Tenv. The minimum
superheating degree of 1◦C is optimal for every point (so the optimal evaporator temperature is
1◦C lower than the turbine inlet temperature). The condenser temperature, however, has a big
impact on the net electrical power production. T1 varies within a range of 22.01◦C to 53.47◦C
and 18.29◦C to 51.05◦C for the standard and the recuperated cycle, respectively. We see that the
condenser temperature is lower for the recuperated cycle (even more at low values of Tenv), which
directly results in a higher net electrical power output which is shown in Figure 7b. The air velocity
varies from −2.50% to 8.05% and from −1.72% to 6.89% for the standard and the recuperated cyclewith respect to its design value as Tenv varies from 29.07
◦C to −4.28◦C. So the fan power is higherat low environment temperatures. The working fluid mass flow rate slightly decreases with a lower
Tenv but the variation is smaller than 0.3% from the design value. The recuperator efficiency stays
within 0.75% of its design value, and slightly increases with a lower Tenv.
4.4. Note on the data reduction errors
By using only 100 data points instead of performing the off-design optimization for every hour in
the reference year, we reduce the number of times the optimization model has to run from 8784 to
100 and thereby reduce the calculation time. In this section we make an estimation of the errors we
make by doing this. The off-design model is used for maximizing the net electrical power output
for every data point as a function of the environment temperature. The average difference between
the electrical power output of two consecutive data points is 2.64 10−2MW and 2.82 10−2MW for
the standard and the recuperated cycle, respectively. This corresponds to 0.85% and 0.83% of
26
(a) Working fluid temperatures (nomenclature of
Figure 1a)
(b) Net electrical power output (Ẇnet)
Figure 7: Results of the off-design optimization model for the reference design and for the 100 data points. The
dashed red line is the reduced duration curve of the environment temperature of Figure 6b. The results for the
standard and the recuperated cycle are shown in blue and green dashed lines, respectively.
Tmaxenv [◦C] Ẇnet [MW] ∆Ẇnet [MW] T
minenv [
◦C] Ẇnet [MW] ∆Ẇnet [MW]
stan
d model 100 points 29.07 1.780.27 (+18%)
-4.28 4.40-0.34 (-7.1%)
reality 33.19 1.51 -8.13 4.74
recu
p model 100 points 29.07 1.940.29 (+18%)
-4.28 4.74-0.35 (-6.9%)
reality 33.19 1.65 -8.13 5.09
Table 9: Estimation of the errors due to the data reduction to 100 points, for the reference case.
the average electrical power production in one year for the standard and the recuperated cycle.
Therefore, the step size results in a good accuracy of the data reduction to 100 points.
The largest errors occur at the extreme values of Tenv since we only consider a range of −4.28◦Cto 29.07◦C instead of the real range of occurring temperatures, from −8.13◦C to 33.19◦C (seeFigures 6a and 6b). Therefore, we calculate the off-design power output for the real extreme values
of the environment temperature and compare them to the values we use in the 100 data points
approximation. Table 9 shows the results.
For the maximum temperature of 29.07◦C instead of 33.19◦C, the model predicts a 18% higher
electrical power output than the real power would be in case of the highest environment temperature.
27
Figure 8: Off-design model results for the net electrical power output as a function of the environment temperature
for the reference case (pDel = 60EUR/MWh and TDenv = 10.85
◦C). The dots indicate the off-design model results for
the considered 100 data points, the lines indicate the spline approximation of the off-design model results.
For the lowest environment temperature, the model under-predicts the electrical power production
by 6.9-7.1%. The errors are almost symmetric so they partly cancel each other. We end up with
a slight under-prediction of the real electrical power output, which justifies the data reduction to
100 data points and speeding up the off-design calculations with almost a factor 88.
Furthermore, we will use spline approximations of the off-design optimization results for a quick
calculation of the hourly power profiles. Figure 8 shows the electrical power - environment tem-
perature dependency for the reference case. The dots are the results of the off-design optimization
process for the 100 data points, and the full lines indicate the spline approximations. The standard
deviation is 7.6 10−3MW , so the spline approximations are of satisfying accuracy.
5. Discussion: Optimal ORC design accounting for off-design performance
5.1. Influence of the design-stage assumptions pDel and TDenv on the real NPV
Figure 9 shows the impact of a parameter assumption in the design step for the electricity price (pDel)
and for the environment temperature (TDenv) on what we refer to as the real NPV of the geothermal
power plant. In qualitative terms, the real, or actual, NPV is the appropriately discounted sum of
costs and revenues occurring during actual operation i.e., subject to varying market and environment
conditions, for a device that has already been invested in and that was optimized for the fixed design
28
(a) Real NPV as a function pDel (b) Real NPV as a function of TDenv
Figure 9: Real NPV as a function of the design value for the electricity price and the design environment temperature.
Every point is the result of one design optimization and 100 runs of the off-design optimization model. The results
for the standard and the recuperated cycle are shown in blue and green dashed lines, respectively.
parameters. In order to calculate the real NPV, we take into account the duration curve for Tenv
of Figure 6b and the corresponding electricity prices of Figure 6d. This is in contrast to the design
optimization procedure (Figure 5), where we have assumed a fixed parameter value for pDel and TDenv,
namely the values which were given in Table 3. In the off-design optimization, however, we are able
to see the effect of these parameter assumptions on the real power production during operation
(mostly in off-design) and on the real NPV of the power plant.
In Figure 9a, the real NPV is given as a function of the parameter value assumption for pDel in
the design step, so for a power plant which is designed for an electricity price of pDel on the x-axis.
From the figure, it is clear that the highest NPV is reached for the average electricity price of pavel =
36.57EUR/MWh (which was the average value for the wholesales prices in 2016). However this
electricity price cannot be predicted in advance; a good approximation is of the utmost importance
for the plant feasibility and thus a reasonable guesstimate of the average wholesale price must be
made for the entire expected lifetime of the plant. For a design value of the electricity price within
30− 60EUR/MWh, the real NPV of the project stays within 10% of the design value. For a badelectricity price assumption, e.g. for pDel = 120EUR/MWh, the NPV might be 50% lower. This
emphasizes the importance of taking the off-design performance into account. In Figure 9b, the
real NPV is given as a function of the parameter value assumption for TDenv in the design step.
29
From the results follows that the design value of TDenv has a smaller impact on the real NPV. The
NPV can be improved by 9.76% by designing the ORC for a higher value of Tenv ≈ 30◦C insteadof T avenv = 10.85
◦C.
5.2. Combined influence of pDel and TDenv on the real NPV
Now the main goal is to find the optimal design, taking into account the off-design performance
as a result of real varying environment conditions and fluctuating electricity prices (as was shown
in Figure 6). Figure 10 shows the net electrical power output and the NPV for a standard ORC
as a function of the parameter value assumption of pDel in the design stage and for multiple values
of the design environment temperature TDenv. The results for the recuperated cycle are similar.
The full lines show the results of the design optimization model, based on the assumptions for the
electricity price (x-axis) and for the environment temperature (multiple lines) in the design stage.
The dashed lines indicate the real average net electrical power output and the real NPV when
the off-design performance is taken into account (changing environment conditions and fluctuating
electricity prices of Figure 6).
From Figure 10a follows that for the reference value of TDenv = 10.85◦C = T avenv, the real average
power output (blue dashed) corresponds very well to the predicted values (blue full line). However,
the discrepancies for TDenv = 20◦C and 30◦C are higher 11. The installed ORC is cheaper and less-
performing for higher design values of Tenv. However, during off-design operation, the environment
temperature is mostly lower than the design value (Figure 6a) and a higher electrical power output
is reached than the power for which the ORC was designed (the dashed lines are above the full
lines). The difference is the highest for TDenv = 30◦C (red). So it is beneficial to design the ORC
for a higher than average value of the environment temperature.
Figure 10b shows the predicted NPV in the design stage (full lines) and the real NPV (dashed lines)
which takes off-design into account, as a function of the design electricity price and for multiple
values of the design environment temperature (TDenv = 10.85◦C, 20◦C and 30◦C in blue, green
and red, respectively). We see that the NPV which is the result of the design optimization is in
11For the design values pDel = 30EUR/MWh and TDenv = 30
◦C, it is not worth it to produce electricity. The value
Ẇnet = −0.5MW corresponds to the well pumps power.
30
(a) Net electrical power output (b) Net present value
Figure 10: Average net electrical power output and NPV of the standard ORC for the design prediction (full line)
and for the real results taking off-design into account (dashed line), as a function of the design electricity price
assumption and for multiple design environment temperature assumptions (TDenv = 10.85◦C, 20◦C, and 30◦C are
shown in blue, green and red, respectively). Every data point on the full lines is the result of one design optimization.
The data points on the dashed lines account for the off-design performance and are based on 100 additional runs of
the off-design optimization model. Note the different ordinate scale used in Figure 10b compared to Figure 9a.
general very different from the real NPV value. This shows the importance of taking the off-design
results into account. As been discussed in Section 5.1, there exists and optimum for every line.
For every design value of the environment temperature, the real NPV reaches an optimal value.
However the corresponding optimal value for pDel is different for every line of TDenv. A higher value
of pDel and a lower value of TDenv in the design stage lead to a higher nominal electrical power output
and a more expensive ORC which is installed. So, there is a trade-off between pDel and TDenv which
causes that every line of TDenv reaches its optimal value for NPV at a different design value for
pDel . In this case—and for the real environment temperature and electricity price profiles of Figure
6—the optimal design of the ORC is the design which corresponds to pDel = 45EUR/MWh and
TDenv = 20◦C. The optimal point is reached for 45EUR/MWh = pDel > p
avel = 36.57EUR/MWh
and 20◦C = TDenv > Tavenv = 10.85
◦C. The average electrical power generation is 2.35MWe and the
real NPV = −12.75MEUR for the standard cycle. For the recuperated cycle, the average powerproduction is 2.53MWe and the real NPV = −12.62MEUR, which are slightly higher valuesthan for the standard ORC. Note that the optimal design parameter assumptions for pDel and T
Denv
are case-specific, and depend on the real profiles for the electricity price and for the environment
31
pDel [EURMWh
] TDenv [◦C] NPV [MEUR] Ẇnet [MW] Eyear [GWh]
reference 60 10.85 -3.74 -14.06 -14.01 3.11 3.13 3.13 24.60 24.74 24.74
Figure 9a 36.57 10.85 -13.23 -12.93 -12.90 2.29 2.31 2.31 18.13 18.25 18.25
Figure 9b 60 30 -13.70 -12.79 -12.75 1.40 2.43 2.43 11.06 19.19 19.19
optimal 45 20 -13.54 -12.75 -12.72 1.82 2.35 2.35 14.39 18.58 18.58
model D O O: spl D O O: spl D O O: spl
Table 10: Performance indicators of the design model results (D), the off-design model results (O) and the spline
approximation based on the off-design model results (O: spl) for the standard geothermal ORC.
temperature.
5.3. Summary
Tables 10 and 11 summarize the results for the standard and the recuperated ORC, respectively.
The NPV, the net electrical power output (Ẇnet) and the energy production during one year (Eyear)
for the reference case, for the optimal point of Figure 9a, for the optimal point of Figure 9b and
for the overall optimal design are given. The first column gives the value which is predicted by the
design optimization model (D). The values of the second column take the off-design performance (O)
into account—the environment temperature variation and electricity price fluctuations of Figure 6.
So, column 2 contains the results of the off-design model for the 100 data points. Column 3 uses the
spline approximations of the off-design optimization model results (O:spl, Figure 8) for calculating
the real hourly net electrical power output as a function of the environment temperature for all
8784 hours during the year. In this approach, all environment temperatures are considered (from
Tminenv = −8.13◦C to Tmaxenv = 33.19◦C). The spline approximation is a quick and accurate way ofcalculating the hourly electricity production profiles (see Figure 8).
From Tables 10 and 11, the following conclusions are made:
• The design optimization model alone is not able to predict the real NPV. Off-design perfor-
mance results should be included!
• The spline approximation of the off-design model allows a quick and accurate calculation of
the hourly profiles of the real electricity production (and the operating variables) as a function
of the environment temperature.
32
pDel [EURMWh
] TDenv [◦C] NPV [MEUR] Ẇnet [MW] Eyear [GWh]
reference 60 10.85 -2.81 -14.04 -13.99 3.38 3.39 3.39 26.72 26.84 26.84
Figure 9a 36.57 10.85 -13.10 -12.80 -12.76 2.47 2.49 2.49 19.56 19.67 19.67
Figure 9b 60 30 -13.54 -12.67 -12.63 1.52 2.62 2.62 12.02 20.69 20.69
optimal 45 20 -13.40 -12.62 -12.58 1.97 2.53 2.53 15.57 20.02 20.02
model D O O: spl D O O: spl D O O: spl
Table 11: Performance indicators of the design model results (D), the off-design model results (O) and the spline
approximation based on the off-design model results (O: spl) for the recuperated geothermal ORC.
• Using the two-step optimization framework to calculate the optimal design and off-design
performance for multiple design parameter assumptions for TDenv and pDel allows finding the
optimal design of the geothermal ORC for a given location, and accounting for off-design.
6. Conclusions
In this paper, we have proposed a two-step optimization procedure for the design and off-design
performance optimization of a low-temperature geothermal organic Rankine cycle (ORC). The
developed optimization tool can be used to design a binary geothermal power plant and to calculate
the off-design performance over its lifetime. Based on the results, the optimal design parameters
can be indicated, which correspond to the ORC design with the highest net present value.
From the design results follows that the recuperated ORC has better economic performance than
the standard cycle. For the investigated reference conditions, which are based on the Belgian
conditions in 2016, the net power output of the recuperated cycle is 3.38MW, which is 8.68%
higher than for the standard ORC. The corresponding net present value (NPV) is -2.81MEUR,
which means that the project is not economically attractive for the investigated conditions. This
is also reflected in the levelized cost of electricity LCOE = 65.67EUR/MWh, which is higher
than the current wholesale electricity prices. However, according to the IEA [56], electricity prices
higher than 80USD/MWh (≈ 67EUR/MWh) are possible for the 450 Scenario, which indicatesthat the low-temperature geothermal power plant might become economically competitive in the
future. Next to the electricity price, also the brine temperature has a very large impact on the plant
33
economics. Therefore, for other geographical locations, a binary geothermal power plant might be
cost-competitive depending on the local climate and electricity prices.
From the off-design results follows that the net power output strongly depends on the environment
temperature. For the recuperated ORC, the net power increases from 1.95MW to 4.74MW for a
decreasing environment temperature from 29.07◦C to -4.28◦C. A data reduction has been performed
to improve the calculation time of the off-design model by a factor 88, and a spline approximation
has been used for a quick calculation of the hourly net power profile as a function of the environment
temperature. Both, the data reduction technique and the spline approximation are found to be of
satisfying accuracy.
Taking the off-design performance into account, the optimal ORC design has been calculated for
the investigated conditions. The recuperated ORC reaches a maximum real NPV of -12.62MEUR
for design parameter values for the environment temperature and electricity price of 20◦C and
45EUR/MWh, which are different from the yearly-averaged values. Note also the difference with
the NPV which has been estimated in the design stage at -2.81MEUR. Since the real average
electricity price is only 36.57EUR/MWh instead of 60EUR/MWh, which has been assumed in the
design stage, the net power output and the corresponding revenues are overestimated. The impact
of the environment temperature assumption in the design stage is smaller, but it is beneficial to
design the ORC for a higher environment temperature than the average value.
The proposed optimization procedure for the design optimization of a low-temperature geothermal
organic Rankine cycle (MW scale) and accounting for the off-design performance already in the
design stage, using hourly weather data and detailed thermoeconomic models is novel compared
to the existing literature. In future work, we will investigate the potential of low-temperature
geothermal combined heat-and-power (CHP) plants where electricity will be generated via an ORC
and, additionally, heat will be provided to a nearby district heating system. The idea is to improve
the revenues by selling two products (heat and electricity). The study of geothermal CHP plants
will be based on a similar two-step optimization methodology, for which the already developed
ORC models will be used. The big advantages of our optimization framework are that detailed
thermoeconomic models are implemented, that the input parameters can be easily adapted (generic
methodology), and that errors related to the use of multiple programming tools are avoided since
the same models are used for the design and the off-design optimization procedure.
34
Acknowledgments
This project receives the support of the European Union, the European Regional Development Fund
ERDF, Flanders Innovation & Entrepreneurship and the Province of Limburg, and is supported by
the VITO PhD grant number 1510829. The authors also want to thank Sylvain Quoilin (KU Leuven
/ University of Liège) for the interesting discussion on the off-design turbine modeling.
Nomenclature
Abbreviations
symbol description
ACC air-cooled condenser
CHP combined heat-and-power
ECO economizer
EES economizer, evaporator, superheater
EVAP evaporator
GWP global warming potential
NW northwest
ODP ozone depletion potential
ORC organic Rankine cycle
RECUP recuperator
SUP superheater
35
Symbols
symbol description
A [m2] heat transfer area
Bc [m] heat exchanger baffle cut
C [USD] equipment cost
D [m] diameter
del [%/year] electricity price increase
dr [%] discount rate
Eyear [GWh] yearly energy production
Ė [MWth] flow exergy
ex [kJ/kg] specific flow exergy
H [mm] height
h [kJ/kg] specific enthalpy
I [MEUR] investment cost
L [year] lifetime
Lbc [m] heat exchanger baffle distance
LCOE [EUR/MWh] levelized cost of electricity
ṁ [kg/s] mass flow rate
MW [g/mole] molecular weight
NPV [MEUR] net present value
N [%] availability factor
ntube ACC number of tubes
pel [EUR/MWh] electricity price
ptube [mm] tube pitch
p [bar] pressure
Q̇ [MWth] heat
S [mm] spacing
SIC [EUR/kW] specific investment cost
s [kJ/kgK] specific entropy
T [◦C] temperature
v [m/s] velocity
Ẇ [MWe] electrical power
w [kJ/kg] specific work
� [%] heat exchanger efficiency
η [%] efficiency
σ standard deviation
36
Subscripts & superscripts
symbol description
av average
b brine
crit critical point
D design conditions
el electricity
en energy
env environment
ex exergy
f ACC fan
fin ACC fin
g generator
inj injection state
M material
m motor
max maximum
min minimum
net net value
p pump
prod production state
shell heat exchanger shell
sup degree of superheating
t turbine
th thermal
tube heat exchanger tube
wf working fluid
wells well drillings
37
Appendix A. Turbine modeling
In this section, we give some more details regarding the modeling of a single-stage axial turbine in
design and off-design conditions.
The isentropic efficiency calculation in the design stage is based on a curve-fit that Walraven et al.
[57] have made for the correlation given by Macchi and Perdichizzi in [32].
Due to the high pressure ratio, the turbine nozzles are choked all the time and the following relation
holds during off-design operation:
ṁOwfṁDwf
=ρO6 c
O6
ρ6DcD6
with c =
√δp
δρ|s (A.1)
Herein is ρ the density, c the speed of sound, p the pressure, and O and D indicate the off-design and
the design conditions, respectively. Since we have to account for the real gas properties, the speed
of sound has to be calculated and no further simplifications based on the ideal gas law are allowed.
By using the turbine inlet conditions (state 6 from Figure 1) instead of the throat conditions, we
make an assumption which is justified for the purpose of this paper (system approach for the ORC
rather than a detailed turbine design).
The turbine efficiency in off-design conditions is calculated via the Keeley correlation [33]:
ηOt = ηDt sin
0.5π
(ṁOwfρ
D6
ṁDwfρO6
)0.1 (A.2)
Since the turbine is in choking conditions, it can be justified that a correlation only based on the
turbine inlet conditions and the mass flow rate is used.
References
[1] M. Imran, M. Usman, B.-S. Park, Y. Yang, Comparative assessment of Organic Rankine
Cycle integration for low temperature geothermal heat source applications, Energy 102 (2016)
473–490.
[2] K. Braimakis, S. Karellas, Integrated thermoeconomic optimization of standard and regener-
ative ORC for different heat source types and capacities, Energy 121 (2017) 570–598.
38
[3] M. Astolfi, M. C. Romano, P. Bombarda, E. Macchi, Binary ORC (Organic Rankine Cycles)
power plants for the exploitation of mediumlow temperature geothermal sources Part B:
Techno-economic optimization, Energy 66 (2014) 435–446.
[4] D. Fiaschi, G. Manfrida, E. Rogai, L. Talluri, Exergoeconomic analysis and comparison be-
tween ORC and Kalina cycles to exploit low and medium-high temperature heat from two
different geothermal sites, Energy Conversion and Management 154 (2017) 503–516.
[5] F. Calise, C. Capuozzo, A. Carotenuto, L. Vanoli, Thermoeconomic analysis and off-design
performance of an organic Rankine cycle powered by medium-temperature heat sources, Solar
Energy 103 (2014) 595–609.
[6] I. S. Kim, T. S. Kim, J. J. Lee, Off-design performance analysis of organic Rankine cycle using
real operation data from a heat source plant, Energy Conversion and Management 133 (2017)
284–291.
[7] D. Hu, S. Li, Y. Zheng, J. Wang, Y. Dai, Preliminary design and off-design performance anal-
ysis of an Organic Rankine Cycle for geothermal sources, Energy Conversion and Management
96 (2015) 175–187.
[8] M. Astolfi, L. N. La Diega, M. Romano, U. Merlo, S. Filippini, E. Macchi, Techno-economic
optimization of a geothermal ORC with novel Emeritus heat rejection units in hot climates,
Renewable Energy (2019).
[9] J. Wang, Z. Yan, P. Zhao, Y. Dai, Off-design performance analysis of a solar-powered organic
Rankine cycle, Energy Conversion and Management 80 (2014) 150–157.
[10] G. Manente, A. Toffolo, A. Lazzaretto, M. Paci, An Organic Rankine Cycle off-design model
for the search of the optimal control strategy, Energy 58 (2013) 97–106.
[11] S. Lecompte, H. Huisseune, M. van den Broek, S. De Schampheleire, M. De Paepe, Part
load based thermo-economic optimization of the Organic Rankine Cycle (ORC) applied to a
combined heat and power (CHP) system, Applied Energy 111 (2013) 871–881.
[12] M. Petrollese, D. Cocco, Robust optimization for the preliminary design of solar organic
Rankine cycle (ORC) systems, Energy Conversion and Management 184 (2019) 338–349.
39
[13] D. Budisulistyo, C. S. Wong, S. Krumdieck, Lifetime design strategy for binary geothermal
plants considering degradation of geothermal resource productivity, Energy Conversion and
Management 132 (2017) 1–13.
[14] M. Usman, M. Imran, Y. Yang, D. H. Lee, B.-S. Park, Thermo-economic comparison of air-
cooled and cooling tower based Organic Rankine Cycle (ORC) with R245fa and R1233zde
as candidate working fluids for different geographical climate conditions, Energy 123 (2017)
353–366.
[15] D. Walraven, Optimization of the Energy Conversion Starting from Low-Temperature Heat
- Application to Geothermal Binary Cycles, Phd thesis, PhD Thesis, KU Leuven - Uni-
versity of Leuven, 2014. URL: https://www.mech.kuleuven.be/en/tme/research/energy_
environment/PublicationsEnergyandenvironment/PhDtheses.
[16] D. Walraven, B. Laenen, W. D’haeseleer, Optimum configuration of shell-and-tube heat ex-
changers for the use in low-temperature organic Rankine cycles, Energy Conversion and Man-
agement 83 (2014) 177–187.
[17] R. Bertani, Perspectives for Geothermal Energy in Europe, World Scientific (Europe),
2017. URL: http://www.worldscientific.com/worldscibooks/10.1142/q0069. doi:10.
1142/q0069.
[18] J. R. Thome, Wolverine Tube Inc, Engineering Data Book III, Wolverine Tube Inc (2010)
1–31.
[19] L. Yang, H. Tan, X. Du, Y. Yang, Thermal-flow characteristics of the new wave-finned flat
tube bundles in air-cooled condensers, International Journal of Thermal Sciences 53 (2012)
166–174.
[20] G. Manente, L. Da Lio, A. Lazzaretto, Influence of axial turbine efficiency maps on the
performance of subcritical and supercritical Organic Rankine Cycle systems, Energy 107 (2016)
761–772.
[21] E. Macchi, M. Astolfi, Organic Rankine Cycle (ORC) Power Systems - Technologies and Ap-
plications, Elsevier, 2017.
40
[22] TEMA, Standards of the tubular exchanger manufacturers association, 1999. URL: http:
//www.funke.de/pdf/zertifikate/tema.pdf.
[23] G. Hewitt, Hemisphere Handbook of Heat Exchanger Design, Hemisphere Publishing Corpo-
ration, New York, 1990.
[24] R. Shah, D. Sekulic, Fundamentals of Heat Exchanger Design, John Wiley and Sons, Inc.,
2003.
[25] T. Tinker, Shell side characteristics of shell and tube heat exchangers, in: General Discussion
on Heat Transfer, 1951, pp. 89–116.
[26] M. Bhatti, R. Shah, Turbulent and transition convective heat transfer in ducts, in: S. Kakaç,
R. Shah, W. Aung (Eds.), Handbook of Single-Phase Convective Heat Transfer, Wiley, New
York, 1987.
[27] B. Petukhov, V. Popov, Theoretical calculation of heat exchange and frictional resistance in
turbulent flow in tubes of an incompressible fluid with variable physical properties, in: High
Temperature 1, 1963, pp. 69–83.
[28] V. Gnielinski, New equations for heat and mass transfer in the turbulent pipe and channel
flow, International Journal of Chemical Engineering 16 (1976) 359–368.
[29] A. Premoli, D. DiFrancesco, A. Prina, A dimensionless correlation for the determination of
the density of two-phase mixtures, Termotecnica (Milan) 25 (1971) 17–26.
[30] D. Chisholm, Pressure gradients due to friction during flow of evaporating two-phase mixtures
in smooth tubes and channels, International Journal of Heat and Mass Transfer 16 (1973)
347–358.
[31] M. Shah, An improved and extended general correlation for heat transfer during condensation
in plain tubes, HVAC&R Research 15 (2009) 889–913.
[32] E. Macchi, A. Perdichizzi, Efficiency predictions for axial-flow turbines operating with non-
conventional fluids, Journal for Engineering for Power 103 (1981) 718–724.
[33] K. Keeley, A theoretical investigation of the part-load characteristics of LP steam turbine
stages, Memorandum RD/L/ES0817/M88, Central Electrical Generating Board (1988).
41
[34] R. Smith, Chemical Process Design and Integration, John Wiley and Sons, Inc., 2005.
[35] A. Bejan, G. Tsatsaronis, M. Moran, Thermal Design and Optimization, Wiley, New York,
1996.
[36] G. P. Towler, R. K. Sinnott, Chemical engineering design: principles, practice and economics
of plant and process design, 2008.
[37] S. Bos, B. Laenen, Development of the first deep geothermal doublet in the Campine Basin of
Belgium, European Geologist 43 (2017) 16–20.
[38] ENTSOE, Central collection and publication of electricity generation, transportation and
consumption data and information for the pan-European market, 2016. URL: https://
transparency.entsoe.eu/.
[39] European Commission, EU Reference Scenario 2016, 2014. URL: https://ec.europa.eu/
energy/sites/ener/files/documents/ref2016_report_final-web.pdf.
[40] S. Lemmens, S. Lecompte, Case study of an organic Rankine cycle applied for excess heat
recovery: Technical, economic and policy matters, Energy Conversion and Management 138
(2017) 670–685.
[41] U.S. Department of Energy, Geothermal electric technology, 2016. URL: https://www.wbdg.
org/resources/geothermal-electric-technology.
[42] Y. Cao, Y. Dai, Comparative analysis on off-design performance of a gas turbine and ORC
combined cycle under different operation approaches, Energy Conversion and Management
135 (2017) 84–100.
[43] J. Foray, Energy efficiency considerations in pumps an pump stations, 2014. URL: http://www.
energy.wsu.edu/LinkClick.aspx?fileticket=t3ubiA8D8A4%3D&tabid=692&mid=1345.
[44] J. Bredell, D. Kröger, G. Thiart, Numerical investigation of fan performance in a forced draft
air-cooled steam condenser, Applied Thermal Engineering 26 (2006) 846–852.
[45] The Dark Sky Company, Dark Sky API, 2012. URL: www.darksky.net.
42
[46] Erdwärme Grünwald, Grüner Strom aus Geothermie, 2013. URL: http://www.
erdwaerme-gruenwald.de/Startseite/Informationen-Medien/Informationen/
News-Archiv/E1172.htm.
[47] J. Calm, G. Hourahan, Physical, Safety and Environmental Data for Current
and Alternative Refrigerants, in: International Congress of Refrigeration, Prague,
Czech Republic, 2011. URL: http://www.hourahan.com/wp/wp-content/uploads/2010/08/
2011-Physical-Safety-and-Environmental-Data2.pdf.
[48] P. Garg, M. S. Orosz, P. Kumar, Thermo-economic evaluation of ORCs for various working
fluids, Applied Thermal Engineering 109 (2016) 841–853.
[49] IEA, Technology Roadmap - Geothermal Heat and Power, 2011. URL:
https://www.iea.org/newsroomandevents/pressreleases/2011/june/
how-to-achieve-at-least-a-tenfold-increase-in-supply-of-geothermal-power-and-hea.
html.
[50] G. van Rossum, Python Tutorial, Technical Report CS-R9526, Technical Report, Centrum
voor Wiskunde en Informatica (CWI), Amsterdam, 1995. URL: http://www.python.org.
[51] J. Andersson, A General-Purpose Software Framework for Dynamic Optimization, Phd,
Arenberg Doctoral School, KU Leuven, 2013. URL: https://lirias2repo.kuleuven.be/
bitstream/id/243411/.
[52] A. Wächter, L. T. Biegler, On the implementation of an interi