01.00 SCOPE OF WORK 01.01 Scope of work includes design, engineering, manufacture, shop tests / tests at recognized Test centres, arranging inspection, packing, insurance, forwarding, transport and delivery at purchaser’s stores of 02 set of 3000A, 415V Non-segregated TPN Al. Busduct along with all fittings and accessories as per specification and supervision of erection, testing & commissioning. 01.02 Exclusions Following are excluded from Contractor’s scope : Provision of civil works Auxiliary supply Erection, testing and commissioning 02 TECHNICAL SPECIFICATION 03 L.T. BUSDUCT 04.01 General Busduct shall be indoor type non-segregated metal enclosed TPN, 415V suitable for connection between LT 1250KVA Diesel generator control panel and the incomer panel of the LT switchboard. The basic requirements of the busduct shall be as specified. 04.02 Type of busduct The busduct shall be rectangular, non-segregated, totally enclosed type with suitable fibre glass / SMC insulating

DG Busduct[1]

Embed Size (px)

Citation preview

Page 1: DG Busduct[1]

01.00 SCOPE OF WORK

01.01 Scope of work includes design, engineering, manufacture, shop tests / tests at recognized Test centres, arranging inspection, packing, insurance, forwarding, transport and delivery at purchaser’s stores of 02 set of 3000A, 415V Non-segregated TPN Al. Busduct along with all fittings and accessories as per specification and supervision of erection, testing & commissioning.

01.02 Exclusions

Following are excluded from Contractor’s scope :

Provision of civil works Auxiliary supply Erection, testing and commissioning

02 TECHNICAL SPECIFICATION

03 L.T. BUSDUCT

04.01 General

Busduct shall be indoor type non-segregated metal enclosed TPN, 415V suitable for connection between LT 1250KVA Diesel generator control panel and the incomer panel of the LT switchboard. The basic requirements of the busduct shall be as specified.

04.02 Type of busduct

The busduct shall be rectangular, non-segregated, totally enclosed type with suitable fibre glass / SMC insulating supports for aluminium busbars and suitable for continuous operation in solidly earthed neutral system.

04.03 Busbars

Busbars shall be made of E91E grade aluminium alloy. Cross section of busbars selected shall ensure temperature rises of busbars, joints and enclosures within

Page 2: DG Busduct[1]

specified limits at rated currents. Neutral busbars where provided shall have a minimum rating of 50% of main busbars. In addition, it shall withstand mechanical force for specified peak short circuit currents and have 1sec. short circuit thermal rating at specified short circuit current for 3 phase, phase to phase and phase to ground/ neutral faults. A current density of 0.8A/ Sq.mm shall be considered for sizing the busbars. In case, a lower size is offered the same will be subject to temperature rise and short circuit test for acceptable limiting values specified.

Busbar surfaces shall be tinned at joints, high tensile cadmium plated bolts with suitable spring washers shall be used for busbar joints. Prior to jointing, oxide-in-hibiting grease shall be applied after cleaning the surfaces.

Phase to phase and phase to ground clearances in air shall not be less than 25.4mm and 19mm respectively.

Busbars shall be identified by colour code for phase sequence at the ends of each factory built busduct length.

Bimetallic joints shall be provided for jointing between dissimilar metals. Provision shall be made to allow for expansions and contractions of busbars caused by temperature variation.

04.04 Constructional features

The busduct shall have rectangular enclosure with 3 phase and neutral busbars supported on fibreglass insulation supports.

The busducts shall be factory built and supplied in fully assembled standard lengths and matching non-standard lengths as required. The busduct enclosure shall be supported on framed constructions with necessary mounting brackets for supporting from a wall or roof or from ground. Mounting brackets shall be supplied along with the busduct. Inspection openings and access covers shall be provided to facilitate maintenance of busbar joints, insulation supports. Alternately the enclosure may be made in split covers with bolted joints. All joints and covers shall have heat resistant gaskets.

Anti-condensation space heaters shall be provided at appropriate locations and wired to external terminal box with heat resistant cables.

Suitable provision shall be made in the busbars at the point of joining the factory made sections, to slightly increase or decrease the assembled busbar length, by

Page 3: DG Busduct[1]

telescoping before bolting. The busduct construction shall be mechanically strong to ensure safe transport and handling.

04.05 Matching

The busducts are to be suitably matched to the busduct termination facilitaties provided at transformer and LT switchboard ends. Phase sequence shall be matched at both ends and if required phase cross over shall be supplied.

04.06 Enclosure

The busduct enclosure shall be made of aluminium. Busducts rated above 2000A shall have aluminium enclosure. The busduct enclosure shall be strong enough to withstand the designed short circuit forces. The busduct shall conform to IP-52 enclosure. Thickness of enclosure shall not be less than 3mm.

04.07 Painting

All runs of conductors shall be identified by painting with heat resisting paint at the extreme ends and at regularly spaced intervals. The paint shade shall be as specified.

04.08 Accessories

The busduct shall be supplied complete with the following accessories wherever required to make the installation complete.

Generator lead in section with aluminium flexibles terminal connection. Straight sectionMatching section (length as required)Corner sections (horizontal or vertical 90 deg. bends)Switchgear lead in section with aluminium flexible terminal connection.Phase cross oversRoof/wall/ floor supports or hanger barsGround bus

Aluminium bus of specified cross section shall run through the whole length of the busduct and shall be positively connected to the body of the busduct enclosure and to the ground system of the shop.

Drawings

Page 4: DG Busduct[1]

The following drawings shall be submitted for approval. Schedule of submission of drawings shall be as specified.Dimensional busduct layout plan and section drawings indicating straight section, bends, end terminations, support points, inspection openings. Dimensional bus duct cross section drawing indicating support insulators, clearances.GA drawings of standard length, bends, non standard lengths of bus duct.Details of end terminations at both ends of busduct.Maintenance manual.Any other drawings required.Calculations for temperature rise and short circuit withstand capability.

Test Requirements

Tests at works shall include the following

Insulation resistance measurement1 minute PF withstand voltage testDimensional check, Physical inspection of clearances, phase sequenceResistance measurement and reactance measurement per meter.

05.00 DESIGN CRITERIA

LT BUSDUCT

1. Applicable standards : 8623 –Part –II-19932. Supply System : 440V Max3. System earthing : Solidly earthed 4. Service : Indoor5. Design ambient temp. : 450C6. Rated voltage & frequency : 415V, 50 Hz.7. Current rating

Continuous rating at specified ambient temp. (rated current)

: 3000 A

Page 5: DG Busduct[1]

8. Dynamic stability current Short time short circuit current rating

::

105kA(Peak)50kA for 1 sec.

9. Busbar material Current density at rated current

::

Aluminium0.9A/sq.mm(max) subject to verification by heat run test

10. Earth bus material & cross section : Aluminium11. Busbar jointing

Surface treatmentBolts & washersBimetallic joints

:::

TinnedCadmium plated boltsTo be provided wherever required

12. Type of enclosure as per IS Material of enclosureThickness of material

:::

IP 52Aluminium3 mm for Aluminium

13. Max. rise of temp. under full load over specified ambient temp.Busbars EnclosureAt joints

:::

400C over 450C250C over 450C400C over 450C

14. Type of end terminationsTransformer end Switchgear end

::

Aluminium flexible -do-

15. Provision of space heater Rated voltage

::

Not applicableNot applicable

16. Measurement of zero sequence impedence

: Not required

06.00 INSPECTION AND TESTING

06.01 Inspection of equipment by the Purchaser shall be only with a view to ensure that the equipment is fabricated/ manufactured, assembled, tested, supplied as per approved drawings and prescribed specifications.

06.02 Inspection by Purchaser shall in no way relieve the supplier of his responsibilities as per Contract and shall be in no way binding on the Purchaser.

Page 6: DG Busduct[1]

06.03 Contractor shall ensure inspection and testing of all the materials, equipment and work at his cost through his engineers and technical staff. Contractor shall also ensure proper supervision and quality assurance during progress of manufacture, erection, testing and commissioning.

06.04 All equipment and accessories forming part of this specification shall be subjected to inspection at contractor’s / sub-suppliers works at any stage of manufacture, by the duly authorised representative of the purchaser.

06.05 The contractors scope includes testing of equipment at manufacturer’s works.

06.06 The contractor shall not restrict himself to carrying out only the tests specified, but all tests as per IEC/ IS shall satisfactorily be conducted on each equipment.

06.07 In case owner desires to conduct tests specifically not mentioned in this specification, to ascertain the quality of work done/ performance of equipment installed, the same shall be conducted by the contractor. In case if some of the tests are to be repeated , at the request of owner the same shall be carried out by the contractor at no extra cost.

06.08 In case of such plant and equipment, where tests set forth in the specification cannot be conducted either partially or fully in contractor’s premises but have to be conducted at site only after assembly/ erection, the provision under this section shall also apply. However, in such cases prior approval of the purchaser shall be obtained by the contractor.

06.09 Owner or his duly authorised representatives shall have at all times access to the contractor’s / his sub-supplier’s works and shall have the power to examine all the records and materials to monitor the progress of work and quality of materials and workmanship to ensure conformance to specification /standards.

Within 30 days of placement of order or as stipulated elsewhere in the contract, contractor in consultation with purchaser’s duly authorised representative shall draw up a preliminary inspection

Page 7: DG Busduct[1]

06.10 schedule to fix up the procedure and timing of inspection of the various equipment /component/ sub assemblies.

06.11 The contractor shall give the purchaser’s duly authorised representative a minimum of 15 days clear notice of any work being ready for inspection, enclosing internal test certificate. Thereafter purchaser/ his inspector shall carryout the inspection at supplier’s works.

06.12 The contractor shall furnish in advance test format for conducting tests at works as per specification and standards and 5 sets of final approved drawings/ documents to enable purchaser’s representative to carryout the inspection.

06.13 For all inspection and tests to be conducted at the suppliers premises, the contractor shall provide all the necessary tools, tackles, fuel, power, personnel and testing equipments free of cost to the owner’s representatives.

06.14 Contractor shall rectify/ replace the defective / rejected equipment/ component during testing and inspection.

06.15 The purchaser upon giving 7 days notice in writing and stating any grounds of objection, shall have the right to reject any or shall have the right to reject any or all the equipment or demand rectification or replacement thereof.

06.16 Incase any inspection/ tests fails, re-inspection/ retest shall be carried out after necessary rectification/ replacement by the contractor.

06.17 When the tests have been satisfactorily completed at contractor’s premises the owner’s representatives shall issue a certificate to that effect. No equipment shall be dispatched before issue of Inspection certificate.

06.18 The satisfactory completion tests or issue of inspection certificate by the owner’s representatives shall not bind the owner to accept the plant, should it, on further inspection/ testing at site be found not to comply with requirement or contract.

Page 8: DG Busduct[1]

06.19 The contractor shall ensure that no tests are applied which may stress equipment above the limits for field testing recommended by the manufacturer. The contractor shall be responsible for any damage to personnel or equipment resulting from improper test procedure.

06.20 All defective materials supplied by the contractor and defects due to poor workmanship revealed through field testing, shall be corrected at the contractor’s expense without affecting the milestone agreed upon.

06.21 The contractor shall bring his own testing equipment for testing and commissioning of equipments /items. List of such testing equipment shall be furnished along with the quotation.

06.22 The contractor shall provide purchaser with complete test certificates for all the equipment being supplied by him. The certificates shall be signed by both the contractor and the owner and the tests shall be completed under supervision of the owner.

06.23 Until the end of the guarantee period the contractor shall have the right of entry at his own risk and expense, by himself or his representative, at all reasonable working hours for the purpose of inspection/ testing with prior intimation to Purchaser

06.24 Tests to be conducted at works are indicated in the technical specifications.

07.00 DRAWINGS AND DOCUMENTATION

07.01 General

07.01.01 The scope of contractor includes supply of all drawings, documents, operation and maintenance manuals, catalogues, as built drawings of the plant, equipment supplied and work done, for comments/ approval/ information/ reference of purchaser/ consultant at no extra cost.

All drawings, specifications, furnished by the consultant shall be treated as strictly confidential property of the owner. All drawings &

Page 9: DG Busduct[1]

07.01.02 informations furnished by the contractor shall become property of the owner.

07.01.03 Drawings, specifications and schedule of quantities shall be treated as supplementary to each other and should anything appear in one that is not described in the other, no advantage shall be taken by the contractor for any such omission. For such discrepancy/ inconsistancy, the contractor shall seek the instructions from the consultant before proceeding with the work and the clarifications/ decisions given by the consultant shall be treated as final and binding on the contractor.

07.02 List of drawings

07.02.01 Within 15 days from the effective date of contract, the contractor shall submit requisite copies of a list of all drawings and documents he proposes to submit for the contract. The drawings shall be categorised into (a) For approval of purchaser (b) For purchaser’s information (c) As built drawings (d0 Operation and maintenance manuals and catalogue (e) manufacturing drawings.

07.02.02 The list shall be approved by the purchaser and may be revised or

extended if necessary for proper execution of work / documentation.

07.02.03 Each drawing and document in the list shall be identified as follows:

a) Serial numberb) Descriptive titlec) Proposed date of submission

07.03 Approval of drawing / documents / manuals

07.03.01 The contractor shall furnish drawings as indicated in technical specification for each item for approval of the purchaser/ consultant according to agreed time schedule

07.03.01.01 Contractor shall furnish, if requested, additional drawings, calculations, information to the consultant/ purchaser to enable him to examine/ study the drawings for approval.

Page 10: DG Busduct[1]

07.03.01.02 If incomplete drawings/ documents not meeting the consultants requirement are sent, the responsibility for any delay in approval shall be that of contractor.

07.03.01.03 Where drawings are returned to the contractor with “Commented”, the contractor shall resubmit the revised drawing for approval.

07.03.01.04 Where the drawings are returned to the contractor with marking “Approved as Noted”, contractor shall make the necessary modifications/ changes and resubmit revised drawings for final approval.

07.03.02 If any subsequent alterations are found necessary and approved by the consultant/ owner, all drawings and data affected by such alteration shall be duly revised and re-submitted for the approval of the engineer as said above.

07.03.03 Purchaser / his consultant will scrutinise drawings/ data furnished by contractor and comments, if any, will be communicated to the supplier within 2 weeks from the date of receipt.

In order to expedite the approval of drawings related to procurement / manufacture, contractor shall present the drawings to the purchaser /consultant and incorporate the necessary changes after discussions and obtain the approval.

07.03.04 Contractor shall be responsible for correctly incorporating all the points conveyed to him and resubmit the drawings to the purchaser for final approval.

07.03.05 If the contractor is unable to incorporate some of the comments, such

non-compliance shall be clearly stated in a forwarding letter with reasons without delay. However, it shall be purchaser’s / his consultant’s discretion to accept or reject the non-compliance.

07.03.06 Work shall be carried out exactly as indicated on the approved drawings and data and no alterations shall be made without the written approval of the Engineer /owner.

Approval of drawings by purchaser/ his consultant shall not relieve the supplier of his contractual obligations and responsibility for

Page 11: DG Busduct[1]

07.03.07 engineering, design, workmanship, materials and performance of the equipment.

07.04 As built drawings

07.04.01 All the drawings/ documents supplied by the contractor for purchaser’s comments/ approval, if required, shall be revised / modified, after purchaser/ consultant’s approval, to incorporate all the modifications / changes necessitated at various stages of execution of contract viz.,

During inspection & testing at works and site

During erection, commissioning of individual equipment

During integrated commissioning of total system

Due to changes in associated connecting equipment not supplied by the contractor (based on the information furnished by the purchaser / consultant)

07.04.02 Contractor shall furnish as –built drawings required for normal operation, maintenance, testing of all equipment in specified number of copies. All the approved drawings, manufacturer’s drawings, installation drawings are included in as-built drawing.

07.05 Documents and Test reports

07.05.01 Contractor shall furnish any relevant calculations asked for. It shall also contain the manufacturer’s catalogues, operation and maintenance manuals for all types of relays used.

07.05.02 Contractor shall furnish bound volumes of copies of factory routine

and type test certificates for all equipment.

After completion of site testing of all equipment, contractor shall furnish the site test results of all equipment. This shall also indicate clearly rectification carried out during testing, in case site test results vary very widely with factory test results, commissioning engineer’s observation shall be clearly indicated against

Page 12: DG Busduct[1]

07.05.03 corresponding equipment, identified by manufacturer’s serial numbers.

07.05.04 Contractor shall furnish bound volume indicating list of spares supplied for each equipment. The volume shall contain, manufacturer’s catalogue number of components with description. It shall also indicate precautions to be taken for storing.

07.06 Operation, Instruction and Maintenance manual/ catalogues

07.06.01 Instruction manual shall give step by step procedure for

1. Erection , testing and commissioning 2. Operation

3. Maintenance and

4. Repair

07.06.02 Instruction manual shall also contain ;

1. List of spare parts with ordering specifications and manufacturer’s catalogues.

2. List of consumables with specifications, brand names and

annual consumption figures.

3. Drawings relevant for erection, operation, maintenance and repair of the equipment

4. Procedure for ordering spares.

07.07 Contractor shall submit the following drawing/ data/ documents in specified number of copies and reproduceable prior to handing over the installation to the owner, whichever is earlier.

All drawings approved by consultant / owner

Equipment manufacturing drawings submitted for information of consultant/ owner

Page 13: DG Busduct[1]

Equipment drawings required for operation and maintenance

Inspection reports, factory and site test certificates in bound volume

As built drawings incorporating all site modifications

Instruction manuals and catalogues

List of spares

07.08 Number of copies

The contractor shall submit drawings, document “As Built” drawings, instruction manuals etc. in following number of copies to the purchaser/ consultant

For approval/ resubmissionFor approval : 5 copies

After approval : 6 copies

As built drawings : 8 copies

1 soft copy Operating & maintenance

manuals, equipment andsystem, catalogues, factoryand site test certificatesvolumes, list of spares volumes : 10 sets

08.00 COMPLETION SCHEDULE

The 3000A, 415V Busduct shall be completed within 6 weeks of Letter of Intent. Due date of delivery shall be reckoned as receipt at JSWSL site at Potteneri.

Page 14: DG Busduct[1]

09.00 SCHEDULE OF QUANTITIES

Sl.No

Description Unit Qty. Unit Rate (Rs.)

Total cost (Rs.)

1 415V, 50Hz, 3000A, 50kA (1sec) non-segregated phase, indoor busduct with aluminium busbars, 3 mm thick aluminium IP 52 enclosure with all accessories comprising of DG and switchgear lead-in sections, straight section, matching sections, horizontal/ vertical bends, phase cross-overs, space heaters etc connecting 1250KVA Diesel generator and EMPCC. Scope shall include for the purpose of quotation Generator and switchgear end terminations with laminated Copper flexibles, 1 no phase crossover, 2 horizontal/vertical cross sections and length of 6M measured along the centre line. Further, following extra rates shall apply for addition/deletion:

Set 02

2 Standard length for 3000 A Bus duct straight run

RM U/R

3 Horizontal/Vertical corner section RM U/R4 Phase cross-over RM U/R56

Non-standard matching sectionSilica gel breather

RM Nos

U/R U/R

ANNEXURE – I

QUESTIONNAIRE

B. LT BUSDUCT

I DATA TO BE FURNISHED WITH THE OFFER

Page 15: DG Busduct[1]

1. Manufacturer’s name2. Applicable standards3. Rated voltage & frequency4. System earthing5. Service6. Design ambient temperature7. Rated current

8. Continuous current rating at specified maximum ambient temperature without exceeding temp. rise limits

9. Short time current rating as per daily load cycle (if applicable)

10. Max. rise of temp. at rated current, over specified ambient temperatureBusbars EnclosureAt joints

11. BusbarsMaterial Cross section of phase and neutral busbars

12 Material & thickness of enclosure

II. Data required for design of Civil engineering1. Approx. weight per metre length

of busduct.2. Cross section of busduct in mm

(Width x height)

III. Data required for Detailed engineering

1. Size, shape & number of busbars used as phase and neutral2. Max. current density at continuous current3. Resistance and reactance per metre run of the busduct

+ve sequence (R+jX)Zero sequence (R+jX)

4. Minimum clearances in air in mmBetween phases Between phase and ground

5. One minute p.f withstand voltage

6. Bus jointingSurface treatment

Page 16: DG Busduct[1]

Bolts and washersBimetallic joints

7. Space heaterRated voltage WattsNumber and location

8. Material and cross section of earth bus9. Drawings as specified10. Paint shade as per IS-511. Type of end terminations

a) Transformer end b) Switchgear end

12. Short circuit ratingDynamic stability current KA …..(Peak) Short time short circuit withstand rating kA (RMS), Sec.

13. EnclosureType

Material Thickness