ANALISA PERBANDINGAN KOMBINASI ALAT TOWER CRANE, MATERIALLIFT DAN CONCRETE PUMP TERHADAP BIAYA DAN WAKTU
PELAKSANAAN( STUDI KASUS : PROYEK PASAR ATUM MALL SURABAYA )
ANALYSIS COMPARISON COMBINATION OF EQUIPMENT OF TOWER CRANE, MATERIAL LIFT ANDCONCRETE PUMP ABOUT COST AND EXECUSION ( STUDY CASE : OF PROJECT PASAR ATUM MALL
SURABAYA )
Created by BUDI INDRIYO
Subject : Konstruksi
Subject Alt : Construction Equipment
Keyword : : Volume Pekerjaan; Waktu Pelaksanaan; Perhitungan Biaya Pengecoran; Tower Crane; MaterialLift; Concrete Pump
Description :Tingkat keberhasilan suatu proyek konstruksi dapat diukur antara lain dengan keuntungan serta ketepatan waktupenyelesaian proyek.Keuntungan ini tergantung pada perencanaan awal yang detail dan cermat terhadap metodepelaksanaan, alat yang dipakai serta jadwal pengerjaan proyek bangunan tersebut. Untuk itu perlu pemilihan kombinasigabungan peralatan untuk melaksanakan pekerjaan struktur pada pembangunan Pasar Atum Mall Surabaya.Penelitian ini bertujuan membandingkan kombinasi peralatan yang paling efisien dari segi metode pelaksanaan,waktudan biaya.Kombinasi yang dipergunakan adalah peralatan 3 Tower Crane + Concrete Pump adalah kondisi existing,kombinasi I( 3 Material Lift + Concrete Pump ) dan kombinasi II( 3 Tower crane + 3 Material Lift + Concrete Pump).Hasil analisa dari ketiga kombinasi peralatan adalah untuk kondisi existing : 290 hari dengan biaya Rp.3.003.485.850,00 dan untuk kombinasiI:diperoleh waktu :315 hari dengan biaya Rp. 1.267.625.100,00 sedangkan untukkombinasi II diperoleh waktu :218 hari dengan biaya : Rp. 3.153.324.600,00.
Description Alt:The succesfull of construction project can be measure by profitability and also accuracy of time copletion.Theprofitability it depend on planning early which was detail and careful to execution method, appliance weared and alsoschedule workmanship of building project.is neeed to select the combinations of equipment because of carry out theAtum Mall Surabaya.The research aim compared the was efficient of equipment combinations.toward method, time and cost.The existingcombination is used 3Tower Crane equipments + Concrete Pump. The first combination is case,3 Material Lift +Concrete Pump, second combination is used 3 Tower crane + 3 Material Lift + Concrete Pum.The Result of third research from third equipments combination for existing considered: : 290 day with cost Rp.3.003.485.850,00 for first combination : 315 day with cost of Rp. 1.267.625.100,00 and for combination : 218 day withcost : Rp. 3.153.324.600,00.
Contributor : SUPANI, ST. MT
Date Create : 15/01/2010
Type : Text
Format : pdf
Page 1
Language : Indonesian
Identifier : ITS-Undergraduate-3100007029454
Collection : 3100007029454
Call Number : RSS 624.028 4 Bud a
Source : Undergraduate Theses, Civil Engineering, RSS 624.028 4 Bud a, 2007
COverage : ITS Community Only
Right : Copyright @2009 by ITS Library. This publication is protected by copyright and permissionshould be obtained from the ITS Library prior to any prohibited reproduction, storage in aretrievel system, or transmission in any form or by any means, electronic, mechanical,photocopying, recording, or likewise. For information regarding permission(s), write to ITSLibrary
Full file - Member OnlyIf You want to view FullText...Please Register as MEMBER
Contact Person : Administrator ([email protected])
Taufik Rachmanu ([email protected])
Moh. Fandika Aqsa ([email protected])
Tondo Indra Nyata ([email protected])
Ansi Aflacha Putri ([email protected])
Aprillia Tri Wulansari ([email protected])
Thank You,
Nur Hasan ( [email protected] )
Supervisor
Page 2