Diff Shortening of Tall Steel Building Columns Taranath

Embed Size (px)

Citation preview

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    1/8

    Differential shorteningof tall steel building columns

    By Bungale S. Taranath, Ph.D., S.E.

    JANUARY 2011

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    2/82 PDH Professional Development Advertising Section Bentley Systems, Inc.

    Differential shortening of tall steel building columnsBy Bungale S. Taranath, Ph.D., S.E.

    Columns in tall buildings

    experience large axialdisplacements because

    they are relatively long

    and accumulate gravity loads from

    a large number of floors. A 60-story

    column of a steel building, for exam-

    ple, may shorten as much as 4 to 5

    inches (100 to 125 mm) at the top.

    If such a shortening is not given due

    consideration, problems may develop

    in providing level floors and assuring

    trouble-free performance of building

    cladding systems. Proper awarenessof this problem is necessary on the

    part of structural engineer, architect,

    and curtain wall supplier to avoid

    unwelcome arguments, lost time, and

    money.

    The maximum shortening of a

    column occurs at the roof level, reduc-

    ing to zero at the base. Very little can

    be done to minimize the physical

    phenomenon of shortening, but the

    design team should be aware of the

    problem particularly at the buildingexterior, so that soft joints are provided,

    if need be, between the building frame

    and cladding to prevent axial load

    being unwittingly transferred into the

    buildings faade. Before fabrication

    of cladding, the in-place elevations of

    the structural frame should be verified,and if required, the cladding should

    be manufactured to fit the existing

    field condition of the steel frame. The

    design should provide for sufficient

    space between the cladding panels to

    allow for the movement of the struc-

    ture. Insufficient space may result in

    bowed cladding components or, in

    extreme cases, the cladding panels

    may even pop out of the building.

    A similar problem occurs when

    mechanical and plumbing lines areattached rigidly to the structure. Frame

    shortening may force the pipes to act

    as structural columns resulting in their

    distress. A general remedy is to make

    sure that nonstructural elements do

    not bear vertical loads. This is done by

    separating them from the structural

    elements.

    The axial loads in all columns of a

    building are seldom the same, giving

    rise to the problem of so-called differ-

    ential shortening. The problem ismore acute in a composite structure

    because steel erection columns that

    are later encased in concrete are typi-

    cally slender, and are therefore subject

    to large axial loads during construc-

    tion. Determining the magnitude of

    axial shortening in a composite systemis complicated because many of the

    variables that contribute to the short-

    ening cannot be predicted with suffi-

    cient accuracy. Consider, for example,

    the lower part of the composite

    column that is continually undergo-

    ing creep. The steel erection column

    during construction is partly enclosed

    in concrete at the lower floors, with

    the bare steel column projecting

    several floors above the concreted

    level. Another factor that is difficult topredict is the gravity load redistribu-

    tion due to frame action of columns

    and, if the building is founded on

    compressible material, the settlement

    of the foundation is another factor

    that influences the relative changes

    in the elevation of the columns. The

    magnitude of load imbalance between

    any two columns is continually chang-

    ing, making an accurate assessment of

    column shortening rather a challeng-

    ing task.Differential rather than the abso-

    lute shortening of columns is more

    significant. Relative displacement

    between columns occurs because

    of the difference between the axial

    Professional Development Series

    Instructions

    The Professional Development Series is a unique oppor-

    tunity to earn continuing education credit at no cost to

    you by reading specially focused, sponsored articles.

    After reviewing the learning objectives below, read

    the Professional Development Series article and complete

    the quiz online at www.stagnitomedia.com/cedu. Quiz

    answers will be graded automatically and, if you answer at

    least 80 percent of the questions correctly, you can imme-

    diately download a certificate of completion and will be

    awarded 1.0 professional development hour (equivalent

    to 0.1 continuing education unit in most states).

    Note: It is the responsibility of the licensee to determine if

    this method of continuing education meets his or her govern-

    ing board(s) of registrations requirements.

    Learning ObjectivesAfter reading this article, you should be able to do the

    following:

    Explain differential shortening of columns in tall steel

    buildings.

    Calculate axial displacement in columns using concise

    hand calculations.

    Explain the concepts behind column length correc-

    tions.

    Explain the importance of column shortening verifica-

    tion during construction.

    Professional Development Series SponsorBentley Systems, Inc.

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    3/8 Professional Development Advertising Section Bentley Systems, Inc. PDH 3

    stresses, or P/A ratios, of columns. P

    is the axial load on and A is the area

    of the column under consideration.

    If all columns in a building were to

    have the same P/Aratio under gravity

    loads, there would be no relative verti-

    cal movement between the columns.In typical buildings, however, this

    condition is seldom present. This is

    because in buildings not all columns

    are designed for the same axial loads.

    For example, the design of frame

    columns is governed by the combined

    gravity and lateral loads while non-

    frame columns are designed essen-

    tially for gravity loads only. This results

    in a rather large difference in the P/A

    ratios between the exterior and inte-

    rior columns. The differential columnshortening between perimeter and

    interior columns may result in slop-

    ing floors leading to unwelcome prob-

    lems in setting partitions, doors, and

    ceilings.

    Consider, for example, a tubular

    system with closely spaced exterior

    columns and widely spaced interior

    columns. Because of their large tribu-

    tary areas, the interior columns are

    more than likely to have large P/A

    ratios. The exterior columns, on theother hand, usually have a small P/A

    ratio for two reasons. First, their tribu-

    tary areas are small because of their

    close spacing. Second, they are sized

    for stiffness to limit lateral displace-

    ments resulting in areas much in

    excess of those required from strength

    consideration alone. Because of this

    imbalance in the gravity stress level,

    these two groups of columns undergo

    different axial shortenings; the interior

    columns shorten much more than theexterior columns.

    The opposite happens in buildings

    with interior-braced core columns and

    widely spaced exterior columns; the

    exterior columns experience more

    axial shortening than the interior

    columns. The behavior of columns in

    buildings with other types of struc-

    tural systems, such as interacting core

    and exterior frames, tends to be some-

    where in between these two limiting

    cases.

    Simplified method of calculating

    z

    , axial shortening of columnsIn a steel building, typically the

    cross-sectional area of a column

    increases in two-story increments from

    a minimum at top to a maximum at

    the base as shown in Figure 1. Theincremental steps in column areas are

    due to the finite choice of available

    column shapes. Similarly, the axial load

    on a column increases at each floor in

    a stepwise manner. In tall buildings,

    the significance of these incremental

    steps diminishes rapidly, allowing us

    to make the following assumptions

    that can be used to derive a simpli-

    fied formulation for axial shortening

    of columns. The first

    assumption relates to

    the variation of grav-

    ity loads, which may be

    assumed to increase linearly from top

    to the bottom. The second is similar to

    the first but applies to the variation ofcolumn areas. However, a linear varia-

    tion using the actual column area at

    the bottom appears to underestimate

    the actual shortening of columns.

    A slight modification in which the

    column area at the bottom is taken

    equal to 0.9 times the actual area (0.9

    x AB) appears to work well in predict-

    ing axial shortening.

    Figure 1: Variation of cross-sectional area of a high-rise column.

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    4/84 PDH Professional Development Advertising Section Bentley Systems, Inc.

    Differential shortening of tall steel building columns

    Derivation of simplifiedexpression for

    z

    Integral calculus in conjunction

    with the simplified assumptions stated

    earlier is used to derive the following

    equation for z:

    z= P

    b/E[(-1/) ln(1 -z/A

    b)]

    /E[-1/2(az+ Abln(1 -z/A

    b))]

    where

    L= height of the building

    z= axial shortening at a height x

    (also denoted as z), above the foun-

    dation level

    At= column area at top

    Ab= modified column area at bottom

    equal to 0.9 times actual area ofcolumn at bottom = 0.9 x A

    B(where A

    B

    is actualcolumn area at bottom.

    Ax= area of column at height x (also

    denoted as z) above foundation

    level

    = rate of change of area of column

    Pt= axial load at top

    Pb= axial load at bottom

    Px= axial load at height xabove foun-

    dation

    = rate of change of axial load

    E= modulus of elasticity of steelIn = natural logarithm

    The derivation of the equation is

    given in Wind and Earthquake Resistant

    Buildings: Structural Analysis and Design

    (Bungale S. Taranath, Ph.D., S.E., CRC

    Press: Taylor & Francis Group, 2005)

    and Structural Analysis and Design

    of Tall Buildings: Steel and Composite

    Construction (Bungale S. Taranath,

    Ph.D., S.E., CRC Press: Taylor & Francis

    Group, 2011). Definitions of the vari-ables used in the equation are shown

    schematically in Figure 2.

    ExampleGiven: (See Figure 3)

    Height of building: L = 682 feet =

    8,184 inches (207.8 m)

    Modulus of elasticity: E= 29,000 ksi

    (200 x 103 MPa)

    Axial of load at top: Pt = 53 kips

    (237.5 kN)

    Area of column at top: At= 12.48

    Figure 2: Axial shortening of columns; closed-form solutions: (1) axialshortening

    z; (2) variation of column area; (3) axial load variation; (4)

    unit load at height z; (5) axial strain; (6) axial shortening.

    Figure 3: For the example below, (1) axial load variations; (2) actual and assumed columncross-sectional areas.

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    5/8 Professional Development Advertising Section Bentley Systems, Inc. PDH 5

    square inches (8,052 square mm)

    Axial load at base: Pb= 2,770 kips (12.32 x 103 kN)

    Actual column area at base: AB = 147 square inches

    (94.84 x 103 square mm)

    Reduced column area at base: Ab = 0.9 x 147 = 133.3

    square inches (86.0 x 103 square mm)

    Required: Find the axial shortening of the top column

    Solution: Since column shortening is calculated at top,

    z= L , therefore

    = (Ab A

    t)/L= (133 12.48)/8,184 = 0.01476 sq. in./in.

    = (Pb P

    t)/L= (2,770 53)/8,184 = 0.332 kip/in.

    ln (1 L/Ab) = ln (1 (0.01476 x 8,184/133.3))

    = ln (0.09362)

    = -2.368

    Therefore,Lat top = 2,770/29,000 [(-1/0.01476) x (-2.368)]

    0.332/29,000[-4,590.15 (0.01476 x 8,184 +

    133.3 x -2.36847)]

    = 15.32 10.20

    = 5.12 in.

    Similarly, the axial shortening is calculated at various

    heights by substituting appropriate values for z.

    Column length corrections, c

    After determining axial shortening of building columns,

    the next step is to assign a column length correction cforeach column. The objective is to attain as level a floor as

    practical. The correction c is thus the difference between

    the theoretical height of a given column and its actual

    height after it has shortened. The magnitude of correction

    cin a tall building of 60 stories is rather small, perhaps 1/8

    inch (3.17 mm) per floor, at the most. Therefore, instead of

    specifying this small correction at each level, in practice it

    is common to specify lumped corrections at a few selected

    floors. For example, in lieu of 1/8 inch correction at each

    level, the designer would lump the correction at every

    eighth floor. Thus cwould be equal to 1/8 x 8 = 1 inch

    (25.4 mm). See the above referenced texts for further infor-mation on this topic.

    Column shortening verification during constructionConsider Figure 4, a hypothetical building that is 48

    stories tall. Identified therein are two columns: C1, an inte-

    rior column with a large tributary area; and C2, an exterior

    column of framed tube with a relatively small tributary area.

    Under gravity loads, C1would shorten more than C

    2for two

    reasons: C1, designed only for gravity loads, has a P/A ratio

    that is relatively high; and C2, designed as a frame column,

    has its P/A ratio significantly less than that for C1because it

    is lightly loaded under gravity loads.

    Bentley Systems, Inc., is proud to have

    sponsored several Professional Development

    Hours (PDH) sections during the last year.

    Visit Stagnito Medias Continuing Education

    page at www.stagnitomedia.com/cedu

    to learn more about the free learning units

    available to the structural engineering

    community.The following Bentley-sponsored PDHs

    are available at the page:

    IPD, BIM, and supply chain optimization:

    Bottom-line benefits of 3D-enabled lean delivery

    for AEC projects

    BIM in a cloud:

    What structural engineers and architects need

    to know about cloud computing for business success

    Slender Column Design Based on ACI 318-08

    Bentley also is proud to have sponsored a

    number of webcasts put on by Structural

    Engineering & Design magazine. By

    visiting the magazines webcast page at

    www.gostructural.com/webcasts, you

    can view the following Bentley-sponsored

    webcasts:

    Beyond Green: Building Designs that Work

    Defining Integrated Project Delivery

    IPD eConference

    BIM Structural Design Series:

    Efficient Structural Workflows for Design

    and Collaboration

    ADVERTISEMENT

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    6/86 PDH Professional Development Advertising Section Bentley Systems, Inc.

    Differential shortening of tall steel building columns

    Assume that you

    as the engineer for

    the project have speci-

    fied column length corrections to C1

    at levels 8, 16, 24, 32, 40, and 48

    with correction of 2 inches specifiedat level 24. Let us say that when steel

    erection is at the level 24, the steel

    erector surveys the top elevations of

    columns, reports the top of column

    C1is 1 inch higher than the top of C

    2,

    and requests that you confirm if this

    is acceptable in view of the fact that

    additional shortening of the column is

    yet to occur.

    Further calculations are needed to

    verify that this 1-inch overlength of C1

    will indeed come down after the appli-cation deadloads at levels 24 through

    roof. This concept of verifying the over-

    length of columns during construction

    is shown in Figure 5. Note that Rn

    shown therein corresponds to the 1

    inch discussed here for the hypotheti-

    cal building.

    ConclusionAxial displacement in tall steel build-

    ing columns is likely to be a problem if

    not given proper consideration duringdesign. Fortunately, clear and concise

    formulas are available for calculating

    axial shortening, as are methodologies

    for mitigating the adverse effects of

    relative axial displacements.

    Figure 5: Interpretation of column overstrength: (1) n= column shortening at nth level

    due to loads on the entire height of column; (2) B= column shortening at nth level dueto loads imposed at and below nth level; (3)

    Rn= column shortening yet to occur due to

    loads above nth level.

    Figure 4: Hypothetical framing plan: column C1, designed for gravity loads only, shortens

    more than C2, designed for both gravity and lateral loads. Compensating for relative eleva-

    tion difference between columns is of importance in tall buildings.

    Bungale S.

    Taranath, Ph.D.,

    S.E., is a corpo-

    rate consultant to

    DeSimone ConsultingEngineers, a consult-

    ing firm with offices

    in New York; Miami;

    San Francisco; New

    Haven, Conn.; Las

    Vegas; Hong Kong; and Abu Dhabi, and

    has served as a principal or senior engi-

    neer for several firms. He is the author

    of five books on tall building design, and

    has conducted seminars on tall build-

    ing design around the world. He can be

    reached at [email protected].

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    7/8 Professional Development Advertising Section Bentley Systems, Inc. PDH 7

    1. In a 60-story, steel-framed build-

    ing, which of the following is likely

    to be true?

    a) Columns may not shorten at all.

    b) Columns may shorten by 4 to 5

    inches.

    c) Columns may shorten by as much

    as 1 foot.

    d) Proper construction practice will

    prevent significant axial shortening.

    2. Which of the following statementsis most true?

    a) Axial displacement is disastrous,

    and should be avoided with bracing

    systems and extremely rigid materi-

    als.

    b) Axial displacement is probably inevi-

    table in large buildings, which is why

    most large buildings have slightly

    uneven floors.

    c) Axial displacement is a minor prob-

    lem for buildings that are less than

    40 stories tall, and can usually beignored.

    d) Large differential axial displace-

    ment is inevitable in tall steel build-

    ing columns, so building designers

    should include mitigating meth-

    ods, such as providing soft joints

    between the building frame and

    cladding components, based on

    actual calculations and, preferably,

    measurements during construction.

    3. If nonstructural building elements

    are not separated from verti-

    cal loads, which of the following

    might occur?

    a) Piping and ducting may be forced to

    act as structural columns, and suffer

    distress.

    b) Cladding system components may

    bow or pop out.

    c) Floors may be out of level.

    d) All of the above.

    4. The phrase differential shortening

    refers to which of the following?

    a) Building columns that shorten by

    different amounts.

    b) Column shortening that varies by

    floor.

    c) Column shortening that varies

    according to temperature.

    d) Building columns that shorten

    during construction, as a result of

    progressive loading.

    5. Differential shortening may bedue to which of the following?

    a) Building columns that have different

    P/Aratios.

    b) Building columns that support differ-

    ent loads.

    c) Building columns designed for grav-

    ity only, and for gravity and lateral

    load.

    d) All of the above.

    6. The P/A ratio is the ratio

    between?

    a) Column height and axial load.

    b) Axial loads of perimeter and interior

    columns.

    c) Axial load and column area.

    d) Axial compression measured at

    the top and midpoint of building

    columns.

    7. In a building with closely spaced

    exterior columns and widely

    spaced interior columns, which ofthe following is most likely to be

    true?

    a) Exterior columns are likely to experi-

    ence greater axial compression than

    interior columns.

    b) Interior columns are likely to experi-

    ence greater axial compression than

    exterior columns.

    c) Axial compression will be roughly

    equal for all columns.

    d) This is a tubular system, and axial

    compression will be minimal.

    8. Which of the following assump-

    tions is made in order to simplify

    the calculation of axial shortening of

    columns in steel buildings?

    a) The column area at the top is

    assumed to be 0.9 times the actual

    column area.

    b) The column area at the top is

    assumed to be 1.1 times the actual

    column area floor.

    c) The column area at the bottom is

    assumed to be 0.9 times the actualcolumn area.

    d) The column area at the bottom is

    assumed to be 1.1 times the actual

    column area.

    9. When determining column length

    corrections, c is which of the

    following?

    a) The difference in shortening between

    exterior and interior columns.

    b) The difference in shortening between

    the top and midpoint of any particu-lar column.

    c) The difference in shortening due to

    change in column area.

    d) The difference between the theoreti-

    cal height of a given column and its

    actual height after it has shortened.

    10. Which of the following statements

    is most true?

    a) Onsite verification of axial displace-

    ment during construction is ineffec-tive due to progressive loading.

    b) Due to a variety of factors that cant

    be determined in advance, onsite

    verification is the only way to deter-

    mine axial shortening.

    c) Onsite verification during construc-

    tion is an excellent way to check

    axial displacement calculations.

    d) Differential shortening cant be

    predicted by calculation, and can

    only be measured during construc-

    tion.

    Differential shortening of tall steel building columns

    Go to www.stagnitomedia.com/ceduto take the following quiz online. Quiz answers will begraded automatically and, if you answer at least 80 percent of the questions correctly, you canimmediately download a certificate of completion.

  • 8/12/2019 Diff Shortening of Tall Steel Building Columns Taranath

    8/8

    IntelligentStructural Design

    www.Bentley.com/Structural

    Having all the applications you need for the tasks at hand, along with the ability

    to easily synchronize your work with the rest of the project information, helps

    you get your job done right, fast and profitably. And when the structural project

    workflow can be integrated, the whole team benefits.

    Bentleys new Passport Subscriptions for structural engineers provide access to

    the full range of structural software (including upgrades) and training documents

    and information that most projects require. These options are available as an

    affordable alternative to traditional licensing.

    Contact us to learn more.

    Model, Analyze, Design, Documentand Deliverin an Integrated Workflow

    With RAM, STAADand

    Documentation Center, Bentleyoffers proven applications for:

    lSteel/Steel Composite

    lReinforced Concrete

    lWood and Wood Products

    lFoundation DesignlPost-Tensioned Design

    lSteel Connections

    lStructural Drawings and Details

    all easily coordinated with the

    Architect and other team members and

    their design applications such as

    AutoCAD, Revit, MicroStationand more.

    2010 Bentley Systems, Incorporated. Bentley, the B Bentley logo, MicroStation, RAM, and STAAD are either registered or unregistered trademarksor service marks of Bentley Systems, Incorporated or one of its direct or indirect wholly-owned subsidiaries. Other brands and product names aretra emar s o t eir respective owners.