Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
www.reg.rw
DISTRIBUTION MASTRER PLAN
June 2019 revision
www.reg.rw
Table of Contents• EXISTING NETWORK, CHALLENGES & SOLUTIONS
• METHODOLOGY FOR DISTRIBUTION PLANNING
• LIST OF COMPLETED PROJECTS 2018/19
• NETWORK REINFORCEMENT
• Nyarugenge and Rulindo Districts
• Kicukiro District
• Nyarugenge and Gasabo Districts
• Rwamagana and Gasabo Districts
• Bugesera District
• Nyagatare, Gatsibo, Kayonza Districts
• Kirehe, Ngoma and Kayonza Districts
• Gisagara, Huye, Nyanza, Nyamagabe Districts
• Musanze, Rubavu, Gakenke, Karongi, Nyabihu, Ngororero, Kamonyi, Rutsiro and Muhanga Districts
• Gicumbi, Burera, Rulindo, and Gatsibo Districts
• LIST OF URGENT PROPOSED PROJECTS & COSTING OF ALL PROJECTS
1
www.reg.rw
Distribution Plan 2
EXISTING CHALLENGES
• Very long feeders;
• Lack of (N-1) solution;
• Network instability;
• Kigali City Center supplied from one
substation only.
SOLUTIONS TO THE EXISTING CHALLENGES
• Reduce feeder length;
• Reduce feeder load;
• Upgrade existing lines;
• Construct new lines to share the load;
• Plan for contingency supply;
• Plan future network.
Map of Existing Distribution Network
www.reg.rw
Methodology
1.Planning ApproachThe major issues on the network have been addressed as follows:
• Major load centers (towns) without substations or reliable supply
• The supply to Industrial Parks
• Improvement of losses on long feeders
• Improvement of low voltage profiles on long feeders
• Contingency (N-1) supply on major load centers, towns and cities.
• Contingency supply (N-1) on long lines with many customers
• Improvement of reliability due to exposure of very long lines (due to
lightning, vandalism, rain, etc.)
• Extension of the network to supply the fast-growing network.
3
2.Load forecastThe load forecast will be the important part for the distribution plan and
will consider the following key factors:
• Growth on existing networks;
• Load Growth for new Electrification;
• Load growth for bulk customers.
3.Geographical location of customers and loads
It is important to know where the load is to be able to do an accurate
simulation of the feeder load.
We have identified geographically the location of bulk loads; location of
settlements and the place of connection on the existing feeder to be able to
plan for them.
www.reg.rw
LIST OF COMPLETED PROJECTS 2018/194
# Project name Components Outcome
1 KKK Feeder extension and load transfer to Gabiro switching station
Nyagatare Feeder (MW),
KKK Feeder (MW) and
Ngarama Feeder (MW)
Load reduction to KKK
feeder and creation of
contingency supply
2 KANAZI FEEDER – Load Transfer to Ntongwe feederInterconnection of Kanazi
and Ntongwe Feeders
Load reduction to Kanazi
Feeder
3 Nzove to Abattoir 2 x 120/20 ACSR to supply Kigali City from NzoveNyabugogo Feeder from
NZOVE Ss
Load reduction to Kigali
Feeder
4Reduce stress on Kigali Feeder (Jabana Ss) using Nzove Substation MV line
interconnections
SKOL Feeder (4.8MW)
and NYABUGOGO
Feeder (1.8MW)
Kigali Feeder now loaded
with 1.8MW
5Reduce stress on Gasogi Feeder (Gikondo Ss) using Gahanga Substation lines
interconnections
Pylon 20 Feeder (0.4MW )
and Master Steel Feeder
(0.59MW)
Gasogi feeder now loaded
with 3.63MW
6 Reinforcement of contingency supply to Kigali using Mont Kigali Substation
Nyamirambo Feeder
(4.5MW) and Rebero
Feeder (1.05MW)
Contingency supply to
Kigali City
7 Interconnection of Byumba feeder with Gabiro substation (30kV Distribution line)
Interconnection of
Ngarama and Byumba
Feeders
Contingency supply to
Byumba Feeder
www.reg.rw
5
Distribution Plan Budget Summary
TOTAL CAPEX FOR PROJECTS
Fin Year USD Km Line
2018/19 - 0
2019/20 69,652,094 699
2020/21 36,332,821 1,103
2021/22 6,638,715 45
2022/23 9,791,371 51
2023/24 5,033,535 39
2024/25 4,771,045 37
2025/26 - -
TOTAL 132,219,581 1,972
www.reg.rw
5
NETWORK REINFORCEMENT:
The required network reinforcement is listed District – by – District in the following pages.
Distribution Plan
www.reg.rw
5
NETWORK REINFORCEMENT:Nyarugenge and Rulindo Districts
Problem statement:
Reduce stress on Kigali (Jabana) short term solution using Base FeederAfter the commissioning of NZOVE substation, the SKOL feeder (from NZOVE SS) supply Water treatment plants and continues towards Rulindo. Reduce the load on this feeder by installing an inter-connector from Base Feeder with step-down transformer and connect also the other part of Kigali Feeder.
Transfo 30/15kV / 5MVA
New line 15kV
Kigali Feeder15kV
SKOL Feeder
BASE Feeder
Distribution Plan
Solution:
Installing an inter-connector from Base Feeder with step-down transformer and connect also the other part of Kigali Feeder.
www.reg.rw
5
NETWORK REINFORCEMENT:Gasabo and Rulindo Districts
Problem statement:
High loading on Rutongo feeder;Lack of Contingency supply to Rutongo, Gikomero, Deutche Welle and Kanombe Feeders:
-Provide a reliable and secure supply to Rutongo and Gasabo
Distribution Plan
Solution:
Connect Shango to existing Deutshe Welle feeder;Construct interconnection feeders from Shango substation to create (N-1) solutions to • Rutongo Feeder• Gikomero Feeder• Kanombe Feeder-Reduce load on Rutongo Feeder
Rutongo Feeder
Kanombe Feeder
Gikomero Feeder
www.reg.rw
8
NETWORK REINFORCEMENTKicukiro District
Upgrade Gahanga – Gikondo Distribution LineNew Gahanga substation has capacity to support heavily loaded Gikondo - Gasogi feeder. The existing line from Gahanga to Gasogi feeder is 70mm² and must be upgraded to 120mm² to be able to support and reduce the load on the Gasogi feeder.
Distribution Plan
Upgrade this line from from 70mm² to 120mm²
www.reg.rw
KIGALI SOUTH
KIGALI NORTH
CITY CENTER
11
KIGALI CITY NETWORK REINFORCEMENTNyarugenge and Gasabo Districts
Problem Statement:• Kigali City is supplied from one substation only
(no N-1)• Kigali City is supplied from 2 feeders only and
cannot operate with only one (No N-1)• The two feeders (Kigali North and Kigali South)
are heavily loaded (7MVA each)• The internal network between K-North and K-
South is over loaded• The carbines don’t have protection or remote
switching functionality which cause long outages
Distribution Plan
www.reg.rw
12Distribution Plan
KIGALI CITY NETWORK REINFORCEMENTNyarugenge and Gasabo Districts
Solutions:• Nzove Substation supplying up to Abattoir
(Nyabugogo feeder)• Upgrade Mont Kigali Substation and capacity• After Mont Kigali commissioned, Kigali north is not
overloaded• Ongoing construction new MV lines ( 2 cables)
from Gikondo to City Center (Cabine MINISTERE) with more capacity
• Ongoing construction new MV line ( 1 cable) from Gikondo to City Center (Cabine MINISTERE) with more capacity to link with other cabines via Kigali South
• Ongoing upgrade 11 cabines in Kigali with remote automatic switchgear for better operation and shorter outages
KIGALI SOUTH
KIGALI NORTH
CITY CENTERNZOVE MINISTERE
ABATTOIR
www.reg.rw
13
KIGALI CITY NETWORK REINFORCEMENTNyarugenge and Gasabo Districts
Outcome:• Kigali was supplied from two loaded feeders (7MVA
each), now supplied from 4 feeders (4.4, 2.3, 3.5 and 4MVA respectively)
• N-1 supply on feeders is achieved• Old feeders are available as backup• Kigali City previously supplied from 1 substation
now has 3 substations to support the supply (n-1 achieved)
• Internal cables were upgraded from 95Al to 240 Cu cables to prevent overloading
• With the positioning of new infeed at Ministere, the length of the cables between K-Noth and K-south is ½ from before
• Internal supply to Gasabo side of the city (including Convention center, Amahoro stadium, etc) is improved in capacity with N-1 supply
KIGALI SOUTH
KIGALI NORTH
CITY CENTERNZOVE MINISTERE
ABATTOIR
Distribution Plan
www.reg.rw
15
Distribution PlanNETWORK REINFORCEMENTRwamagana and Gasabo Districts
Problem Statement:• Musha substation transformer is over loaded (100%)• Very long feeder (Kanombe feeder) supplying up to Fumbwe with no N-1 on most
of the feeder• Industries supplied on this line with poor reliability• Rwamagana Industries have poor supply on over loaded line
Solutions• Upgrade Musha substation from 10MVA to 20MVA transformer for more capacity• Construct new distribution lines to support the Kanombe feeder and provide N-1
solution• Construct double circuit dedicated line to supply the Industrial area
Outcome• Transformer loading reduced from 100% to 50% with capacity for expansion• N-1 supply for the entire Kanombe feeder• Rwamagana feeder load reduced from 7.7 MVA to 4.2 MVA• Dedicated reliable supply for Industrial Park
Proposed N-1 supply to Kanombe feeder
www.reg.rw
17
NETWORK REINFORCEMENTBugesera District
Problem Statement:
• Kanazi feeder is very long (303km)
• Highly loaded (7.8 MVA)
• No alternative supply
• Very low voltage at the end of the feeder (11%)
• Heavy industries in the south of Kanazi feeder
(Bugesera district)
• Industrial park development in Bugesera
• New airport development with no reliable supply
Kanazi fdr
Kanazi fdr
Kanazi fdr
Kanazi fdr
Ntongwe fdr
AIRPORT
Distribution Plan
www.reg.rw
18
NETWORK REINFORCEMENTBugesera District
Solutions:
• A 30kV interconnection from Ntongwe feeder to Kanazifeeder has been constructed and 0.816MW have been transferred to Ntongwe feeder and N-1 option obtained
• Construct Juru (Airport) Substation with 110kV supply from Gahanga
• Construct Airport 30kV substation supplied from Juru to supply the airport
• Construct Rilima (Bugesera) 110kV substation supplied from Juru near the industrial Park
Outcome
• Kanazi feeder length reduced from 303km to 152km
• Kanazi feeder load reduced from 7.8 MVA to 3.2MVA
• Reliable supply for the airport
• Reliable supply for Bugesera District and Industrial park
Distribution Plan
www.reg.rw
19
Distribution Plan
NETWORK REINFORCEMENTNyagatare, Gatsibo and Kayonza Districts
www.reg.rw
KKK Feeder:
11
0km
20
Distribution PlanNETWORK REINFORCEMENT
Problem Statement:
• KKK feeder from Kabarondo Substation is very long (727km total )
• Low voltage is experienced in the north
• Factories are connected in Nyagatare in the north far from the source
(Kabarondo)
• Industrial park development planned in Nyagatare
• Very poor reliability due to long feeder length
• High load of 5.5 MVA
• Single phase lines has low voltage and small capacity and causes unbalanced
loading
• No N-1 supply on the entire feeder
• Voltage drop in the far north end is >11%
www.reg.rw
21Distribution PlanNETWORK REINFORCEMENT
Solution:
• Construct Gabiro Substation in Gatsibo area (completed)
• Load transfered from the KKK Feeder to new Gabiro Substation (Gabiro 1, 2 and 3 feeders);
• Construct a new Substation in Nyagatare for supply to problematic single phase networks and
create capacity for the Industries on feeder 3;
• Upgrade single lines to three phase lines;
• Connection of Ngarama Feeder from new Gabiro substation to Byumba Feeder (2) for N-1 Supply.
Outcome
• KKK feeder length reduced from 727km to 216km
• KKK feeder load reduced from 5.5MVA to 1.4MVA
• Improved reliability due to shorter feeder length
• Reliable supply and improved capacity for the Factories in Nyagatare
• Reliable supply for Kayonza; Gatsibo & Nyagatare Districts
• Balanced system after single phase upgrade and voltage drops reduced
• Most voltage drop on all feeders is <4%
• N-1 supply on most of the network
www.reg.rw
22
Distribution Plan
NETWORK REINFORCEMENTKirehe, Ngoma and Kayonza Districts
www.reg.rw
23
NETWORK REINFORCEMENTProblem Statement:
• Existing Zaza feeder from Kabarondo is very long (64km main feeder)
• Low voltage at the end of the Zaza feeder• Limited supply to Nasho Irrigation from Rwinkwavu
15kV network• More irrigation planned in the east of Kirehe district
cannot be supplied• No alternative supply (N-1)Solution • Construct Kirehe 110kV substation supplied from 2 sides
for reliability (2025/26)• Construct a 30kV line from Kabarondo to Nasho with
30.15kV transformer to support the 15kV network (on-going 2019)
Outcome• Zaza feeder length has reduced from 64km to 25km• Zaza feeder has N-1 supply option• Low voltage problems have been corrected• Improved capacity to supply Nasho irrigation scheme• Additional capacity from Kirehe SS for new irrigation in
the east
Zaza feeder
Zaza feeder
Kirehe SS
Nasho
Zaza feeder
Distribution Plan
www.reg.rw
24
Distribution Plan
NETWORK REINFORCEMENTGisagara, Huye, Nyanza and Nyamagabe Districts
www.reg.rw
25
Problem Statement:
• Butare feeder is very long (520 km total feeder length)
• Poor reliability due to long feeder exposure to faults
• N-1 supply option and maintenance is difficult
• Butare town has very poor quality of supply
• Planned Huye Industrial park cannot be supplied
Butare Feeder
Rukarara Feeder
Distribution PlanNETWORK REINFORCEMENT
www.reg.rw
26
Solution:
• Construct Gisagara substation in Gisagara District (2020)
• Construct Huye substation in Huye District (2022/23)
• Build MV feeders to configure new MV feeder network
• Interconnect all 110kV substations for N-1 supply option
Outcome
• Huye feeder length is reduced from 520km to 160km total
line length
• Supply to Gisagara and Huye districts is reinforced
• Supply is available for industrial Park
• Improved reliability due to shorter feeder lengths
• All MV feeders are within acceptable length and voltage
limits
• N-1 supply on all major distribution feeders
Rukarara
Huye
Gisagara
Butare
Distribution PlanNETWORK REINFORCEMENT
www.reg.rw
27
Distribution Plan
NETWORK REINFORCEMENTMusanze, Rubavu, Gakenke, Karongi, Nyabihu, Ngororero, Kamonyi, Rutsiro and Muhanga Districts
www.reg.rw
Gisenyi feeder
Gisenyi feeder
Kibuye feeder
Problem Statement:
• Gisenyi feeder from Mukungwa is very long and supply all the load up to Rubavu (442km)
• High load (7.5 MVA)• Quality of supply is bad due to long network• Maintenance is difficult due to lack of alternative supply (N-1)• Low voltage at the end of the line. • Supply in Rubavu district is dependent on Hydro power which is
not reliable (some plants are under rehabilitation)• Supply to Muhanga Industrial park is not sufficient• Gatumba feeder from Kigoma is long with no alternative supply• Supply in Ngororero area is limited as is far from all sources• Unreliable and limited evacuation route for hydros at Rwaza II,
Mukungwa II hydros.• Musanze is on the same line as the Gisenyi feeder which is
causing many outages for Musanze• Gisenyi town has many interruptions as it is supplied on the
long Gisenyi feeder from Mukungwa• Kibuye feeder from Karongi substation is long
Distribution PlanNETWORK REINFORCEMENT
Kiyumba feeder
Gatumba feeder
www.reg.rw
Solutions:
• Construct Nyabihu 110/30kV substation• Construction of Musanze 110/30kV substation• Upgrade Camp Belge substation• Reconduct (upgrade) the small section lines from
Mukungwa and Ntaruka to Camp Belge substation• Construct a new line from Mukungwa to connect
Mukungwa II, Rwaza and continue to connect Janja and the Ngororero network
• Construction of Rubavu substation to supply Rubavu area and remove this from the Gisenyi feeder
• Change the open point of Kibuye feeder to reduce the length of the feeder
• Construction of Nyabarongo substation for reliable supply in Ngororero area, also interconnect with Gatumba and Kiyumba and Ngororero T-off from Gisenyi feeder.
• Construct 110kV line from Nyabarongo to Musanze and Ntaruka for N-1 supply on all substations
Distribution PlanNETWORK REINFORCEMENT
Nyabarongo
Kibuye fdr
Rubavu
Gisenyi fdr
Kiyumba feeder
Gatumba feeder
www.reg.rw
Outcome:
• More reliable supply at Musanze after upgrade of Camp Belgesubstation (Musanze is not on the same feeder as Gisenyi)
• Musanze substation will provide strong and reliable supply to Musanze and industrial park and also allow for upgrade of the old feeders from Mukungwa to Camp Belge
• Gisenyi feeder length is reduced from 442 km to 116km• This improves quality of supply and reliability• The load on Gisenyi feeder is reduced from 7.5 MVA to 3.2 MVA• Rubavu has a strong and reliable supply also to supply the
industrial park.• Kibuye feeder length is reduced from 228km to 138km• The supply from Nyabarongo will reinforce the supply to
Muhanga industrial park• Muhanga substation will supply Muhanga Industrial park• Nyabarongo substation provides N-1 supply on Gatumba,
Kiyumba and Ngororero feeders
Distribution PlanNETWORK REINFORCEMENT
Nyabarongo
Kibuye fdr
Rubavu
Gisenyi fdr
Kiyumba feeder
Gatumba feeder
www.reg.rw
Distribution Plan
NETWORK REINFORCEMENTGicumbi, Burera, Rulindo, and Gatsibo Districts
31
www.reg.rw
32
Problem Statement:
• Byumba Feeder is supplied with only one substation, only the
supply from Uganda which is not secured can be the alternative
source;
• Byumba Feeder is long from the substation (462km)
• The distribution line from Rulindo is too old and constructed
with a small conductor (35mm²);
Distribution PlanNETWORK REINFORCEMENT
Rulindo SS
Byumba Feeder
Uganda connection
Musasa Feeder Base
Feeder
www.reg.rw
33
Byumba – Ngarama Line
NETWORK REINFORCEMENTSolutions:
• Construction of Byumba – Ngarama Line for interconnecting Byumba and Ngarama
• Construction of 30kV line from Shango to ByumbaFeeder;
• Reconducting Musasa Feeder (35mm²) with 120mm²;
• Construction of 110/30kV Byumba substation (2025);
• Shift the connection points from Byumba Feeder to Byumba substation.
• Reconducting the section Byumba – Kageyo line (35mm²) with 120mm².
Outcome:• Alternative source of supply from Gabiro Substation;• Stress reduced by reducing the feeder length from 462km
to 94km;• Reliable supply for Byumba and Burera District.
Distribution Plan
Musasa Feeder
www.reg.rw
34
List of Distribution Projects
# Project Name
Line Length
(km)
Budget Estimate
(USD)
Available Budget
(USD)-
MINECOFIN
Finance
Requested (USD)
Balance
required (USD)
Source of
Funds
Starting
Period
1 Upgrade of Camp Belge Substation 1,500,000 1,597,500 - AfDB 2019
2
Reconducting the existing 70mm2 conductor for 30kV Distribution lines
Mukungwa-Camp Belge with 120mm2
13 359,198 382,545 - AfDB 2019
3
Rwaza 30/30kV switching substation with 30kV distribution line to Janja
Feeder (ongoing Project) 5.2 250,000 250,000 - MINECOFIN 2019
4 Upgrade of Rubavu Network from 6.6kV to 30kV 11 4,950,000 4,950,000 - ENABEL 2019
5 30kV underground Double circuit line Bugesera to Airport 7.5 1,012,500 1,012,500 1,078,313 - AfDB 2019
6 Reconducting of the last section (35mm2 ) of Ngororero T-off with 9 248,675 264,839 - AfDB 2019
7
Split Busbars in Kigali North and Kigali South for more flexibility in
supply 80,000 85,200 AFDB 2019
8
Build a new feeder from Nyabarongo I substation and Load transfer
from Gatumba and Ngororero feeders to the new feeders from 8.5 1,174,300 1,174,300 - AfDB 2019
9 Feeder interconnetion between Kibogora & Karongi 3 414,459 414,459 2019
10 Feeder interconnection between Kilinda & Kigoma 6.2 856,548 912,224 - AfDB 2019
11 Load transfer from Kibuye Feeder to Rubavu substation 5 690,765 690,765 2019
12 upgrade of STEG network 400 6,000,000 6,000,000 - ENABEL 2019
13 construction of a 15kV double circuit line to supply industrial bulk loads 3.4 620,000 297,500 660,300 - AfDB 2019
14 UTEXRWA load transfer to DW (OHL) 1.7 200,000 213,000 - WB 2019
15 upgrade of Gahanga-Gikondo distribution line (OHL 15kV to 120/20 7.2 952,941 1,014,882 - WB 2019
16 Gikondo to Ministere feeders (underground 2x240mm2) 2.4 2,000,000 2,130,000 - WB 2019
17 30kV Airport to Nyamata (Backup OHL Line) 8.1 1,057,191 1,125,908 - AfDB 2019
18 30/30kV Switching substation in Nyamata for efficient supply 250,000 250,000 2019
19 30kV Single circuit Nyagasozi-Kavumu 36 795,054 846,732 - AfDB 2019
20
Mukungwa to Ngororero 30kV Distribution line and switching station at
Mukungwa II 34 2,550,000 2,715,750 - AfDB 2019
21 Extension of 9.3km of MV power supply to Gako beef project 9.3 1,268,777 1,351,248 - AfDB 2019
22 30kV Double circuit line from Gabiro Ss to Gabiro commercial farm 43 4,386,000 4,671,090 - AfDB 2019
23 Nasho-Kabarondo 30kV Double circuit distribution line 30 4,581,901 4,879,725 - AfDB 2019
24 Connection of 51,254 households for 100% Kigali Access (55km of 55 33,453,785 23,417,650 10,036,136 AfDB 2019
www.reg.rw
34
List of Distribution Projects…
# Project Name
Line Length
(km)
Budget Estimate
(USD)
Available Budget
(USD)-
MINECOFIN
Finance
Requested (USD)
Balance
required (USD)
Source of
Funds
Starting
Period
25 Reconducting Byumba-Kageyo Line (35mm2 ) with 120mm
24 110,522 117,706 - AfDB 2020
26 Reconducting Musasa main feeder with 120mm2
20 552,612 588,532 - AfDB 2020
27 30kV distribution line to connect Rusizi feeder 0.05 7,000 7,000 2020
28 upgrade of single to three phase network-countrywide 995.5 25,908,228 25,908,228 - AfDB 2020
29
Reconduct part of Kanazi Feeder from Nyamata to Nemba 70mm2 with
120mm2 40 290,000 308,850 - AfDB 2020
30 Interconnection of Ntongwe Feeder with Rwabusoro Substation 3 414,459 414,459 2020
31 Abattoir upgrade to accommodate Nzove Supply 1,250,000 1,250,000 2020
32 Nzove to Abattoir 1 x 120/20 ACSR to supply Kigali City from Nzove 5.5 750,000 750,000 2020
33 upgrade of distribution substations in secondary cities 2,500,000 2,500,000 2020
34 upgrade and extension of different MV lines for improved supply 35 4,550,000 4,550,000 2020
35 Reduce stress on Kigali (Jabana) short term solution using Base Feeder 721,000 767,865 - AfDB 2021
36 Connect Rutongo, Gikomero and Kanombe Feeders to Shango 9.9 1,367,715 1,367,715 2021
37 upgrade and extension of different MV lines for improved supply 35 4,550,000 4,550,000 2021
38 30kV distribution line to connect Muhanga Industrial Park 0.5 69,076 69,076 2022
39 30kV distribution lines to connect existing lines to new feeders from 15 2,072,294 2,072,294 2022
40 Load transfer of Gisenyi Feeder to Rubavu substation 100,000 100,000 2022
41 upgrade of distribution substations in secondary cities 3,000,000 3,000,000 2022
42 upgrade and extension of different MV lines for improved supply 35 4,550,000 4,550,000 2022
43 Interconnection of Kiyumba feeder with the new feeder in Nyabarongo 3.5 483,535 483,535 2023
44 upgrade and extension of different MV lines for improved supply 35 4,550,000 4,550,000 2023
45 Load transfer of Musasa Feeder to Nyabarongo II 110/30kV 1.6 221,045 221,045 2024
46 upgrade and extension of different MV lines for improved supply 35 4,550,000 4,550,000 2024
TOTAL 1972.05 132,219,581 1,560,000 87,162,386 46,376,484
www.reg.rw
34Distribution PlanCAPEX
The total required budget for the implementation
of the above project is USD 132,219,581
Project Funding USD
MINECOFIN 1,560,000.00
AfDB 72,854,504.37
WB 3,357,882.00
ENABEL 10,950,000.00
No Budget 46,376,483.61
TOTAL CAPEX FOR PROJECTS
Fin Year USD Km Line
2018/19 - 0
2019/20 69,652,094 699
2020/21 36,332,821 1,103
2021/22 6,638,715 45
2022/23 9,791,371 51
2023/24 5,033,535 39
2024/25 4,771,045 37
2025/26 - -
TOTAL 132,219,581 1,972
www.reg.rw
35
Distribution Plan
Conclusion and Recommendation
We have realized that some areas need urgent interventions considering the substantial projects to be developed
and the running business contributing to the development of the Country.
Among the supply areas that need quick solutions, Bugesera and Rubavu networks as well as the reinforcement
for Kigali City network that supplies a big load Center must be given priority while thinking also to the Southern
network specially Butare feeder which suffers from instability due to the length of the Feeder.
We have estimated the projects costs in this report and therefore recommend to secure the fund and look for
alternative solutions for projects that need immediate action.
www.reg.rw
36
THANK YOU