Upload
jsrilakshmi4272
View
218
Download
0
Embed Size (px)
Citation preview
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 1/8
Embedded generation
Voltage rise
the big issue when
c
nnecting
embedded generat on to long
11 k V
overhead lines
There has recently been much interest in embedding sma ll generator s deep within
distribution systems. The steady-state voltage rise resultingfrom the connection
of
these gener ators ca n be
a
ma jor obstacle to the ir connection
at
the lower voltage
levels. This article sum marises the results of some generic studies, explaining this
voltage rise issue and how it ma y be overcome.
by C. L. Masters
here has recently been much interest in
connecting small generators, between
200kW and lOMW, deep within distri-
T
ution systems. These networks are,
by tradition, passive networks. They were
designed to pass power from the national
grid system, down the voltage levels, to LV
customers. They were generally not designed
for the connection
of
generators. There are
many technical issues that must be considered
when connecting a generating scheme to the
distribution system, such as:
thermal rating of equipment
system fault levels
stability
reverse power
flow
capability of tap-changers
line-drop compensation
steady-state voltage rise
losses
power quality (such as flicker, harmonics)
protection.
This article concentrates on the steady-state
voltage rise that occurs when connecting
small generators to
l l k V
networks and often
seriously impacts on the technical feasibility of
such schemes.
Allowable voltage variations
The Electricity Supply Regulations’ stipulate
that, unless otherwise agreed, the steady-state
voltage
of
systems between l OOOV and 132kV
should be maintained within
+6%
of the
nominal voltage. For systems above 50V and
below lOOOV , variations of between +lo%
and -6% of nominal voltage are permitted.
Prior to the
1994
amendments, variations of
+6% were permitted. This change was a result
of proposals to harmonise the UK electricity
system with those in Europe.
The Electricity Supply Regulations are soon
to be replaced with the Electricity Safety,
Quality and Continuity Regulations.’ They
were due to come into force in October 2001,
but have been delayed due to the numerous
comments made during the consultation
process. The Electricity Safety, Quality and
Continuity Regulations do not propose to
make any immediate changes to the permitted
voltage variations. However, it is proposed
that, with effect from January 2003, the
permitted voltage variations for systems
between
50V
and lOOOV will change to
+lo .
It is the Distribution Network Operator’s
(DNO’s) responsibility to ensure that its
systems are operated within the limits
permitted by the Electricity Supply Regula-
tions. However, at the planning stage, the
l k V
system is often designed to maintain voltages
within *3% of nominal,
so
that the voltage
variations seen by the LV connected customers
remain within the permitted +lo and -6%
limits.
When a generator is to be connected to the
distribution system, the DNO will consider
POWER ENGINEERING JOUR NAL FEBRUARY 2002
5
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 2/8
Embedded generation
1 Voltage profile along
the heavily loaded
11kV
overhead line used
in
the example
primary
substation
IO
r
ominal voltage at primary substation
03 of nominal voltage at primary substation
06 of nominal voltage at primary substation
+6 voltage limit
1 6
1 4
102
1
98
96
94
92
I
I I
I
0 4 8 12 16 2
distance from the primary substation, km
the worst case operating scenarios and ensure
that their network and customers will not be
adversely affected. Typically, these scenarios
are:
no generation and maximum system demand
maximum generation and maximum system
maximum generation and minimum system
demand
demand.
Some
DNOs
take into account the diversity
of
the local load and consider the system with the
minimum expected demand. Others do not,
and assume no load
as
the worst case scenario.
Distribution system s with no embedded
generation
To transmit power from an l l k V primary
substation to
a
typical LV connected customer
some distance away will require the voltage
at the primary substation to be higher than
the voltage at the point of connection
of the customer to the 11 kV system. This
is
explained using Panel 1.
Generally the X/R ratio of an ll kV overhead
line tends to be low,so neither
of
the terms R
or X Q can be neglected. This, coupled with the
fact that the reactive power pushed down the
line is usually much lower in magnitude than
the power (assuming the customer imports
reactive power), leads to there being a voltage
drop along the line from the primary substation
to the point of connection
of
the customer.
To demonstrate this, consider the following
example (Fig. 1 : connected to a primary
substation is a 2Okm long, 1 l k V overhead line ,
comprising 16mm2 copper conductors . Every
4km along the line is a three-phase load of
lOOkW
and 20kvar. As the distance from the
primary substation increases the voltage falls.
With the primary substat ion at nominal voltage
(Il kV) , the far end
of
the line
fal ls
to 10.3kV
(6% below the nominal voltage). This is right
on the permitted limit. If the line had been
longer or the load greater, the voltage would
have fallen even further.
To maintain system voltages within permit-
ted limits, DNOs often maintain primary
substations above nominal voltage using
automatic voltage control (AVC), on-load
tap-changers and line-drop compensation.
POWER ENGINEERING JO URN AL FEBRUARY 2002
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 3/8
Embedded generat ion
where
VPS is the primary sub station voltage
VC is the vol tage at the customer connect ion p oint
R,
X
are the resistance and reactance
of
the overhead line
P, Q
are the power and r eactive power transm itted
from
the primary substation nto the overhead line
Controlling the primary substation, in this
example, to
103%
and
106
of
nominal voltage
(11.3 kV and 11.7 kV) maintains the end of the
l lkV line well within the permitted voltage
limits.
Although the Electricity Supply Regulations
allow voltage variations on the
11kV
system of
c6 , D N O s often impose limits of *3 at the
planning stage. This is in order to maintain
the LV connected customers within the
permitted + lo and -6% of nominal voltage.
In this generic study the +3 planning limit is
ignored. The
l l k V
system voltages are allowed
to
vary by +6% of nominal voltage, to more
clearly demonstrate the effect of connecting a
generator.
Effect of connecting generation to
distribution systems
Connecting a generator to the distribution
system will affect the flow of power and the
voltage profiles. To export its power, a genera-
tor is likely to have to operate at a higher
able to absorb a significant amount of reactive
power. This is explained using Panel
2.
As the
XIR
ratio of the l l kV line is small,
neither
R P
nor X Q is negligible. The XQ term
may be positive or negative, depending on
whether the generator is exporting or
importing reactive power. However, as the
magnitude of the reactive power will be small
compared to that of the power (unless some
form of compensation is used), the RP XQ
term will tend to be positive. Thus , the voltage
at the point
of
connection of the generator to
the l l k V system will rise above that of the
primary substation.
To demonstrate this, a 300kW generator
(operating at unity power factor) is connected
l2km from the primary substation (controlled
at 103% of nominal voltage). The output of the
generator is equal to the downstream demand,
so the direction of the power flow from the
primary substation is not altered. The voltage
falls as the distance from the primary sub-
station increases, as before. But the magnitude
voltage than the primary substation, unless it is
of the voltage drop
is
less profound (Fig. 2).
-- I _ _ _ _ _I I - . I ___
where
VG N
t
PS
VPS
is the primary substation voltage I
VG N
IS
the voltage at the generator connection point
R X are the resistance and reactance
of
the overhead line
P Q
are the power and reactive power transmitted from
the generator into the overhead line
I . . ..
....
POWER ENGINEERING JOURNA L FEBRUARY
2002
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 4/8
Embedded generation
o generation
00
kW
generator
MW
generator
/
g 109
<
107
._ 105
E
103
101
-
979 0 12 16 20
0 4 8
12 16 20
no demand on the lineull demand on the line
distance from the primary substation, km
2
Effect of connecting
a
Increasing the generation to 1MW reverses
- -
generator On thevoltage
profile along the 11kV
line
used
n the
the flow of power along the line, from the
generator towards the primary substation.
The voltage at the generator rises above that
elsewhere, thus allowing the power to be
exported in both directions. In this example,
the voltage in some parts of the system rises
above the permitted +6%voltage limit.
The voltage rise is more onerous when
there is no demand on the system,
as
all
the generation is exported back to the
primary substation. With 1MW of generation
connected, the voltage rises to 112% of
nominal. This suggests that it
is
the voltage rise
during periods of no/minimum demand that
limits how much generation can be connected.
When connecting
a
generator to the distri-
bution system, a
D N O
must consider whether
3
the power may be exported back through the
primary substation primary substation and must ensure that
ru r l
311 1kV
the transformer's tap-changers are capable of
operating with a reverse power flow.
How
can this voltage rise be counteracted?
If the connection of a generator to an 11 kV
overhead line causes an excessive voltage
rise, there are several techniques that can
be employed to alleviate the situation, for
example:
reduce the primary substat ion voltage
allow the generator to import reactive power
(reducing the RP+XQ term)
install auto transformers, or voltage regu-
lators as they are often called, along the line
(resetting the voltage along the line)
increase the conductor size (reducing the
resistance)
constrain the generator at times of low
demand (reducing the transmitted power)
a combination of the above.
Reduce the primary substation voltage
It is common practice for
DNOs
to maintain
llkV primary substations above nominal
voltage to ensure that system voltages remain
within the permitted
-6%
voltage limit. In the
previous example, the voltage at the 1MW
generator is 109% of nominal (under full-
load conditions). Lowering the voltage at the
primary substation from
103%
to 100% of
nominal reduces the voltage rise to just below
the permitted +6%voltage limit (Fig. 4). I t
also
reduces the voltage during periods of no
system demand to around 110% of nominal,
which is not sufficient.
Before lowering the voltage at
a
primary
substation, a D N O must ensure that it will not
adversely impact on any of its customers. If
there are other feeders connected to the
primary substation or teed off the l l k V line,
the voltage profile along these circuits may be
depressed. This may reduce the voltage of the
LV customers connected to these feeders below
the permitted
-6%
limit.
Also, if the generator is not exporting power,
the system voltages will be depressed. In this
example, the primary substa tion is maintained
at 103%of nominal to ensure that the voltage
2Okm away is satisfactory. If the primary
substation voltage is reduced to l l kV in order
to connect the generator, the voltage at the end
of the line will drop to 94% of nominal
whenever the generator is not export ing power.
The D N O must consider how it will correct this
voltage depression. One solution may involve
POWER ENG
N
EERlNG JOURNAL FEBRUARY
2002
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 5/8
Embedded generation
xample system
ffect of reducing primary substation to nominal voltage
ffect of the generator operating at
0
9
power factor leading
ffect of installing an auto transformer,
8 km
from the
ffect of upgrading he line with 70mm copper conductor
ffect of constraining the generator
primary substation
110
...
+6 volta
I I I I I I I I I
0 4 8 12
16
20 4 8 12
16
2
full demand on the line no demand on the line
distance from the primary substation,km
customer minutes lost while the off-circuit
tap-changers are reset on the 11/0-415kV
distribution transformers. However, this may
not be practical if there are long lines or many
distribution transformers involved.
Import reactive power
DNOs may stipulate that generators operate at
leading, lagging or even unity power factor,
depending on the
X / R
ratio of the system,
voltage regulation, local load etc. Generators
are typically operated at a power factor such
that if they trip, when at rated generation, the
disturbance to the system is minimised.
The amount of reactive power that can
be imported is generally governed by the
parameters of the generator. Typically a
synchronous generator can import reactive
power at a 0.95 power factor. Wind turbines,
with uncompensated induction generators, can
import reactive power at around a 0.9 power
factor.
In the initial example the 1MW generator
operates at unity power factor. The voltage
rises to almost 109% of nominal (under full
load conditions) and 113% of nominal (under
no load conditions). Allowing the generator to
operate at a leading power factor of 0.9 limits
the voltage rise to
104%
and 108%of nominal,
respectively (Fig. 4). With maximum demand
on the system, this brings the voltages within
the permitted +6% voltage limit. During
periods
of
no system demand, the voltage is not
Effect of using various
methods to r educe he
voltage rise on the 11kV
line used in the example
lowered sufficiently.
If a generator is to import significant levels
of reactive power, it may be necessary to agree
a charging mechanism with a supplier to cover
the costs involved with purchasing and
transporting
these extra kvars. The
DNO
must
also consider the effect that this additional
reactive power flow
will
have on system losses
and the loading on circuits. The effect
of
the
generator tripping must also be considered, as
this will cause a transient voltage rise. It may
take the transformer tap-changers at the
primary substation several seconds to respond
and restore the voltages. Under such circum-
stances a DNO may be able to use a switched
'capacitor bank or some other form of reactive
5
Typical rur l l k v
overhead line
POWER ENGINEERING JOURNA L FEBRUARY 2002
9
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 6/8
Embedded generation
6
Some
guidance as to
the
level
of generation
that can be accepted
onto
an 11kV overhead
line
6
mm2
conductor, 11 kV at primary substation
6 mm2conductor, 11.3 kV at primary subs tation
6 mm2 conductor, 11.6 kV at primary substation
70 mm2 conductor, 11 kV at primary substation
70 mm conductor, 11.3 kV at primary substation
70 mm2
conductor, 11.6 kV at primary substation
2 4 6 8 IO 12 14 16 18 20 22 24 26 28 30
dis tance, km
power compensation to restore the system
voltages.
Install auto transformers along the line
Auto transformers (voltage regulators or
voltage boosters) are simply transformers with
a voltage ratio of 1:land on-load tap-changers
for voltage regulation. Essentially, inserting an
auto transformer into a long circuit splits it into
two sections. The voltage along one section
will be regulated by the AVC, tap-changers
and line-drop compensation at the primary
substation. The auto transformer will regulate
the voltage along the other section.
Inserting an auto transformer 8km from the
primary substation, in the initial example, has
little effect on the voltage profile between itself
and the primary substation. Under full and
no load conditions the primary of the auto
transformer rises to 106% and 109% of
nominal voltage, respectively
(Fig. 4).
The on-
load tap-changer, in this example, is set to
control the voltage at the secondary of the auto
transformer to nominal voltage (using a tap
range of
~ 5
n five steps). Under both full and
no load conditions it operates to reduce the
voltage to 101%of nominal, thus maintaining
the voltage rise along the remainder of the
llkV line below the permitted +6% voltage
limit. In this example, the auto transformer
does not prevent this limit being exceeded
when there is no demand. However, by careful
positioning of either one or two auto
transformers, the voltages may be maintained
within limits.
Auto transformers have not traditionally
been used by
DNOs
in this manner because
there has been little generation connected to
the distribution system. However, as the levels
of embedded generation are set to increase
their use may become more common.
When installing an auto transformer into the
distribution system the
DNO
must consider its
effect' on the system voltages under all the
worst case operating scenarios to ensure that
no customers will be adversely affected. The
effect of the auto transformer on the line
loading must also be taken into account, as it
may increase the flow of reactive power along
the line. The
DNO
must also consider how the
presence of the auto transformer will affect
system security, as it will introduce another
factor of unreliabil ity into the sys tem.
Upgrade
the conductor
Small overhead line conductors have higher
impedance than large conductors. A 70mm2
copper conductor has approximately one-third
of the resistance and 90% of the reactance of
a 16mm2conductor. Thus, upgrading the con-
ductor on an llkV overhead line will signifi-
cantly reduce its resistance and will smooth the
voltage profile along the line.
In the initial example, the voltage at the
1MW generator was 109% of nominal (under
full load conditions) and 113% of nominal
10
POWER ENGINEERING JOUR NAL FEBRUARY
2002
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 7/8
Embedded generation
(under no load conditions). The voltage profile
along the line is improved by replacing the
16mm2conductor with 70mm2copper (Fig. 4).
It reduces the voltage at the generator to
less than 105% of nominal (under full load
conditions). With no demand on the line, it is
marginally above the permitted +6% voltage
limit.
This suggests that upgrading the conductors
is
a very effective method of counteracting the
voltage rise problem. However, replacing the
conductors can be expensive and may make a
scheme uneconomic.
Constrain the generation
The sophisticated control systems available
these days will allow a generator to control i ts
output in line with the system voltage. Thus if
the voltage is approaching the permitted +6%
voltage limit, a generator can reduce its output
in order to maintain the voltage below the
threshold. This will allow the generator to
continue operating, rather than being con-
strained off during periods of low system
demand. Conversely, should the system voltage
fall below nominal, a generator may be able to
respond by increasing its output.
The initial example suggests that the 1MW
generator cannot be accepted onto the llkV
line, even when it is fully loaded. Its output has
to be constrained to 750kW to maintain the
system voltages within the permitted +6% limit
(Fig. 4). It will have to be constrained further
as the system loading
is
reduced. Under no load
conditions the generator has to be constrained
to 300kW to maintain the voltages below the
permitted +6%threshold.
Constraining an embedded generator will
obviously affect the economic benefit of the
scheme. It is usually only-aviable option when
the constraints are expected to be infrequent
and where significant system reinforcement
costs are avoided.
How much generation can be connected to
an
kV
overhead line?
The level of generation that can be absorbed
onto the distribution system is determined by
many factors, such as:
voltage level
voltage at the primary substation
distance from the primary substation
size of conductor
demand on the system
other generation on the system
operating regime of the generation.
Fig. 6 gives some indication as to the amount
of generation that can be connected to an 11kV
overhead line. It is clear that, as the distance
from the primary substation increases, the
amount
of
generation that can be accepted
reduces.
Case studies
Three brief case studies are presented here to
show how Innogy plc has approached this
voltage rise issue when developing small
generating schemes.
ChiRex.CHP scheme
The ChiRex combined heat and power (CHP)
scheme in Northumberland (Fig. 7) comprises
a 4.5MW gas turbine. It has been operational
since June 1994, providing electricity and
steam to the ChiRex pharmaceutical plant.
Both are normally connected to the llkV
primary substation by a single ll k V cable.
During some periods, such as Christmas, the
demand at the pharmaceutical plant falls
dramatically, and the CHP scheme exports the
majority of its power into the distribution
system. This causes the voltage to rise and the
generator was once tripped off by the
overvoltage protection.
This problem was overcome by altering the
operating procedure of the CHP scheme. The
output and power factor of the generator are
7 ChiRexCHPscheme
a
POWER ENGINEERING JOUR NAL FEBRUARY 2002
1 1
7/24/2019 DG 3 Voltage Rise
http://slidepdf.com/reader/full/dg-3-voltage-rise 8/8
Embedded generation
8 Typical small hydro
generating scheme
Blantyre, Scotland)
now manually adjusted by the operators who
monitor the local demand and the system
voltage.
9 Jenbacher gas
engine, produced by
Clarke, or small
embedded generation
schemes photo:
courtesyof Clarke
Energy, www.clarke-
energy.co.uk)
I
500k
W hydro-generating scheme
Innogy Hydro is in the early stages of
developing a 500kW hydro-generating scheme
in the north of Scotland (Fig. 8).The generator
is to be connected to an l l k V overhead
line, comprising 16 copper conduc tors,
approximately 15km from the primary
substation. Also connected to this 1lk V line
are numerous domestic customers fed by
individual 1U0.415 kV distribution trans-
formers with off-circuit tap-changers.
The DNO has stipulated that the voltage
along this l l kV line must not exceed 11.13 kV
(1.2 above nominal voltage) as th is will raise
customers' voltages above 53\3 the +lo%
tolerance specified in the Electricity Supply
Regulations.
Provisional studies have shown that the
existing llkV system cannot accept 500kW
of generation. Reducing the voltage at the
primary substation is not feasible, as there are
other l l k V circuits connected to the primary
subst ation. Upgrading the line with 70
copper conductors increases the amount of
generation that can be connected, but not
sufficiently.
I
The cost and feasibility of two methods of
overcoming the voltage rise problem are
currently being considered-installing reactive
power compensation at the generator, or an
auto transformer part way along the 11kV line.
1OMW mines gas generating scheme
Cogen, an Innogy subsidiary, is currently
developing a lOMW generating scheme to bu rn
methane gas from a disused coal mine. The
scheme will comprise two 5MW plants (Fig. 9)
connected separately to two existing llkV
cables that run along the edge of the proposed
site. Studies have shown that the generation
cannot be accepted onto the existing system
due to the excessive voltage rise.
The local DNO currently operates the
primary substation at 11.6kV. Following tests
on the system, the DNO has agreed to reduce
the primary substation voltage to 11.3kV
so
the
generation can be connected. However, should
the generating scheme be out of service, the
system voltages will be depressed and the
voltage of a few customers will fall below the
permitted limit. As the generating scheme is
expected to operate at base load, this scenario
will not occur frequently. It has been agreed
that, when this does occur, the DNO will
dispatch an engineer to manually alter the
distribution transformers' tap-changers and
'the DNO will be compensated appropriately by
Innogy.
Conclusions
In conclusion, there are many factors that
determine the level of generation that can be
connected to the distribution system at 1lkV
Thus every scheme will face different technical
and commercial issues and must be studied on
a site-by-site basis. One of the major technical
difficulties is the voltage rise resulting from the
reversed power flow. There are methods of
counteracting this voltage rise; however, a
developer must consider whether the addi-
tional costs are justified.
References
1 The Electricity Supply Regulationsl988: Regulation
30, paragraph 2, amended in 1994
2 The Electricity Safety, Quality and Continuity
Reg ulation s. 2001: Draft copy-available for con -
sulta tion purposes on the D TI wehsite
IEE: 2002
Dr C. L. Masters is a Power Systems Engineer in
Operations and Engineering, lnnogy plc. She is a
Member of the IEE.
12
POWER ENGINEERING JOURNAL FEBRUARY
2002