Upload
mourad-
View
81
Download
2
Embed Size (px)
Citation preview
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
UNIONUNIONUNION Jul-11-16 Jul-11-16 May-31-16 518 531 103 Apr-03-18 Apr-18-18PermitsPermitsPermits Jul-11-16 Jul-11-16 Jul-11-16 60 69 62 Sep-20-16 Sep-30-16A6900 Foundation Permit Completed Jul-11-16 Jul-11-16 Jul-11-16 0 0 0 Jul-11-16 Jul-11-16 Jul-11-16
A7710 Building Permit Not Started Sep-20-16 Sep-30-16 0 0 0 Sep-20-16 Sep-30-16
A7720 Plumbing Permit - Delayed Completed Aug-10-16 Sep-30-16 Sep-22-16 0 0 0 Aug-10-16 Sep-30-16 Sep-22-16
MeetingsMeetingsMeetings Jul-11-16 Jul-11-16 Jul-11-16 518 531 44 Apr-03-18 Apr-18-18ConsultantsConsultantsConsultants Jul-11-16 Jul-11-16 Jul-11-16 515 524 36 Mar-30-18 Apr-10-18A1180 Consultants meeting 1 Completed Jul-11-16 Jul-11-16 Jul-11-16 0 0 0 Jul-11-16 Jul-11-16 Jul-11-16A1210 Consultants meeting 2 Completed Jul-26-16 Jul-26-16 Jul-26-16 0 0 0 Jul-26-16 Jul-26-16 Jul-26-16A1220 Consultants meeting 3 - Cancelled Completed Aug-09-16 Aug-09-16 Aug-09-16 0 0 0 Aug-09-16 Aug-09-16 Aug-09-16A1230 Consultants meeting 4 Completed Aug-23-16 Aug-23-16 Aug-23-16 0 0 0 Aug-23-16 Aug-23-16 Aug-23-16A1360 Consultants meeting 5 - Cancelled Completed Sep-06-16 Sep-06-16 Aug-23-16 0 0 0 Sep-06-16 Sep-06-16 Aug-23-16A6310 Consultants meeting 6 Not Started Sep-20-16 Sep-30-16 0 0 0 Sep-20-16 Sep-30-16A6320 Consultants meeting 7 Not Started Oct-04-16 Oct-15-16 0 0 0 Oct-04-16 Oct-15-16A6330 Consultants meeting 8 Not Started Oct-18-16 Oct-28-16 0 0 0 Oct-18-16 Oct-28-16A6340 Consultants meeting 9 Not Started Nov-01-16 Nov-12-16 0 0 0 Nov-01-16 Nov-12-16A6350 Consultants meeting 10 Not Started Nov-16-16 Nov-26-16 0 0 0 Nov-16-16 Nov-26-16A6360 Consultants meeting 11 Not Started Nov-30-16 Dec-10-16 0 0 0 Nov-30-16 Dec-10-16A6370 Consultants meeting 12 Not Started Dec-14-16 Dec-24-16 0 0 0 Dec-14-16 Dec-24-16A6380 Consultants meeting 13 Not Started Dec-29-16 Jan-10-17 0 0 0 Dec-29-16 Jan-10-17A6390 Consultants meeting 14 Not Started Jan-13-17 Jan-24-17 0 0 0 Jan-13-17 Jan-24-17A6540 Consultants meeting 15 Not Started Jan-27-17 Feb-07-17 0 0 0 Jan-27-17 Feb-07-17A6550 Consultants meeting 16 Not Started Feb-11-17 Feb-22-17 0 0 0 Feb-11-17 Feb-22-17A6560 Consultants meeting 17 Not Started Feb-25-17 Mar-08-17 0 0 0 Feb-25-17 Mar-08-17A6570 Consultants meeting 18 Not Started Mar-11-17 Mar-22-17 0 0 0 Mar-11-17 Mar-22-17A6580 Consultants meeting 19 Not Started Mar-30-17 Apr-10-17 0 0 0 Mar-30-17 Apr-10-17A6590 Consultants meeting 20 Not Started Apr-13-17 Apr-24-17 0 0 0 Apr-13-17 Apr-24-17A6600 Consultants meeting 21 Not Started Apr-27-17 May-08-17 0 0 0 Apr-27-17 May-08-17A6610 Consultants meeting 22 Not Started May-11-17 May-22-17 0 0 0 May-11-17 May-22-17A6620 Consultants meeting 23 Not Started May-26-17 Jun-06-17 0 0 0 May-26-17 Jun-06-17A6630 Consultants meeting 24 Not Started Jun-09-17 Jun-20-17 0 0 0 Jun-09-17 Jun-20-17A6640 Consultants meeting 25 Not Started Jun-23-17 Jul-06-17 0 0 0 Jun-23-17 Jul-06-17A6650 Consultants meeting 26 Not Started Jul-10-17 Jul-20-17 0 0 0 Jul-10-17 Jul-20-17A6660 Consultants meeting 27 Not Started Jul-24-17 Aug-04-17 0 0 0 Jul-24-17 Aug-04-17A6670 Consultants meeting 28 Not Started Aug-08-17 Aug-18-17 0 0 0 Aug-08-17 Aug-18-17A6680 Consultants meeting 29 Not Started Aug-22-17 Sep-01-17 0 0 0 Aug-22-17 Sep-01-17A6690 Consultants meeting 30 Not Started Sep-06-17 Sep-16-17 0 0 0 Sep-06-17 Sep-16-17A6700 Consultants meeting 31 Not Started Sep-20-17 Sep-30-17 0 0 0 Sep-20-17 Sep-30-17A6710 Consultants meeting 32 Not Started Oct-04-17 Oct-16-17 0 0 0 Oct-04-17 Oct-16-17A6720 Consultants meeting 33 Not Started Oct-19-17 Oct-30-17 0 0 0 Oct-19-17 Oct-30-17A6730 Consultants meeting 34 Not Started Nov-02-17 Nov-15-17 0 0 0 Nov-02-17 Nov-15-17A6740 Consultants meeting 35 Not Started Nov-18-17 Nov-29-17 0 0 0 Nov-18-17 Nov-29-17A6750 Consultants meeting 36 Not Started Dec-02-17 Dec-13-17 0 0 0 Dec-02-17 Dec-13-17A6760 Consultants meeting 37 Not Started Dec-16-17 Dec-28-17 0 0 0 Dec-16-17 Dec-28-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Sep-30-16, Permits
Foundation Permit
Building Permit
Plumbing Permit - Delayed
Consultants meeting 1Consultants meeting 2
Consultants meeting 3 - CancelledConsultants meeting 4
Consultants meeting 5 - CancelledConsultants meeting 6
Consultants meeting 7Consultants meeting 8
Consultants meeting 9Consultants meeting 10
Consultants meeting 11Consultants meeting 12
Consultants meeting 13Consultants meeting 14
Consultants meeting 15Consultants meeting 16
Consultants meeting 17Consultants meeting 18
Consultants meeting 19Consultants meeting 20
Consultants meeting 21Consultants meeting 22
Consultants meeting 23Consultants meeting 24
Consultants meeting 25Consultants meeting 26
Consultants meeting 27Consultants meeting 28
Consultants meeting 29Consultants meeting 30
Consultants meeting 31Consultants meeting 32
Consultants meeting 33Consultants meeting 34
Consultants meeting 35Consultants meeting 36
Consultants meeting 37
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A6770 Consultants meeting 38 Not Started Jan-02-18 Jan-12-18 0 0 0 Jan-02-18 Jan-12-18A6780 Consultants meeting 39 Not Started Jan-16-18 Jan-26-18 0 0 0 Jan-16-18 Jan-26-18A6790 Consultants meeting 40 Not Started Jan-30-18 Feb-10-18 0 0 0 Jan-30-18 Feb-10-18A6800 Consultants meeting 41 Not Started Feb-14-18 Feb-24-18 0 0 0 Feb-14-18 Feb-24-18A6810 Consultants meeting 42 Not Started Feb-28-18 Mar-10-18 0 0 0 Feb-28-18 Mar-10-18A6820 Consultants meeting 43 Not Started Mar-14-18 Mar-24-18 0 0 0 Mar-14-18 Mar-24-18A6830 Consultants meeting 44 Not Started Mar-30-18 Apr-10-18 0 0 0 Mar-30-18 Apr-10-18
TradesTradesTrades Jul-19-16 Jul-19-16 Jul-18-16 511 524 35 Apr-03-18 Apr-18-18A6910 Trade meeting 1 Completed Jul-19-16 Jul-19-16 Jul-18-16 0 0 0 Jul-19-16 Jul-19-16 Jul-18-16A6920 Trade meeting 2 Completed Jul-27-16 Jul-27-16 Jul-25-16 0 0 0 Jul-27-16 Jul-27-16 Jul-25-16A6930 Trade meeting 3 Completed Aug-05-16 Aug-03-16 Aug-02-16 0 0 0 Aug-05-16 Aug-03-16 Aug-02-16A6940 Trade meeting 4 Completed Aug-13-16 Aug-10-16 Aug-08-16 0 0 0 Aug-13-16 Aug-10-16 Aug-08-16A6950 Trade meeting 5 Completed Aug-22-16 Aug-16-16 Aug-15-16 0 0 0 Aug-22-16 Aug-16-16 Aug-15-16A6960 Trade meeting 6 Completed Aug-30-16 Aug-24-16 Aug-22-16 0 0 0 Aug-30-16 Aug-24-16 Aug-22-16A6970 Trade meeting 7 Completed Sep-07-16 Sep-06-16 Aug-29-16 0 0 0 Sep-07-16 Sep-06-16 Aug-29-16A6980 Trade meeting 8 Not Started Sep-15-16 Sep-30-16 0 0 0 Sep-15-16 Sep-30-16A6990 Trade meeting 9 Not Started Sep-23-16 Oct-08-16 0 0 0 Sep-23-16 Oct-08-16A7000 Trade meeting 10 Not Started Oct-01-16 Oct-18-16 0 0 0 Oct-01-16 Oct-18-16A7010 Trade meeting 11 Not Started Oct-11-16 Oct-26-16 0 0 0 Oct-11-16 Oct-26-16A7020 Trade meeting 12 Not Started Oct-19-16 Nov-03-16 0 0 0 Oct-19-16 Nov-03-16A7030 Trade meeting 13 Not Started Oct-27-16 Nov-12-16 0 0 0 Oct-27-16 Nov-12-16A7040 Trade meeting 14 Not Started Nov-04-16 Nov-21-16 0 0 0 Nov-04-16 Nov-21-16A7050 Trade meeting 15 Not Started Nov-14-16 Nov-29-16 0 0 0 Nov-14-16 Nov-29-16A7060 Trade meeting 16 Not Started Nov-22-16 Dec-07-16 0 0 0 Nov-22-16 Dec-07-16A7070 Trade meeting 17 Not Started Nov-30-16 Dec-15-16 0 0 0 Nov-30-16 Dec-15-16A7080 Trade meeting 18 Not Started Dec-08-16 Dec-23-16 0 0 0 Dec-08-16 Dec-23-16A7090 Trade meeting 19 Not Started Dec-16-16 Jan-03-17 0 0 0 Dec-16-16 Jan-03-17A7100 Trade meeting 20 Not Started Dec-24-16 Jan-11-17 0 0 0 Dec-24-16 Jan-11-17A7110 Trade meeting 21 Not Started Jan-04-17 Jan-19-17 0 0 0 Jan-04-17 Jan-19-17A7120 Trade meeting 22 Not Started Jan-12-17 Jan-27-17 0 0 0 Jan-12-17 Jan-27-17A7130 Trade meeting 23 Not Started Jan-20-17 Feb-04-17 0 0 0 Jan-20-17 Feb-04-17A7140 Trade meeting 24 Not Started Jan-28-17 Feb-14-17 0 0 0 Jan-28-17 Feb-14-17A7150 Trade meeting 25 Not Started Feb-06-17 Feb-22-17 0 0 0 Feb-06-17 Feb-22-17A7160 Trade meeting 26 Not Started Feb-15-17 Mar-02-17 0 0 0 Feb-15-17 Mar-02-17A7170 Trade meeting 27 Not Started Feb-23-17 Mar-10-17 0 0 0 Feb-23-17 Mar-10-17A7180 Trade meeting 28 Not Started Mar-03-17 Mar-18-17 0 0 0 Mar-03-17 Mar-18-17A7190 Trade meeting 29 Not Started Mar-11-17 Mar-31-17 0 0 0 Mar-11-17 Mar-31-17A7200 Trade meeting 30 Not Started Mar-20-17 Apr-08-17 0 0 0 Mar-20-17 Apr-08-17A7210 Trade meeting 31 Not Started Apr-01-17 Apr-17-17 0 0 0 Apr-01-17 Apr-17-17A7220 Trade meeting 32 Not Started Apr-10-17 Apr-25-17 0 0 0 Apr-10-17 Apr-25-17A7230 Trade meeting 33 Not Started Apr-18-17 May-03-17 0 0 0 Apr-18-17 May-03-17A7240 Trade meeting 34 Not Started Apr-26-17 May-11-17 0 0 0 Apr-26-17 May-11-17A7250 Trade meeting 35 Not Started May-04-17 May-19-17 0 0 0 May-04-17 May-19-17A7260 Trade meeting 36 Not Started May-12-17 May-29-17 0 0 0 May-12-17 May-29-17A7270 Trade meeting 37 Not Started May-20-17 Jun-06-17 0 0 0 May-20-17 Jun-06-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Consultants meeting 38Consultants meeting 39
Consultants meeting 40Consultants meeting 41
Consultants meeting 42Consultants meeting 43
Trade meeting 1Trade meeting 2
Trade meeting 3Trade meeting 4
Trade meeting 5Trade meeting 6
Trade meeting 7Trade meeting 8
Trade meeting 9Trade meeting 10
Trade meeting 11Trade meeting 12
Trade meeting 13Trade meeting 14
Trade meeting 15Trade meeting 16
Trade meeting 17Trade meeting 18
Trade meeting 19Trade meeting 20
Trade meeting 21Trade meeting 22
Trade meeting 23Trade meeting 24
Trade meeting 25Trade meeting 26
Trade meeting 27Trade meeting 28
Trade meeting 29Trade meeting 30
Trade meeting 31Trade meeting 32
Trade meeting 33Trade meeting 34
Trade meeting 35Trade meeting 36
Trade meeting 37
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A7280 Trade meeting 38 Not Started May-30-17 Jun-14-17 0 0 0 May-30-17 Jun-14-17A7290 Trade meeting 39 Not Started Jun-07-17 Jun-22-17 0 0 0 Jun-07-17 Jun-22-17A7300 Trade meeting 40 Not Started Jun-15-17 Jun-30-17 0 0 0 Jun-15-17 Jun-30-17A7310 Trade meeting 41 Not Started Jun-23-17 Jul-11-17 0 0 0 Jun-23-17 Jul-11-17A7320 Trade meeting 42 Not Started Jul-04-17 Jul-19-17 0 0 0 Jul-04-17 Jul-19-17A7330 Trade meeting 43 Not Started Jul-12-17 Jul-27-17 0 0 0 Jul-12-17 Jul-27-17A7340 Trade meeting 44 Not Started Jul-20-17 Aug-05-17 0 0 0 Jul-20-17 Aug-05-17A7350 Trade meeting 45 Not Started Jul-28-17 Aug-14-17 0 0 0 Jul-28-17 Aug-14-17A7360 Trade meeting 46 Not Started Aug-07-17 Aug-22-17 0 0 0 Aug-07-17 Aug-22-17A7370 Trade meeting 47 Not Started Aug-15-17 Aug-30-17 0 0 0 Aug-15-17 Aug-30-17A7380 Trade meeting 48 Not Started Aug-23-17 Sep-08-17 0 0 0 Aug-23-17 Sep-08-17A7390 Trade meeting 49 Not Started Aug-31-17 Sep-16-17 0 0 0 Aug-31-17 Sep-16-17A7400 Trade meeting 50 Not Started Sep-09-17 Sep-25-17 0 0 0 Sep-09-17 Sep-25-17A7410 Trade meeting 51 Not Started Sep-18-17 Oct-03-17 0 0 0 Sep-18-17 Oct-03-17A7420 Trade meeting 52 Not Started Sep-26-17 Oct-12-17 0 0 0 Sep-26-17 Oct-12-17A7430 Trade meeting 53 Not Started Oct-04-17 Oct-20-17 0 0 0 Oct-04-17 Oct-20-17A7440 Trade meeting 54 Not Started Oct-13-17 Oct-28-17 0 0 0 Oct-13-17 Oct-28-17A7450 Trade meeting 55 Not Started Oct-21-17 Nov-06-17 0 0 0 Oct-21-17 Nov-06-17A7460 Trade meeting 56 Not Started Oct-30-17 Nov-16-17 0 0 0 Oct-30-17 Nov-16-17A7470 Trade meeting 57 Not Started Nov-07-17 Nov-24-17 0 0 0 Nov-07-17 Nov-24-17A7480 Trade meeting 58 Not Started Nov-17-17 Dec-02-17 0 0 0 Nov-17-17 Dec-02-17A7490 Trade meeting 59 Not Started Nov-25-17 Dec-11-17 0 0 0 Nov-25-17 Dec-11-17A7500 Trade meeting 60 Not Started Dec-04-17 Dec-19-17 0 0 0 Dec-04-17 Dec-19-17A7510 Trade meeting 61 Not Started Dec-12-17 Dec-28-17 0 0 0 Dec-12-17 Dec-28-17A7520 Trade meeting 62 Not Started Dec-20-17 Jan-06-18 0 0 0 Dec-20-17 Jan-06-18A7530 Trade meeting 63 Not Started Dec-29-17 Jan-15-18 0 0 0 Dec-29-17 Jan-15-18A7540 Trade meeting 64 Not Started Jan-08-18 Jan-23-18 0 0 0 Jan-08-18 Jan-23-18A7550 Trade meeting 65 Not Started Jan-16-18 Jan-31-18 0 0 0 Jan-16-18 Jan-31-18A7560 Trade meeting 66 Not Started Jan-24-18 Feb-09-18 0 0 0 Jan-24-18 Feb-09-18A7570 Trade meeting 67 Not Started Feb-01-18 Feb-17-18 0 0 0 Feb-01-18 Feb-17-18A7580 Trade meeting 68 Not Started Feb-10-18 Feb-26-18 0 0 0 Feb-10-18 Feb-26-18A7590 Trade meeting 69 Not Started Feb-19-18 Mar-06-18 0 0 0 Feb-19-18 Mar-06-18A7600 Trade meeting 70 Not Started Feb-27-18 Mar-14-18 0 0 0 Feb-27-18 Mar-14-18A7610 Trade meeting 71 Not Started Mar-07-18 Mar-22-18 0 0 0 Mar-07-18 Mar-22-18A7620 Trade meeting 72 Not Started Mar-15-18 Apr-02-18 0 0 0 Mar-15-18 Apr-02-18A7630 Trade meeting 73 Not Started Mar-23-18 Apr-10-18 0 0 0 Mar-23-18 Apr-10-18A7640 Trade meeting 74 Not Started Apr-03-18 Apr-18-18 0 0 0 Apr-03-18 Apr-18-18
Start upStart upStart up Jul-11-16 Jul-11-16 Jul-11-16 296 292 44 Jul-06-17 Jun-29-17A1170 Start-up meeting - Matcon Completed Jul-11-16 Jul-11-16 Jul-11-16 0 0 0 Jul-11-16 Jul-11-16 Jul-11-16A1190 Structural Engineer/Contractor meeting Completed Jul-11-16 Jul-11-16 Jul-12-16 0 0 0 Jul-11-16 Jul-11-16 Jul-12-16A7660 Start-up meeting - G-Form Completed Aug-26-16 Sep-08-16 Aug-17-16 0 0 0 Aug-26-16 Sep-08-16 Aug-17-16A7650 Start-up meeting - MidVally Completed Aug-26-16 Sep-24-16 Sep-01-16 0 0 0 Aug-26-16 Sep-24-16 Sep-01-16A7670 Start-up meeting - Berts Not Started Aug-26-16 Sep-30-16 0 0 0 Aug-26-16 Sep-30-16A7680 Start-up meeting - Trotter and Morton Not Started Sep-12-16 Oct-08-16 0 0 0 Sep-12-16 Oct-08-16A7690 Start-up meeting - Dry wall contractor Not Started Feb-17-17 Feb-13-17 0 0 0 Feb-17-17 Feb-13-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Trade meeting 38Trade meeting 39
Trade meeting 40Trade meeting 41
Trade meeting 42Trade meeting 43
Trade meeting 44Trade meeting 45
Trade meeting 46Trade meeting 47
Trade meeting 48Trade meeting 49
Trade meeting 50Trade meeting 51
Trade meeting 52Trade meeting 53
Trade meeting 54Trade meeting 55
Trade meeting 56Trade meeting 57
Trade meeting 58Trade meeting 59
Trade meeting 60Trade meeting 61
Trade meeting 62Trade meeting 63
Trade meeting 64Trade meeting 65
Trade meeting 66Trade meeting 67
Trade meeting 68Trade meeting 69
Trade meeting 70Trade meeting 71
Trade meeting 72
Jun-29-17, Start up
Start-up meeting - MatconStructural Engineer/Contractor meeting
Start-up meeting - G-FormStart-up meeting - MidVally
Start-up meeting - BertsStart-up meeting - Trotter and Morton
Start-up meeting - Dry wall contractor
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A7700 Start-up meeting - OTIS Not Started Jul-06-17 Jun-29-17 0 0 0 Jul-06-17 Jun-29-17
InspectionsInspectionsInspections Jul-11-16 Jul-11-16 Jul-08-16 440 388 71 Dec-28-17 Oct-25-17Earth workEarth workEarth work Jul-11-16 Jul-11-16 Jul-28-16 53 79 54 Sep-12-16 Oct-13-16AnchorsAnchorsAnchors Jul-19-16 Jul-25-16 Jul-28-16 29 57 54 Aug-23-16 Sep-30-16A1280 Review shoring installation and anchor testing North side row 1 Completed Jul-25-16 Jul-25-16 Jul-28-16 0 0 9 Jul-25-16 Jul-25-16 Aug-09-16A2120 Review shoring installation and anchor testing North side row 2 Completed Aug-02-16 Aug-11-16 Aug-11-16 0 0 7 Aug-02-16 Aug-11-16 Aug-19-16A2160 Review shoring installation and anchor testing South side row 1 Completed Jul-21-16 Aug-11-16 Aug-09-16 0 0 3 Jul-21-16 Aug-11-16 Aug-12-16A2210 Review shoring installation and anchor testing East side row 1 Completed Jul-19-16 Aug-15-16 Aug-19-16 0 0 0 Jul-19-16 Aug-15-16 Aug-19-16A2130 Review shoring installation and anchor testing North side row 3 Completed Aug-09-16 Aug-22-16 Aug-19-16 0 0 2 Aug-09-16 Aug-22-16 Aug-22-16A2170 Review shoring installation and anchor testing South side row 2 Completed Jul-22-16 Aug-22-16 Aug-19-16 0 0 2 Jul-22-16 Aug-22-16 Aug-22-16A2220 Review shoring installation and anchor testing West side row 1 Completed Jul-27-16 Aug-22-16 Aug-19-16 0 0 2 Jul-27-16 Aug-22-16 Aug-22-16A2230 Review shoring installation and anchor testing West side row 2 Completed Jul-28-16 Aug-29-16 Aug-26-16 0 0 1 Jul-28-16 Aug-29-16 Aug-27-16A2190 Review shoring installation and anchor testing South side row 4 - Cancelled Completed Jul-23-16 Aug-30-16 Aug-25-16 0 0 0 Jul-23-16 Aug-30-16 Aug-25-16A2140 Review shoring installation and anchor testing North side row 4 In Progress Aug-16-16 Sep-05-16 Aug-26-16 0 0 30 Aug-16-16 Sep-05-16A2180 Review shoring installation and anchor testing South side row 3 In Progress Jul-23-16 Sep-05-16 Aug-26-16 0 0 30 Jul-23-16 Sep-05-16A2150 Review shoring installation and anchor testing North side row 5 Not Started Aug-23-16 Sep-30-16 0 0 0 Aug-23-16 Sep-30-16A2240 Review shoring installation and anchor testing West side row 3 Not Started Jul-29-16 Sep-30-16 0 0 0 Jul-29-16 Sep-30-16A2250 Review shoring installation and anchor testing East side row 3 Not Started Aug-11-16 Sep-30-16 0 0 0 Aug-11-16 Sep-30-16A4530 Review shoring installation and anchor testing East side row 2 Not Started Jul-28-16 Sep-30-16 0 0 0 Jul-28-16 Sep-30-16
Excavation slopesExcavation slopesExcavation slopes Jul-11-16 Jul-11-16 Jul-29-16 37 69 23 Aug-24-16 Sep-30-16A1260 Review of stripping depth Completed Jul-11-16 Jul-11-16 Aug-14-16 0 0 0 Jul-11-16 Jul-11-16 Aug-14-16A1270 Review temporary cut slopes P1 Completed Aug-02-16 Aug-02-16 Jul-29-16 0 0 0 Aug-02-16 Aug-02-16 Jul-29-16A2100 Review temporary cut slopes P2 Completed Aug-16-16 Sep-06-16 Aug-26-16 0 0 0 Aug-16-16 Sep-06-16 Aug-26-16A2110 Review temporary cut slopes P3 Not Started Aug-24-16 Sep-30-16 0 0 0 Aug-24-16 Sep-30-16
BackfillBackfillBackfill Sep-09-16 Oct-13-16 2 0 0 Sep-12-16 Oct-13-16A6230 Review of foundation subgrade Not Started Sep-12-16 Oct-13-16 0 0 0 Sep-12-16 Oct-13-16A6280 Review of fill materials and compaction Not Started Sep-09-16 Oct-13-16 0 0 0 Sep-09-16 Oct-13-16A6290 Review of subgrade and underslab fill materials and compaction Not Started Sep-09-16 Oct-13-16 0 0 0 Sep-09-16 Oct-13-16A6300 Review of backfill materials and placement against foundation walls Not Started Sep-09-16 Oct-13-16 0 0 0 Sep-09-16 Oct-13-16
CivilCivilCivil Jul-11-16 Jul-11-16 Jul-08-16 132 153 41 Dec-15-16 Jan-11-17A1160 Sedimentation and erosion 1st inspection Completed Jul-11-16 Jul-11-16 Jul-08-16 0 0 2 Jul-11-16 Jul-11-16 Jul-11-16A1290 Sedimentation and erosion 2nd inspection Completed Jul-25-16 Jul-25-16 Jul-25-16 0 0 4 Jul-25-16 Jul-25-16 Jul-29-16A1310 Sedimentation and erosion 3rd inspection Completed Aug-09-16 Aug-13-16 Aug-11-16 0 0 1 Aug-09-16 Aug-13-16 Aug-12-16A6480 Sedimentation and erosion 4th inspection Completed Aug-23-16 Aug-26-16 Aug-24-16 0 0 2 Aug-23-16 Aug-26-16 Aug-26-16A6470 Sedimentation and erosion 5th inspection Not Started Sep-06-16 Sep-30-16 0 0 0 Sep-06-16 Sep-30-16A6460 Sedimentation and erosion 6th inspection Not Started Sep-20-16 Oct-15-16 0 0 0 Sep-20-16 Oct-15-16A6450 Sedimentation and erosion 7th inspection Not Started Oct-04-16 Oct-29-16 0 0 0 Oct-04-16 Oct-29-16A6440 Sedimentation and erosion 8th inspection Not Started Oct-19-16 Nov-14-16 0 0 0 Oct-19-16 Nov-14-16A6430 Sedimentation and erosion 9th inspection Not Started Nov-02-16 Nov-28-16 0 0 0 Nov-02-16 Nov-28-16A6410 Sedimentation and erosion 10th inspection Not Started Nov-17-16 Dec-12-16 0 0 0 Nov-17-16 Dec-12-16A6420 Sedimentation and erosion 11th inspection Not Started Dec-01-16 Dec-27-16 0 0 0 Dec-01-16 Dec-27-16A6400 Sedimentation and erosion 12th inspection Not Started Dec-15-16 Jan-11-17 0 0 0 Dec-15-16 Jan-11-17
FormworkFormworkFormwork Sep-19-16 Sep-30-16 237 223 0 Jul-06-17 Jun-29-17FoundationsFoundationsFoundations Sep-19-16 Sep-30-16 0 0 0 Sep-19-16 Sep-30-16A7810 Form inspection Not Started Sep-19-16 Sep-30-16 0 0 0 Sep-19-16 Sep-30-16
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Start-up meeting - OTISOct-25-17, Inspections
Oct-13-16, Earth workSep-30-16, Anchors
Review shoring installation and anchor testing North side row 1Review shoring installation and anchor testing North side row 2
Review shoring installation and anchor testing South side row 1Review shoring installation and anchor testing East side row 1Review shoring installation and anchor testing North side row 3Review shoring installation and anchor testing South side row 2Review shoring installation and anchor testing West side row 1Review shoring installation and anchor testing West side row 2Review shoring installation and anchor testing South side row 4 - Cancelled
Review shoring installation and anchor testing North side row 4Review shoring installation and anchor testing South side row 3Review shoring installation and anchor testing North side row 5Review shoring installation and anchor testing West side row 3Review shoring installation and anchor testing East side row 3Review shoring installation and anchor testing East side row 2Sep-30-16, Excavation slopes
Review of stripping depthReview temporary cut slopes P1
Review temporary cut slopes P2Review temporary cut slopes P3
Oct-13-16, Backfill
Review of foundation subgradeReview of fill materials and compactionReview of subgrade and underslab fill materials and compactionReview of backfill materials and placement against foundation walls
Jan-11-17, Civil
Sedimentation and erosion 1st inspectionSedimentation and erosion 2nd inspection
Sedimentation and erosion 3rd inspectionSedimentation and erosion 4th inspection
Sedimentation and erosion 5th inspectionSedimentation and erosion 6th inspection
Sedimentation and erosion 7th inspectionSedimentation and erosion 8th inspection
Sedimentation and erosion 9th inspectionSedimentation and erosion 10th inspection
Sedimentation and erosion 11th inspectionSedimentation and erosion 12th inspection
Jun-29-17, FormworkSep-30-16, Foundations
Form inspection
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
P3P3P3 Oct-17-16 Oct-12-16 28 28 0 Nov-19-16 Nov-15-16A7820 Form inspection Not Started Oct-17-16 Oct-12-16 0 0 0 Oct-17-16 Oct-12-16A7830 Falsework inspection Not Started Nov-19-16 Nov-15-16 0 0 0 Nov-19-16 Nov-15-16
P2P2P2 Dec-08-16 Dec-03-16 13 13 0 Dec-23-16 Dec-19-16A7840 Form inspection Not Started Dec-08-16 Dec-03-16 0 0 0 Dec-08-16 Dec-03-16A7850 Falsework inspection Not Started Dec-23-16 Dec-19-16 0 0 0 Dec-23-16 Dec-19-16
P1P1P1 Jan-05-17 Dec-30-16 12 12 0 Jan-19-17 Jan-14-17A7860 Form inspection Not Started Jan-05-17 Dec-30-16 0 0 0 Jan-05-17 Dec-30-16A7870 Falsework inspection Not Started Jan-19-17 Jan-14-17 0 0 0 Jan-19-17 Jan-14-17
L1L1L1 Feb-07-17 Feb-02-17 8 8 0 Feb-17-17 Feb-13-17A7880 Form inspection Not Started Feb-07-17 Feb-02-17 0 0 0 Feb-07-17 Feb-02-17A7890 Falsework inspection Not Started Feb-17-17 Feb-13-17 0 0 0 Feb-17-17 Feb-13-17
Town house 1Town house 1Town house 1 Mar-03-17 Feb-27-17 7 7 0 Mar-11-17 Mar-07-17A7900 Form inspection Not Started Mar-03-17 Feb-27-17 0 0 0 Mar-03-17 Feb-27-17A7910 Falsework inspection Not Started Mar-11-17 Mar-07-17 0 0 0 Mar-11-17 Mar-07-17
Town house 2Town house 2Town house 2 Mar-03-17 Feb-27-17 7 7 0 Mar-11-17 Mar-07-17A7920 Form inspection Not Started Mar-03-17 Feb-27-17 0 0 0 Mar-03-17 Feb-27-17A7930 Falsework inspection Not Started Mar-11-17 Mar-07-17 0 0 0 Mar-11-17 Mar-07-17
L2L2L2 Mar-06-17 Mar-01-17 9 9 0 Mar-16-17 Mar-11-17A7940 Form inspection Not Started Mar-06-17 Mar-01-17 0 0 0 Mar-06-17 Mar-01-17A7950 Falsework inspection Not Started Mar-16-17 Mar-11-17 0 0 0 Mar-16-17 Mar-11-17
L3L3L3 Mar-31-17 Mar-22-17 6 6 0 Apr-07-17 Apr-03-17A7960 Form inspection Not Started Mar-31-17 Mar-22-17 0 0 0 Mar-31-17 Mar-22-17A7970 Falsework inspection Not Started Apr-07-17 Apr-03-17 0 0 0 Apr-07-17 Apr-03-17
L4L4L4 Apr-11-17 Apr-06-17 2 2 0 Apr-13-17 Apr-08-17A7980 Form inspection Not Started Apr-11-17 Apr-06-17 0 0 0 Apr-11-17 Apr-06-17A7990 Falsework inspection Not Started Apr-13-17 Apr-08-17 0 0 0 Apr-13-17 Apr-08-17
L5L5L5 Apr-15-17 Apr-11-17 2 2 0 Apr-18-17 Apr-13-17A8000 Form inspection Not Started Apr-15-17 Apr-11-17 0 0 0 Apr-15-17 Apr-11-17A8010 Falsework inspection Not Started Apr-18-17 Apr-13-17 0 0 0 Apr-18-17 Apr-13-17
L6L6L6 Apr-20-17 Apr-15-17 2 2 0 Apr-22-17 Apr-18-17A8020 Form inspection Not Started Apr-20-17 Apr-15-17 0 0 0 Apr-20-17 Apr-15-17A8030 Falsework inspection Not Started Apr-22-17 Apr-18-17 0 0 0 Apr-22-17 Apr-18-17
L7L7L7 Apr-25-17 Apr-20-17 2 2 0 Apr-27-17 Apr-22-17A8040 Form inspection Not Started Apr-25-17 Apr-20-17 0 0 0 Apr-25-17 Apr-20-17A8050 Falsework inspection Not Started Apr-27-17 Apr-22-17 0 0 0 Apr-27-17 Apr-22-17
L8L8L8 Apr-29-17 Apr-25-17 2 2 0 May-02-17 Apr-27-17A8060 Form inspection Not Started Apr-29-17 Apr-25-17 0 0 0 Apr-29-17 Apr-25-17A8070 Falsework inspection Not Started May-02-17 Apr-27-17 0 0 0 May-02-17 Apr-27-17
L9L9L9 May-04-17 Apr-29-17 2 2 0 May-06-17 May-02-17A8080 Form inspection Not Started May-04-17 Apr-29-17 0 0 0 May-04-17 Apr-29-17A8090 Falsework inspection Not Started May-06-17 May-02-17 0 0 0 May-06-17 May-02-17
L10L10L10 May-09-17 May-04-17 2 2 0 May-11-17 May-06-17A8100 Form inspection Not Started May-09-17 May-04-17 0 0 0 May-09-17 May-04-17A8110 Falsework inspection Not Started May-11-17 May-06-17 0 0 0 May-11-17 May-06-17
L11L11L11 May-13-17 May-09-17 2 2 0 May-16-17 May-11-17A8120 Form inspection Not Started May-13-17 May-09-17 0 0 0 May-13-17 May-09-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Nov-15-16, P3
Form inspectionFalsework inspection
Dec-19-16, P2
Form inspectionFalsework inspection
Jan-14-17, P1
Form inspectionFalsework inspection
Feb-13-17, L1
Form inspectionFalsework inspection
Mar-07-17, Town hous e 1
Form inspectionFalsework inspectionMar-07-17, Town hous e 2
Form inspectionFalsework inspectionMar-11-17, L2
Form inspectionFalsework inspection
Apr-03-17, L3
Form inspectionFalsework inspectionApr-08-17, L4
Form inspectionFalsework inspectionApr-13-17, L5
Form inspectionFalsework inspectionApr-18-17, L6
Form inspectionFalsework inspectionApr-22-17, L7
Form inspectionFalsework inspectionApr-27-17, L8
Form inspectionFalsework inspectionMay-02-17, L9
Form inspectionFalsework inspectionMay-06-17, L10
Form inspectionFalsework inspectionMay-11-17, L11
Form inspection
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A8130 Falsework inspection Not Started May-16-17 May-11-17 0 0 0 May-16-17 May-11-17L12L12L12 May-18-17 May-13-17 2 2 0 May-20-17 May-16-17A8140 Form inspection Not Started May-18-17 May-13-17 0 0 0 May-18-17 May-13-17A8150 Falsework inspection Not Started May-20-17 May-16-17 0 0 0 May-20-17 May-16-17
L14L14L14 May-24-17 May-18-17 2 2 0 May-26-17 May-20-17A8160 Form inspection Not Started May-24-17 May-18-17 0 0 0 May-24-17 May-18-17A8170 Falsework inspection Not Started May-26-17 May-20-17 0 0 0 May-26-17 May-20-17
L15L15L15 May-29-17 May-24-17 3 3 0 Jun-01-17 May-27-17A8180 Form inspection Not Started May-29-17 May-24-17 0 0 0 May-29-17 May-24-17A8190 Falsework inspection Not Started Jun-01-17 May-27-17 0 0 0 Jun-01-17 May-27-17
L16L16L16 Jun-03-17 May-30-17 2 2 0 Jun-06-17 Jun-01-17A8200 Form inspection Not Started Jun-03-17 May-30-17 0 0 0 Jun-03-17 May-30-17A8210 Falsework inspection Not Started Jun-06-17 Jun-01-17 0 0 0 Jun-06-17 Jun-01-17
L17L17L17 Jun-08-17 Jun-03-17 2 2 0 Jun-10-17 Jun-06-17A8220 Form inspection Not Started Jun-08-17 Jun-03-17 0 0 0 Jun-08-17 Jun-03-17A8230 Falsework inspection Not Started Jun-10-17 Jun-06-17 0 0 0 Jun-10-17 Jun-06-17
L18L18L18 Jun-13-17 Jun-08-17 2 2 0 Jun-15-17 Jun-10-17A8240 Form inspection Not Started Jun-13-17 Jun-08-17 0 0 0 Jun-13-17 Jun-08-17A8250 Falsework inspection Not Started Jun-15-17 Jun-10-17 0 0 0 Jun-15-17 Jun-10-17
L19L19L19 Jun-17-17 Jun-13-17 2 2 0 Jun-20-17 Jun-15-17A8260 Form inspection Not Started Jun-17-17 Jun-13-17 0 0 0 Jun-17-17 Jun-13-17A8270 Falsework inspection Not Started Jun-20-17 Jun-15-17 0 0 0 Jun-20-17 Jun-15-17
L20L20L20 Jun-22-17 Jun-17-17 2 2 0 Jun-24-17 Jun-20-17A8280 Form inspection Not Started Jun-22-17 Jun-17-17 0 0 0 Jun-22-17 Jun-17-17A8290 Falsework inspection Not Started Jun-24-17 Jun-20-17 0 0 0 Jun-24-17 Jun-20-17
L21L21L21 Jun-27-17 Jun-22-17 2 2 0 Jun-29-17 Jun-24-17A8300 Form inspection Not Started Jun-27-17 Jun-22-17 0 0 0 Jun-27-17 Jun-22-17A8310 Falsework inspection Not Started Jun-29-17 Jun-24-17 0 0 0 Jun-29-17 Jun-24-17
RoofRoofRoof Jul-04-17 Jun-27-17 2 2 0 Jul-06-17 Jun-29-17A8320 Form inspection Not Started Jul-04-17 Jun-27-17 0 0 0 Jul-04-17 Jun-27-17A8330 Falsework inspection Not Started Jul-06-17 Jun-29-17 0 0 0 Jul-06-17 Jun-29-17
ReinforcementReinforcementReinforcement Sep-21-16 Sep-30-16 237 225 0 Jul-08-17 Jul-04-17FoundationsFoundationsFoundations Sep-21-16 Sep-30-16 0 0 0 Sep-21-16 Sep-30-16A8340 Reinforcement Not Started Sep-21-16 Sep-30-16 0 0 0 Sep-21-16 Sep-30-16
P3P3P3 Oct-28-16 Oct-24-16 24 24 0 Nov-26-16 Nov-22-16A8370 Vertical Reinforcement Not Started Oct-28-16 Oct-24-16 0 0 0 Oct-28-16 Oct-24-16A8360 Bottom Reinforcement Not Started Nov-22-16 Nov-17-16 0 0 0 Nov-22-16 Nov-17-16A8350 Top Reinforcement Not Started Nov-26-16 Nov-22-16 0 0 0 Nov-26-16 Nov-22-16
P2P2P2 Dec-15-16 Dec-10-16 10 10 0 Dec-28-16 Dec-22-16A8400 Vertical Reinforcement Not Started Dec-15-16 Dec-10-16 0 0 0 Dec-15-16 Dec-10-16A8390 Bottom Reinforcement Not Started Dec-24-16 Dec-20-16 0 0 0 Dec-24-16 Dec-20-16A8380 Top Reinforcement Not Started Dec-28-16 Dec-22-16 0 0 0 Dec-28-16 Dec-22-16
P1P1P1 Jan-07-17 Jan-03-17 16 16 0 Jan-26-17 Jan-21-17A8430 Vertical Reinforcement Not Started Jan-07-17 Jan-03-17 0 0 0 Jan-07-17 Jan-03-17A8420 Bottom Reinforcement Not Started Jan-21-17 Jan-17-17 0 0 0 Jan-21-17 Jan-17-17A8410 Top Reinforcement Not Started Jan-26-17 Jan-21-17 0 0 0 Jan-26-17 Jan-21-17
L1L1L1 Feb-10-17 Feb-04-17 12 12 0 Feb-24-17 Feb-20-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Falsework inspectionMay-16-17, L12
Form inspectionFalsework inspectionMay-20-17, L14
Form inspectionFalsework inspectionMay-27-17, L15
Form inspectionFalsework inspectionJun-01-17, L16
Form inspectionFalsework inspectionJun-06-17, L17
Form inspectionFalsework inspectionJun-10-17, L18
Form inspectionFalsework inspectionJun-15-17, L19
Form inspectionFalsework inspectionJun-20-17, L20
Form inspectionFalsework inspectionJun-24-17, L21
Form inspectionFalsework inspectionJun-29-17, Roof
Form inspectionFalsework inspectionJul-04-17, Reinforcement
Sep-30-16, Foundations
ReinforcementNov-22-16, P3
Vertical ReinforcementBottom ReinforcementTop Reinforcement
Dec-22-16, P2
Vertical ReinforcementBottom ReinforcementTop Reinforcement
Jan-21-17, P1
Vertical ReinforcementBottom ReinforcementTop Reinforcement
Feb-20-17, L1
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A8460 Vertical Reinforcement Not Started Feb-10-17 Feb-04-17 0 0 0 Feb-10-17 Feb-04-17A8450 Bottom Reinforcement Not Started Feb-20-17 Feb-15-17 0 0 0 Feb-20-17 Feb-15-17A8440 Top Reinforcement Not Started Feb-24-17 Feb-20-17 0 0 0 Feb-24-17 Feb-20-17
Town house 1Town house 1Town house 1 Mar-06-17 Mar-01-17 8 8 0 Mar-15-17 Mar-10-17A8490 Vertical Reinforcement Not Started Mar-06-17 Mar-01-17 0 0 0 Mar-06-17 Mar-01-17A8480 Bottom Reinforcement Not Started Mar-13-17 Mar-08-17 0 0 0 Mar-13-17 Mar-08-17A8470 Top Reinforcement Not Started Mar-15-17 Mar-10-17 0 0 0 Mar-15-17 Mar-10-17
Town house 2Town house 2Town house 2 Mar-06-17 Mar-01-17 8 8 0 Mar-15-17 Mar-10-17A8520 Vertical Reinforcement Not Started Mar-06-17 Mar-01-17 0 0 0 Mar-06-17 Mar-01-17A8510 Bottom Reinforcement Not Started Mar-13-17 Mar-08-17 0 0 0 Mar-13-17 Mar-08-17A8500 Top Reinforcement Not Started Mar-15-17 Mar-10-17 0 0 0 Mar-15-17 Mar-10-17
L2L2L2 Mar-09-17 Mar-04-17 12 12 0 Mar-24-17 Mar-18-17A8550 Vertical Reinforcement Not Started Mar-09-17 Mar-04-17 0 0 0 Mar-09-17 Mar-04-17A8540 Bottom Reinforcement Not Started Mar-18-17 Mar-14-17 0 0 0 Mar-18-17 Mar-14-17A8530 Top Reinforcement Not Started Mar-24-17 Mar-18-17 0 0 0 Mar-24-17 Mar-18-17
L3L3L3 Apr-04-17 Mar-30-17 5 5 0 Apr-10-17 Apr-05-17A8580 Vertical Reinforcement Not Started Apr-04-17 Mar-30-17 0 0 0 Apr-04-17 Mar-30-17A8570 Bottom Reinforcement Not Started Apr-07-17 Apr-03-17 0 0 0 Apr-07-17 Apr-03-17A8560 Top Reinforcement Not Started Apr-10-17 Apr-05-17 0 0 0 Apr-10-17 Apr-05-17
L4L4L4 Apr-12-17 Apr-07-17 3 3 0 Apr-15-17 Apr-11-17A8610 Vertical Reinforcement Not Started Apr-12-17 Apr-07-17 0 0 0 Apr-12-17 Apr-07-17A8600 Bottom Reinforcement Not Started Apr-13-17 Apr-08-17 0 0 0 Apr-13-17 Apr-08-17A8590 Top Reinforcement Not Started Apr-15-17 Apr-11-17 0 0 0 Apr-15-17 Apr-11-17
L5L5L5 Apr-14-17 Apr-10-17 5 5 0 Apr-20-17 Apr-15-17A8640 Vertical Reinforcement Not Started Apr-14-17 Apr-10-17 0 0 0 Apr-14-17 Apr-10-17A8630 Bottom Reinforcement Not Started Apr-18-17 Apr-13-17 0 0 0 Apr-18-17 Apr-13-17A8620 Top Reinforcement Not Started Apr-20-17 Apr-15-17 0 0 0 Apr-20-17 Apr-15-17
L6L6L6 Apr-21-17 Apr-17-17 3 3 0 Apr-25-17 Apr-20-17A8670 Vertical Reinforcement Not Started Apr-21-17 Apr-17-17 0 0 0 Apr-21-17 Apr-17-17A8660 Bottom Reinforcement Not Started Apr-22-17 Apr-18-17 0 0 0 Apr-22-17 Apr-18-17A8650 Top Reinforcement Not Started Apr-25-17 Apr-20-17 0 0 0 Apr-25-17 Apr-20-17
L7L7L7 Apr-26-17 Apr-21-17 3 3 0 Apr-29-17 Apr-25-17A8700 Vertical Reinforcement Not Started Apr-26-17 Apr-21-17 0 0 0 Apr-26-17 Apr-21-17A8690 Bottom Reinforcement Not Started Apr-27-17 Apr-22-17 0 0 0 Apr-27-17 Apr-22-17A8680 Top Reinforcement Not Started Apr-29-17 Apr-25-17 0 0 0 Apr-29-17 Apr-25-17
L8L8L8 May-01-17 Apr-26-17 3 3 0 May-04-17 Apr-29-17A8730 Vertical Reinforcement Not Started May-01-17 Apr-26-17 0 0 0 May-01-17 Apr-26-17A8720 Bottom Reinforcement Not Started May-02-17 Apr-27-17 0 0 0 May-02-17 Apr-27-17A8710 Top Reinforcement Not Started May-04-17 Apr-29-17 0 0 0 May-04-17 Apr-29-17
L9L9L9 May-05-17 May-01-17 3 3 0 May-09-17 May-04-17A8760 Vertical Reinforcement Not Started May-05-17 May-01-17 0 0 0 May-05-17 May-01-17A8750 Bottom Reinforcement Not Started May-06-17 May-02-17 0 0 0 May-06-17 May-02-17A8740 Top Reinforcement Not Started May-09-17 May-04-17 0 0 0 May-09-17 May-04-17
L10L10L10 May-10-17 May-05-17 3 3 0 May-13-17 May-09-17A8790 Vertical Reinforcement Not Started May-10-17 May-05-17 0 0 0 May-10-17 May-05-17A8780 Bottom Reinforcement Not Started May-11-17 May-06-17 0 0 0 May-11-17 May-06-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Vertical ReinforcementBottom ReinforcementTop Reinforcement
Mar-10-17, Town hous e 1
Vertical ReinforcementBottom ReinforcementTop Reinforcement
Mar-10-17, Town hous e 2
Vertical ReinforcementBottom ReinforcementTop ReinforcementMar-18-17, L2
Vertical ReinforcementBottom ReinforcementTop Reinforcement
Apr-05-17, L3
Vertical ReinforcementBottom ReinforcementTop ReinforcementApr-11-17, L4
Vertical ReinforcementBottom ReinforcementTop ReinforcementApr-15-17, L5
Vertical ReinforcementBottom ReinforcementTop ReinforcementApr-20-17, L6
Vertical ReinforcementBottom ReinforcementTop ReinforcementApr-25-17, L7
Vertical ReinforcementBottom ReinforcementTop ReinforcementApr-29-17, L8
Vertical ReinforcementBottom ReinforcementTop ReinforcementMay-04-17, L9
Vertical ReinforcementBottom ReinforcementTop ReinforcementMay-09-17, L10
Vertical ReinforcementBottom Reinforcement
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A8770 Top Reinforcement Not Started May-13-17 May-09-17 0 0 0 May-13-17 May-09-17L11L11L11 May-15-17 May-10-17 3 3 0 May-18-17 May-13-17A8820 Vertical Reinforcement Not Started May-15-17 May-10-17 0 0 0 May-15-17 May-10-17A8810 Bottom Reinforcement Not Started May-16-17 May-11-17 0 0 0 May-16-17 May-11-17A8800 Top Reinforcement Not Started May-18-17 May-13-17 0 0 0 May-18-17 May-13-17
L12L12L12 May-19-17 May-15-17 3 3 0 May-24-17 May-18-17A8850 Vertical Reinforcement Not Started May-19-17 May-15-17 0 0 0 May-19-17 May-15-17A8840 Bottom Reinforcement Not Started May-20-17 May-16-17 0 0 0 May-20-17 May-16-17A8830 Top Reinforcement Not Started May-24-17 May-18-17 0 0 0 May-24-17 May-18-17
L14L14L14 May-25-17 May-19-17 3 3 0 May-29-17 May-24-17A8880 Vertical Reinforcement Not Started May-25-17 May-19-17 0 0 0 May-25-17 May-19-17A8870 Bottom Reinforcement Not Started May-26-17 May-20-17 0 0 0 May-26-17 May-20-17A8860 Top Reinforcement Not Started May-29-17 May-24-17 0 0 0 May-29-17 May-24-17
L15L15L15 May-31-17 May-26-17 3 3 0 Jun-03-17 May-30-17A8910 Vertical Reinforcement Not Started May-31-17 May-26-17 0 0 0 May-31-17 May-26-17A8900 Bottom Reinforcement Not Started Jun-01-17 May-27-17 0 0 0 Jun-01-17 May-27-17A8890 Top Reinforcement Not Started Jun-03-17 May-30-17 0 0 0 Jun-03-17 May-30-17
L16L16L16 Jun-05-17 May-31-17 3 3 0 Jun-08-17 Jun-03-17A8940 Vertical Reinforcement Not Started Jun-05-17 May-31-17 0 0 0 Jun-05-17 May-31-17A8930 Bottom Reinforcement Not Started Jun-06-17 Jun-01-17 0 0 0 Jun-06-17 Jun-01-17A8920 Top Reinforcement Not Started Jun-08-17 Jun-03-17 0 0 0 Jun-08-17 Jun-03-17
L17L17L17 Jun-09-17 Jun-05-17 3 3 0 Jun-13-17 Jun-08-17A8970 Vertical Reinforcement Not Started Jun-09-17 Jun-05-17 0 0 0 Jun-09-17 Jun-05-17A8960 Bottom Reinforcement Not Started Jun-10-17 Jun-06-17 0 0 0 Jun-10-17 Jun-06-17A8950 Top Reinforcement Not Started Jun-13-17 Jun-08-17 0 0 0 Jun-13-17 Jun-08-17
L18L18L18 Jun-14-17 Jun-09-17 3 3 0 Jun-17-17 Jun-13-17A9000 Vertical Reinforcement Not Started Jun-14-17 Jun-09-17 0 0 0 Jun-14-17 Jun-09-17A8990 Bottom Reinforcement Not Started Jun-15-17 Jun-10-17 0 0 0 Jun-15-17 Jun-10-17A8980 Top Reinforcement Not Started Jun-17-17 Jun-13-17 0 0 0 Jun-17-17 Jun-13-17
L19L19L19 Jun-19-17 Jun-14-17 3 3 0 Jun-22-17 Jun-17-17A9030 Vertical Reinforcement Not Started Jun-19-17 Jun-14-17 0 0 0 Jun-19-17 Jun-14-17A9020 Bottom Reinforcement Not Started Jun-20-17 Jun-15-17 0 0 0 Jun-20-17 Jun-15-17A9010 Top Reinforcement Not Started Jun-22-17 Jun-17-17 0 0 0 Jun-22-17 Jun-17-17
L20L20L20 Jun-23-17 Jun-19-17 3 3 0 Jun-27-17 Jun-22-17A9060 Vertical Reinforcement Not Started Jun-23-17 Jun-19-17 0 0 0 Jun-23-17 Jun-19-17A9050 Bottom Reinforcement Not Started Jun-24-17 Jun-20-17 0 0 0 Jun-24-17 Jun-20-17A9040 Top Reinforcement Not Started Jun-27-17 Jun-22-17 0 0 0 Jun-27-17 Jun-22-17
L21L21L21 Jun-28-17 Jun-23-17 3 3 0 Jul-04-17 Jun-27-17A9090 Vertical Reinforcement Not Started Jun-28-17 Jun-23-17 0 0 0 Jun-28-17 Jun-23-17A9080 Bottom Reinforcement Not Started Jun-29-17 Jun-24-17 0 0 0 Jun-29-17 Jun-24-17A9070 Top Reinforcement Not Started Jul-04-17 Jun-27-17 0 0 0 Jul-04-17 Jun-27-17
RoofRoofRoof Jul-05-17 Jun-28-17 3 3 0 Jul-08-17 Jul-04-17A9120 Vertical Reinforcement Not Started Jul-05-17 Jun-28-17 0 0 0 Jul-05-17 Jun-28-17A9100 Top Reinforcement Not Started Jul-08-17 Jul-04-17 0 0 0 Jul-08-17 Jul-04-17A9110 Bottom Reinforcement Not Started Jul-08-17 Jul-04-17 0 0 0 Jul-08-17 Jul-04-17
ElectricElectricElectric Mar-31-17 Mar-22-17 85 85 0 Jul-11-17 Jul-06-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Top ReinforcementMay-13-17, L11
Vertical ReinforcementBottom ReinforcementTop ReinforcementMay-18-17, L12
Vertical ReinforcementBottom ReinforcementTop ReinforcementMay-24-17, L14
Vertical ReinforcementBottom ReinforcementTop ReinforcementMay-30-17, L15
Vertical ReinforcementBottom ReinforcementTop ReinforcementJun-03-17, L16
Vertical ReinforcementBottom ReinforcementTop ReinforcementJun-08-17, L17
Vertical ReinforcementBottom ReinforcementTop ReinforcementJun-13-17, L18
Vertical ReinforcementBottom ReinforcementTop ReinforcementJun-17-17, L19
Vertical ReinforcementBottom ReinforcementTop ReinforcementJun-22-17, L20
Vertical ReinforcementBottom ReinforcementTop ReinforcementJun-27-17, L21
Vertical ReinforcementBottom ReinforcementTop ReinforcementJul-04-17, Roof
Vertical ReinforcementTop ReinforcementBottom ReinforcementJul-06-17, Electric
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A12740 Generator Not Started Mar-31-17 Mar-22-17 5 5 0 Apr-05-17 Mar-31-17A12730 Commissioning Not Started Jul-06-17 Jun-29-17 5 5 0 Jul-11-17 Jul-06-17
MechanicalMechanicalMechanical Jul-17-17 Jul-12-17 21 21 0 Aug-10-17 Aug-05-17A12770 Commissioning - HVAC Not Started Jul-17-17 Jul-12-17 5 5 0 Jul-21-17 Jul-17-17A12750 Commissioning - Plumbing Not Started Jul-18-17 Jul-13-17 5 5 0 Jul-22-17 Jul-18-17A12760 Commissioning - Elevators Not Started Aug-05-17 Jul-31-17 5 5 0 Aug-10-17 Aug-05-17
CityCityCity Oct-30-17 Oct-25-17 0 0 0 Oct-30-17 Oct-25-17A12050 Occupancy Not Started Oct-30-17 Oct-25-17 0 0 0 Oct-30-17 Oct-25-17
HydroHydroHydro Dec-28-17 Aug-23-17 0 0 0 Dec-28-17 Aug-23-17A12040 Services connections Not Started Dec-28-17 Aug-23-17 0 0 0 Dec-28-17 Aug-23-17
MaterialsMaterialsMaterials Sep-14-16 Sep-30-16 242 224 0 Jul-06-17 Jun-29-17Concrete OrdersConcrete OrdersConcrete Orders Sep-14-16 Sep-30-16 242 224 0 Jul-06-17 Jun-29-17FoundationsFoundationsFoundations Sep-14-16 Sep-30-16 12 16 0 Sep-27-16 Oct-19-16A12060 Concrete order for Crane base Not Started Sep-14-16 Sep-30-16 1 1 0 Sep-14-16 Sep-30-16A12150 Concrete order for Core raft Not Started Sep-27-16 Sep-30-16 1 1 0 Sep-27-16 Sep-30-16A12170 Concrete order for isolated footing Not Started Sep-19-16 Sep-30-16 1 1 0 Sep-19-16 Sep-30-16A12160 Concrete order for strip footing Not Started Sep-16-16 Oct-19-16 1 1 0 Sep-16-16 Oct-19-16
P3P3P3 Oct-05-16 Sep-30-16 38 38 0 Nov-19-16 Nov-15-16A12080 Concrete order for Verticals Not Started Oct-05-16 Sep-30-16 1 1 0 Oct-05-16 Sep-30-16A12620 Concrete order for S.O.G Not Started Nov-09-16 Nov-04-16 4 4 0 Nov-14-16 Nov-08-16A12070 Concrete order for Slab Not Started Nov-19-16 Nov-15-16 1 1 0 Nov-19-16 Nov-15-16
P2P2P2 Dec-08-16 Dec-03-16 14 14 0 Dec-23-16 Dec-19-16A12100 Concrete order for Verticals Not Started Dec-08-16 Dec-03-16 1 1 0 Dec-08-16 Dec-03-16A12090 Concrete order for Slab Not Started Dec-23-16 Dec-19-16 1 1 0 Dec-23-16 Dec-19-16
P1P1P1 Jan-05-17 Dec-30-16 13 13 0 Jan-19-17 Jan-14-17A12120 Concrete order for Verticals Not Started Jan-05-17 Dec-30-16 1 1 0 Jan-05-17 Dec-30-16A12110 Concrete order for Slab Not Started Jan-19-17 Jan-14-17 1 1 0 Jan-19-17 Jan-14-17
L1L1L1 Feb-07-17 Feb-02-17 9 9 0 Feb-17-17 Feb-13-17A12140 Concrete order for Verticals Not Started Feb-07-17 Feb-02-17 1 1 0 Feb-07-17 Feb-02-17A12130 Concrete order for Slab Not Started Feb-17-17 Feb-13-17 1 1 0 Feb-17-17 Feb-13-17
Town house 1Town house 1Town house 1 Mar-03-17 Feb-27-17 8 8 0 Mar-11-17 Mar-07-17A12190 Concrete order for Verticals Not Started Mar-03-17 Feb-27-17 1 1 0 Mar-03-17 Feb-27-17A12180 Concrete order for Slab Not Started Mar-11-17 Mar-07-17 1 1 0 Mar-11-17 Mar-07-17
Town house 2Town house 2Town house 2 Mar-03-17 Feb-27-17 8 8 0 Mar-11-17 Mar-07-17A12210 Concrete order for Verticals Not Started Mar-03-17 Feb-27-17 1 1 0 Mar-03-17 Feb-27-17A12200 Concrete order for Slab Not Started Mar-11-17 Mar-07-17 1 1 0 Mar-11-17 Mar-07-17
L2L2L2 Mar-06-17 Mar-01-17 10 10 0 Mar-16-17 Mar-11-17A12230 Concrete order for Verticals Not Started Mar-06-17 Mar-01-17 1 1 0 Mar-06-17 Mar-01-17A12220 Concrete order for Slab Not Started Mar-16-17 Mar-11-17 1 1 0 Mar-16-17 Mar-11-17
L3L3L3 Mar-31-17 Mar-22-17 7 7 0 Apr-07-17 Apr-03-17A12250 Concrete order for Verticals Not Started Mar-31-17 Mar-22-17 1 1 0 Mar-31-17 Mar-22-17A12240 Concrete order for Slab Not Started Apr-07-17 Apr-03-17 1 1 0 Apr-07-17 Apr-03-17
L4L4L4 Apr-11-17 Apr-06-17 3 3 0 Apr-13-17 Apr-08-17A12270 Concrete order for Verticals Not Started Apr-11-17 Apr-06-17 1 1 0 Apr-11-17 Apr-06-17A12260 Concrete order for Slab Not Started Apr-13-17 Apr-08-17 1 1 0 Apr-13-17 Apr-08-17
L5L5L5 Apr-15-17 Apr-11-17 3 3 0 Apr-18-17 Apr-13-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
GeneratorCommissioning
Aug-05-17, Mechanical
Commissioning - HVACCommissioning - Plumbing
Commissioning - ElevatorsOct-25-17, City
OccupancyAug-23-17, Hydro
Services connectionsJun-29-17, Materials
Jun-29-17, Concrete OrdersOct-19-16, Foundations
Concrete order for Crane baseConcrete order for Core raftConcrete order for isolated footing
Concrete order for strip footingNov-15-16, P3
Concrete order for VerticalsConcrete order for S.O.GConcrete order for Slab
Dec-19-16, P2
Concrete order for VerticalsConcrete order for Slab
Jan-14-17, P1
Concrete order for VerticalsConcrete order for Slab
Feb-13-17, L1
Concrete order for VerticalsConcrete order for Slab
Mar-07-17, Town hous e 1
Concrete order for VerticalsConcrete order for Slab
Mar-07-17, Town hous e 2
Concrete order for VerticalsConcrete order for SlabMar-11-17, L2
Concrete order for VerticalsConcrete order for Slab
Apr-03-17, L3
Concrete order for VerticalsConcrete order for SlabApr-08-17, L4
Concrete order for VerticalsConcrete order for SlabApr-13-17, L5
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A12290 Concrete order for Verticals Not Started Apr-15-17 Apr-11-17 1 1 0 Apr-15-17 Apr-11-17A12280 Concrete order for Slab Not Started Apr-18-17 Apr-13-17 1 1 0 Apr-18-17 Apr-13-17
L6L6L6 Apr-20-17 Apr-15-17 3 3 0 Apr-22-17 Apr-18-17A12310 Concrete order for Verticals Not Started Apr-20-17 Apr-15-17 1 1 0 Apr-20-17 Apr-15-17A12300 Concrete order for Slab Not Started Apr-22-17 Apr-18-17 1 1 0 Apr-22-17 Apr-18-17
L7L7L7 Apr-25-17 Apr-20-17 3 3 0 Apr-27-17 Apr-22-17A12330 Concrete order for Verticals Not Started Apr-25-17 Apr-20-17 1 1 0 Apr-25-17 Apr-20-17A12320 Concrete order for Slab Not Started Apr-27-17 Apr-22-17 1 1 0 Apr-27-17 Apr-22-17
L8L8L8 Apr-29-17 Apr-25-17 3 3 0 May-02-17 Apr-27-17A12350 Concrete order for Verticals Not Started Apr-29-17 Apr-25-17 1 1 0 Apr-29-17 Apr-25-17A12340 Concrete order for Slab Not Started May-02-17 Apr-27-17 1 1 0 May-02-17 Apr-27-17
L9L9L9 May-04-17 Apr-29-17 3 3 0 May-06-17 May-02-17A12370 Concrete order for Verticals Not Started May-04-17 Apr-29-17 1 1 0 May-04-17 Apr-29-17A12360 Concrete order for Slab Not Started May-06-17 May-02-17 1 1 0 May-06-17 May-02-17
L10L10L10 May-09-17 May-04-17 3 3 0 May-11-17 May-06-17A12390 Concrete order for Verticals Not Started May-09-17 May-04-17 1 1 0 May-09-17 May-04-17A12380 Concrete order for Slab Not Started May-11-17 May-06-17 1 1 0 May-11-17 May-06-17
L11L11L11 May-13-17 May-09-17 3 3 0 May-16-17 May-11-17A12410 Concrete order for Verticals Not Started May-13-17 May-09-17 1 1 0 May-13-17 May-09-17A12400 Concrete order for Slab Not Started May-16-17 May-11-17 1 1 0 May-16-17 May-11-17
L12L12L12 May-18-17 May-13-17 3 3 0 May-20-17 May-16-17A12430 Concrete order for Verticals Not Started May-18-17 May-13-17 1 1 0 May-18-17 May-13-17A12420 Concrete order for Slab Not Started May-20-17 May-16-17 1 1 0 May-20-17 May-16-17
L14L14L14 May-24-17 May-18-17 3 3 0 May-26-17 May-20-17A12450 Concrete order for Verticals Not Started May-24-17 May-18-17 1 1 0 May-24-17 May-18-17A12440 Concrete order for Slab Not Started May-26-17 May-20-17 1 1 0 May-26-17 May-20-17
L15L15L15 May-29-17 May-24-17 4 4 0 Jun-01-17 May-27-17A12470 Concrete order for Verticals Not Started May-29-17 May-24-17 1 1 0 May-29-17 May-24-17A12460 Concrete order for Slab Not Started Jun-01-17 May-27-17 1 1 0 Jun-01-17 May-27-17
L16L16L16 Jun-03-17 May-30-17 3 3 0 Jun-06-17 Jun-01-17A12490 Concrete order for Verticals Not Started Jun-03-17 May-30-17 1 1 0 Jun-03-17 May-30-17A12480 Concrete order for Slab Not Started Jun-06-17 Jun-01-17 1 1 0 Jun-06-17 Jun-01-17
L17L17L17 Jun-08-17 Jun-03-17 3 3 0 Jun-10-17 Jun-06-17A12510 Concrete order for Verticals Not Started Jun-08-17 Jun-03-17 1 1 0 Jun-08-17 Jun-03-17A12500 Concrete order for Slab Not Started Jun-10-17 Jun-06-17 1 1 0 Jun-10-17 Jun-06-17
L18L18L18 Jun-13-17 Jun-08-17 3 3 0 Jun-15-17 Jun-10-17A12530 Concrete order for Verticals Not Started Jun-13-17 Jun-08-17 1 1 0 Jun-13-17 Jun-08-17A12520 Concrete order for Slab Not Started Jun-15-17 Jun-10-17 1 1 0 Jun-15-17 Jun-10-17
L19L19L19 Jun-17-17 Jun-13-17 3 3 0 Jun-20-17 Jun-15-17A12550 Concrete order for Verticals Not Started Jun-17-17 Jun-13-17 1 1 0 Jun-17-17 Jun-13-17A12540 Concrete order for Slab Not Started Jun-20-17 Jun-15-17 1 1 0 Jun-20-17 Jun-15-17
L20L20L20 Jun-22-17 Jun-17-17 3 3 0 Jun-24-17 Jun-20-17A12570 Concrete order for Verticals Not Started Jun-22-17 Jun-17-17 1 1 0 Jun-22-17 Jun-17-17A12560 Concrete order for Slab Not Started Jun-24-17 Jun-20-17 1 1 0 Jun-24-17 Jun-20-17
L21L21L21 Jun-27-17 Jun-22-17 3 3 0 Jun-29-17 Jun-24-17A12590 Concrete order for Verticals Not Started Jun-27-17 Jun-22-17 1 1 0 Jun-27-17 Jun-22-17A12580 Concrete order for Slab Not Started Jun-29-17 Jun-24-17 1 1 0 Jun-29-17 Jun-24-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Concrete order for VerticalsConcrete order for SlabApr-18-17, L6
Concrete order for VerticalsConcrete order for SlabApr-22-17, L7
Concrete order for VerticalsConcrete order for SlabApr-27-17, L8
Concrete order for VerticalsConcrete order for SlabMay-02-17, L9
Concrete order for VerticalsConcrete order for SlabMay-06-17, L10
Concrete order for VerticalsConcrete order for SlabMay-11-17, L11
Concrete order for VerticalsConcrete order for SlabMay-16-17, L12
Concrete order for VerticalsConcrete order for SlabMay-20-17, L14
Concrete order for VerticalsConcrete order for SlabMay-27-17, L15
Concrete order for VerticalsConcrete order for SlabJun-01-17, L16
Concrete order for VerticalsConcrete order for SlabJun-06-17, L17
Concrete order for VerticalsConcrete order for SlabJun-10-17, L18
Concrete order for VerticalsConcrete order for SlabJun-15-17, L19
Concrete order for VerticalsConcrete order for SlabJun-20-17, L20
Concrete order for VerticalsConcrete order for SlabJun-24-17, L21
Concrete order for VerticalsConcrete order for Slab
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
RoofRoofRoof Jul-04-17 Jun-27-17 3 3 0 Jul-06-17 Jun-29-17A12610 Concrete order for Verticals Not Started Jul-04-17 Jun-27-17 1 1 0 Jul-04-17 Jun-27-17A12600 Concrete order for Slab Not Started Jul-06-17 Jun-29-17 1 1 0 Jul-06-17 Jun-29-17
Construction workConstruction workConstruction work Jul-11-16 Jul-11-16 Jun-18-16 440 388 87 Dec-27-17 Oct-24-17Earth workEarth workEarth work Jul-11-16 Jul-11-16 Jun-18-16 97 93 87 Nov-02-16 Oct-28-16A1000 Mobilization Equipment ( Excavation ) Completed Jul-11-16 Jul-11-16 Jul-12-16 0 0 0 Jul-11-16 Jul-11-16 Jul-12-16A1020 Hauling out topsoil Completed Jul-11-16 Jul-11-16 Jul-12-16 1 1 1 Jul-11-16 Jul-11-16 Jul-13-16A1010 Excavate - Stockpile Completed Jul-12-16 Jul-12-16 Jul-13-16 1 1 1 Jul-12-16 Jul-12-16 Jul-14-16A1140 Drill piles North side 23 piles - 5 cancelled by the engineer Completed Jul-13-16 Jul-13-16 Jul-14-16 3 3 0 Jul-15-16 Jul-15-16 Jul-14-16A1130 Drill piles East side 12 piles - cancelled by the engineer Completed Jul-16-16 Jul-16-16 Jul-14-16 2 2 4 Jul-18-16 Jul-18-16 Jul-19-16A1110 Mobilization Equipment ( Shoring ) Completed Jul-19-16 Jul-19-16 Jul-20-16 0 0 1 Jul-19-16 Jul-19-16 Jul-21-16A1120 Drill piles South side 7 piles Completed Jul-19-16 Jul-19-16 Jul-19-16 1 1 1 Jul-19-16 Jul-19-16 Jul-20-16A1060 Demobilization Equipment ( Piling ) Completed Aug-03-16 Aug-03-16 Jul-20-16 0 0 0 Aug-03-16 Aug-03-16 Jul-20-16P1P1P1 Jul-13-16 Jul-13-16 Jun-18-16 17 33 53 Aug-02-16 Aug-20-16 Aug-22-16NorthNorthNorth Jul-13-16 Jul-13-16 Jun-18-16 17 23 47 Aug-02-16 Aug-09-16 Aug-15-16A1650 Excavate dril l bench North side row 1 Completed Jul-13-16 Jul-13-16 Jun-18-16 1 1 1 Jul-13-16 Jul-13-16 Jun-19-16A1390 Drilling Anchors North side row 1 - 33 anchors ( 15 IBO ) Completed Jul-19-16 Jul-19-16 Jul-21-16 2 2 4 Jul-20-16 Jul-20-16 Jul-26-16A1730 Trimming North side row 1 Completed Jul-21-16 Jul-21-16 Jul-26-16 1 1 1 Jul-21-16 Jul-21-16 Jul-27-16A1420 Shore North side row 1 Completed Jul-22-16 Jul-22-16 Jul-27-16 2 2 2 Jul-23-16 Jul-23-16 Jul-29-16A1370 Excavate dril l bench North side row 2 Completed Jul-25-16 Aug-02-16 Aug-02-16 1 1 2 Jul-25-16 Aug-02-16 Aug-04-16A1400 Drilling Anchors North side row 2 - 33 anchors Completed Jul-26-16 Aug-03-16 Aug-03-16 2 2 3 Jul-27-16 Aug-04-16 Aug-06-16A1740 Trimming North side row 2 Completed Jul-28-16 Aug-05-16 Aug-08-16 1 1 5 Jul-28-16 Aug-05-16 Aug-13-16A1430 Shore North side row 2 Completed Jul-29-16 Aug-06-16 Aug-08-16 2 2 5 Jul-30-16 Aug-08-16 Aug-13-16A1100 Excavate P1 North side Completed Jul-30-16 Aug-08-16 Jul-22-16 1 1 18 Jul-30-16 Aug-08-16 Aug-13-16A1080 Removal P1 North soil Completed Aug-02-16 Aug-09-16 Jul-22-16 1 1 19 Aug-02-16 Aug-09-16 Aug-15-16
EastEastEast Jul-13-16 Aug-02-16 Jul-19-16 7 7 12 Jul-20-16 Aug-09-16 Aug-03-16A6490 Excavate dril l bench East side row 1 Completed Jul-13-16 Aug-02-16 Aug-02-16 1 1 0 Jul-13-16 Aug-02-16 Aug-02-16A6530 Drilling Anchors East side row 1 - 6 anchors Completed Jul-14-16 Aug-03-16 Aug-02-16 1 1 1 Jul-14-16 Aug-03-16 Aug-03-16A7750 Trimming East s ide row 1 - N/A Completed Jul-15-16 Aug-04-16 Aug-03-16 1 1 0 Jul-15-16 Aug-04-16 Aug-03-16A7740 Shore East side row 1 - N/A Completed Jul-16-16 Aug-05-16 Aug-03-16 2 2 0 Jul-18-16 Aug-06-16 Aug-03-16A1880 Excavate P1 East side Completed Jul-19-16 Aug-08-16 Jul-19-16 1 1 12 Jul-19-16 Aug-08-16 Aug-03-16A1990 Removal P1 East soil Completed Jul-20-16 Aug-09-16 Aug-03-16 1 1 0 Jul-20-16 Aug-09-16 Aug-03-16
SouthSouthSouth Jul-14-16 Aug-02-16 Jul-22-16 8 8 19 Jul-22-16 Aug-10-16 Aug-15-16A1660 Excavate dril l bench South side row 1 Completed Jul-14-16 Aug-02-16 Aug-02-16 1 1 1 Jul-14-16 Aug-02-16 Aug-03-16A1520 Drilling Anchors South side row 1 - 33 anchors Completed Jul-15-16 Aug-03-16 Aug-02-16 2 2 1 Jul-16-16 Aug-04-16 Aug-03-16A1780 Trimming South side row 1 Completed Jul-18-16 Aug-05-16 Aug-08-16 1 1 2 Jul-18-16 Aug-05-16 Aug-10-16A1440 Shore South side row 1 Completed Jul-19-16 Aug-06-16 Aug-08-16 2 2 3 Jul-20-16 Aug-08-16 Aug-11-16A1890 Excavate P1 South side Completed Jul-21-16 Aug-09-16 Jul-22-16 1 1 17 Jul-21-16 Aug-09-16 Aug-12-16A2010 Removal P1 South soil Completed Jul-22-16 Aug-10-16 Jul-22-16 1 1 19 Jul-22-16 Aug-10-16 Aug-15-16
WestWestWest Jul-20-16 Aug-09-16 Jul-22-16 8 11 25 Jul-28-16 Aug-20-16 Aug-22-16A1900 Excavate P1 West side Completed Jul-27-16 Aug-09-16 Jul-22-16 1 1 9 Jul-27-16 Aug-09-16 Aug-03-16A2000 Removal P1 West s oil Completed Jul-28-16 Aug-10-16 Jul-22-16 1 1 9 Jul-28-16 Aug-10-16 Aug-03-16A1700 Excavate dril l bench West s ide row 1 Completed Jul-20-16 Aug-15-16 Aug-11-16 1 1 1 Jul-20-16 Aug-15-16 Aug-12-16A1590 Drilling Anchors West side row 1 - 17 anchors Completed Jul-21-16 Aug-16-16 Aug-15-16 2 2 2 Jul-22-16 Aug-17-16 Aug-17-16A1800 Trimming West side row 1 Completed Jul-23-16 Aug-18-16 Aug-18-16 1 1 3 Jul-23-16 Aug-18-16 Aug-22-16
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Jun-29-17, Roof
Concrete order for VerticalsConcrete order for Slab
Oct-24-17, Construction work
Oct-28-16, Earth work
Mobil ization Equipment ( Excavation )Hauling out topsoilExcavate - StockpileDrill piles North side 23 piles - 5 cancelled by the engineerDrill piles East side 12 piles - cancelled by the engineerMobilization Equipment ( Shoring )Drill piles South side 7 piles
Demobilization Equipment ( Piling )Aug-22-16 A, P1
Aug-15-16 A, North
Excavate drill bench North side row 1Drilling Anchors North side row 1 - 33 anchors ( 15 IBO )Trimming North side row 1Shore North side row 1Excavate drill bench North side row 2Drilling Anchors North side row 2 - 33 anchors
Trimming North side row 2Shore North side row 2Excavate P1 North sideRemoval P1 North soil
Aug-03-16 A, East
Excavate dri ll bench East side row 1Drilling Anchors East side row 1 - 6 anchorsTrimming East s ide row 1 - N/AShore East side row 1 - N/AExcavate P1 East sideRemoval P1 East soil
Aug-15-16 A, South
Excavate drill bench South side row 1Drilling Anchors South side row 1 - 33 anchorsTrimming South side row 1Shore South side row 1Excavate P1 South sideRemoval P1 South soil
Aug-22-16 A, West
Excavate P1 West sideRemoval P1 West s oil
Excavate drill bench West s ide row 1Drilling Anchors West side row 1 - 17 anchorsTrimming West side row 1
A
A
IBOs
aaa
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A1630 Shore West side row 1 Completed Jul-25-16 Aug-19-16 Aug-18-16 2 2 3 Jul-26-16 Aug-20-16 Aug-22-16P2P2P2 Jul-15-16 Aug-15-16 Aug-09-16 27 38 40 Aug-16-16 Sep-27-16 Sep-24-16NorthNorthNorth Aug-02-16 Aug-15-16 Aug-15-16 13 13 35 Aug-16-16 Aug-29-16 Sep-24-16A1410 Excavate dril l bench North side row 3 Completed Aug-02-16 Aug-15-16 Aug-16-16 1 1 1 Aug-02-16 Aug-15-16 Aug-17-16A1480 Drilling Anchors North side row 3 - 33 anchors Completed Aug-03-16 Aug-16-16 Aug-15-16 2 2 3 Aug-04-16 Aug-17-16 Aug-18-16A1750 Trimming North side row 3 Completed Aug-05-16 Aug-18-16 Aug-18-16 1 1 13 Aug-05-16 Aug-18-16 Sep-02-16A1490 Shore North side row 3 Completed Aug-06-16 Aug-19-16 Aug-18-16 2 2 13 Aug-08-16 Aug-20-16 Sep-02-16A1620 Excavate dril l bench North side row 4 Completed Aug-09-16 Aug-22-16 Aug-22-16 1 1 26 Aug-09-16 Aug-22-16 Sep-21-16A1470 Drilling Anchors North side row 4 - 33 anchors Completed Aug-10-16 Aug-23-16 Aug-20-16 2 2 28 Aug-11-16 Aug-24-16 Sep-22-16A1760 Trimming North side row 4 Completed Aug-12-16 Aug-25-16 Aug-25-16 1 1 26 Aug-12-16 Aug-25-16 Sep-24-16A1500 Shore North side row 4 Completed Aug-13-16 Aug-26-16 Aug-25-16 2 2 26 Aug-15-16 Aug-27-16 Sep-24-16A1910 Excavate P2 North side Completed Aug-15-16 Aug-27-16 Aug-29-16 1 1 23 Aug-15-16 Aug-27-16 Sep-24-16A2020 Removal P2 North soil Completed Aug-16-16 Aug-29-16 Aug-29-16 1 1 23 Aug-16-16 Aug-29-16 Sep-24-16
EastEastEast Jul-21-16 Sep-19-16 Sep-14-16 11 8 3 Aug-03-16 Sep-27-16 Sep-17-16A6500 Excavate dril l bench East side row 2 Completed Jul-21-16 Sep-19-16 Sep-14-16 1 1 0 Jul-21-16 Sep-19-16 Sep-14-16A6520 Drilling Anchors East side row 2 - 13 anchors Completed Jul-22-16 Sep-20-16 Sep-15-16 2 2 1 Jul-23-16 Sep-21-16 Sep-16-16A7770 Trimming East s ide row 2 Completed Jul-25-16 Sep-22-16 Sep-16-16 1 1 1 Jul-25-16 Sep-22-16 Sep-17-16A7760 Shore East side row 2 Completed Jul-26-16 Sep-23-16 Sep-16-16 2 2 1 Jul-27-16 Sep-24-16 Sep-17-16A1940 Excavate P2 East side Completed Aug-02-16 Sep-26-16 Sep-17-16 1 1 0 Aug-02-16 Sep-26-16 Sep-17-16A2030 Removal P2 East soil Completed Aug-03-16 Sep-27-16 Sep-17-16 1 1 0 Aug-03-16 Sep-27-16 Sep-17-16
SouthSouthSouth Jul-15-16 Aug-15-16 Aug-09-16 16 13 20 Aug-03-16 Aug-29-16 Sep-01-16A1670 Excavate dril l bench South side row 2 Completed Jul-15-16 Aug-15-16 Aug-09-16 1 1 6 Jul-15-16 Aug-15-16 Aug-16-16A1530 Drilling Anchors South side row 2 - 33 anchors Completed Jul-16-16 Aug-16-16 Aug-12-16 2 2 4 Jul-18-16 Aug-17-16 Aug-17-16A1820 Trimming South side row 2 Completed Jul-19-16 Aug-18-16 Aug-18-16 1 1 3 Jul-19-16 Aug-18-16 Aug-22-16A1580 Shore South side row 2 Completed Jul-20-16 Aug-19-16 Aug-18-16 2 2 3 Jul-21-16 Aug-20-16 Aug-22-16A1680 Excavate dril l bench South side row 3 Completed Jul-16-16 Aug-22-16 Aug-23-16 1 1 0 Jul-16-16 Aug-22-16 Aug-23-16A1540 Drilling Anchors South side row 3 - 24 anchors Completed Jul-18-16 Aug-23-16 Aug-24-16 2 2 2 Jul-19-16 Aug-24-16 Aug-26-16A1810 Trimming South side row 3 Completed Jul-20-16 Aug-25-16 Aug-25-16 1 1 2 Jul-20-16 Aug-25-16 Aug-27-16A1570 Shore South side row 3 Completed Jul-21-16 Aug-26-16 Aug-25-16 2 2 6 Jul-22-16 Aug-27-16 Sep-01-16A1930 Excavate P2 South side Completed Aug-02-16 Aug-27-16 Aug-29-16 1 1 3 Aug-02-16 Aug-27-16 Sep-01-16A2050 Removal P2 South soil Completed Aug-03-16 Aug-29-16 Aug-29-16 1 1 3 Aug-03-16 Aug-29-16 Sep-01-16
WestWestWest Jul-21-16 Aug-22-16 Aug-20-16 11 8 7 Aug-03-16 Aug-30-16 Aug-29-16A1710 Excavate dril l bench West s ide row 2 Completed Jul-21-16 Aug-22-16 Aug-20-16 1 1 2 Jul-21-16 Aug-22-16 Aug-23-16A1600 Drilling Anchors West side row 2 - 17 anchors Completed Jul-22-16 Aug-23-16 Aug-22-16 2 2 3 Jul-23-16 Aug-24-16 Aug-25-16A1830 Trimming West side row 2 Completed Jul-25-16 Aug-25-16 Aug-25-16 1 1 2 Jul-25-16 Aug-25-16 Aug-27-16A1240 Shore West side row 2 Completed Jul-26-16 Aug-26-16 Aug-25-16 2 2 2 Jul-27-16 Aug-27-16 Aug-27-16A1920 Excavate P2 West side Completed Aug-02-16 Aug-29-16 Aug-29-16 1 1 0 Aug-02-16 Aug-29-16 Aug-29-16A2040 Removal P2 West s oil Completed Aug-03-16 Aug-30-16 Aug-29-16 1 1 0 Aug-03-16 Aug-30-16 Aug-29-16
P3P3P3 Jul-18-16 Aug-23-16 Aug-25-16 32 36 26 Aug-24-16 Oct-03-16 Sep-24-16SouthSouthSouth Jul-18-16 Aug-23-16 Aug-25-16 26 35 26 Aug-17-16 Oct-01-16 Sep-24-16A1690 Excavate dril l bench South side row 4 - Cancelled Completed Jul-18-16 Aug-23-16 Aug-25-16 1 1 0 Jul-18-16 Aug-23-16 Aug-25-16A1550 Drilling Anchors South side row 4 - 13 anchors - Cancelled Completed Jul-19-16 Aug-24-16 Aug-25-16 1 1 0 Jul-19-16 Aug-24-16 Aug-25-16A1790 Trimming South side row 4 - Canc elled Completed Jul-20-16 Aug-25-16 Aug-25-16 1 1 0 Jul-20-16 Aug-25-16 Aug-25-16A1560 Shore South side row 4 - Cancelled Completed Jul-21-16 Aug-26-16 Aug-25-16 2 2 0 Jul-22-16 Aug-27-16 Aug-25-16A1980 Excavate P3 South side - Cancelled Completed Aug-16-16 Aug-30-16 Aug-25-16 1 1 0 Aug-16-16 Aug-30-16 Aug-25-16
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Shore West side r ow 1Sep-24-16 A, P2Sep-24-16 A, North
Excavate drill bench North side row 3Drilling Anchors North side row 3 - 33 anchors
Trimming North side row 3Shore North side row 3
Excavate drill bench North side row 4Drilling Anchors North side row 4 - 33 anchorsTrimming North side row 4Shore North side row 4Excavate P2 North sideRemoval P2 North soil
Sep-17-16 A, East
Excavate drill bench East side row 2Dril ling Anchors East side row 2 - 13 anchorsTrimming East s ide row 2Shore East side row 2Excavate P2 East sideRemoval P2 East soil
Sep-01-16 A, South
Excavate drill bench South side row 2Drilling Anchors South side row 2 - 33 anchorsTrimming South side r ow 2Shore South side row 2Excavate drill bench South side row 3Drilling Anchors South side row 3 - 24 anchorsTrimming South side r ow 3Shore South side row 3Excavate P2 South sideRemoval P2 South soilAug-29-16 A, West
Excavate drill bench West s ide row 2Drilling Anchors West side row 2 - 17 anchorsTrimming West side row 2Shore West side r ow 2Excavate P2 West sideRemoval P2 West s oil
Sep-24-16 A, P3Sep-24-16 A, South
Excavate drill bench South side row 4 - CancelledDrilling Anchors South side row 4 - 13 anchors - CancelledTrimming South side r ow 4 - Canc elledShore South side row 4 - CancelledExcavate P3 South side - Cancelled
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A2070 Removal P3 South soil - Cancelled Completed Aug-17-16 Aug-31-16 Aug-25-16 1 1 0 Aug-17-16 Aug-31-16 Aug-25-16A22150 Drill Anchors South side core raft support - 27 anchors 3 Rows - 3R eliminated ( 9 anchors )Completed Sep-19-16 Sep-21-16 0 3 2 Sep-21-16 Sep-23-16A22160 Trimming South side core raft support 3 rows Completed Sep-22-16 Sep-22-16 0 6 2 Sep-28-16 Sep-24-16A22170 Shoring South side core raft support 3 rows - 2 days sequence Completed Sep-29-16 Sep-22-16 0 3 2 Oct-01-16 Sep-24-16
WestWestWest Jul-22-16 Sep-06-16 Aug-29-16 22 9 22 Aug-17-16 Sep-15-16 Sep-23-16A1720 Excavate dril l bench West s ide row 3 Completed Jul-22-16 Sep-06-16 Aug-29-16 1 1 20 Jul-22-16 Sep-06-16 Sep-21-16A1610 Drilling Anchors West side row 3 - 17 anchors Completed Jul-23-16 Sep-07-16 Aug-31-16 2 2 19 Jul-25-16 Sep-08-16 Sep-22-16A1840 Trimming West side row 3 Completed Jul-26-16 Sep-09-16 Sep-01-16 1 1 19 Jul-26-16 Sep-09-16 Sep-23-16A1320 Shore West side row 3 Completed Jul-27-16 Sep-10-16 Sep-01-16 2 2 19 Jul-28-16 Sep-12-16 Sep-23-16A1960 Excavate P3 West side Completed Aug-16-16 Sep-14-16 Sep-06-16 1 1 15 Aug-16-16 Sep-14-16 Sep-23-16A2060 Removal P3 West s oil Completed Aug-17-16 Sep-15-16 Sep-06-16 1 1 15 Aug-17-16 Sep-15-16 Sep-23-16
NorthNorthNorth Aug-16-16 Sep-05-16 Aug-30-16 8 8 21 Aug-24-16 Sep-13-16 Sep-23-16A1640 Excavate dril l bench North side row 5 Completed Aug-16-16 Sep-05-16 Sep-01-16 1 1 16 Aug-16-16 Sep-05-16 Sep-20-16A1460 Drilling Anchors North side row 5 - 33 anchors Completed Aug-17-16 Sep-06-16 Aug-30-16 2 2 19 Aug-18-16 Sep-07-16 Sep-21-16A1770 Trimming North side row 5 Completed Aug-19-16 Sep-08-16 Sep-01-16 1 1 18 Aug-19-16 Sep-08-16 Sep-22-16A1510 Shore North side row 5 Completed Aug-20-16 Sep-09-16 Sep-01-16 2 2 18 Aug-22-16 Sep-10-16 Sep-22-16A1950 Excavate P3 North side Completed Aug-23-16 Sep-12-16 Sep-01-16 1 1 19 Aug-23-16 Sep-12-16 Sep-23-16A1330 Removal P3 North soil Completed Aug-24-16 Sep-13-16 Sep-01-16 1 1 19 Aug-24-16 Sep-13-16 Sep-23-16
EastEastEast Aug-04-16 Sep-24-16 Sep-17-16 12 8 2 Aug-17-16 Oct-03-16 Sep-20-16A6510 Excavate dril l bench East side row 3 Completed Aug-04-16 Sep-24-16 Sep-17-16 1 1 0 Aug-04-16 Sep-24-16 Sep-17-16A1450 Drilling Anchors East side row 3 - 9 anchors Completed Aug-05-16 Sep-26-16 Sep-19-16 2 2 0 Aug-06-16 Sep-27-16 Sep-19-16A7790 Trimming East s ide row 3 Completed Aug-08-16 Sep-28-16 Sep-19-16 1 1 1 Aug-08-16 Sep-28-16 Sep-20-16A7780 Shore East side row 3 Completed Aug-09-16 Sep-29-16 Sep-19-16 2 2 1 Aug-10-16 Sep-30-16 Sep-20-16A1970 Excavate P3 East side Completed Aug-16-16 Oct-01-16 Sep-20-16 1 1 0 Aug-16-16 Oct-01-16 Sep-20-16A1380 Removal P3 East soil Completed Aug-17-16 Oct-03-16 Sep-20-16 1 1 0 Aug-17-16 Oct-03-16 Sep-20-16
Detailed excavationDetailed excavationDetailed excavation Aug-25-16 Sep-23-16 Aug-03-16 59 30 50 Nov-02-16 Oct-28-16A1850 Detailed excavation - Crane base Completed Aug-25-16 Sep-23-16 Sep-06-16 1 1 1 Aug-25-16 Sep-23-16 Sep-07-16A1860 Detailed excavation Core raft Completed Aug-26-16 Sep-24-16 Sep-21-16 2 2 3 Aug-27-16 Sep-26-16 Sep-24-16A2080 Trench Excav ate In Progress Sep-09-16 Sep-24-16 Sep-23-16 2 7 6 Sep-10-16 Oct-01-16A1870 Detailed excavation - footings In Progress Aug-29-16 Sep-27-16 Aug-03-16 10 10 50 Sep-08-16 Oct-07-16A6270 Compaction Not Started Oct-18-16 Oct-13-16 5 5 0 Oct-22-16 Oct-18-16A6260 Backfil l Not Started Oct-28-16 Oct-24-16 5 5 0 Nov-02-16 Oct-28-16
StructuralStructuralStructural Aug-26-16 Sep-06-16 Sep-06-16 260 247 21 Jul-10-17 Jul-05-17FoundationFoundationFoundation Aug-26-16 Sep-06-16 Sep-06-16 34 41 21 Oct-04-16 Oct-24-16Crane BaseCrane BaseCrane Base Aug-26-16 Sep-06-16 Sep-06-16 24 7 6 Sep-22-16 Sep-13-16 Sep-13-16FormingFormingForming Aug-26-16 Sep-06-16 Sep-06-16 24 7 6 Sep-22-16 Sep-13-16 Sep-13-16A2330 Concrete outline layout Completed Aug-26-16 Sep-06-16 Sep-06-16 0 0 1 Aug-26-16 Sep-06-16 Sep-07-16A2340 Forming Completed Sep-12-16 Sep-06-16 Sep-07-16 2 1 0 Sep-13-16 Sep-06-16 Sep-07-16A2370 Bracing Completed Sep-21-16 Sep-09-16 Sep-07-16 0 0 0 Sep-21-16 Sep-09-16 Sep-07-16A2380 Pouring Completed Sep-21-16 Sep-12-16 Sep-13-16 1 1 0 Sep-21-16 Sep-12-16 Sep-13-16A2390 Deshuttering Completed Sep-22-16 Sep-13-16 Sep-07-16 1 1 0 Sep-22-16 Sep-13-16 Sep-07-16
ReinforcementReinforcementReinforcement Sep-13-16 Sep-07-16 Sep-06-16 8 3 5 Sep-21-16 Sep-09-16 Sep-12-16A2350 Reinforcement - Bottom - Include Base plates mesh Completed Sep-13-16 Sep-07-16 Sep-06-16 1 1 5 Sep-13-16 Sep-07-16 Sep-12-16A2360 Reinforcement - Top Completed Sep-21-16 Sep-09-16 Sep-12-16 1 1 0 Sep-21-16 Sep-09-16 Sep-12-16
Core raftCore raftCore raft Aug-29-16 Sep-24-16 Sep-23-16 32 15 0 Oct-04-16 Oct-12-16
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Removal P3 South soil - CancelledDrill Anchors South side core raft support - 27 anchors 3 Rows - 3R eliminated ( 9 anchors )Trimming South side c ore raft support 3 rowsShoring South side core raft support 3 rows - 2 days sequenceSep-23-16 A, West
Excavate drill bench West s ide row 3Drilling Anchors West side row 3 - 17 anchorsTrimming West side row 3Shore West side row 3Excavate P3 West sideRemoval P3 West soilSep-23-16 A, North
Excavate dril l bench North side row 5Drilling Anchors North side row 5 - 33 anchorsTrimming North side row 5Shore North side row 5Excavate P3 North sideRemoval P3 North soilSep-20-16 A, East
Excavate drill bench East side row 3Drilling Anchors East side row 3 - 9 anchorsTrimming East s ide row 3Shore East side row 3Excavate P3 East sideRemoval P3 East soil
Oct-28-16, Detailed excavation
Detailed excavation - Crane baseDetailed excavation Core raft
Trench ExcavateDetailed excavation - footings
CompactionBackfill
Jul-05-17, StructuralOct-25-16, Foundation
Sep-13-16 A, Crane BaseSep-13-16 A, Forming
Concrete outl ine layoutForming
BracingPouringDeshuttering
Sep-12-16 A, Reinforcement
Reinforcement - Bottom - Include Base plates meshReinforcement - Top
Oct-03-16, Core raft
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
FormingFormingForming Aug-29-16 Sep-24-16 Sep-23-16 32 15 0 Oct-04-16 Oct-12-16A2260 Concrete outline layout Completed Aug-29-16 Sep-24-16 Sep-23-16 0 0 0 Aug-29-16 Sep-24-16 Sep-23-16A2270 Forming - Cancelled Completed Sep-24-16 Oct-01-16 Sep-23-16 2 2 0 Sep-26-16 Oct-03-16 Sep-23-16A2290 Pouring Not Started Sep-30-16 Oct-03-16 1 1 0 Sep-30-16 Oct-03-16A2280 Bracing - Cancelled Completed Sep-29-16 Oct-06-16 Sep-23-16 1 1 0 Sep-29-16 Oct-06-16 Sep-23-16A2300 Deshuttering - Cancelled Completed Oct-04-16 Oct-12-16 Sep-23-16 1 1 0 Oct-04-16 Oct-12-16 Sep-23-16
ReinforcementReinforcementReinforcement Sep-27-16 Sep-30-16 2 2 0 Sep-28-16 Oct-01-16A2310 Reinforcement - Bottom Not Started Sep-27-16 Sep-30-16 1 1 0 Sep-27-16 Sep-30-16A2320 Reinforcement - Top Not Started Sep-28-16 Oct-01-16 1 1 0 Sep-28-16 Oct-01-16
Isolated footingsIsolated footingsIsolated footings Sep-09-16 Sep-24-16 Sep-21-16 15 15 6 Sep-26-16 Oct-12-16 Sep-28-16FormingFormingForming Sep-09-16 Sep-24-16 Sep-22-16 15 15 5 Sep-26-16 Oct-12-16 Sep-28-16A2400 Concrete outline layout Completed Sep-09-16 Sep-24-16 Sep-22-16 1 1 5 Sep-09-16 Sep-24-16 Sep-28-16A2410 Forming - Cancelled Completed Sep-10-16 Sep-26-16 Sep-22-16 7 7 0 Sep-17-16 Oct-03-16 Sep-22-16A2450 Pouring - Zone 1 Completed Sep-24-16 Oct-05-16 Sep-23-16 1 1 4 Sep-24-16 Oct-05-16 Sep-28-16A2440 Bracing - Cancelled Completed Sep-23-16 Oct-08-16 Sep-22-16 1 1 0 Sep-23-16 Oct-08-16 Sep-22-16A2460 Deshuttering - Cancelled Completed Sep-26-16 Oct-12-16 Sep-22-16 1 1 0 Sep-26-16 Oct-12-16 Sep-22-16
ReinforcementReinforcementReinforcement Sep-19-16 Sep-30-16 Sep-21-16 4 4 6 Sep-22-16 Oct-04-16 Sep-28-16A2420 Reinforcement - Bottom Completed Sep-19-16 Sep-30-16 Sep-21-16 2 2 5 Sep-20-16 Oct-01-16 Sep-27-16A2430 Reinforcement - Top Completed Sep-21-16 Oct-03-16 Sep-24-16 2 2 3 Sep-22-16 Oct-04-16 Sep-28-16
Strip footingsStrip footingsStrip footings Sep-09-16 Oct-08-16 Sep-06-16 13 13 21 Sep-23-16 Oct-24-16FormingFormingForming Sep-09-16 Oct-08-16 Sep-06-16 13 13 21 Sep-23-16 Oct-24-16A2470 Concrete outline layout In Progress Sep-09-16 Oct-08-16 Sep-06-16 1 1 21 Sep-09-16 Oct-08-16A2480 Forming In Progress Sep-10-16 Oct-11-16 Sep-06-16 5 5 21 Sep-15-16 Oct-15-16A2510 Bracing In Progress Sep-21-16 Oct-21-16 Sep-06-16 1 1 21 Sep-21-16 Oct-21-16A2520 Pouring - Zone 1,2,3 In Progress Sep-22-16 Oct-22-16 Sep-12-16 1 1 16 Sep-22-16 Oct-22-16A2530 Deshuttering Completed Sep-23-16 Oct-24-16 Sep-13-16 1 1 1 Sep-23-16 Oct-24-16 Sep-14-16
ReinforcementReinforcementReinforcement Sep-16-16 Oct-17-16 Sep-07-16 4 4 20 Sep-20-16 Oct-20-16A2490 Reinforcement - Bottom In Progress Sep-16-16 Oct-17-16 Sep-07-16 2 2 20 Sep-17-16 Oct-18-16A2500 Reinforcement - Top In Progress Sep-19-16 Oct-19-16 Sep-07-16 2 2 20 Sep-20-16 Oct-20-16
S.O.GS.O.GS.O.G Oct-06-16 Oct-01-16 34 34 0 Nov-16-16 Nov-10-16A6190 Concrete slopes layout Not Started Oct-06-16 Oct-01-16 1 1 0 Oct-06-16 Oct-01-16A6200 Reinforcement Not Started Oct-07-16 Oct-03-16 2 2 0 Oct-08-16 Oct-04-16A6210 Forming Diamonds Not Started Nov-08-16 Nov-03-16 1 1 0 Nov-08-16 Nov-03-16A6240 Pouring Not Started Nov-14-16 Nov-08-16 1 1 0 Nov-14-16 Nov-08-16A6250 Saw cut - Crack control lines Not Started Nov-15-16 Nov-09-16 1 1 0 Nov-15-16 Nov-09-16A6220 Pouring Diamonds Not Started Nov-16-16 Nov-10-16 1 1 0 Nov-16-16 Nov-10-16
P3P3P3 Oct-05-16 Sep-24-16 Sep-22-16 48 53 7 Dec-01-16 Nov-26-16VerticalsVerticalsVerticals Oct-05-16 Sep-24-16 Sep-22-16 28 33 7 Nov-07-16 Nov-02-16FormingFormingForming Oct-05-16 Sep-24-16 Sep-22-16 28 33 7 Nov-07-16 Nov-02-16A6130 Concrete outline layout - Zone 1,2,3 In Progress Oct-05-16 Sep-24-16 Sep-22-16 9 9 7 Oct-15-16 Oct-04-16A6140 Forming Walls - Zone 1,2,3 Not Started Oct-05-16 Sep-30-16 9 9 0 Oct-15-16 Oct-11-16A6160 Form closing and Bracing Walls - Zone 1,2,3 Not Started Oct-18-16 Oct-13-16 9 9 0 Oct-27-16 Oct-22-16A6170 Pouring Walls - Zone 1,2,3 Not Started Oct-28-16 Oct-24-16 9 9 0 Nov-07-16 Nov-02-16A6180 Deshuttering Walls - Zone 1,2,3 Not Started Oct-28-16 Oct-24-16 9 9 0 Nov-07-16 Nov-02-16
ReinforcementReinforcementReinforcement Oct-18-16 Oct-06-16 Sep-22-16 9 9 7 Oct-27-16 Oct-17-16
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Oct-03-16, Forming
Concrete outline layoutForming - CancelledPouringBracing - CancelledDeshuttering - CancelledOct-01-16, Reinforcement
Reinforcement - BottomReinforcement - Top
Sep-28-16 A, Isolated footingsSep-28-16 A, Forming
Concrete outline layoutForming - CancelledPouring - Zone 1
Bracing - CancelledDeshuttering - CancelledSep-28-16 A, Reinforcement
Reinforcement - BottomReinforcement - Top
Oct-25-16, Strip footingsOct-25-16, Forming
Concrete outline layoutFormingBracingPouring - Zone 1,2,3
DeshutteringOct-22-16, Reinforcement
Reinforcement - BottomReinforcement - Top
Nov-10-16, S.O.G
Concrete slopes layoutReinforcement
Forming DiamondsPouringSaw cut - Crack control linesPouring Diamonds
Nov-26-16, P3Nov-02-16, VerticalsNov-02-16, Forming
Concrete outline layout - Zone 1,2,3Forming Walls - Zone 1,2,3
Form closing and Bracing Walls - Zone 1,2,3Pouring Walls - Zone 1,2,3Deshuttering Walls - Zone 1,2,3
Oct-22-16, Reinforcement
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A6150 Reinforcement Walls - Zone 1,2,3 In Progress Oct-18-16 Oct-06-16 Sep-22-16 9 9 7 Oct-27-16 Oct-17-16HorizontalsHorizontalsHorizontals Nov-08-16 Nov-03-16 20 20 0 Dec-01-16 Nov-26-16FormingFormingForming Nov-08-16 Nov-03-16 20 20 0 Dec-01-16 Nov-26-16A2540 Concrete outline layout Not Started Nov-08-16 Nov-03-16 3 3 0 Nov-10-16 Nov-05-16A2550 Setting ( Flying ) Tables and Forming Not Started Nov-16-16 Nov-10-16 3 3 0 Nov-18-16 Nov-14-16A2580 Bracing Not Started Nov-26-16 Nov-22-16 3 3 0 Nov-29-16 Nov-24-16A2590 Pouring Not Started Nov-30-16 Nov-25-16 1 1 0 Nov-30-16 Nov-25-16A2600 Deshuttering Not Started Dec-01-16 Nov-26-16 1 1 0 Dec-01-16 Nov-26-16
ReinforcementReinforcementReinforcement Nov-19-16 Nov-15-16 6 6 0 Nov-25-16 Nov-21-16A2560 Reinforcement - Bottom Not Started Nov-19-16 Nov-15-16 2 2 0 Nov-21-16 Nov-16-16A2570 Reinforcement - Top Not Started Nov-23-16 Nov-18-16 3 3 0 Nov-25-16 Nov-21-16
P2P2P2 Dec-01-16 Nov-26-16 24 24 0 Dec-30-16 Dec-24-16VerticalsVerticalsVerticals Dec-01-16 Nov-26-16 15 15 0 Dec-19-16 Dec-14-16FormingFormingForming Dec-01-16 Nov-26-16 15 15 0 Dec-19-16 Dec-14-16A6070 Concrete outline layout Not Started Dec-01-16 Nov-26-16 1 1 0 Dec-01-16 Nov-26-16A6080 Forming Not Started Dec-02-16 Nov-28-16 5 5 0 Dec-07-16 Dec-02-16A6100 Form closing and Bracing Not Started Dec-15-16 Dec-10-16 2 2 0 Dec-16-16 Dec-12-16A6110 Pouring Not Started Dec-17-16 Dec-13-16 1 1 0 Dec-17-16 Dec-13-16A6120 Deshuttering Not Started Dec-19-16 Dec-14-16 0 0 0 Dec-19-16 Dec-14-16
ReinforcementReinforcementReinforcement Dec-09-16 Dec-05-16 5 5 0 Dec-14-16 Dec-09-16A6090 Reinforcement Not Started Dec-09-16 Dec-05-16 5 5 0 Dec-14-16 Dec-09-16
HorizontalsHorizontalsHorizontals Dec-19-16 Dec-14-16 9 9 0 Dec-30-16 Dec-24-16FormingFormingForming Dec-19-16 Dec-14-16 9 9 0 Dec-30-16 Dec-24-16A2610 Concrete outline layout Not Started Dec-19-16 Dec-14-16 1 1 0 Dec-19-16 Dec-14-16A2620 Setting ( Flying ) Tables and Forming Not Started Dec-20-16 Dec-15-16 3 3 0 Dec-22-16 Dec-17-16A2650 Bracing Not Started Dec-28-16 Dec-22-16 1 1 0 Dec-28-16 Dec-22-16A2660 Pouring Not Started Dec-29-16 Dec-23-16 1 1 0 Dec-29-16 Dec-23-16A2670 Deshuttering Not Started Dec-30-16 Dec-24-16 0 0 0 Dec-30-16 Dec-24-16
ReinforcementReinforcementReinforcement Dec-23-16 Dec-19-16 3 3 0 Dec-27-16 Dec-21-16A2630 Reinforcement - Bottom Not Started Dec-23-16 Dec-19-16 1 1 0 Dec-23-16 Dec-19-16A2640 Reinforcement - Top Not Started Dec-27-16 Dec-21-16 1 1 0 Dec-27-16 Dec-21-16
P1P1P1 Dec-30-16 Dec-24-16 29 29 0 Feb-02-17 Jan-28-17VerticalsVerticalsVerticals Dec-30-16 Dec-24-16 10 10 0 Jan-11-17 Jan-06-17FormingFormingForming Dec-30-16 Dec-24-16 10 10 0 Jan-11-17 Jan-06-17A6010 Concrete outline layout Not Started Dec-30-16 Dec-24-16 1 1 0 Dec-30-16 Dec-24-16A6020 Forming Not Started Dec-31-16 Dec-27-16 3 3 0 Jan-04-17 Dec-29-16A6040 Form closing and Bracing Not Started Jan-07-17 Jan-03-17 2 2 0 Jan-09-17 Jan-04-17A6050 Pouring Not Started Jan-10-17 Jan-05-17 1 1 0 Jan-10-17 Jan-05-17A6060 Deshuttering Not Started Jan-11-17 Jan-06-17 1 1 0 Jan-11-17 Jan-06-17
ReinforcementReinforcementReinforcement Jan-06-17 Dec-31-16 1 1 0 Jan-06-17 Dec-31-16A6030 Reinforcement Not Started Jan-06-17 Dec-31-16 1 1 0 Jan-06-17 Dec-31-16
HorizontalsHorizontalsHorizontals Jan-12-17 Jan-07-17 19 19 0 Feb-02-17 Jan-28-17FormingFormingForming Jan-12-17 Jan-07-17 19 19 0 Feb-02-17 Jan-28-17A2680 Concrete outline layout Not Started Jan-12-17 Jan-07-17 3 3 0 Jan-14-17 Jan-10-17A2690 Setting ( Flying ) Tables and Forming Not Started Jan-16-17 Jan-11-17 3 3 0 Jan-18-17 Jan-13-17
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2016 2017 2018
Reinforcement Wall s - Zone 1,2,3Nov-26-16, HorizontalsNov-26-16, Forming
Concrete outline layoutSetting ( Flying ) Tables and Forming
BracingPouringDeshuttering
Nov-21-16, Reinforcement
Reinforcement - BottomReinforcement - Top
Dec-24-16, P2Dec-14-16, VerticalsDec-14-16, Forming
Concrete outline layoutForming
Form closing and BracingPouringDeshuttering
Dec-09-16, Reinforcement
ReinforcementDec-24-16, HorizontalsDec-24-16, Forming
Concrete outline layoutSetting ( Flying ) Tables and FormingBracingPouringDeshuttering
Dec-21-16, Reinforcement
Reinforcement - BottomReinforcement - Top
Jan-28-17, P1Jan-06-17, VerticalsJan-06-17, Forming
Concrete outline layoutFormingForm closing and BracingPouringDeshuttering
Dec-31-16, Reinforcement
ReinforcementJan-28-17, HorizontalsJan-28-17, Forming
Concrete outline layoutSetting ( Flying ) Tables and Forming
Detailed Construction ScheduleMourad Eldeeb
Oct. 01 2016
Date Revision Checked Approved Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity ID Activity Name Activity Status
BL1 Start Planned Start
Actual Start
BL1Duration
Original
Duration
ActualDuration
BL1 Finish
Planned Finish
Actual Finish
QA/QC Safety
A2720 Bracing Not Started Jan-26-17 Jan-21-17 3 3 0 Jan-28-17 Jan-24-17A2730 Pouring Not Started Jan-30-17 Jan-25-17 3 3 0 Feb-01-17 Jan-27-17A2740 Deshuttering Not Started Feb-02-17 Jan-28-17 1 1 0 Feb-02-17 Jan-28-17
ReinforcementReinforcementReinforcement Jan-19-17 Jan-14-17 6 6 0 Jan-25-17 Jan-20-17A2700 Reinforcement - Bottom Not Started Jan-19-17 Jan-14-17 2 2 0 Jan-20-17 Jan-16-17A2710 Reinforcement - Top Not Started Jan-23-17 Jan-18-17 3 3 0 Jan-25-17 Jan-20-17
L1L1L1 Feb-02-17 Jan-28-17 23 23 0 Mar-01-17 Feb-24-17VerticalsVerticalsVerticals Feb-02-17 Jan-28-17 8 8 0 Feb-13-17 Feb-07-17FormingFormingForming Feb-02-17 Jan-28-17 8 8 0 Feb-13-17 Feb-07-17A5950 Concrete outline layout Not Started Feb-02-17 Jan-28-17 1 1 0 Feb-02-17 Jan-28-17A5960 Forming Not Started Feb-03-17 Jan-30-17 3 3 0 Feb-06-17 Feb-01-17A5980 Form closing and Bracing Not Started Feb-10-17 Feb-04-17 1 1 0 Feb-10-17 Feb-04-17A5990 Pouring Not Started Feb-11-17 Feb-06-17 1 1 0 Feb-11-17 Feb-06-17A6000 Deshuttering Not Started Feb-13-17 Feb-07-17 0 0 0 Feb-13-17 Feb-07-17
ReinforcementReinforcementReinforcement Feb-09-17 Feb-03-17 1 1 0 Feb-09-17 Feb-03-17A5970 Reinforcement Not Started Feb-09-17 Feb-03-17 1 1 0 Feb-09-17 Feb-03-17
HorizontalsHorizontalsHorizontals Feb-13-17 Feb-07-17 15 15 0 Mar-01-17 Feb-24-17FormingFormingForming Feb-13-17 Feb-07-17 15 15 0 Mar-01-17 Feb-24-17A2750 Concrete outline layout Not Started Feb-13-17 Feb-07-17 1 1 0 Feb-13-17 Feb-07-17A2760 Setting ( Flying ) Tables and Forming Not Started Feb-14-17 Feb-09-17 3 3 0 Feb-16-17 Feb-11-17A2790 Bracing Not Started Feb-24-17 Feb-20-17 3 3 0 Feb-27-17 Feb-22-17A2800 Pouring Not Started Feb-28-17 Feb-23-17 1 1 0 Feb-28-17 Feb-23-17A2810 Deshuttering Not Started Mar-01-17 Feb-24-17 1 1 0 Mar-01-17 Feb-24-17
ReinforcementReinforcementReinforcement Feb-17-17 Feb-13-17 6 6 0 Feb-23-17 Feb-18-17A2770 Reinforcement - Bottom Not Started Feb-17-17 Feb-13-17 2 2 0 Feb-18-17 Feb-14-17A2780 Reinforcement - Top Not Started Feb-21-17 Feb-16-17 3 3 0 Feb-23-17 Feb-18-17
Town house 1Town house 1Town house 1 Mar-01-17 Feb-24-17 15 15 0 Mar-17-17 Mar-13-17VerticalsVerticalsVerticals Mar-01-17 Feb-24-17 7 7 0 Mar-08-17 Mar-03-17FormingFormingForming Mar-01-17 Feb-24-17 7 7 0 Mar-08-17 Mar-03-17A5890 Concrete outline layout Not Started Mar-01-17 Feb-24-17 1 1 0 Mar-01-17 Feb-24-17A5900 Forming Not Started Mar-02-17 Feb-25-17 1 1 0 Mar-02-17 Feb-25-17A5920 Form closing and Bracing Not Started Mar-06-17 Mar-01-17 1 1 0 Mar-06-17 Mar-01-17A5930 Pouring Not Started Mar-07-17 Mar-02-17 1 1 0 Mar-07-17 Mar-02-17A5940 Deshuttering Not Started Mar-08-17 Mar-03-17 1 1 0 Mar-08-17 Mar-03-17
ReinforcementReinforceme