SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 1 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
PURPOSE: To obtain safe and operational high yield of structure erection works which saves time
and cost and serves to avoid rework.
SCOPE: Describe steps in details how to proceed for a quality, high productive method for structure
erection works.
RESPONSIBILITY: Project Manager/Site In-Charge, Section In-Charge & DC Contractors
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 2 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
DESCRIPTION
1. REQUIRED TOOLS AND MATERIALS:
S. No. Tool Photo Application
1 Torque Wrenches
Used to apply torque of
desired value
2 Spanners
For tightening of Nut
Bolts
3 Measurement tape
For measurement distance
4 Cotton cord
Used as a reference for
alignment of structure
5 Power Tools
Makita power tools should
be used to torque nut bolts
at desired torque value
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 3 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
6 Inclinometer
To check alignment of
structure
7 Water level pipe
To check height of two
stubs for straight
alignment of structure
assembly
8 A- type ladder
Used for working at
height part of structure
9 PPE
To protect worker from
get hurt
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 4 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
2. WORK PROCEDURE
2.1 PRELIMINARY ACTION
Inspection of the stub casting and alignment. Record for any deviation and report to
concern.
Check the actual vertical level difference between different foundations in one array using
water level pipe
2.2 STRUCTURE INSTALLATION
Before commencement of structure erection work all modules pallets should be shifted to
location where erection work will be started.
Checking of
Verticality of stub using
inclinometer
Checking actual vertical difference between two
stubs using water level pipe
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 5 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
Module pallets should have to be only lifted by fork lift attached to excavator. Ensure that
pallets should be placed in such a way so that it will not affect structure erection work.
NOTE: Tool Box Training (TBT) should be given before shuffling of module pallets.
Tools used for erection of structure need to be calibrated and calibration should be checked
at site before commencement of work.
Module Pallets
shake out at respective
location
Pallets of module
lifting from container using
fork lift
Fork lift
attached to
excavator
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 6 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
After shuffling of module pallets to their location assembly of rafter should be done at stub.
Tool Box Training should be given to worker before erection work about safety at working
area.
After the installation verify that all the fasteners are as per the BOM provided by the design
drawing. If any deviation is found during the assembly immediately report to the concerned.
Make sure that the spring washer is placed along with nut always and not with the head of
the bolt. It is advisable to use flat washers of appropriate thickness wherever slotted holes
are encountered in the structure.
TBT
about safety and handing
of structure
materials Assembly
of rafter
Calibrated tools
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 7 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
After assembly of rafter other structure material viz. purlin, mounting rail etc. should be
done using cotton cord for alignment of structure.
Tightening of structure parts should be done using power tools and spanner. Torqueing of
nut bolts should be checked using torque wrenches at required Nm and torque marking
already done.
Ensure that both the extreme end members are tightened with specified torque and specified
tools. Use calibrated torque wrench and spanners for final tightening. To save on time and
labour requirement use power tools i.e. pneumatic power tools / electric battery based
power drive tools.
Assembly and
alignment of
structure parts
Nut Bolts tightening using
power tool
M10 Bolt
M10 Flat
washer
M10 Nut
M10 Spring
washer
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 8 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
Now place end clamp and mid clamp with proper nut bolt assembly at their respective
positions. Ensure that clamp without rubber should not be placed in structure.
Take the structure already installed as a reference and proceeds with installation of other
structures.
2.3 LIST OF FASTENERS.
Item
Photo
M10 Bolt
M10 Nut
M10 Flat Washer
Placement of end and
mid clamps
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 9 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
M10 Spring
Washer
M6 Bolt
M6 Nut
M6 Flat Washer
M6 Spring
Washer
2.4 RECORDS
Structure Erection Checklists
Notes: Tools must be calibrated with NABL accredited lab.
3. SAFETY PRECAUCATION
3.1) PERSONAL PROTECTIVE EQUIPMENT
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 10 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
Appropriate safety helmet must be worn at all times in all sites.
Appropriate safety footwear must be worn at all times in all sites.
Approved safety glasses must be worn at all times in all sites.
Approved Full Body Harness with double lanyard must be worn at all times in all
sites.
Approved reflective jacket must be worn at all times in all sites.
Appropriate ladder must be used.
Use appropriate type of gloves. Safety gloves should be worn when handling steel,
securing straps, ropes or chain slings
Appropriate scaffold must be used.
Ring or Jewelry must not be worn and removed.
3.2) PRE-OPERATIONAL SAFETY CHECKS
Close co-operation and effective supervision during handling of structural material at site.
Check the area where the material is to be unloaded. There needs to be clear space for
subsequent handling of material.
The capacity of the lifting equipment on site to be checked vis-à-vis weight of the load
specific requirements for safe slinging or handling of the load, should consider following:
All the risks have been assessed.
Are the Working Load Limits Adequate?
What is the weight of the load?
Where is the centre of gravity?
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 11 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
What is the sling angle?
Capacity of the gear?
Will the Load Be Under Control?
Tag Line available?
Is there any possibility of fouling?
Clear of Personnel?
All lifting tools / Machine needs to be inspected from TPI.
Securing of load components to lifting.
Bundle length Max bundle Weight Slinging Point
< 6m <150 kg Min 3 points
Unloading of MMS Should be carried out once all the risks have been assessed.
Don’t tie the load to an object to drag it off by moving the vehicle
If the load becomes unstable in some way during unloading, unloading should stop
immediately and the relevant competent person should be informed. Access to the vehicle
may be dangerous in these circumstances as the load could move unexpectedly and a larger
exclusion zone should be imposed around the vehicle. A decision to re-commence
unloading should only be made by staffs who are competent to make such a decision.
4. RECORDS: CHECKLIST
5. REVISION DETAILS: -
S. No Date Rev No Rev. History Remarks
SOP FOR STRUCTURE
ERECTION
Doc.No.: PRJ(SOL)-SOP-04
Rev.No: 00
Eff. Dt.:01-08-2018
Approval Date: 31.07.2018
Page 12 of 12
Prepared by: Project Planning Vetted by: Quality & Design
Approved by: Head – Solar Ground Mounted
1 00 New release