40
California Multi-Family New Homes A Third-Party Program of the Pacific Gas and Electric Company (PG&E) Design for Net Zero: Multi-Family Modeling and Measuring Techniques July 19, 2011

Design for Net Zero: Multi-Family Modeling and Measuring ......California Multi-Family New Homes A Third-Party Program of the Pacific Gas and Electric Company (PG&E) Design for Net

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

  • California Multi-Family New Homes

    A Third-Party Program of the Pacific Gas and Electric Company (PG&E)

    Design for Net Zero: Multi-Family Modeling

    and Measuring Techniques

    July 19, 2011

  • October 2009 

    Sponsored by PG&E

    “PG&E” refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation.© 2010 Pacific Gas and Electric Company. All rights reserved.

  • 3

    Program DescriptionPublic service programCash Incentives Energy Design AssistanceProject RoundtableEducational Opportunities Program Coordination

    Facilitate energy efficient design and construction in new multi-family

    housing through cash incentives and design assistance

  • 4

    Eligible CustomersMulti-family buildings in PG&E

    service territory: 3 or more attached units New construction Exceed 2008 Title 24 Standards

    by at least 15% Submit complete application

    package prior to construction start

    Complete construction and verification by December 31, 2015

    * Please contact HMG if you are unsure of the eligibility of your project.

  • Program Process Participant provides HMG with:

    Completed application Title 24 documentation Architectural plan-set (+MEP) Service territory verification W9 Form

    HMG conducts a plan review to verify energy measures, estimated savings, % better than Title 24

    Project enrolled, receives ‘Letter of Enrollment’ Third party HERS verification conducted during construction to

    ensure energy measures installed* HMG verifies any changes to project since enrollment and ensures

    as-built still exceeds Title 24 by at least 15% Project completed and incentives paid

    5

    *Note: the program verification protocols are in addition to any HERS measures on your Title 24

  • 6

    Incentive Information

    Developer Incentives: $100 per unit plus incremental incentives based on energy savings HERS verification incentive: $60 per unit (max of $12,000 per project)

    Energy Consultant Incentives: $50 per unit (max of $10,000 per project)

  • 7

    Program Contact Information

    Toll Free: 866-352-7457 Email: [email protected] Website: www.h-m-g.com/multifamily

    Program Manager: Amy Barr, [email protected] Review Manager: Linda S. Murphy, [email protected] Manager: Sophia Hartkopf, [email protected] Plan Review Manager: Keith Sage, [email protected] Associate: Ashley Heath, [email protected] Assistant: Lauren Moreno, [email protected]

  • Design for Net Zero: Multi-Family Modeling and Measuring

    Techniques

  • Definition of Zero Net Energy

    The California Energy Efficiency Strategic Plan

    The plan adopts three “zero net energy” strategies: All new residential construction in

    California will be zero net energy by 2020

    All new commercial construction in California will be zero net energy by 2030

    Fifty percent of existing buildings will be zero net energy by 2030

  • Definition of Zero Net Energy

    Zero net energy generally means a building will consume no net energy in a typical year. Amount of energy demanded by the building is

    equal to the amount provided by on‐site or near‐by renewable energy sources. When the building is producing more electricity

    than it needs, it exports its surplus to the grid. When the building requires more electricity than is

    being produced on‐site, it draws from the grid.

  • Definition of Zero Net Energy

    ZNE Loading Order Energy efficiency is the highest priority. Generally, when constructing a ZNE building, energy

    efficiency measures can result in up to 70% savings relative to existing building practices.

    Allows for renewables to meet the remaining load.

    ZNE is not a ‘electric-only’ concept Need to account for all fuel uses Need to account for all end-uses

    Heating, cooling, ventilation, DHW, lighting, plug loads, appliances

  • Steps to Net Zero

    Site selection Load reduction Envelope and massing Infiltration reduction Lighting Appliances Misc. plug loads

    HVAC and DHW systems efficiency Renewable energy Commissioning Occupant Behavior

  • Integrated Design Process

    Engage all design team members early in design

  • Building Analysis Tools

    Whole building energy modeling Natural ventilation Computational Fluid Dynamics (CFD)

    Thermal comfort ASHRAE 55 Toolkit, EnergyPlus, California Simulation

    Engine for compliance with 2013 Title 24 Standards, Renewable energy systems

    Microsoft Excel

  • Whole Building Energy Modeling

    Comparative analysis to determine relative impacts of design and energy efficiency measures

    Annual analysis to estimate the annual energy consumption of building

    Code compliance

    Green building rating programs

  • Estimating w/ Energy Modeling

    Many energy modeling tools at our disposal with specific capabilities and setbacks compared to the others Capability to model complex measures Capability to model emerging technologies Capability to perform code compliance Capability to perform weather normalization Difficulty to use software, learning curve Lack of robust HVAC system types Inability to model multiple HVAC system types Inability to accurately model baseloads

  • Estimating w/ Energy Modeling

    EnergyPro / Micropas: lack of advanced controls, uses fixed assumptions for lighting and appliances per T24 Primarily for code compliance Limited systems options

    eQuest More system choices Can input detailed lighting and plugs

    TREAT Targeted toward retrofits, can be used for NC Weather/billing data normalization (bill matching)

    EnergyPlus very detailed with max flexibility and capability very steep learning curve

  • Measuring Actual Performance

    Continuous calibration of energy model

    Facilitates improved understanding of which design features performance is as expected, better, or worse

    Practical implications for future projects

    Commissioning of building will improve likelihood systems operating as intended

  • Site Selection

    Affects ability to utilize conditions for Natural Ventilation Passive solar design features Solar PV Solar DHW

    Optimize for all four with new developments

    More limited with urban infill and redevelopment projects

  • Envelope and Massing

    Thermal mass and passive solar design

    Insulation Windows Overhangs Wall and roof construction Advanced wall framing

    Quality Insulation Installation (QII)

  • Use Overhangs

    Shading opportunities

  • Thermal and Pressure Boundaries

    Thermal boundary around a building is the line that stops heat from moving between unconditioned to conditioned

    Pressure boundary is the line that stops air movement between unconditioned to conditioned

    These two boundaries need to be aligned Effective insulation u-value reduced if not

  • Infiltration Airflow Driving Forces

    Wind Effects Positive pressure on windward side, negative pressure on

    downwind side Mechanical Effects Induced by exhaust fans and ventilation fans

    Stack Effect Negative pressure at the foundation brings air into

    structure, heats and rises, and pressurizes the top of building and exfiltrates

  • Stack Effect Reduction

    Compartmentalization Isolation of units from each other and corridors, shafts,

    elevators, and stairwells Instead of sealing the exterior of the building only

    Local exhaust fans Instead of central exhaust fans

  • Modeling Envelope Tightness

    Inputs Specific leakage area

    3.8 ducted HVAC / 3.2 non-ducted HVAC is default per CEC

  • Envelope & HVAC Interaction

    High performance envelope system can result in smaller HVAC equipment

    Tightly sealed envelope and residential mechanical ventilation per Title 24-2008

  • Lighting, Appliances, and Misc. Plug Loads

    Large component of total MF building energy use Hardwired high-efficacy lighting to limit use of

    incandescent lamps

    Lighting Controls Occupancy sensors Vacancy sensors

    Energy Star appliances Plug load sensors

  • Lighting, Appliances, and Misc. Plug Loads

    The key is what is the lighting baseline? How low wattage and light output can you go without

    affecting lighting quality Poor lighting levels or poorly designed layout may result in

    tenants installing incandescent portable lamps CEC approved software (EnergyPro) requires default

    average wattage for high efficacy lighting instead of actual wattage

    Other non-CEC approved have more flexibility Need to calculate actual lighting for PV design

  • Heating Systems

    Don’t oversize the heating system

    ZNE MF buildings do not need to have exotic super engineered complex HVAC systems

    Use high-efficiency equipment Furnaces w/modulating capabilities Condensing furnaces Heat pumps (air-to-air, water-source, ground-source) Hydronic systems

  • Heating Systems

    Distribution systems Duct sizing (fan power) tight ducts (heat loss)

    Utilize all available HERS measures

  • Cooling Systems

    If cooling is installed, don’t over-size the cooling system Oversizing causes excessive cycling of the compressor

    which wears down the equipment Will operate inefficiently at part load

    High-efficiency DX equipment Standard equipment (heat pump, a/c) VRF: EnergyPro submitted new algortithims to model

    these system more accurately in DOE2 (high-rise only) Mini-split

    Utilize all appropriate HERS measures

  • Mitsubishi City-Multi VRF System

  • Ventilation

    Natural ventilation Thermal comfort analysis to ensure comfort of tenants

    Passive options, z-ducts, operable window, trickle vents Requires advanced tools to model

    Mechanical ventilation with heat recovery

  • Methods of Ventilation

    Natural Local exhaust only Central exhaust “Balanced” system with central supply ventilation air to

    corridor DOE-2 OA-FROM command

  • Central Exhaust Systems

    Advantages Cheap and easy to build

    Dis-advantages Difficult to balance Difficult to maintain Susceptible to fluctuations in system pressure resulting

    from wind and stack effect Makes compartmentalization impossible

  • Domestic Hot Water Systems

    High efficiency condensing DHW or boiler Instantaneous DHW Central DHW Modulating condensing boilers with custom curves EnergyPro can’t model DHW or boiler performance curve EnergyPlus and eQuest can

    Solar thermal Need to combine tools

  • Renewable Energy Options

    Rooftop to conditioned floor area ratio impacts potential Low-rise can likely

    incorporate more solar with a large rooftop area

    Small rooftop of typical high-rise MF will limit ability to maximize solar

  • Renewable Energy Options

    Solar Thermal for DHW CSI calculator F-chart TRANSYS Poly-sun and T-Sol (proprietary)

    Solar PV for electricity (Hourly output is necessary to know net balance) PV Watts full version CECPV F-chart TRANSYS

  • Software: What’s Coming Up

    California simulation engine Will be basis for compliance with 2013 title 24 code Goal to more accurately estimate

    Solar gain impact on cooling energy and peak load Building shell and interior mass on cooling loads and indoor

    temperature variation Ventilation interaction with building mass and its impact on

    cooling energy and peak load Adds new capabilities for comfort analysis, mechanical

    ventilation Integrate HERS II procedures

    EnergyPlus an option for commercial, high-rise residential buildings

  • Questions?

    Jeff Staller916-962-7001

    [email protected]

    Abhijeet Pande916-962-7001

    [email protected]