6
3-- ., , i v# g . ' ' e..; - Carolina Power & Ught Company 4 ' ( 1 Brunswick Nuclear Project * p P. O. Box 10429 . ' Southport, NC 28461-0429 March 22, 1990 PILE: B09-135100: r. SERIAL: BSEP/90-0244 . U U.S. Nuclear Regulatory Commission ATTN: Document Control Desk , Washington.-DC 20555 y- ji BRUNSWICK STEAM ELECTRIC PLANT UNITS 1 AND 2 L DOCKET NOS. 50-324 & 50-325 ' !- LICENSE NOS. DPR-62 & DPR-71 F RESPONSE TO NRC IFI 50-325/88-36-02 AND 50-324/88-36-02 s Gentlemen: [ The Final Summary Report for 15' Bulletin 79-02 is submitted in response to NRC. . Inspection Report 50-325/88-36 and 50-324/88-36, dated November 3, 1988. Item 4 4 s - of this| inspection report closed Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts - IEB 79-02, and opened Inspector Follow-up- ' Items 50-325/88-36-02 and 50-324/88-36-02, which stated that CP&L would submit a Final Summary Report summarizing the bulletin requirements.and BSEP's response. The review of Ililti Bolt allowables (Inspector Follow-up Item 50-325/88-36-03:and 50-324/88-36-03) will be addressed at a later date, a IE Bulletin 79-02 requirements coupled With appropriate CP&L actions are as follows: '1. Verify that pipe support base plate flexibility was accounted for in the calculation'of anchor bolt loads. CP&L action is as follows: |' References: , a. Details of NRC Exit Interview (dated 8/7/80) which reference LER 2-80-55 A b. Letter BSEP/81-0440 (dated 2/25/81) c. Letter BSEP/82-1616 (dated 7/26/82) which provides a chronological account of CP&Ls actions taken to assure compliance of already installed base plates to the bulletin flexibility position. | ~9003290176 900322 7 ~ ADOCK0500ggj4 PDR f6 , * - 9 _ >

DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

3--.,,

i v#g .

''e..;

-Carolina Power & Ught Company4

'

(1 Brunswick Nuclear Project*

p P. O. Box 10429.

'

Southport, NC 28461-0429March 22, 1990

PILE: B09-135100:r. SERIAL: BSEP/90-0244

.

U U.S. Nuclear Regulatory CommissionATTN: Document Control Desk

,

Washington.-DC 20555y-ji BRUNSWICK STEAM ELECTRIC PLANT UNITS 1 AND 2L DOCKET NOS. 50-324 & 50-325'

!- LICENSE NOS. DPR-62 & DPR-71F RESPONSE TO NRC IFI 50-325/88-36-02 AND 50-324/88-36-02s

Gentlemen:

[ The Final Summary Report for 15' Bulletin 79-02 is submitted in response to NRC..

Inspection Report 50-325/88-36 and 50-324/88-36, dated November 3, 1988. Item 44

s - of this| inspection report closed Pipe Support Base Plate Designs UsingConcrete Expansion Anchor Bolts - IEB 79-02, and opened Inspector Follow-up-

' Items 50-325/88-36-02 and 50-324/88-36-02, which stated that CP&L would submita Final Summary Report summarizing the bulletin requirements.and BSEP'sresponse. The review of Ililti Bolt allowables (Inspector Follow-up Item50-325/88-36-03:and 50-324/88-36-03) will be addressed at a later date, a

IE Bulletin 79-02 requirements coupled With appropriate CP&L actions are asfollows:

'1. Verify that pipe support base plate flexibility was accounted for in thecalculation'of anchor bolt loads.

CP&L action is as follows:

|' References:,

a. Details of NRC Exit Interview (dated 8/7/80)which reference LER 2-80-55

A b. Letter BSEP/81-0440 (dated 2/25/81)c. Letter BSEP/82-1616 (dated 7/26/82)

which provides a chronological account of CP&Ls actions taken toassure compliance of already installed base plates to the bulletinflexibility position.

|

~9003290176 900322 7 ~

ADOCK0500ggj4PDR

f6,

*- 9

_ >

Page 2: DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

- - - - z

'

:,,.;

'.,

U.S. Nuclear' Regulatory Commission -2-.

%u ' . .

Relative to new design, in order to ensure that new base ~ plate designs.took-'

into account the flexibility position, Attachment'l to CP&L Letter,.Serial: -GD-79-1739 was adopted and issued as a part of Power DisciplineTechnical Bulletin 7B to be used as.a design _ guideline for base plate design, ,

:This was'later included in UE&C's H-21 evaluation criteria and later in, '

the Brunswick Engineering Support Unit's (BESU). Structural Design Guides 2and.7 which are the on-site guideline for pipe support design. |

'

o2 .- Verify that the concrete expansion anchor. bolts have the following

minimum-factor of safety between the bolt design. load.and the bolt; ,

4 ultimate capacity determined'from static tests which sim'ulate:the actualconditions of. installation. .,.

$ .

I

CP&L action is as-follows:-i

r.

t References:

a. Letter GD-79-1739 (dated 7/12/79)'

'b. Letter GD-79-3130 (dated 12/6/79)c. Letter BSEP/80-2139 (dated 12/30/80) ;d. Letter BSEP/81-0440 (dated 2/25/81) '

e. Letter BSEP/82-1616-(dated 7/26/82)-f. Letter NLS 84-214 (dated 11/26/84) ,:

,

which discuss in detail CP&L's anchor bolt testing and reanalysis |programs which assure compliance of "in place" anchor bolts relative

' |,

to the accepted factors of safety.

Power Discipline Technical Bulletin 7B covers the new design and was jwritten to include the factors of safety provided by Bulletin 79-02.Ae' stated before this information was used in UE&C's M-21 evaluationcriteria and in BESU's Structural Design Guides 2 and 7.

.

3. Describe the. design requirements, if applicabic,-for anchor bolts to !

withstand cyclic loads such as seismic' loads and high cycle' operating ;

loads,,

E CP&L. action is as. follows:t

References: :, !

a. Letter GD-79-1739 (dated 7/12/79) ;b. Letter BSEP/82-1616 (dated 7/26/82)c. Letter NLS-84-214-(dated 11/26/84) !

which explain the position taken by CP&L relative to cyclic loading.

and the torquing program that was adopted to ensure that existing ;

expansion anchors could withstand such loading.,

;

v

h

-t

a

Page 3: DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

pq 3-

~r

, ,

?yqx ; < . ,,

6, ,.pp. ,

fy %|) *~

.

, - 4 .

L U;S. Nuclear Regulatory Commission- -3-,

%$

-

j|A To ensure that e.'# design.is acceptable 1 relative to. cyclic loading*

.f -the same series of-design documents. listed under requirements i and 2 _. !

above nyre updated with the new pretensioning loads _ relative to the ;._

.

design allowable as mentioned in CP&L's torquing program.; '

,

~4. Verify from-existing QC documentation that design requirements have been>

met for anchor bolts relative to cyclic loading and bolt size and type.'

CP&L's compliance with this part of Bulletin 79-02/is. covered by'the= -|.

testing program as described in the letters referenced in Section11' j

above. That test program was used to check:for-indication of-incorrect- |

proload'and incorrect bolt size, type,.and embedment.

cf For nos design work- QC hold points were established-~as a part of site,'

installation specification BSEP 248-107, to ensure that these require-,

i monts were met'. i,

i ?

5. Determine the extent that= expansion anchor bolts were used in-concrete" ' block (masonry)' walls to attach piping supports in Seismic Category-+

,,

1/ Safety Related systems. ]CP&L |did- noti use expansion anchors . to attach safety-related'systen s',

~

to concrete block walls.

6', Determine:the extent that pipe supports with expansion" anchor' bolts used'N structural steel shapes instead of base. plates. 3

-As stated in CP&L Letter GD-79-3130, support.. meeting this criteriawere included in the inspection and reanalysis program which was-

,Iestablished.at the beginning of the bulletin compliance effort and

w continued until-program completion..

Relative:to new design work-the same criteria established in the

..design documents in Sections l', 2,-and 3 above' applies to supports. H

.

with' standard' structural steel shapes used in lieu of base plates, ["!~ although base plates are used almost exclusively for new design on

safety-related systems.t

N |Tho'remainderzof the requirements listed in IE Bulletin 79-02 refer to the- *

scheduling of requirement completion. ;,

' : Attachmcrit 1 provides a short synopsis'of those correspondences referred to inthis letter.

!

This report summarizes the correspondence between the Brunswick Steam Electric !Plant and the NRC pertaining to the requirements-of IE Bulletin 79-02.

t

h

.

1

!

[ d!

Page 4: DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

v , - , .

.4 : 1 * ' ' . , _ _ - . ._. _' 'r #. ,7 4 $ + Ir g, y-

._

-/ f. f 1 1 ;1)O -%tjp?ggf%m m) 7 p' ,r E ;d; i n.> t as T, 4(% . . s 1

. a, " ' ' ' T ,s,We ,m.

, , ,., y ,<

WNhk$d ( .|N th,.'|, ' ? U:g'.'m, 4 ~~-W, * * ;,

.

* * i + E kNU |$4, ,.

G l'- ,' s \ ai

p t.. 2 < .L F 1 74 -.T'- . j'c,.

. (r-' ;t ._ 7=> :, ~ .

;

go - a w. .n., 4.

Q.*_ (. 3

o -

4 , .,

. . j-f }

;e 4x4Cy [ ''' 44j '. - [ . ., Q; .g' ^ -4 (

2 I ''

-fy iv ;> r ura t

t e.+ ' _-

( i+ -- ;t

e - m'1:, i ,a :9- , . . .g :;* -,

_ f . f = m'' e

m , ' 's,v. 't_ff s h~ f |:)| 3

'"'d '

,,

+ c ,

{g[x).g, , , ,

','g. . . . . . c . 2 - , .. -M '. . -[ . . f . sJ~

/ TR. f~ ; U.S. ' Nuclearc-Regul' atory, Commission;,. c - 4,-,. -

> +

p,. w;w; ' s* , , , - , 4

~n. w m -

p 0,p r.w- i

.-,

,

y-E , i,

q.Q 4' >hM q

- <- - t,,. ,. s . ..+ , = . , 1

T Q:r , y,._! Please'refertany(questionsfregarding'this- submittal'to Mr.1Je W.: Moystrat.; y y

' '

f- | bW L(919) 457-24041'

~ ~

t, -..

-

' '

w ~ n7.- <

-

1 _ :.,

-9L.

- .g-~

{gbi Very,trulyfyoursb'

(

y,,

1n+ , --

1

,

D. .

,. , .-g g,1,

< ' ' .f-- .;i - - - -

s

m s . 7_ ,.

, -i

;a , A -" ' . L. IJarness,E General' Manager' f,

s.

'

&, t- . Brunswick NucleartProjectJ 4, -

..

=-

a,.-

-. . _ . .v ..,,

.

p' ~ TMJ/mcg1_ ,

1'

, ,

.upgy.p.

. q,

. .. ,

H c ! Enclosure. 's - mw , -.. ry.n v ; . >. r:.

R '+ 'cc: - Mrs S.: D. iEbneteri.

-

' ~ jM y -Mr.1E d G.5:Tourigny _.4:

' " . .. '-' 4' / ' f '1-

.

dia 'BSEP<NRC Resident Office < '

s

+ - - -

+.u\ ' 5

g ,'4ey - - . t -..g4

'

: (t a , 4. )w ,

'

- , / [ i,il'., ' $, ;5

; 4. '3

*1 .

,tg yw:v.. , .

: wy.

,> ;4A

, .,*r, m

#(~ 51 ,. t g

[ ! i ;. i j :. ' ,,-=

,-

p; v , m. . u . - g .(;) :- r < ,

'*'

qj;. Q , A; ' ',

f3_ ;m '. p . 7 / $,* *

, e-

>er.; ;;: + ~ - _-' ,:q '{ n . (gu -p. . -

- 3)L ,ii :

. pm: n r s 1 ,e

-

"s, ' . r..

g'e % . -h

f: f.,' ;-n ,. ,

'4.-s, ,

4.

}4 'h

4 3 .g; ..g.'"

. ..J

. . . - . , - - , -'-\_, l'.''*.b*-1'e

g

'

?l .?y@

%'s

- 4' i)'

, .

;$*>

i

J

f 4 L r ; >

| i, % 1

Ev ,7 ;,

: ry.

I #''.^~'f.- j g&4-g+ -.2 - -.r 4. , .* '' ' ;}.I -)

''

-

| ...l..'(

4'\ 'i&%s 4

.t> '- f;- ?-Q,, 3*-i .-r < y : \;.

' IiIsta --:T.

Nko x'!-t s' '*

-+cw u ,, f f W d i s n. '

', $Y!h . h b' a%,pqQC * t :

- 3'1 h j[.N. Ej

-

m;. i

;. I',w ' .

v y.. .y. -

,

,

r.,- -*: j

r}:cg

.

.i, =q-| .?.

,

.

i S w .p..f i

,,|

3

pm f,,.. >

,.

.vk,

y' k}.

\ .,j ,'

, ,'. .1 |-> ;4g ' ' '. !..

b r' ', v' ,

i 3- 1 ( r'e ''

f Yy % 1 i Yh Y . pp h .iw ?,e = o .. ,Q ? .7 X. 9 r. 2! !

y ..e w , V .s. . ,. e..tu - )J.h &.s ,4 ,

~~d' e t >.

*.

|;>

w%ynn,' f '''%y:c ,

fa [" Z h:# j I f [, .; .5v' 'j.. m+u - - p. ,w'.m '; N P y1 8 -..,

,N . ,

, M. . m ..sKa:n ,&. :e

v..w>

h , ' : 'p p t ,q' . c 3 ..- y.g g .. ,

r s; q. .

g ,.-g. -

...o

h"p . .. I

f ,.,'

$ ,p-:P*'{.' 6. 'e..v,

N O D ?,ya-g'| q ,'- 4

N' '

+ fh+t -,i,u..'

-

> '' ' \ ""h*,

,4 1g

- s. . g ~ .-

-

,i r .-' b i, jr

-

1 3-

Page 5: DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

- o ,

p x.; p .

.

git

|- ,V . - -

b i /, ' L ATTACllMENT 11

Q/,y:'y !$hesfollowing list is composed of pertinent letters and memorandums dealing-~

; with' tho' BSEP closure of IEB 79-02 along with the . appropriate actions taken to'gf. . resolve any'open items., --Note that this. list,is intended to deal with IEB-

'79-02_tnly, even though much of the information-included references IEB'79-07.-.and:IEB 79-14,

~

-1. LLetter GD-79-1739 CP&L to NRC, dated July 12, 19794

R

y This letter explained, item by item, CP&L's current position regarding -g- cach-facet of IEB 79-02. Safety-related~ piping base plates ' wore -

reanalyzedifor new loads per the.new IEB 79.-07. guidelines. This was' done-

, ,

'by BSEP Plant ModAfications 79-123'and 79-124. Work was ongoing to-. .

J comply with the noe safety factors for expansion anchora. The nuts onif expansion anchorsJwere to be retorqued to satisfy the requirements for

cyclic loading. . An expansion alachor test program was initiated at.BSEP,.

y the results of which would be m31ntained on. site' for. NRC inspection.

2. Letter GD-79-3130, CP&L to NRC, dated December 6,1979m~

This letter stated that the requirements of IEB 79-02'had'been satisfied"' .by CP&L, -A few. inaccessible hangers were noted, butischeduled for

..

E completion during the next outage. Appropriate documentation was in the-plant vault available~.for NRC review.

~

3.. Detall's-of:NRC Exit Interview, dated August 7, 1980

y,~ Due to-LER 2-80-55, it was realized that the CRD-linerb4se plates were'

not included in the base plate flexibility roanalysis. Because of this,

~

the-Bulletin would remain open. 'A completion commitment date of3;j,"

LDecember 31,~1980, was given<by CP&L.

4. Letter BSEP/80-2139, CP&L to NRC, dated December- 30~ 1980'

,

, ,

CP&L stated that approximately 300- additional supports per unit' had been-

(identified for expansion anchor testing. requiring.that the final IEBs79-02schedule be pushed forward. The final schedule would be presented-February-25, 1981.

,W 5. ~. Letter BSEP/81-0440, CP&L to NRC, dateel February 25,L 1981

' Flexure acolysis was completied for the essential-CRD base plates.Completion of base plate flexibility tecting relative to piping not- . ,

, essential to safe shutdown was scheduled as.a part of the Phase IIc j, ~f program.(March 51,.1982). Test.ing of the-accessiblo-portion of the 600-

.

' additional supports (see above) was scheduled for completion by July 31,.o

p, 1981..

1

\

|Q' t

.

> }'

, ,

'''

,

'

e

g h'a 4' ' ,.- I1

4% '

, ,, , ,

Page 6: DOCKET NOS. 50-324 & 50-325 LICENSE NOS. DPR-62 ...Letter NLS 84-214 (dated 11/26/84),: which discuss in detail CP&L's anchor bolt testing and reanalysis , programs which assure compliance

,

NCT;46'

.I

g , Wpy * W <

j,'

oh 1y S ** ,'

,

: p; ATTACHMENT 1:(Cont'd)*

.

6. ' Letter.BSEPL82-1616,- CP&L to NRC' dated July' 26,11982 ,

'%' CP&L stated that nonessential-portions of the CRD system (Phase II) are.

~

*,

not safety related;and, therefore, reanalysis is not-required. Also.*

7 stated was the fact that the. additional BSEP-2 support: testing was:.

-

4

completed. -BSEP-1 testing-is essentially. complete with.the few: remainingsupports to be finished during the-upcoming' September 1982 outage.

-t

7. Letter NLS 84-214, CP&L to NRC,' dated November 26, 1984 .,

.. ;<

c -This was the last submittal concerning'IEB.79-02.~ . It statedLthat the"-

t

expansion anchor testing was completed. The BSEP-1-CRD support; fixes ;,

were' completed and BSEP-2 CRD supports'are to be completed pending'

-redesign of the Reactor Pressure-Vessel foundation wall window supports. ;.

The remaining work toL complete the obligation in Letter NLS -84-214 = (Item 7 - -

above) was done by;PlantiModification 82-147. This documents'the. completion,s

of the brunswick Steam Electric Plant. work pertinent to IE' Bulletin 79-02. .iBased onJthe information provided'to the NRC' relative to this Bulletin,' we- ?

irequest the closure.of-IEE 79-02.'

.

P

r

k

-

],>

;W 't

'+

-i

c

gf

4

i

,.

9/ .I

~'

bi,

1

t

!

C 41 3 .- r

,- < ii

P 4