 Testing of Distribution Transformer

Distribution Transformer Testing

Embed Size (px)

Citation preview

  • Testing of Distribution Transformer

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of Transformer

    2

  • Principle of transformer action

    3

    A current flowing through a

    coil produces a magnetic field

    around the coil. The magnetic

    field strength H,

    required to produce a

    magnetic field of flux density

    B, is proportional to the

    current flowing in the coil.

  • Principle of transformer action

    4

    A transformer is a static piece of

    apparatus used for transferring

    power from one circuit to

    another at a different voltage,

    but without change in frequency.

    It can raise or lower the voltage

    with a corresponding

    decrease or increase of current.

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of transformer actions

    5

  • CONSERVATOR TANK

    TAP SWITCH

    HV / LV WINDING

    OIL

    EXPLOSION VENT

    BREATHER

    RADIATOR

    L.T BUSHING

    BOTTOM VALVE

    H.T BUSHING

    Construction of Transformer

    6

  • Construction of Transformer

    DELTA / STAR

    7

    .

    R

    Y

    B

    y

    r

    b

    n

    HV LV

    ETH

  • 6/25/2015 8 Distribution Transformer

  • 6/25/2015 9 Core and Coil Assembly

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of transformer actions

    10

  • Transformer Name Plate Details

    - Before any testing study of name plate details is must, The HV/LV voltage

    ,HV/LV current, Size of transformer, Vector group & Impedance volts play

    an important roll for calculating test values.

    MAKE : ( XYZ )

    KVA : (315)

    NO LOAD VOLTS HV / LV ( 11000 / 415 ) Volts

    FULL LOAD AMPS. HV / LV ( 16.5 / 438.2 ) Amps

    FREQUENCY : 50 HZ

    TAPPING : No. of Taps :- 7

    VECTOR GROUP : Dyn11

    TYPE OF COOLING : ONAN

    IMPEDANCE VOLTS : 5 %

    11

  • Name plate of Distribution transformer-Sample

    12

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of transformer actions

    13

  • Routine Test

    Generally routine test is carried out at stores where we received New /

    Recovered transformers from manufacturer and site.

    Following Test are perform as routine test.

    Insulation Resistance Test

    Continuity test

    Ratio test (Voltage / Turns ratio)

    Short circuit test (Short circuit current)

    Open circuit test (Magnetizing current )

    Magnetic balance test

    Vector Group test

    Oil test

    14

  • Insulation Resistance Test

    (IR VALUE)

    Insulation resistance test to be carried out by 1 / 2.5 / 5 KV manual or motor driven megger, It gives us the status of insulation of HV

    winding and LV winding with respect to earth and between the

    winding.

    HV WDG. TO EARTH = _____ M

    LV WDG. TO EARTH = _____ M

    HV WDG.TO LV WDG. = _____ M

    15

  • 0

    M

    MEGGER

    HV

    R

    Y

    B

    TR BODY TR BODY

    0

    M

    MEGGER

    LV

    R

    Y

    B

    N

    Insulation resistance measurement

    between LV winding and earth

    Insulation resistance measurement

    between HV winding and earth

    16

  • TR BODY

    0

    M

    MEGGER

    HV

    R

    Y

    B

    LV

    R

    Y

    B

    N

    Insulation resistance measurement between LV winding and HV

    winding

    17

  • Continuity Test

    CONTINUITY TEST CARRIED OUT BY MEGGER OR AVO METER TO CHECK ANY OPEN CIRCUIT FAULT IN THE HV & LV WINDING OF THE

    TRANSFORMER.

    HV SIDE LV SIDE

    RY = _____ rn = _____

    YB = _____ yn = _____

    BR = _____ bn = _____

    VALUE = ZERO ( CONTINUITY O.K )

    VALUE = INFINITY ( CONTINUITY NOT O.K)

    18

    R

    Y

    B

    r

    y

    n

    b

  • TR BODY

    0

    M

    MEGGER

    LV

    R

    Y

    B

    N

    TR BODY

    HV

    R

    Y

    B

    0

    M

    MEGGER

    Continuity test for HV

    winding

    Continuity test for LV

    winding

    19

  • Voltage ratio test

    Objective:

    To check that the ratio of voltages ( in 3-phase transformers, line to line voltages) is as per designed

    value in all tap position.

    The % Error of the voltage ratio is not more that +/- 0.5 % as per the IS 2026 and IEC 60076

    Apparatus:

    3 phase supply -415V (Applied to HV side)

    Clip on meter for measuring voltage at LV side.

    20

  • Voltage ratio test

    Procedure:

    Apply 3 phase 415V supply on HV side and LV side voltage is to be measured.

    Output voltage will be measure between phase & neutral (VRN, VYN, VBN). Ratio will be changed in respect to tap positions.

    21

    Tap position Vrn Vyn Vbn Vry Vyb Vbr

    1

    2

    3

    4

    5

    6

    7

  • 400v AC

    supply

    ICTP

    TR BODY

    LV R

    Y

    B

    N

    HV

    R

    Y

    B

    VOLT-METER

    Voltage ratio test

    22

  • Voltage ratio test

    23

    HV side 415V

    applied

    Tap switch

    position

    LV side voltage

    measurement

  • Short circuit test

    Objective:

    To determine the Short Circuit impedance voltage.

    To determine the Load losses of the transformer

    Short circuit loss = I2R Loss + stray loss

    Apparatus:

    Voltage injection set (Applied on HV side)

    Clip on meter (Measuring current at LV side).

    Shorting Link (For passing full load current).

    24

  • Short circuit test

    Procedure: LV side will be shorted through

    shorting link.

    Applied the 3 phase voltage on

    HV side and increased the voltage

    till the full load current passed

    through the transformer.

    Unbalance current and phase to phase current measure with the help of Clip on meter.

    Unbalance current should not be more than 2% of full load current.

    Load loss and impedance voltage measured on power analyser. This Load loss measured at Room temperature Converted this loss into 75

    Degree C and it should be within the specified limit.

    25

  • 400v AC

    supply

    ICTP

    TR BODY

    LV R

    Y

    B

    N HV

    R

    Y

    B

    Short circuit test

    Load loss at 75 Degree C = Load loss at RT (A+75) / (A+RT)

    Here RT= Room Temperature

    A= 235 for CU wound

    A= 225 for Al wound

    26

  • Open circuit test

    Objective:

    To know the Excitation losses and currents of Transformer when excited at rated kV at rated Hz

    To determine the No load losses(Core loss) of the transformer

    To check healthiness of winding and stampings.

    No load loss = hysteresis loss + eddy current loss

    Apparatus:

    Voltage injection set (Applied on LV side)

    Clip on meter for measuring no load current at LV side.

    27

  • Hysteresis Loss

    28

    when a magnetic field is applied all the

    grains of the magnetic material will

    orient in the direction of magnetizing

    force. In another cycle this grains will

    orient in opposite direction in the

    direction of magnetizing force. The

    energy required to change the

    orientation of the magnetic grains in the

    direction of the magnetic field is lost in

    the form of heat. This loss is called

    hysteresis loss.

  • Eddy current Loss

    29

    Eddy Current Loss:

    When an alternating magnetic flux is applied to the iron

    core small emf will be induced due to change in flux

    linkage. This induced emf will cause small circulating

    current s called eddy currents. Eddy current flowing

    through the material causes I2R losses in the material.

    In order to reduce the Eddy Current loss:

    Use of Material having high electrical resistivity:

    By using superior grain orientation CRGO steel will have

    higher electrical resistivity. Thus eddy current loss can

    be reduced.

    Lamination Cores are used:

    By using thin laminations the core thickness is reduced

    so eddy current losses are reduced. So CRGO steel

    laminations are used as a core material.

    Insulation between laminations:

    Oxide coating is provided for CRGO laminations to

    reduce eddy current losses.

  • Open circuit test

    Procedure:

    Rated voltage applied on LT side

    of distribution transformer for

    energizing transformer.

    No load current measured by

    clip on meter and no load loss

    measured by power analyzer.

    No load current should not be

    more than 3% of full load current.

    Note: Nobody can go closer to HV side

    because it is subject to 11KV.

    30

  • TR BODY

    LV R

    Y

    B

    N

    HV

    R

    Y

    B

    400v AC

    supply

    ICTP Open circuit test

    31

  • 32

    Rating 1 star 2 star 3 star 4 star 5 star

    KVA Max Losses

    at 50% (Watts)

    Max Losses at 100% (Watts)

    Max Losses at

    50% (Watts)

    Max Losses at

    100% (Watts)

    Max Losses at

    50% (Watts)

    Max Losses at

    100% (Watts)

    Max Losses at

    50% (Watts)

    Max Losses at

    100% (Watts)

    Max Losses at

    50% (Watts)

    Max Losses at

    100% (Watts)

    16 200 555 165 520 150 480 135 440 120 400

    25 290 785 235 740 210 695 190 635 175 595

    63 490 1415 430 1335 380 1250 340 1140 300 1050

    100 700 2020 610 1910 520 1800 475 1650 435 1500

    160 1000 2800 880 2550 770 2200 670 1950 570 1700

    200 1130 3300 1010 3000 890 2700 780 2300 670 2100

    Star Rating of Transformer(BEE)

  • BEE Star Labeling

    33

  • Full load current and loss of different rating

    transformers

    KVA

    HV

    (Amp)

    LV

    (Amp)

    NO LOADLOSS

    ( Watts)

    LOAD LOSS

    (Watts)

    160 8.4 222.6 300 1600

    315 16.5 438.2 515 2750

    630 33.1 876.5 800 4700

    990 52 1377 1250 6200

    34

  • Magnetic Balance Test:

    rn yn bn

    rn= 240 240 156 84

    yn= 240 120 240 120

    bn =240 84 156 240

    Applied 240V on LV side and voltage measured on respective LV terminals

    as under.

    Division should 65:35 between central and the other extreme limb if one

    of the extreme limbs is excited and is 50:50 for central limb excitation

    35

  • 36

  • Break down voltage test of Oil

    Transformer oil is used insulation as well as cooling

    purpose.

    BDV tester ranging from 0-100KV used for test.

    Gap between two electrodes must be maintain 2.5mm.

    BDV of new insulating oil

    Should be more than 60KV.

    37

  • Acidity test of Oil

    In this test we will measure the value of free carbonic and non-carbonic acid in oil and this will be measured

    with the help of acidity testing kit.(mgKOH/gm)

    Acidity must be less than 0.03 for new insulating oil.

    38

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of transformer actions

    39

  • Factory Test

    In addition to routine test some more test are carryout at factory, This

    type of test required some specific testing instruments and testing

    facilities, even through some of the test carryout at site also.

    Winding resistance test

    Vector group test

    Separate source voltage test

    Temperature rise test

    Induced overvoltage test

    40

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of transformer actions

    41

  • Over and above routine test some important test are carried out at

    factory or laboratory like ERDA & CPRI, this type of test required

    some special testing instrument and testing facility.

    Impulse Voltage Test - 95KVp

    Short circuit withstand test - 18.4 KA for 3 sec

    Partial discharge test

    Type Test

    42

  • Distribution Transformer

    Construction of Transformer

    Transformer Name plate details

    Routine Test

    Factory test

    Transformer failure and causes

    Type Test

    Principle of transformer actions

    43

  • Failure & Causes

    Insufficient Oil level.

    Seepage of water in oil.

    Prolonged Over loading.

    Single Phase loading.

    Unbalanced loading.

    Faulty Termination (Improper sized lugs etc)

    Power Theft.

    Prolonged Short Circuit.

    Faulty operation of tap changer switch.

    Lack of installation checks.

    Faulty design

    Poor Workmanship Improper formation of core.

    Improper core bolt insulation.

    Burr to the lamination blades

    Improper brazing of joints.

    Burr /sharp edges to the winding conductor.

    Incomplete drying.

    Bad insulation covering.

    Insufficient cooling ducts in the winding.

    44

  • Failure & Causes

    Faulty design

    Poor Workmanship

    Improper formation of core. Improper core bolt insulation. Burr to the lamination blades Improper brazing of joints. Burr /sharp edges to the winding conductor. Incomplete drying. Bad insulation covering. Insufficient cooling ducts in the winding.

    Bad Quality of raw material.

    Transit damaged transformers. After failure , transformer is removed and replaced with

    new/repaired one without removing the cause of failure which results in immediate or short time failure.

    45

  • 46

  • 6/25/2015 47

  • 6/25/2015 48

  • 49

  • 50

  • 51

  • Thank You