Upload
isaac-mohanadasan
View
216
Download
0
Embed Size (px)
Citation preview
7/31/2019 Design Project Isaac Final
1/22
Design projectTask 3: Individual
design of wasteheat boiler
Department: Chemical & Environmental Engineering
Name: Isaac Mohanadasan
Student ID:
Group 2
Date due: 12/3/2011
Date Submitted: 15/3/2011
7/31/2019 Design Project Isaac Final
2/22
Contents
Summary
Introduction
Design basis and objectives
Design constraints
Existing designs
Operating conditions and distributions
Material selection
Design methodology and steps
Process control
Safety and maintenance
Start up and shutdown Procedures
Economics
Equipment drawing
Equipment specification
Appendix A: References
Appendix B: Design equations
Appendix C: Excel calculations
Appendix D: Mass and energy balances
Appendix E: correlations
7/31/2019 Design Project Isaac Final
3/22
Introduction
Energy conservation and its optimum utilisation are of key importance to all plant design.
The aim of all plant designers is to maximise the use of all available energy to reduce
operating costs and increase potential revenue. Our design group objectives are simply tomaximise profits by minimising incurred costs and manufacturing more sellable products. In
our sulphuric acid manufacturing process, a sulphur burner aids in producing sulphur dioxide,
a raw material required for sulphuric acid manufacture. The conversion of sulphur to sulphur
dioxide is highly exothermic, and the process stream has to be cooled before it meets the
necessary conditions required to enter the sulphur trioxide converter. The thermal energy
released during this cooling process, known as waste heat, is proposed to be used to produce
sellable steam thus generating profit. The production of steam takes place in a waste-heat
boiler and may be used to generate electricity. I have been asked to design a waste-heat boiler
which meets the design group and clients requirements. This report outlines the design
objectives and constraints and provides an idea on the design consideration and methodology
used for the waste heat boiler. The design procedure is broken up into four stages, which
include; materials of construction, thermal design, mechanical design and an
evaluation/optimisation of the design. Other design considerations have been included in the
report such as safety, economic, control and maintenance.
Design objectives and constraints
The overall design objective of the sulphuric acid manufacturing plant is to maximise profits
by producing more sellable products while reducing capital and operating costs. The wasteheat boiler must abide by the overall design objective. To achieve the main objective, there
must be an efficient transfer of thermal energy between the process flue gas and water within
the waste-heat boiler. Effective heat transfer leads to the production of more steam which
increases profits. In addition, the mechanical design of the process equipment must be simple
as possible and easy to maintain. Low maintenance and simplicity reduce both capital and
operating costs. Furthermore, the material of construction, and boiler itself, must be able to
withstand its desired design life. The process should be relatively easy to control, which
reduce operating costs.
The design is constrained by several factors both externally and internally. Externalconstraints are fixed, in the sense that the design must comply with them. Externally, the
design must comply with Government control, economics & resources available.
Governments have imposed emission standards which the plant and therefore the waste heat
boiler must conform to. The economics and resources available heavily influence the design
of any piece of equipment. Mechanical codes and standards are imposed to standardise
equipment sizing, for ease of manufacturing. Physical and chemical laws aid in producing a
reliable design which can withstand its design life. Internal constraints are less rigidand
include the material of construction, choice of process and its conditions. As a designer, we
must meet the requirements of the client whilst abiding by any constraints imposed.
7/31/2019 Design Project Isaac Final
4/22
7/31/2019 Design Project Isaac Final
5/22
pressure across the shell drops as the processes gas flows through. There is a steady decrease
in pressure across the tubes as the water flows through. Careful considerations need to be
made for efficient operations. For instance, the operating temperature should not fall below
the dew points of the gases, as this reduces heat transfer area which decreases the production
of steam. Too high temperatures will lead to failures within the structure of the equipment asmechanical properties deteriorate. High temperatures may promote scaling and fouling all of
which reduce thermal efficiencies. Pressures within the boiler affect the stresses applied to
equipment and flow rates of fluids exiting the boiler. Distribution of heat can be considered to
be roughly uniform as baffles ensure the process gas flows evenly across the tubes within the
shell. Hence, temperature and pressure boundaries are defined.
Material Selection
The governing factor in material selection is the ability of said material to resist corrosion.
In addition, mechanical & thermal properties, fabrications, availability and cost all need to beconsidered carefully for the correct selection of construction materials. The most economical
material that satisfies both process and mechanical requirements should be selected. This
will be the material that gives the lowest cost over the working life of the plant, allowing for
maintenance and replacement. Its selection directly affects operating, capital and
maintenance costs and as a result must be chosen with caution.
Steels are the most common materials used for equipment design. This is because of its high
durability, availability, thermal properties and costs. Carbon steel is the cheapest form
available. It has a higher thermal conductivity and strength compared to other forms of steel.
However, the process gas consists of carbon dioxide, nitrogen, oxygen and sulphur dioxide
entering the boiler at a temperature of 938.96oC. Carbon steels heated for prolonged periods
at temperatures above 455C may be subject to carbon segregation, which is then
transformed into graphite (Ref. E5, p. 23.5). When this occurs the structural strength of the
steel is reduced. In addition, oxygen in the process gas causes the carbon steel surface to
oxidise, which decrease thermal transfer efficiencies. Even though the process gas is non-
corrosive, any leakage within the tube side will create an environment that produces sulphuric
acid. Carbon steel has a low resistance to corrosion, which indicates that it is not ideal for our
design. Studies have found that an increase of chromium content within steel allow for
operating temperatures to be more flexible. According to literature, an alloy of 14% to 18%chromium extends the service to 850C
[5]. Our process gas stream enters the boiler at
938.96oC. As a result, steel containing 26% chromium is selected as the material of
construction, known as stainless steel grade 310. Amongst its flexibility and stability at high
temperatures, there are many other benefits of its use. The high chromium content ensures
resistance to oxidations and surface corrosion. According to literature, the material has a
Good resistance to oxidation in intermittent service in air at temperatures up to 1040C and
1150C in continuous service.it has a Good resistance to thermal fatigue and cyclic heating.
Widely used where sulphur dioxide gas is encountered at elevated temperature[6]s.
In
addition, its high youngs modulus and tensile strength insure the stability of the equipment
design. It has a good resistance to scaling, which greatly improves the thermal efficiencies of
7/31/2019 Design Project Isaac Final
6/22
the boiler. Grade 310, combining excellent high temperature properties with good ductility
and weldability, is designed for high temperature service. It resists oxidation in continuous
service at temperatures up to 1150C[7]. Therefore, mechanically, the material can easily be
welded for ease of fabrications. Steel 310 has a similar thermal expansion coefficient to
carbon steel, and is relatively low which is beneficial. However, a compromise has to bemade as its thermal conductivity is lower than that of carbon steel. Nevertheless, in
comparison to other more suitable materials it has one the highest thermal conductivity. It is
readily available and is relatively cheap. Hence, one can conclude that all the material
requirements have been fulfilled. As a result, stainless steel 310 has been selected as the
material of construction for both the shell and tube.
Design Methodology & Steps
The design selected is a 1-2 shell and tube heat exchanger in which the exit water/steam
composition within the tubes is connected to a steam drum. The heat exchanger selected is an
open floating head heat exchanger to allow for thermal expansions. The number of tube
passes was set as 2 for a greater heat transfer coefficient. A shell and tube heat exchanger was
selected due to its simplicity and versatility. It provides a large surface area within a small
volume. The benefit of a floating head exchanger is that the tubes can be easily removed for
cleaning. In addition, a clamp ring-type internal floating-head exchanger is selected. This
split-flange design reduces the large clearances otherwise needed in other internal floating-
head exchangers.
Before any numbers can be calculated we must first understand the fundamental parameters
that affect the design of the waste heat boiler and thus thermal transfer efficiencies. High flow
rates, fluid velocities and viscosities all ensure the flow regimes within the boiler are
turbulent. Turbulent flow improves thermal transfer efficiencies. However, higher pressure
drop occur. Higher pressure drops incur additional costs of operating as the pumps have to
work harder. In addition, higher velocities increase the rate of erosion of the metal surface. A
benefit is that particles from the burner, such as ash, cannot settle as easily. As a result
phenomenon such as fouling and scaling are reduced. Water has a great chance of causing
fouling the tube surface; hence its velocity is kept high. Common tube velocities are between
the range of 1-3 m/s. The velocities form the basis of the design as most of the critical
parameters are in one way or another related to it. To begin the design process, an estimate of
the overall heat transfer coefficient needs to be made. For the purpose of my design, I have
used an initial value of 100w/m.k. This estimation helps us determine the internal
configuration of the boiler.
The next part of the design involves the selection of the tube diameter and length. In order to
select the optimum tube dimensions, tube lengths were varied at fixed diameters until a fluid
velocity of 1 was found. The obtained values are shown below:
7/31/2019 Design Project Isaac Final
7/22
ID (mm) L(m) V (m/s)
Pressure
drop (Pa)
number
of tubes
10 9 1.03 3888054.55 1897.175
15 15 1.03 4366357.75 878.48
20 21 1.03 4536846.62 496.7388
25 27 1.03 4613501.62 319.73
30 33 1.02 4653191.98 223.12
As you can see from the table above, as the diameter increases, the number of tubes required
decreases. On the other hand, the lengths of the tubes increase with diameter in order to
maintain the same fluid velocity. In addition, pressure drop also increases with diameter.
Hence, a compromise needs to be made between the properties above to obtain an optimum
value. Larger tubes will generally result in a lower cost exchanger[9], as it reduces shell
diameter. However, it increases pump requirements. As a result, a tube internal diameter of
25mm (1inch) is selected with a length of 27m based on optimum selection. Once the tubedimensions are determined, we are then able to determine other internal components. Tube
arrangement was selected as triangular as it is the best arrangement for maximum heat
transfer. It does however; increase the pressure drop on the shell side. As a rule of thumb, the
tube pitch is 1.25 time the outer diameter of the tubes. Hence the outer diameters of the tubes
are computed as low as possible to ensure the size of the shell is at its optimum. All
thicknesses in the design include a 2mm corrosion allowance. Baffles play an important role
in the heat transfer process as they direct the process gas flow path. The also provide support
for the tubes within the shell. Hence, the spacing of the baffles along the length is of
importance. According to literature, the optimum spacing is 1/5th
of the shell diameter with a
baffle cut of 25%. These values have been used in the calculations.
The next part of the design is the re-evaluation of the estimated overall thermal coefficient.
Both the kern and bell methods have been compiled and used for the calculations. This is
because the kern method is inaccurate for calculating the shell-side heat transfer coefficient
and shell-side pressure drop[8]. This is because the method does not take into consideration
bypass and leakage factors. These methods are based on experimental work with standard
tolerances. They give reasonable results in most cases and are therefore applied here. A
preliminary estimation was made in order to obtain geometrical data of the equipment to
apply these method. Based on the estimated thermal conductivity, a new calculated thermal
conductivity is derived from the selected methods. These methods consider the tube side and
shell side thermal coefficients independently and equate them together to obtain the overall
thermal coefficient. The estimated value is then re-evaluated until the estimate equals the
value obtained by the kern method. Geometry of the equipment is changed for optimum
sizing and to increase surface area of the tubes, if it is required. Details of the calculations
have been included in the appendix.
The overall thermal coefficient calculated was 196.21w/m.k. The pressure drop on the tube
side was computed as 802441.3 pa. The pressure drop on the shell side was found to be25166081 pa which all seems reasonable. Since the bell method is more accurate for
7/31/2019 Design Project Isaac Final
8/22
determining thermal coefficients, its overall thermal coefficient is used for the design. The
steam drum sits on the top of the heat exchanger, and is a relatively simple design. Details of
the calculations used are shown in the appendix.
Mechanical designThe sizing of the equipment was done in accordance with British codes and standards which
include the following:
BS 3274 (1960): Tubular Heat Exchangers for General Purposes.
BS 3606 (1978): Specification for Shell Tubes in Heat Exchangers.
BS 5500 (1985): Unfired Fusion Welded Pressure Vessels.
Maintenance
If water quality is not good, it may cause the tubes to degrade gradually. This will reduce the design
life of the equipment. As a result, the water must be Deaerated in order to reduce the oxygen content
within the water. Deposition, such as ash, from the gas stream coming from the burner needs to be
handled as it will reduce heat transfer areas thus reducing thermal transfer efficiencies. It is proposed
that a boiler blow down system is used to remove any particulate matter and condensate from the shell
side. The floating head design allows the tubes to be removed for cleaning. Erosion is not considered
as the material of construction is erosion resistant and fluid velocities are within the allowable range..
Start up and shut down procedures
The boiler must initially be preheated so that the material properties within the boiler are
stable. The drum and water feed valves have to be fully open initially so that the tubes are not
empty. The heating of empty tubes may be hazardous. The process gas valve is the last valve
that should be opened. The liquid hold-up volume within the steam drum acts as a time
constraint. To shut down the boiler, the process gas valve must be closed first, to avoid
heating of empty tubes. Next, the feed water, and finally the steam drum valve must be closed
in that order.
Safety considerations
Several factors need to be considered for a successful and safe design. Firstly all parameters must be
controlled with the appropriate monitoring and control mechanisms. If the process gas flow rate was
higher than its design value, then there would be a pressure build-up within the boiler system. More
steam is produced which increase the pressure demands of the steam drum. This could lead to material
failure if not properly controlled. In addition, higher water flow rates will reduce the temperature of
the process gas making its conditions undesirable for the converter. Hence water flow rates need to be
monitored carefully. Any leakages along the tube side could potentially be catastrophic as acid will be
produced from the combination of process gas and water. It is proposed that pigs be used to monitor
the inner surface of the tubes. Pigs are devices that flow through pipes and monitor their integrity.
However, a pig catcher needs to be installed, adding to capital costs. In the event of a tube leakage,the process gas must be by-passed.
7/31/2019 Design Project Isaac Final
9/22
Process control
According to literature, the most effective type of control is a PID controller. Hence, this control has
been used in the design to regulate parameters. What it does is basically restores any deviated variable
back to its set point. It has been employed to control the flow rates of the water and process gas. Flow
rates directly affect other parameters such as temperature and pressures. The exit process gas must be
at a temperature suitable for the converter. Hence temperature control has been used in the design by
manipulating flow rates. The following diagram shows the control mechanisms of the design:
Where the exit steam enters a steam drum.
Costing
Costing was determined using plant design equations as follows.
[ ]
*+2]
Cost of the equipment was found to be
7/31/2019 Design Project Isaac Final
10/22
References
1. Coulson-Richardson-s-Chemical-Engineering-Vol-6 design2. Equitment description of componets & design considerations3. Types control and maitainance evaluation components page 24. Design calculation and samples p1985. Design calculation and samples p1986. http://www.azom.com/article.aspx?ArticleID=9667. http://www.azom.com/article.aspx?ArticleID=9668.http://www.engr.iupui.edu/me/courses/shellandtube 9. Coulson-Richardson-s-Chemical-Engineering-Vol-6 design
http://www.azom.com/article.aspx?ArticleID=966http://www.azom.com/article.aspx?ArticleID=966http://www.engr.iupui.edu/me/courses/shellandtubehttp://www.engr.iupui.edu/me/courses/shellandtubehttp://www.engr.iupui.edu/me/courses/shellandtubehttp://www.engr.iupui.edu/me/courses/shellandtubehttp://www.azom.com/article.aspx?ArticleID=966http://www.azom.com/article.aspx?ArticleID=9667/31/2019 Design Project Isaac Final
11/22
Appendix: Calculations
For the purpose of these calculations, I have assumed the flowing
Water is vaporises within the tubes The process gas has the same properties as that of air
The energy evolved from the process gas:
Where 1 represents properties of the process gas and 2 is that of the water
From the above equation, the mass of the water can be calculated
Calculation of mean temperature difference
For counter current flow, log mean temperature difference is
The log mean temperature difference is corrected by the correlations given in appendix B
Heat transfer area
Where the overall heat transfers coefficient is estimated a 100w/m.k for determination of equitment
dimensions.
Based on trial and error method for determining the most effective dimensions of the tubes, a tube
with an internal diameter of an inch and a length of 27 was selected
Number of tubes:
Tube cross sectional area
=
Volumetric flow rates:
7/31/2019 Design Project Isaac Final
12/22
Tube side velocity
Tube side velocity ( The tube bundle Diameter:
Shell clearance:
Area of shell:
tube pitch =1.25
baffle spacing =
From the area of the shell we can then calculate the the velocity as follows;
Tube side heat transfer coefficient
(kf/di)
Shell side heat transfer coefficient (kern method)
( )
7/31/2019 Design Project Isaac Final
13/22
Shell side heat transfer coefficient (Bell method)
hs = hoc Fn Fw Fb FL
where hs heat transfer coefficient calculated for cross-flow over an ideal tube bank,
no leakage or bypassing.
Fn = correction factor to allow for the effect of the number of vertical tube rows,
Fw = window effect correction factor
Fb = bypass stream correction factor,FL = leakage correction factor.
Overall heat transfer coefficient:
Tube side pressure drop:
[ ] Shell side pressure drop: (Kerns method),
Shell side pressure drop: (bell method)
Steam drum design
Settling velocity:
7/31/2019 Design Project Isaac Final
14/22
Volumetric flow rates
= Lv/Dv ratio was at 4 based on the outlet steam pressure
Vapour velocity:
Vapour residence time:
=
Assuming real time is the same as actual time, we can calculate the diameter of the vessel and hence
the length.
7/31/2019 Design Project Isaac Final
15/22
Excel calculations
Mechanical design of waste heat boiler
Shell side
Variables
Flue gas inlet pressure
Flue gas inlet temperature
Shell thickness
Pressure 0.011 N/mm2
Dsi 616.0714269 mmStress factor 515 na
Joint factor 0.8 na
Thickness 0.008224364 mm
with
corrosion 2.008224 mm
Tube side
Pressure 0.385 N/mm2
Ds 25 mm
Stress factor 515 na
Joint factor 0.8 na
tube thickness 0.01167537
with
corrosion 2.011675 mm
Steam drum
Pressure 0.385 N/mm2
Ds 1934.280457 mm
Stress factor 0.515 na
Joint factor 0.8 na
Shell thickness 615.9619323
with
corrosion 617.9619 mm
Physical and chemical data
Process gas
Propertise inlet mean outlet units
7/31/2019 Design Project Isaac Final
16/22
temperature 938 677.5 417 c
cp 1.1427 1.10885 1.075 kj/kgmol.k
k 0.068 0.06018 0.05236 w/m.c
density 0.34 0.425 0.51 kg/m3
viscosity 0.000042 0.00003766 0.00003332 pa.s
water propertise
Propertise inlet mean outlet units
temperature 25 133.5 242 c
cp 4.181322 3.999261 3.8172 kj/kgmol.k
k 0.607 0.328175 0.04935 w/m.c
density 997.13 507.315 17.5 kg/m3viscosity 0.00089 0.0004536 0.0000172 pa.s
energy calculations
Mass flow rate of gas 61.34451514 Kg/s
heat evolved 35439.39198 kj/s
Mass of water 40.83633712 kg/s
Overall heat transfer coefficient estimate
U 196 w/m2C
Mean temperature difference
log Mean temperature 450.2489347 C
Heat transfer area
A 401.585 m2
Number of tubes And tube sizes
tube OD 29.02335 mm
Tube ID 25 mm i
Length 27 m
Number of tubes 163.128228
Tube cross area 0.000490859 m2
area per pass 0.04003651 m2
7/31/2019 Design Project Isaac Final
17/22
Tube side velocity
Volumetric flow 0.080495032 m3/s
tube side velocity 2.010540677 m/s
Bundle and shell diameter
Nt 163.1282
db 548.0714 mm Diameter of tube bundle
K 0.249
Shell ID 616.0714 mm
Area of shell
tube pitch 36.27918843 mm
baffle spacing 123.2142854 mm
Ds 616.0714269 mmdo 29.02335074 mm
Area of shell 0.01518176 m2
Mass flow rate gas 220840.2545 Kg/hr input
Mass flowrate/s 61.34451514
Gs 4040.672139
Vs 9507.463856 m/s
Tube side heat coifficient
Kern
Re 65262.71
Pr 0.005528
di 25
L/di 1080
Jh 0.0035 Input
hi 539.4351 w/m2c
Shell side heat transfer coificient
Re 2211107.101
equialent diameter 20.60803019 mmPr 0.000693906
Jh 0.007 input
h0 4.099707088 w/m2c
Overall heat rransfer coificient
thermal conductivity of steel 310 18.7 w/mC
1/u 0.246189459
fi 0.0002 Input
fo 0.0001
U 4.061912342 -0.97928
7/31/2019 Design Project Isaac Final
18/22
pressure drop tube side
Number of passes 2
Jf 0.045 input
pressure drop 802441.3121 pa
Pressure drop shell side
Jf 0.025 input
pressure drop 25166080.57 pa
steam drum
settling velocity 0.523733138 m/s
without pad 0.078559971 m/s
vapor vol flow rate 3.505400865 m3/s
selected Lv/Dv ratio 4
Lv Lv = 0.5Dv
DV
cross sectional area 0.393 Dv^2
vapour velocity 8.919595077 Dv^-2
vapour res time 1.677852349 Dv
actual res time 0.448450851 Dv^3
Dv 1.934280457 m
Liquid hold up 0.000648196 m3/s
liq cross sec 1.469217069 m2
length 7.73712183 2
hold up vol 11.36751145 m3/s
hold up time 17537.15617 s
Bells method calculations
crossflow area 2.634740615 m2
shell side mass
velocity 23.28294284 Kg/sm2
equivalent diameter 20.60803019 mm
Mean temp 677.5 C
density 0.425 kg/m3
Kf 0.06018 w/mk
Re 618240.649
Pr 0.000693906
Baffle
cut 0.25
Jh 0.002 input
ho 327.5160302
7/31/2019 Design Project Isaac Final
19/22
CORRECTION FACTOR Tube row
Vertical tube pitch 31.56289393 mm
Baffle height 154.0178567 mm
height between baf 308.0357135
number of res cross 9.75942555
Fn 1 find
CORRECTION FACTOR window
height of baffle cord -42.75446418
ra 0.14
Tubes in one window 22.83795192
Tubes in cross flow 117.4523241
Rw 0.28
Fw 1.08
CORRECTION FACTOR bypass
Ab 0.008378571
ratio 0.003180037
Fb 1
1
Hs 353.7173126
Overall heat transfer coieffiecent
1/U 0.00509671
U 196.2050128 0.001045983
Pipe sizing
Designed so fluid velocity is between 1-2 m/s
ID (mm) L(m) V Pressuredrop number oftubes
10 9 1.03 3888054.55 1897.175
15 15 1.03 4366357.75 878.48
20 21 1.03 4536846.62 496.7388
25 27 1.03 4613501.62 319.73
30 33 1.02 4653191.98 223.12
tubes selected are of 1 inch diamter and a length of 21
7/31/2019 Design Project Isaac Final
20/22
Mass balance
7/31/2019 Design Project Isaac Final
21/22
Energy balance
7/31/2019 Design Project Isaac Final
22/22