Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
© 2014 HDR, all rights reserved.
Aqua Ohio’s Use of Progressive Design-Build at the Marion WTP
Designing, Constructing, and Commissioning New Pretreatment Facilities in 8 Months
Authors:Pete Kusky, PE, AQUA
Jason Lemire, PE, BowenLee Tourek, PE, HDR
01 Project Drivers & Plant Background
02 Delivery Approach & Design
03 Project Execution & Construction
04 Start Up
05 Moving the Marion WTP Forward & Conclusion
Agenda
Acquired American Water’s Ohio operations
in 2012
Over 150,000 customers served in 19
counties
AQUA Ohio
Dual source water types
Conventional lime – soda softening plant
6.8 MGD average demand
10.2 MGD capacity
Marion Water Treatment Plant
Improve redundancy
Improve maintenance operations
Age/condition
Risk based comparison
Project Drivers
Existing Water Treatment Plant
Label BuildingA Raw Water BasinsB AeratorC Little Scioto IntakeD Low Service Pump
BuildingsE High Service Pump
StationF Filter and Clearwell
BuildingG Mixing TanksH Clarifier TankI Settling TankJ Recarbonation Tank
Schedule, schedule, schedule!
Owner involvement
Single path of communication
Design-builder provides majority of trade
resources
Why Progressive Design-Build for AQUA?
Equipment SuppliersTrade Subcontractors
Owner
Design-Builder
Contract
Communication
Source: Construction Industry Institute (CII)/Penn State
Research comparison of 351 projects of varying sectors, ranging from 5K to 2.5M square feet in size
Design-Build Versus the Rest
Metric D-B vs D-B-B D-B vs. CMARUnit Cost 6.1% lower 4.5% lower
Construction Speed 12% faster 7% fasterDelivery Speed 33.5% faster 23.5% faster
Cost Growth 5.2% less 12.6% lessSchedule Growth 11.4% less 2.2% less
Truly separate treatment trains
Replace only what is necessary
Future adaptability
Planning Considerations
Conversion to conventional sedimentation
Provisions for sludge handling
Hydraulic profile for future plant
Future Adaptability
Basis of Design HighlightsDesign ParametersPre-sedimentation basins
Quantity 2Dimensions 24’ W x 80’ L x
16’ SWDAerators
Quantity 2Loading Rate 5 gpm/sf
Equalization basinsQuantity 2
Dimensions 24’ W x 108’ L x 15’ SWD
Project Challenge Bowen-HDR SolutionExtended duration or repeated reviews impacts delivery schedule
Facilitate review process through early and frequent communication and conducting a design brief with the OEPA
The plan review process results in unforeseen changes to project
Clearly communicate the design criteria and basis of design to obtain concurrence from the OEPA at an early stage
‘Over driving the headlights’-submitting detailed information before the base concept has been discussed with OEPA for general concurrence puts the project at risk for rework and schedule impact
Conduct a facilitated review process – a series of discussions and meetings to present the design information
Overcoming Permitting Challenges Associated with Integrated Delivery
Lock in on critical items
Stage delivery of disciplines
Early action on critical path
Transition from Design to Procurement
Accelerated development of deliverables
Design Milestones
RFP 9/24/15
B.O.D. Finalized 11/20/15
30% Design &OEPA Submittal
12/18/1560% Design
& GMP1/27/16
Building Department Submittal
2/3/16
IFC Set 1 (Civil & Structural)
2/12/16Basin slab, rebar, mix design shop drawings
approved2/25/16
Start-Up8/3/16
Groundbreaking, IFC Set 2 (Process
& Electrical2/26/16
Quick decisions are essential on
design build delivery if the schedule
is to be maintained
Design-Build is a continuous process
Project Pacing
Low Service Pump Stationo Constrained work areao Existing valveso Planning approach
Construction Challenges
Define the Process
Challenges
o Piping Tie-Ins
o Instrumentation
o Chemical Feed
Resolution
o Collaboration
o Active Management of Issues
Start Up
Schedule, schedule, schedule!
Owner involvement/single point of
responsibility
Risk/cost management
Flexibility and collaboration
Conclusion