56
Document of The World Bank Report No: ICR1376 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47280) ON A LOAN IN THE AMOUNT OF US$91 MILLION TO THE PEOPLE‟S REPUBLIC OF CHINA FOR A FOURTH INLAND WATERWAYS PROJECT December 28, 2011 China and Mongolia Sustainable Development Unit Sustainable Development Department East Asia and Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

Document of

The World Bank

Report No: ICR1376

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IBRD-47280)

ON A

LOAN

IN THE AMOUNT OF US$91 MILLION

TO THE

PEOPLE‟S REPUBLIC OF CHINA

FOR A

FOURTH INLAND WATERWAYS PROJECT

December 28, 2011

China and Mongolia Sustainable Development Unit

Sustainable Development Department

East Asia and Pacific Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

CURRENCY EQUIVALENTS

(Exchange Rate Effective April 1, 2011)

Currency Unit = Renminbi

RMB1.00 = US$0.15

US$ 1.00 = RMB 6.55

FISCAL YEAR

January 1-December 31

ABBREVIATIONS AND ACRONYMS

CPS Country Partnership Strategy

dwt

EAP

Deadweight ton (for vessels)

Environmental Action Plan

EIA Environmental Impact Assessment

EIRR Economic Internal Rate of Return

FIRR Financial Internal Rate of Return

GPTD

GOC

Guangdong Provincial Transport Department

(former Guangdong Provincial Communications Department)

Government of China

GPWB Guangdong Provincial Waterway Bureau

GXTD Guangxi Transport Department (former Guangxi Communications Department)

GWh Gigawatt hour

GXWCDC

ICB

Guangxi Xijiang Waterways Construction & Development Co.

International Competitive Bidding

ICR Implementation Completion and Results Report

IWT Inland Water Transport

KWh Kilowatt hour

MIS Management Information System

MOT Ministry of Transport (former Ministry of Communications)

MOF Ministry of Finance

NCB National Competitive Bidding

NEPA National Environmental Protection Agency

NPV Net Present Value

OED Operations Evaluation Department

PAD Project Appraisal Document

PMO Project Management Office

QCBS Quality and Cost Based Selection

RAP Resettlement Action Plan

RMB Renminbi

SOE State-owned Enterprise

TA Technical Assistance

Page 3: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

Vice President: James W. Adams, EAPVP

Country Director: Klaus Rohland, EACCF

Sector Manager: Paul Kriss, EASCS

Project Team Leader: Wenlai Zhang, EASCS

ICR Team Leader: Wenlai Zhang, EASCS

Page 4: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel
Page 5: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

CHINA

FOURTH INLAND WATERWAYS PROJECT

Implementation Completion and Results Report

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design ............................................... 1 2. Key Factors Affecting Implementation and Outcomes .............................................. 6

3. Assessment of Outcomes ............................................................................................ 9

4. Assessment of Risk to Development Outcome ......................................................... 13 5. Assessment of Bank and Borrower Performance ..................................................... 13 6. Lessons Learned ....................................................................................................... 15

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 15 Annex 1. Project Costs and Financing .......................................................................... 17

Annex 2. Outputs by Component ................................................................................. 19 Annex 3. Economic and Financial Analysis ................................................................. 22 Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 26 Annex 5. Summary of Borrower's ICR and/or Comments ........................................... 28

Annex 6. List of Supporting Documents ...................................................................... 39 Maps:

1. IBRD 32887

2. IBRD 32888

3. IBRD 32889

4. IBRD 32890

Page 6: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

i

A. Basic Information

Country: China Project Name: Fourth Inland

Waterways Project

Project ID: P077137 L/C/TF Number(s): IBRD-47280

ICR Date: 12/28/2011 ICR Type: Core ICR

Lending Instrument: SIL Borrower: PEOPLE'S REPUBLIC

OF CHINA

Original Total

Commitment: USD 91.0M Disbursed Amount: USD 90.55M

Revised Amount: USD 90.55M

Environmental Category: A

Implementing Agencies:

Guangdong Provincial Transport Department

(Former Guangdong Provincial Communications Department)

Guangxi Transport Department

(Former Guangxi Communications Department)

Co-financiers and Other External Partners:

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 10/30/2002 Effectiveness: 01/09/2005 01/09/2005

Appraisal: 08/27/2003 Restructuring(s): - -

Approval: 03/25/2004 Mid-term Review: - -

Closing: 01/31/2010 06/30/2011

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately Satisfactory

Risk to Development Outcome: Low

Bank Performance: Moderately Satisfactory

Borrower Performance: Moderately Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Satisfactory Government: Satisfactory

Quality of Supervision: Moderately Satisfactory Implementing

Agency/Agencies: Moderately Satisfactory

Overall Bank

Performance: Moderately Satisfactory

Overall Borrower

Performance: Moderately Satisfactory

Page 7: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

ii

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem Project

at any time (Yes/No): No

Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): No

Quality of Supervision

(QSA): None

DO rating before

Closing/Inactive status: Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Ports, waterways and shipping 65 60

Power 10 15

Renewable energy 15 15

Sub-national government administration 10 10

Theme Code (as % of total Bank financing)

Climate change 17 17

Infrastructure services for private sector development 33 33

Rural services and infrastructure 17 17

Water resource management 33 33

E. Bank Staff

Positions At ICR At Approval

Vice President: James W. Adams Jemal-ud-din-Kassum

Country Director: Klaus Rohland Yukon Huang

Sector Manager: Paul Kriss Jitendra Bajpai

Project Team Leader: Wenlai Zhang Graham Smith

ICR Team Leader: Wenlai Zhang

ICR Primary Author: Kek Choo Chung

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

The objective of the Project (as stated in the Loan Agreement) is to assist the Borrower in:

(1) improving the market access for its southern region by upgrading navigation conditions

on the region's major east-west river and other waterways feeding into the Zhujiang River

Delta region; and

Page 8: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

iii

(2) meeting the growing energy demand in Guangdong and Guangxi by harnessing water

flow in two rivers in such region to generate environmentally clean electricity.

Revised Project Development Objectives (as approved by original approving authority)

Not Applicable.

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : GX-Waterway traffic (thousand tons) - (i) Baise-Nanning

Value

quantitative or

Qualitative)

814 2,180 - 2,395.9

Date achieved 12/31/2003 12/31/2009 12/31/2009

Comments

(incl. %

achievement)

Tonnage of cargo carried on project waterway almost trebled since the project was

launched, is about 110% of target.

Indicator 2 : GD-Waterway traffic (thousand tons) - (ii) Shaoguan-Qingyuan

Value

quantitative or

Qualitative)

4,900 7,180 - 5,760

Date achieved 12/31/2003 12/31/2009 12/31/2010

Comments

(incl. %

achievement)

Freight carried on the waterway was 80% of target, because the construction of the

new Qingyuan Complex reduced freight volume on the corridor.

Indicator 3 : GD-Waterway traffic (thousand tons) - (iii) Laolonghu Waterway

Value

quantitative or

Qualitative)

1,200 9,300 - 1,334

Date achieved 12/31/2003 12/31/2009 12/31/2010

Comments

(incl. %

achievement)

The target volume of freight could not be achieved due to the delay in completion of

the reconstruction of Lianyao and Longma Bridges. The existing old bridges had

inadequate height clearance to allow the passage of 1,000 dwt vessels.

Indicator 4 : GX-Average barge size (dwt) - (i) Baise-Nanning

Value

quantitative or

Qualitative)

97 152 - 144.7

Date achieved 12/31/2003 12/31/2009 12/31/2009

Comments

(incl. %

achievement)

Average size of vessels using the project waterway is 95% of the target, but has

grown almost 50% since the project appraisal.

Indicator 5 : GD-Average barge size (dwt) - (ii) Shaoguan-Qingyuan

Value

quantitative or

Qualitative)

150 300 - 199

Page 9: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

iv

Date achieved 12/31/2003 12/31/2009 12/31/2010

Comments

(incl. %

achievement)

Average barge size using the waterway has grown by 33% since the project

appraisal, but is 66% of target. There is usually a lag for barge operators to replace

old/small barges with larger ones after the waterway is improved.

Indicator 6 : GD-Average barge size (dwt) - (iii) Laolonghu Waterway

Value

quantitative or

Qualitative)

80 500 - 100

Date achieved 12/31/2003 12/31/2009 12/31/2010

Comments

(incl. %

achievement)

Only 20% of target was achieved, as the use of larger vessels on this waterway was

not possible because of the delayed completion of the reconstruction of two existing

bridges. The underneath clearance of the existing bridges limited the maximum size

of vessels to 100 dwt.

Indicator 7 : GX-Powerplant output (GWh) at (i) Naji

Value

quantitative or

Qualitative)

none 253 - 227

Date achieved 12/31/2003 12/31/2009 12/31/2009

Comments

(incl. %

achievement)

90% of target was achieved due to the delay in filling the reservoir.

Indicator 8 : GD-Powerplant output (GWh) at (ii) Xiniu

Value

quantitative or

Qualitative)

none 46 - none

Date achieved 12/31/2003 12/31/2009 12/31/2010

Comments

(incl. %

achievement)

Power generation had not yet started due to the delay in installation of generators

and in the erection of the transmission line.

Indicator 9 : GX-Transit time through lock incl. waiting time (minutes) - (i) Naji

Value

quantitative or

Qualitative)

none 90 - 90

Date achieved 12/31/2003 12/31/2009 12/31/2009

Comments

(incl. %

achievement)

Transit time through lock meets designed performance.

Indicator 10 : GD-Transit time through lock incl. waiting time (minutes) - (ii) Xiniu

Value

quantitative or

Qualitative)

none 90 - 90

Date achieved 12/31/2003 12/31/2009 12/31/2009

Comments (incl. %

achievement) Transit time through lock meets designed performance.

Page 10: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

v

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : % of civil works completed - Guangxi

Value

(quantitative

or Qualitative)

0% 100% - 100%

Date achieved 12/31/2003 12/31/2008 12/31/2009

Comments

(incl. %

achievement)

Civil works contracts were completed as scheduled although commencement of

main contracts was delayed by about 9 months due to protracted processing for

award of contract.

Indicator 2 : % of civil works completed - Guangdong

Value

(quantitative

or Qualitative)

0% 100% - 98%

Date achieved 12/31/2003 12/31/2008 12/31/2010

Comments

(incl. %

achievement)

98% of target achieved. All Bank-funded contracts were substantially completed,

while a couple of contracts financed by counterpart funds were on-going at the time

of monitoring.

Indicator 3 : % of equipment (by value) contracted – Guangxi

Value

(quantitative

or Qualitative)

0% 100% - 100%

Date achieved 12/31/2003 12/31/2008 12/31/2008

Comments

(incl. %

achievement)

All contracts for the supply and installation of equipment were executed by the

target completion date.

Indicator 4 : % of equipment (by value) contracted - Guangdong

Value

(quantitative

or Qualitative)

0% 100% - 100%

Date achieved 12/31/2003 12/31/2008 12/31/2010

Comments

(incl. %

achievement)

All contracts for the supply and installation of equipment were executed.

Indicator 5 : % of training (person-months) completed - Guangxi

Value

(quantitative

or Qualitative)

0% 100% - 100%

Date achieved 12/31/2003 12/31/2008 04/30/2010

Comments

(incl. %

achievement)

Overall target achieved 100%, while the reduction in overseas training was counter-

balanced by an increase in domestic training.

Page 11: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

vi

Indicator 6 : % of training (person-months) completed - Guangdong

Value

(quantitative

or Qualitative)

0% 100% - 80%

Date achieved 12/31/2003 12/31/2008 12/31/2010

Comments

(incl. %

achievement)

Overall target achieved 80% due to a 20% reduction in the person-months of

overseas training.

Indicator 7 : % of resettlement completed – Guangxi

Value

(quantitative

or Qualitative)

0% 100% - 100%

Date achieved 12/31/2003 12/31/2008 12/31/2009

Comments

(incl. %

achievement)

Indicator 8 : % of resettlement completed – Guangdong

Value

(quantitative

or Qualitative)

0% 100% - 100%

Date achieved 12/31/2003 12/31/2008 12/31/2010

Comments

(incl. %

achievement)

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 06/17/2004 Satisfactory Satisfactory 0.00

2 12/22/2004 Satisfactory Satisfactory 0.00

3 04/29/2005 Satisfactory Satisfactory 0.46

4 12/23/2005 Satisfactory Satisfactory 2.46

5 07/19/2006 Satisfactory Satisfactory 14.44

6 01/11/2008 Satisfactory Satisfactory 39.63

7 02/20/2009 Satisfactory Moderately Satisfactory 71.93

8 01/12/2010 Moderately Satisfactory Moderately Satisfactory 83.84

9 06/10/2011 Satisfactory Satisfactory 90.55

H. Restructuring (if any)

Not Applicable

Page 12: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

vii

I. Disbursement Profile

Page 13: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel
Page 14: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

China‟s vigorous growth has strained the country‟s transport networks and the rate of

growth in cargo had outpaced the increase in transport network capacity. Logistics costs in

China in 1999 were estimated to account for 18% of GDP compared to 9.5% in the USA.

Internal transport costs were so high that coastal provinces enjoyed considerable advantage

in the export of goods over their inland provincial competitors. For the inland provinces to

share in the export boom, either directly or as suppliers of inputs to manufacturers near the

coast, special efforts were required to improve their access to seaports and to overcome

resistance to cooperation across institutional boundaries.

China‟s inland waterway transport (IWT) network at the time of project appraisal was the

world‟s largest in terms of length and freight volume. However, freight density (tons per

waterway km) was only 40 percent of that of the United States and some European

countries due to the low standard of navigation infrastructure; low investment in IWT; and

institutional arrangements that made it difficult to attain coordinated actions to optimize

IWT development. In the three preceding Five Year Plans (1986-2000)1, IWT‟s share of

investment significantly lagged behind its share of the total traffic carried. Under-funding

caused waterway infrastructure to deteriorate, reducing the net size of the navigable

network from 172,000 km in 1960 to 110,200 km by the time of project appraisal.

Shipping services that were not cost effective: many of the vessels were small family-

owned barges and operated as independent units; the few commercial fleets in operation

were provincial or municipal government owned, companies with little incentive to become

more efficient. The greatest impediment to increased operating efficiency and increased

modal share was the lack of incentive to increase vessel size and thereby reduce costs.

Recognizing that IWT could support a much larger volume of China‟s inland transportation,

the Government of China (GOC) took measures under the 9th

Five-Year Plan (1996-2000)

to develop the Pearl River in Guangdong Province and the Grand Canal in Jiangsu

Province, the second and third largest IWT systems. These developments were supported

by the Bank in the form of three inland waterway projects in 1996 (Guangxi, Hunan, and

Zhejiang), 1998 (Guangdong and Jiangsu), and 2001 (Hunan).

The project that is the subject of this report (the Project) was the Bank‟s fourth inland

waterway initiative in China. It combined the dual purpose of improving the inland

waterway networks in Guangxi and Guangdong with meeting power shortages in the

provinces through hydropower generation. The Bank‟s involvement in the Project was in

line with the 2002 Country Assistance Strategy (CAS) which supported China in making

two historic transitions --from a rural, agricultural society to an urban, industrialized

1 China‟s short-term national development plans are based upon five year intervals. Currently China is

delivering the 12th

Five Year Plan (2011-2015).

Page 15: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

2

society, and from a centrally-planned economy to a more globally integrated market-based

economy.

1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)

The objective of the Project was to assist the Borrower in: (a) improving the market access

for its southern region by upgrading navigation conditions on the region's major east-west

river and other waterways feeding into the Zhujiang River Delta region; and (b) meeting

the growing energy demand in Guangdong and Guangxi by harnessing water flow in two

rivers in such region to generate environmentally clean electricity. .

Key indicators for monitoring and evaluating the achievement of the project development

objective included the volume of waterway traffic and the average size of vessels in the

project waterways, power output at the project power plants, and transit time (inclusive of

waiting time) through the project ship locks.

1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and

reasons/justification

There was no revision of the project development objective or key indicators.

1.4 Main Beneficiaries

The main Project beneficiaries would be users of the transport corridor from Yunnan and

Guizhou Provinces through Guangxi to Guangzhou who would be able to take direct

advantage of the water transport from Baise to the Pearl River Delta. The Project covered

some of the poorest areas in Guangdong and Guangxi. Baise and Tianyang counties of the

Guangxi component were both province-designated poverty counties. The Guangdong

component would impact on six of the sixteen poverty counties of the province where the

average GDP ranged between 20-30% of the province. Other inhabitants of the corridor

would also benefit indirectly from the reduced congestion on the competing rail route and

from the creation of new industries attracted by the transport improvements.

1.5 Original Components (as approved)

The Project consisted of the following parts:

Part A: Guangxi

(a) Construction of the Naji Navigation Complex on the Youjiang River between

the cities of Baise and Nanning, including: construction of a 20 meter high dam;

construction of a shiplock; construction of a power plant with a 57 megawatt

capacity and two substations to link the power plant to the Baise grid; acquisition

and installation of turbines and related equipment for the powerhouse; and

acquisition and installation of lock gates.

Page 16: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

3

(b) Construction of access roads on both banks of the Youjiang River with a total

length of about 9 kilometers; including the construction of a bridge across the river

at the dam site.

(c) Construction of reservoir protection embankments.

(d) Carrying out of channel improvement, including construction of dikes and

dredging of shoals between Baise and Nanning, and upgrading of navigational aids.

(e) Resettlement and rehabilitation of Displaced Persons in respect of (a) and (b).

(f) Capacity building of the Guangxi Transport Department (GTD), including the

Project Management Office and the Guangxi Xijiang Waterway Construction and

Development Company, and provision of technical assistance, training and study

tours.

(g) Carrying out of studies on (a) the financing, management and operation of

integrated waterways and power generation resources, and (b) the development and

installation of a comprehensive management information and control system.

Part B: Guangdong

(a) Carrying out of channel improvements and regulation works on about 16

kilometers of the Lao-Long-Hu-Waterway, including deepening and widening

of the waterway, replacement of dikes, construction of a diversion channel,

construction of embankment protection, and installation of navigational aids.

(b) Replacement of two bridges over the Lao-Long-Hu Waterway at Lianyao and

Longma.

(c) Carrying out of channel improvements on about 180 kilometers on the middle

reaches of the Beijiang River between Shaoguan and Qingyuan, including

upgrading of navigational aids and construction of auxiliary facilities along the

Beijiang River.

(d) Construction of the Xiniu Navigation Complex on the Lian River between

the cities of Xiniu and Hanguang, including: construction of a 10.5 meter high

dam; construction of a ship lock; construction of a power plant with a 10

megawatt capacity and two substations to link the power plant to the grid

serving the city of Yingde; construction of auxiliary facilities; acquisition and

installation of turbines, lock gates and related equipment for the powerhouse;

and upgrading of navigational aids.

(e) Resettlement and rehabilitation of Displaced Persons in respect of (a) and (d).

(f) Capacity building of the Guangdong Provincial Transport Department (GPTD),

including the Provincial Waterways Bureau and the Project Management Office,

and provision of technical assistance, training and study tours.

Page 17: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

4

(g) Carrying out of a study for the development of a waterway electronic mapping

system, and implementation of such system; and a study for the development of

a shiplock management system, and implementation of such system.

(h) Acquisition of service vehicles, service vessels, and surveying and monitoring

equipment.

1.6 Revised Components

There was no revision of the Project‟s components.

1.7 Other significant changes

While there was no revision of project components, some changes were made in the design,

scope and scale, implementation schedule, and Bank loan allocations during project

implementation.

For the Guangxi part of the Project, the significant changes were:

Design Changes

(a) Lowering the lowest navigational water level downstream of the Naji Dam by 0.8 m to

minimize the impact on land use and resettlement behind the next downstream dam

(Yuliang Navigation Complex) whose construction commenced in 2008. This change

required some revisions of the main civil works contract as well as the technical

specifications for the power generators; these added RMB29.07 million to costs.

(b) The foundation level of the lower head of the ship lock was lowered by 4 meters as the

excavation of the foundation exposed a weak stratum at the original design level. In

addition to the extra excavation, casting of some additional 4,000 cubic meters of concrete

was required to bring the lower part of the ship lock to the revised design level.

(c) The installation capacity of the power plants was increased from the original 57

megawatt to 66 megawatt as a result of design optimization.

Scope and Scale

The number of person-months of overseas training was reduced by some 58 person-months

due to government restrictions on overseas travel. This reduction was counter-balanced by

an expanded program in domestic training.

Implementation Schedule

(a) Despite the delay in the award of the main works contract, the Guangxi partwas

essentially completed as scheduled except for some minor finishing works and the

implementation of 3 overseas training and study tours which were completed in the first

quarter of 2010. The slight delay in the completion of the Project did not affect the original

loan Closing Date for the Guangxi part which was January 31, 2010.

Loan Re-allocation

Page 18: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

5

The Loan Agreement was amended on December 5, 2008 with retroactive effect to the date

of signing of the agreement (October 24, 2004), the disbursement percentage for Category

1 (a) (Works) from 50% to 70% and for Category 1 (c) (Consultants‟ Services) from 91%

to 100%, and to re-allocate the amount under Category 1 (e) (Unallocated) to the categories

for works and goods. Section 1.01 of the “General Conditions of Applicable to Loan and

Guarantee Agreements for Single Currency Loans of the Bank, dated May 30, 2005 was

also amended on the same date to enable the Borrower to withdraw the proceeds of the loan

to pay for taxes levied by, or in the territory, of the Borrower on goods or services financed

under the loan.

For the Guangdong part of the Project, the significant changes were:

Design Changes

There was a small change in the design of the Xiniu Complex to include a fish passage as

required under the State Environmental Protection Agency (SEPA) clearance of the EA. At

project appraisal, this facility had been dropped in favor of a release of fries on the

reservoir to ensure a more-than-adequate supply of fisheries. SEPA (now the Ministry of

Environmental Protection) did not accept this change and the fish passage was added at the

late construction stage of the Xiniu Complex.

Scope and Scale

(a) The scope of Contract-W3 for channel improvement works on the middle reaches

of the Beijiang River had to be revised due to the river changing its course between

Suoyitan and Jiangwannan.

(b) Due to difficulties in the acquisition of land, Guangdong Provincial Waterway

Bureau (GPWB) decided to drop the construction of the terminal and maintenance station

at Qingyuan from the Project, but complete the on-going land acquisition under the Project.

GPWB will undertake the construction of the facilities outside the scope of the Project.

(c) Land acquisition increased from 56.6 hectares in the Resettlement Plan to 77.8

hectares, an increase of 50%.

(d) Contracts for consulting services for construction supervision had to be extended as

a result of delays in the construction of the Xiniu Complex and channel improvement

works on the Lao-Long-Hu and the middle reaches of the Beijiang River.

Implementation Schedule

As a result of delays experienced in almost all contracts, the closing date for the loan had to

be extended from the original January 31, 2010 to June 30, 2011. Some domestically

funded works in the contracts for the construction of the terminal at Yinde, reconstruction

of the two bridges on Lao-Long-Hu waterway, and the channel marker telemetry system

are expected to be completed by the end of 2011, delaying the achievement of some of the

Guangdong outcome indicators by about a year.

Loan Re-allocation

The Loan Agreement was amended on December 5, 2008 to increase the disbursement

percentage for Category 2 (a) (Works) from 50% to 80% and for Category 3 (c)

(Consultants‟ Services) from 91% to 100% retroactive to the date of signing of the

Page 19: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

6

agreement (October 24, 2004), and the amount under unallocated was transferred to works

and goods.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

Both Guangxi and Guangdong had experience in implementing the previous Bank-funded

IWT projects and took lessons from them into account in the preparation of the project.

Project agencies adopted international practices and Bank policies on procurement,

environmental assessments and resettlement plans. Technical risks associated with design

and construction were mitigated by appointing experienced consultants for design and for

construction supervision. The importance of dam safety was recognized, and a dam safety

panel of experts was established for each of the two dams early in the project cycle to

provide guidance, advice and quality assurance in the design, construction and maintenance

of the dam and related infrastructural works.

Careful assessment was made about the impact of operation of neighboring dams on the

operation of the dams under the Project. The capacity of ports on the project waterways

was examined in details as it was recognized that the upgrading of the navigation channel

would only achieve the desired outcome if loading/unloading facilities at ports on the

project waterways were able to handle vessels of the size for which the channel was

upgraded to accommodate.

It was recognized that market response to the availability of improved IWT would depend

on factors mostly beyond the control of the project implementing entities. In previous

completed inland waterway projects, users responded positively to the improvements, e.g.,

the Bank-financed first Inland Waterways Project, completed in 2001, the average size of

vessels passing through the Guigang ship lock increased by 17% in the first year of

operation and a further 44% in the following year. Both Guangxi and Guangdong therefore

decided not to stimulate the transition to larger vessels but to monitor traffic volumes

against forecasts.

2.2 Implementation

Early in the project cycle, each implementing entity set up a Project Management Office

(PMO) adequately staffed with experienced engineers and various other specialists to

manage the implementation of the Project. Procurement packaging and bid documents for

major contracts were finalized ahead of loan approval in order that bids for major contracts

could be called as soon as the loan was effective.

Both provinces institutionalized the structure for implementing the resettlement program,

including resettlement offices at the provincial, county, and township offices, the design

institutes, as well as the independent monitor. These offices had experienced staff and

necessary equipment. An internal management and monitoring system was already

designed and documented in the draft resettlement action plans.

Page 20: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

7

During project implementation, effective mitigation measures to safeguard the environment

were promptly taken to ensure that all environmental indicators were within acceptable

standards and protection targets were protected appropriately.

Guangxi

In Guangxi, the Project was implemented competently by the GXWCDC at a cost

equivalent to US$133.22 million (US$1=RMB8.28), about 10% less than the original

US$148.06 million appraisal estimate. The difference was due largely to the lower-than-

estimated costs of turbines, lock gates and other equipment, channel improvement works

between Baise and Nanning, and institutional strengthening consultant services and training,

which in aggregate yielded a cost saving of about US$27.47 million. These were partially

offset by the increased cost of the larger than appraised site of the administration complex,

and resettlement and land acquisition cost exceeding the estimate by about US$15 million.

The loan amount of US$44.775 was fully utilized.

Project implementation proceeded satisfactorily except for the following difficulties:

(a) Contract award - The award of the main civil works contract took longer than

expected due to the clarifications required by the Bank to understand the reasons to justify

the rejection of the lowest evaluated bid.

(b) Contractor performance - The performance of the main civil works contractor was

constrained by limited resources in finance, manpower and equipment. Works, especially

in the early stages of construction, were slow and the contractor had to be frequently

required to ensure that sufficient labor and equipment were provided at site to meet

contractual obligations.

(c) Unusual weather - A severe storm in July 2005 led to flooding of the construction site.

Torrential rains from abnormally severe typhoons in July 2006 caused a sudden and

unpredictable landslide on the side slope in the ship lock foundation pit resulting in the

death of four laborers.

Guangdong

In Guangdong, project implementation suffered delays due mainly to delayed contract

awards, poor contractor performance, unusual bad weather (the worst flooding in 50 years),

contract variations and difficulties in land acquisition. The root of the problem with the

main contract for the Xiniu Complex appeared to be the contractor‟s low bid price, which

the GPWB believed to be below cost. This resulted in a shortage of labor, plant and

equipment being provided at site. Considerable delays in land acquisition affected the

construction of maintenance terminals at Yinde, Shaoquan and Qingyuan significantly to

the extent that GPWB decided not to undertake the construction of the terminal at

Qingyuan under the Project as it could not be completed by loan closing. Land for the

terminal at Qinyuan has been acquired as part of the Project, but construction of the

terminal would be undertaken outside the Project.

The Guangdong part was completed at the cost of approximately US$102 million, about

91% of the cost of US$112 million estimated at appraisal. Channel improvements at both

Page 21: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

8

the Lao-Long-Hu Waterway and the middle reaches of the Beijiang River cost significantly

less than estimated, but this reduction in cost was offset by the increased cost of land

acquisition.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

Indicators established to determine the achievement of the Project‟s development objective

provided the means by which its design, implementation and utilization were monitored

and evaluated.

The key indicators for monitoring the achievement of the navigational aspect of the

development objective included the volume of traffic carried on the waterway and the size

of vessels using it. For power supply, investment efficiency was determined by the cost per

kilowatt of capacity installed and the cost per kilowatt of electricity delivered. Efficiency in

operation and maintenance of the power plants was measured by the hours when the

turbines were available for use. Given the purpose of the Project, the indicators were

appropriate and had been used in the previous three inland waterways projects financed by

the Bank.

Mechanisms for monitoring project implementation included: the review of semi-annual

progress reports; the review of the audited annual financial statements; and two supervision

missions a year.

2.4 Safeguard and Fiduciary Compliance

Fiduciary compliance was satisfactory. Project financial management met acceptable

standards. Comments of independent auditors on annual financial statements, when they

arose, were satisfactorily clarified and corrected.

Compliance with the EMP was generally satisfactory. Environmental monitoring during

project implementation was undertaken by the Guangxi Communications Science and

Research Institute for Guangxi and by the Water Environmental Monitoring Center of Pearl

River Basin for Guangdong. Additionally in Guangdong, Guangdong Provincial Hydraulic

and Hydroelectric Science Research Academy was engaged to conduct water and soil

conservation monitoring to ensure full compliance with the relevant laws, regulations and

contract specifications. Environmental monitoring reports were regularly submitted to the

Bank for review in compliance with the provisions in the Project Agreement (Schedule 2,

B8).

In Guangxi, land acquisition and resettlement were implemented satisfactorily and without

undue hardship. Land acquisition was 864 ha., 4.2% higher than the planned in the

Resettlement Plan (RP); and 131 households were relocated, 82 households more than in

the RP. Total compensation paid came to RMB237 million, significantly higher than the

budgeted amount of RMB66 million.

Living standards of households affected by land acquisition and resettlement has been

found to be improved as a result of the implementation of the RP. At the dam site, the

Page 22: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

9

average income per capita increased by 112% between 2003 and 2008 while those in the

reservoir area increased by 32%. All relocated households were able to build brick-

concrete houses.

In Guangdong, the total area of land acquired was some 82.4 ha., about 46% more than the

planned 56.6 ha. in the RP; the increase in land acquisition was localized in Zhangwu and

Hetou villages. Compensation rates were generally higher than provided in the RP, and the

overall resettlement cost was about 31% more than the planned sum of RMB56 million.

Living standards of households affected by resettlement was improved by about 24% and

income per capita by about 29%. There was a noticeable shift in the composition of

household income from agriculture, forestry, fishing and animal husbandry to retails and

services.

2.5 Post-completion Operation / Next Phase

The Guangxi part of the Project, upon completion, is being operated and maintained by

GXWCDC, which is already operating similar complexes at Guigang and Guiping. Income

generated by GXWCDC will be sufficient to meet operating and maintenance costs, as well

as the repayment of the loan and other financial obligations.

Following the Naji development, GXWCDC has undertaken the construction of another

navigation complex at Yuliang, and is also embarking on a further phase of development of

its Guigang Complex with the construction of a second ship lock.

For the Guangdong part of the Project, GPWB has assigned an operating unit for the

operation and maintenance of Xiniu Complex upon its completion. The local waterway

bureaus are responsible for routine maintenance and dredging of the improved Beijiang

River and Lao-Long-Hu Waterways, with the earmarked annual budget allocated by the

provincial government.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

The Project's development objective remains relevant in the context of China's present

transport needs demonstrated by its increasing share of the country‟s freight market.

Between 2004 (the year of appraisal) and 2008 (the year for which the most recent

published data is available), IWT freight traffic intensity in ton-kms increased by 22.5%

annually which is higher than the national total annual increase of 17.4% .

Page 23: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

10

China Freight Transport by Modes (2004-2008) (in units of billion ton-km)

Year Railways Highways Waterways Civil

Aviation Pipelines Total

Ocean Coastal IWT Subtotal

2004 1,928.88 784.09 3,225.50 698.88 218.44 4,142.87 7.18 81.5 6,944.50

2005 2072.6 869.32 3,855.20 849.49 262.57 4,967.23 7.89 108.8 8,025.80

2006 2,195.44 975.42 4,257.70 988.3 302.5 5,548.57 9.43 155.1 8,884.00

2007 2,379.70 1,135.47 4,868.60 1204.6 355.3 6,428.48 11.64 186.6 10,141.90

2008 2,510.63 3,286.82 3,285.10 1,326.06 415.15 5,026.27 11.96 194.4 1,1030.08

Average

Annual

Growth

7.5% 79.8% 0.5% 22.4% 22.5% 5.3% 16.6% 34.6% 14.7%

Source: China Statistic Yearbook, 2009

IWT is the least energy intensive, most cost effective, and lowest contributor to green

house gases of all transport modes. IWT is also essential to the promotion of greater

efficiency, productivity and competitiveness in the use of inland water resources in

Guangxi and in Guangdong. The Project is consistent with the strategic objective of Pillar

3 (Managing Resource Scarcity and Environmental Challenges), as well as Pillar 4

(Financing Sustained and Efficient Growth), of the Bank‟s Country Partnership Strategy

(CPS) for China for 2006-2010. The project objective and design are also expected to be

still relevant to the most current government strategy and the new CPS for 2011-2015.

3.2 Achievement of Project Development Objectives

With the successful completion and operation of navigation and hydropower facilities

along the Pearl River as originally designed at appraisal, project objectives (see Section

1.2) are largely met.

The main economic benefits identified at appraisal included: (a) the reduction in transport

costs for existing traffic flows on the river; (b) the consumers or producers surplus

associated with traffic diverted from road or rail to river transport, together with newly

generated traffic; and (c) the social and economic gains from increased electricity

generation and consumption.

Guangxi Component. Traffic on the project waterway in Guangxi, based on data available

to date, has exceeded expectations, both in volume and in the average size of vessels using

the waterway. The Naji Complex has supplied the local region with additional clean

renewable energy of about 273 GWh per year.

Guangdong Component. IWT traffic under the three sub-components (Laolonghu sub-

component, Beijiang River sub-component, and the Xiniu sub-component) in 2010 was

only 1.3 million tons, 5.76 million tons, and 15,000 tons respectively; this was lower than

the 2.60 million tons, 7.6 million tons, and 15,000 tons projected in the PAD. Most of the

indicators are below the targets, but will catch up once the on-going works on the

reconstruction of two existing cross-river bridges (that have insufficient clearance), and the

Page 24: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

11

Xiniu Complex are completed; these currently make the river section virtually not

navigable.

The installation of the turbines with a total generation capacity of 10 MW was not

completed until 2011. Electricity planned to be generated in 2011 is only 7.73 GWh, much

lower than the projection of 46 GWh in the PAD. Based on the latest data, projected power

generation will be 30.9 GWh in 2012 and 38.7 GWh from 2013. The lower-than-designed

electricity generation was due to lower-than-designed water elevation behind the dam.

With the full completion and operation of the infrastructure hydropower generation will

pick up to the designed level.

The Project will also achieve global environmental benefits due to avoided CO2 emission

from both transport energy savings and hydropower generation, which were not included in

EIRR calculation at project appraisal. In addition, as envisaged at appraisal, the Project has

particularly benefited poor regions and poor populations through providing local economic

development opportunities and improving the living standard of local populations.

3.3 Efficiency

Economic. With the successful completion and operation of the navigation and

hydropower facilities along the Pearl River as appraised, the project‟s objectives of

improving the market access and IWT and generating environmentally clean electricity are

largely met.

Guangxi Component. Cost-benefit analysis conducted at appraisal estimated an EIRR of

18%, as reported in the PAD. Following exactly the same valuation approach and using the

same assumptions of travel cost saving per ton and the economic benefit of electricity

generated per KWh, the EIRR at completion is 15.8%. The slightly lower EIRR is mainly

due to the two-year delay in electricity generation at full capacity.

Guangdong Component. The same approach was applied to the economic analysis of three

sub-components in Guangdong – Laolonghu Waterway, Middle Reach of Beijang River,

and Xiniu Complex. The recalculated EIRR of the three sub-components at completion are

26.5%, 24.8%, and 5.1%, compared to the appraisal estimates of 51.0%, 24.1%, and 12.8%,

respectively. The aggregated EIRR of the three sub-components is 15.3%, which may be

considered acceptable despite being lower than the appraisal estimate of 23.0%.

Financial. Since the principal objective of the Project is the provision of public goods, the

low financial return (or even a net loss) of the government-owned project implementing

entities may be considered acceptable.

Guangxi Component. A FIRR of 3.4% was estimated at appraisal under the assumptions

that electricity sale price would be RMB0.35 per KWh and the ship lock fee would be

RMB0.40 per ton. However, these assumptions are no longer valid due to: the recent

government decision that there would be no ship lock fee along the entire Xijiang River

section in Guangxi in order to promote IWT; and the lower electricity sale price of

RMB0.29 per KWh (six cents lower than the price proposed at project appraisal). The

Page 25: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

12

recalculated FIRR, using the latest data and projection of power outputs and sale prices,

shows a decrease from 3.4% to 0.74%.

Guangdong Component. The PAD estimated a negative FIRR. The recalculation in ICR

continues to show a net financial loss to the operator of the Xiniu complex. However, the

government has agreed to cover the financial losses of the complex from its annual budget.

3.4 Justification of Overall Outcome Rating

The performance indicators for Guangxi part are achieved satisfactorily, while the

indicators for the Guangdong part of the Project fall short of some of the targets established

at appraisal due to the delayed completion of the relevant sub-components. Therefore, the

overall outcome of the Project is considered moderately satisfactory based on:

(a) the most achievement of Project‟s development objectives;

(b) the consistency of the Project‟s development objective with the Bank's strategy for

improving transport services to alleviate bottlenecks and China's policy and plan for

increased economic development in interior regions;

(c) the achievement of acceptable economic and financial efficiency;

(d) attention given to lessons learned from the previous inland waterway and other

transport projects in the design of the Project, and

(e) compliance of the Project with Bank safeguard and fiduciary policies.

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

The gender aspect of the Project was taken into account in the design of the Project,

particularly in the context of project impacts, mitigation measures and ethnic minority

groups. They were included in the terms of reference of the social assessment and

resettlement planning exercises. The social assessments conducted focus group discussions

with women and interviewed women representatives of the affected communities.

The poverty impact of the Project was very positive. In Tianyang County, which was

directly impacted by the Naji development, income per capita of the farmers rose from

RMB1,923 in 2004 to RMB3,579 in 2009 and of urban dwellers from RMB5,546 to

RMB14,623. In the areas affected by the Guangdong part of the Project, average income

per capita rose 28% to RMB4,690.

(b) Institutional Change/Strengthening

The impact of the Project on institutional development in the sector has been positive. As

with the previous inland waterway projects, with the improvements in the navigational

channel and increased capacity of the ship lock, larger vessels are being used. Measures to

speed up the transition to larger vessels by standardizing the type and size of vessels using

the waterway and discouraging the use of smaller vessels are being implemented. Tows of

two to four barges, a more efficient and cost effective form of operation, have begun to be

used. A shift from small family-based ownership to larger business enterprises is evident.

Page 26: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

13

TA studies under the Project have been conducted efficiently, and their outputs have been

adopted into the management practices of the project provinces. GXWCDC has agreed to

share the impressive features and capability of the real-time system developed by the study

on the management of integrated water resources with other provincial IWT enterprises.

The international and domestic training programs under the Project have been well

implemented, and have increased capacity of staff.

(c) Other Unintended Outcomes and Impacts (positive or negative)

There were no unintended outcomes or impacts.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

No beneficiary survey or stakeholder workshops were conducted in the Project.

4. Assessment of Risk to Development Outcome

The risk to development outcome is negligible to low. Central and provincial governments'

commitment to the Project continues to be strong. Economic conditions in the country and

in both provinces have remained robust. Local staff has been adequately trained to manage

and operate the Complexes. Traffic on the Guangxi waterway has met expectations,

reflecting improvement in services and reduction in transport cost; however, the volume of

traffic carried on the Guangdong waterways and the expected increase in vessel size have

not yet met expectations. Increased attention is being paid to the maintenance of the

waterway transport facilities in recent years. The risk that the development outcome would

not be sustained, either in terms of the demand for the facilities provided, or in terms of

the ability and capacity of the executing agencies to properly manage, operate, and

maintain them, is low.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Bank performance in ensuring quality at entry was satisfactory.

The design of the Project was technically sound. Lessons learned in past Bank financed

projects were taken into account. Risks were identified and appropriate measures were

taken to mitigate them. Care was exercised in preparing the PMO for project

implementation. Key indicators selected to monitor and evaluate the performance and

outcome of the Project provided the focus on project implementation.

The Resettlement Action Plan (RAP) was comprehensively developed and included

processes for consultation and participation of the various stakeholders in the planning,

adverse impact analysis, legal framework for resettlement, strategy and implementation

program for compensation, relocation and livelihood development, monitoring, and airing

and resolution of grievances.

Page 27: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

14

Environmental protection measures were adequate and included the control of air, water

and noise pollution, regular sprinkling of roads in the project sites, restricting the speed of

vehicles in the work area to 20 km/hr, limiting the height of wastes carried on trucks to

prevent over-spilling, and the construction of sedimentation tanks and sewage treatment

facilities to ensure the outcomes met the required standards.

(b) Quality of Supervision

The quality of Bank supervision was moderately satisfactory.

Regular implementation review missions focused on the quality and progress of works and

their impacts on the achievement of the development objective. Issues that emerged during

implementation were attended to efficiently and promptly. The Bank task team contributed

positively in helping to overcome delays caused by contractors‟ financial, manpower and

technical resources. These efforts were appreciated by the PMO as well as the contractors.

Compliance with safeguard and fiduciary policies was closely monitored and

recommendations for improving the implementation of the EMP and the RAP were

provided whenever necessary. Regular reviews of the work undertaken by independent

monitors ensured the proper implementation of the plans and measures for environmental

and social safeguards.

(c) Justification of Rating for Overall Bank Performance

Overall Bank performance was moderately satisfactory, based on performance in preparing

and supervising the Project.

5.2 Borrower Performance

(a) Government Performance

Government performance was moderately satisfactory, based on its commitment to the

Project. Ministry of Transport (MOT) provided technical support and subsidy to GXTD

and GDTD/GPWB in the preparation and implementation of the Project. At the provincial

level, the Project was considered one of the key projects in the provinces and was given a

high level of attention. GXTD and GPTD exercised close supervision on project

implementation, with senior management personally participating with the Bank task team

in regular review missions, and provided effective co-ordination between the project

implementing entity and other governmental agencies. The commitment of the transport

departments of both project provinces was evident by their interventions to overcome

obstacles encountered in project implementation that were sometimes beyond the control of

the implementing agencies.

(b) Implementing Agency or Agencies Performance

The performance of implementing agencies was moderately satisfactory.

GXWCDC was highly motivated and completed the Project competently within budget and

schedule. The GPWB project team was relatively young but made it up with dedication and

perseverance. Cooperation between the implementing agencies and the Bank was very

good; consultations were extensive and meaningful; and issues were promptly raised and

Page 28: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

15

jointly resolved. Both GXWCDC and GPWB discharged their fiduciary responsibilities

conscientiously and correctly. Compliance with Bank requirements during project

implementation was satisfactory.

(c) Justification of Rating for Overall Borrower Performance

Overall Borrower performance was moderately satisfactory, taking into account both

Government and implementing agency performance.

6. Lessons Learned

6.1 The following lessons and conclusions may be drawn from the Project:

(a) Inland water transport in China is a viable transport mode. The increase in traffic

carried on the project waterways reflects the overall gain in market share in the

freight transportation especially for low-value commodities in large consignments

from and to origins alongside or near a river or inland waterway. During the

project implementation period (2004-2008), IWT freight traffic intensity in ton-kms

increased by 22.5% annually which is higher than the national total annual increase

of 17.4%.

(b) Measures to increase efficiency and cost effectiveness in the sector are well

received by the market. Users responded positively to the Project by increasing the

size of vessels operating in the project waterways.

(c) Developments similar to the Project can be replicated taking advantage of

experience gained in inland waterway network planning, macro-economic

considerations, technical design, safety provisions and environmental and social

safeguards.

(d) Overseas training plans designed for implementation need to be more realistic and

modest with due consideration given to government regulations on overseas travel.

(e) Land acquisition has become more contentious and more time has to be given to

resolve differences over compensation.

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

(a) Borrower/implementing agencies

Several issues regarding procurement were raised by the implementing agency, which are

listed below with the comments of the Bank team.

(From Guangxi) - „As the local construction market is immature, the possibility of

potential risks caused by the adoption of the principle of awarding contract to the

lowest bidder may not be ruled out. In view of this, it is recommended that the

employer be granted certain rights on decision-making where the Bank‟s rules and

regulations allow.‟

Bank’s Comments: It needs to be clarified that the principle of contract award in

Bank-financed procurement is the contract being awarded to the bidder who has

submitted the lowest evaluated responsive bid and who also meets the minimum

qualification requirements. It should not be simply or by misunderstanding to

Page 29: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

16

interpret that the contract is awarded to the lowest price bidder. The employer is of

course the main decision-maker in selecting the contractor. But the process for bid

evaluation and selection of contractor should follow Bank procurement guidelines.

(From Guangdong) – „We suggest that the World Bank take the actual situation of

China into account and apply the World Bank policies to the project management

flexibly and systematically, with the economy and efficiency as the first principles,

while the Bank is promoting its normative procurement and project management

system. ‟

Bank’s Comments: The Bank task team has made its endeavor to apply Bank policies

into the actual context of the project in a pragmatic and flexible manner. And Bank

management has encouraged the adoption of country systems, where it is applicable.

Nevertheless, a Bank-funded project is also aimed to improve practices which have

been used by introducing proven international practices.

(From Guangdong) - We suggest that relevant governmental departments make

greater efforts to promote the waterways and the local government attach more

importance to the waterways. Meanwhile, the fund raising channel for the waterway

construction should be broadened and more capital should be invested. Through the

improvements of waterways, the local economy can be boosted, forming a good

economy cycle.

Bank’s Comments: The importance of inland waterway transport to the local

economy and to the comprehensive transport system has gradually been accepted by

the central and local governments. However, more financing support and incentive

policies from the central government will be needed to encourage local government

investment in waterways development.

(b) Cofinanciers

None

(c) Other partners and stakeholders

None

Page 30: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

17

Annex 1. Project Costs and Financing

Project Costs: Guangxi

(US$1=RMB8.28)

Components Appraisal Estimate

(US$ million)

Actual/Latest Estimate

(US$ million)

Percentage of

Appraisal

Construction of Naji Dam, Power Station,

and Ship lock 38.51 42.43 110%

Construction of Access Roads 3.33 4.22 127%

Bank Protection (Dam and Reservoir) 2.33 4.48 192%

Turbines, Lock Gates, and Other

Equipment 29.76 20.62 69%

Channel Improvement (Baise-Nanning) 13.56 0.42 3%

Institution Strengthening, Consultants

Services, Training 14.49 9.30 64%

Resettlement and Land Acquisition 22.31 37.25 167%

Site Management Complex 1.92 3.61 188%

Total Baseline Cost 126.11 122.33 97%

Physical Contingencies 10.08

Price Contingencies 5.05

Total Project Cost 141.24 122.33 87%

Interest During Construction 6.37 10.06 158%

Front End Fee 0.45 0.23 51%

Total Financing Required 148.06 133.22 90%

Project Costs: Guangdong

(US$1=RMB8.28)

Components Appraisal Estimate

(US$ million)

Actual/Latest Estimate

(US$ million)

Percentage of

Appraisal

Channel Improvement-Lao-Long-Hu 15.71 9.60 61%

Replacement of 2 bridges 7.02 1.01 14%

Channel Improvement, North River Middle

Reaches 15.33 10.65 69%

Construction of Xiniu dam, power station,

shiplock and access road 19.91 24.37 122%

Turbine, lock gates and other equipment 10.45 11.60 111%

Upgrading navigational aids 0.79 0.70 89%

Computer hardware for electronic mapping,

shiplock management and MIS 1.40 2.21 158%

Page 31: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

18

Service vessels, service vehicles, survey,

monitoring and ancillary equipment 1.20 2.10 175%

Institutional strengthening, consultant

services, training 16.69 18.02 108%

Land acquisition 8.28 15.93 192%

Total Baseline Cost 96.78 96.19 99%

Physical Contingencies 7.74

Price Contingencies 3.87

Total Project Cost 108.39 96.19 89%

Interest During Construction 3.51 5.51 157%

Front End Fee 0.46 0.23 50%

Total Financing Required 112.36 101.93 91%

Financing: Guangxi

Source of Funds Type of

Co-financing

Appraisal

Estimate

(US$ million)

Actual/Latest

Estimate

(US$ million)

Percentage of

Appraisal

Borrower 0.00 103.285 88.445 85.6%

International Bank for Reconstruction

and Development 0.00 45.000 44.775 99.5%

Financing: Guangdong

Source of Funds Type of

Co-financing

Appraisal

Estimate

(US$ million)

Actual/Latest

Estimate

(US$ million)

Percentage of

Appraisal

Borrower 0.00 66.135 56.930 84.6%

International Bank for Reconstruction

and Development 0.00 46.000 45.770 99.5%

Page 32: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

19

Annex 2. Outputs by Component

Component Planned Outputs Actual Outputs

Part A: Guangxi

1. Construction of the Naji

Navigation Complex on the

Youjiang River between the

cities of Baise and Nanning

2. Construction of access

roads and a bridge

3. Construction of reservoir

protection embankment

4. Channel improvement

works

5. Resettlement and

rehabilitation of displaced

persons affected by Naji

navigation complex

development

6. Capacity building of

GXTD and the GXWCDC

7. Carry out technical studies

a) 20 meter high dam

b) shiplock

c) power plant with 57

megawatt capacity

d) acquisition and installation

of turbines and related

equipment for the powerhouse

e) acquisition and installation

of lock gates

Access roads on both banks of

the Youjiang River with a total

length of about 9 km and a

bridge across the river at the

dam site

About 30 km of embankment

to be reinforced

a) Dikes and dredging of

shoals between Baise and

Nanning

b) Upgrade navigational aids

49 households, 151 persons

for relocation and

rehabilitation. 16,532 sq.m of

new home construction

Technical assistance, training

and study tours

a) Financing, management and

operation of integrated

waterways and power

generation resources

b) development and

a) 20 meter high dam

b) shiplock

c) power plant with 66

megawatt capacity

d) equipment for the

powerhouse procured and

installed as designed

e) lock gates installed as

designed

Access roads on both banks of

the Youjiang River with a total

length of 9 km and a bridge

across the river on the crest of

the dam.

About 30 km of embankment

reinforced as designed.

a) Channel improvement works

undertaken according to

requirements.

b) Navigational aids between

Baise and Nanning upgraded as

planned

131 households and 559 persons

were relocated and rehabilitated.

15,622 sq.m of new

brick/concrete homes were

reconstructed

Domestic training of 546

person-months and overseas

training and study tours

amounting to 43 person-months

provided.

Studies completed as planned

Page 33: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

20

installation of management

and information control

system

Part B: Guangdong

1. Channel improvement and

regulation works on Lao-

Long-Hu Waterway

a) deepening and widening of

16 km long waterway,

b) replacement of dikes,

c) construction of a diversion

canal and embankment

protection, and

d) installation of navigation

aids.

Lao-Long-Hu waterway

improved to Class 3 standard for

navigation of vessels up to 1,000

dwt.

2.Replacement of two bridges

New bridges at Lianyao and

Longma with sufficient

clearance for 1,000 dwt

vessels

New bridges under construction

at Lianyao and Longma that will

have enough clearance for 1,000

dwt vessels

3. Channel improvement

works on about 180 km of the

middle reaches of Beijiang

River between Shaoguan and

Qingyuan

a)Removal of shoals between

Shaoguan and Qingyuan,

b) upgrading of navigation

aids, and

c) construction of auxiliary

facilities

Channel between Shaoguan and

Qingyuan improved to

accommodate 300 dwt vessels

through removal of shoals and

upgrading of navigation aids.

Auxiliary facilities at Yingde

and Shaoguan are under

construction.

4. Construction of the Xiniu

Navigation Complex on the

Lian River

a) a 10.5 meter high dam,

b) a shiplock

c) a power plant with a 10

megawatt capacity and 2

substations to link the power

plant to the grid serving the

city of Yingde,

d) auxiliary facilities,

e) acquisition and installation

of turbines, lock gates and

related equipment for the

power house, and

f) upgrading navigation aids.

a) 10.5 meter high dam,

b) a shiplock for 1,000 dwt

vessels,

c) power plant of 10 megawatt

capacity,

d) auxiliary facilities at the

complex,

e) turbines, lock gates and

related equipment for power

house and shiplock, and

f) upgrading navigation aids

5. Resettlement and

rehabilitation of displaced

persons

Acquisition of 849.32 mu of

land

Land acquired was some

1,236.37 mu

6. Capacity building

Provision of technical

assistance, training and study

tours

19 training groups involving 127

persons were sent overseas. 17

domestic training programs

were provided to 293 persons.

Page 34: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

21

7. Carrying out studies for

development

a) waterway electronic

mapping system, and

b) shiplock management

system.

a) electronic waterway mapping

system, and

b) shiplock management system

completed as planned

Page 35: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

22

Annex 3. Economic and Financial Analysis

Economic Analysis

The development objectives of this Project are: (a) to improve the market access by

upgrading navigation conditions on the region's major east-west river feeding into the

Zhujiang (Pearl) River Delta region; and (b) to generate environmentally clean electricity

(hydropower) to help meet the growing energy demand in the region. There were no

changes in the PDO since appraisal. With the successful completion and operation of

navigation and hydropower facilities along the Pearl River as originally designed at

appraisal, these objectives are largely met.

The Project beneficiaries are local people, communities, and business entities engaged in

waterway transport in the transport corridor from Yunnan and Guizhou Provinces through

Guangxi to Guangzhou. They include many inhabitants of poor and remote rural areas in

inland and western China, as these areas are commonly the source of many of the cargoes

carried on the river.

The main economic benefits identified at appraisal have remained unchanged. They

included: (a) reduction in transport costs for existing traffic flows on the river; (b)

consumers or producers surplus associated with traffic diverted from road or rail to river

transport, together with newly generated traffic; and (c) social and economic gains from

increased electricity generation and consumption. At appraisal, the potential global

environmental benefits due to avoided CO2 emission from both transport energy savings

and hydropower generation were not included in the EIRR calculation.

The key monitoring indicators associated with economic benefits are the volume of

waterway traffic, the average size of vessels in the project waterways, and power output at

the project power plants.

Part A: Guangxi

2009 data shows that waterway traffic has reached 2.396 million tons, representing an

increase of 193% from 0.814 million tons in base year 2003, and a 9.9% increase compared

with the 2009 target value of 2.180 million tons.

Waterway transport capacity has also improved remarkably. Ship owners in the Baise

Municipality have been responding to the improved navigation conditions very positively

by increasing the size of their vessels. The average vessel size increased from 97 dwt in

2003 to 144.7 dwt in 2009, while the number of vessels registered in Baise dropped from

412 in 2006 to 330 in 2009. These results mean that ship owners have been able to replace

their ships with larger-sized ones due to improvements in navigation conditions in the

Baise section of the Youjiang River.

Bulky goods carried in the Youjiang River section between Baise and Nanning are mainly

construction materials (transported locally) and coal (transported from neighboring

Page 36: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

23

Guizhou Province downstream to Guangdong). Other materials, which would take

advantage of the improved waterway navigation in future, include other minerals and cane

sugar, as well as timber. The Guangxi Government has recently made an ambitious plan to

develop the entire Xijiang River system as a “Golden Navigation Channel” with an annual

transport capacity of 100 million tons. The You River is the main tributary of the Xijiang

River. The Naji Complex is an important part of a ladder of ten dams on the whole length

of the You River, and the Yu River into which it flows. Its contribution to IWT would

significantly increase once the completion of other navigation facilities, especially the ship

lift of Baise Dam (already planned), Yuliang Complex (under construction), and Laokou

Complex (under preparation). Together these navigation complexes will help further

unleash the potential of IWT in the Pearl River basin. It is therefore expected that the

Guangxi (Naji) component of the Project will achieve its objective targets related to IWT

and market access.

The installation of three turbines with a total generation capacity of 66 MW (higher than

the originally designed 57 MW at appraisal) was completed on schedule in 2008.

Electricity generated in 2009 was 227 GWh, 10.2% lower than the 2009 target of 253 GWh.

The lower-than-designed electricity generation was due to two factors: a delayed reservoir

filling to the designed 115 meter elevation behind the dam, and a drought in 2009. The

reservoir‟s water elevation was 113.8 m in the period from January to October 2009, and

114.2 m in November and most of December 2009 due to a slight delay in the completion

of resettlement works. The river level reached its designed 115 meter by the end of 2009.

It is anticipated that the annual average amount of electricity generated by the Naji Dam

will be 273 GWh or higher during the rest of the project implementation period. This

represents a higher hydropower output than the appraisal target value. The average cost of

electricity generation is RMB 0.24 per KWh; the electricity tariff that residential consumers

pay is much higher (RMB 0.6003 in dry season and RMB 0.4563 in wet season), and the

tariff for business and manufacturers is even higher. This implies a significant consumers‟

surplus, which is normally bigger than the difference between the average production cost

and average electricity tariff for residential use. The consumers‟ surplus of electricity was

not quantified at appraisal; instead, the opportunity cost of gas turbine was used to estimate

the economic benefit of electricity generation.

Cost-benefit analysis conducted at appraisal estimated an EIRR of 18% as reported in the

PAD. Following exactly the same valuation approach and taking the same assumptions of

travel cost saving per ton and the economic benefit of electricity generated per KWh, the

EIRR at ICR is 15.8%. The slightly lower EIRR is mainly due to the delay of full capacity

electricity generation by 2 years. Most IWT traffic is local instead of long-distance from

Guangxi or even upstream Guizhou Province to the Pearl River Delta in Guangdong

Province.

Overall the component will achieve its economic targets based on the examination of

project outputs or outcomes, including a big increase in IWT potential in the region,

electricity generation, and global environmental benefits. Note that global environmental

benefits were not quantified at appraisal and could be important. In 2009 the hydropower

electricity generation of 227 GWh is equivalent to a reduction of about 170,100 tons of

Page 37: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

24

CO2, which is worth US$1.7 million at a conservative valuation of the economic benefit of

CO2 emission reduction at $10 per ton of CO2. The global environmental benefit

(conservatively estimated and omitted at appraisal) is equivalent to 8% of the sum of

transport saving and power generation benefits.

Part B: Guangdong

The same approach was used in the economic analysis of three subcomponents in

Guangdong Province – Laolonghu Waterway, the Middle Reach in Beijiang River, and

Xiniu Complex.

Laolonghu Sub-component. IWT traffic in 2010 was only 1.33 million tons, much lower

than the projected 2.60 million tons. The lower traffic volume is due to the delay in

completing the reconstruction of two existing cross-river bridges that have insufficient

clearance.

The EIRR at appraisal was 51.0%. The estimated EIRR at completion is 26.5%. The lower

EIRR is attributed to the delay in project completion, especially the reconstruction of two

existing cross-river bridges. However, the revised EIRR is still high and satisfactory.

North River Sub-component. 2010 data shows that waterway traffic was 5.76 million tons,

which is lower than the projected 7.18 million tons at appraisal. The IWT data was

obtained from Feilaixia Shiplock in the Beijiang River section, so it may represent a low

end figure.

EIRR at appraisal was 24.1%. The estimated EIRR at completion is 24.8%. The slightly

higher EIRR is attributed to the lower capital investment in the early years of the

construction period.

Xiniu Sub-component. 2010 data shows that the waterway traffic passing the Complex‟s

shiplock was merely 15,000 tons, much lower than the projected 2.6 million tons at

appraisal. The low IWT is due to the delay in completing the Xiniu Complex, which has

made the river section virtually not navigable. In the ICR analysis, it is assumed that the

IWT in 2012 will be at the level projected in the PAD.

The installation of the turbines with a total generation capacity of 10 MW was not

completed until 2011. Electricity planned to be generated in 2011 was only 7.73 GWh,

much lower than the projection of 46 GWh at appraisal. Based on the latest data, it is

projected that the power generation will be 30.9 GWh in 2012 and 38.7 GWh from 2013.

The lower-than-designed electricity generation was due to lower-than-designed elevation

behind the dam. The consumers‟ surplus of electricity was not quantified at appraisal;

instead, the opportunity cost of gas turbine was used to estimate the economic benefit of

electricity generation.

The EIRR at appraisal was 12.83%. The EIRR estimated at completion is only 5.12%. The

lower EIRR is attributed to the lower IWT and power generation projection than at

appraisal.

Page 38: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

25

The Guangdong component as a whole yields an aggregated EIRR of 15.3% which despite

being lower than the appraisal estimate of 23.0%., is still satisfactory.

In summary, the project‟s economic objectives have largely been achieved.

Financial Analysis

For the Guangxi component, a FIRR of 3.4% was estimated at appraisal under the

assumptions that electricity sale price would be RMB0.35 per KWh and that the shiplock

fee would be RMB0.40 per ton. However, these assumptions are no longer valid because:

Guangxi Government decided, after project appraisal, to local economic development with

river navigation facilitation as a public service, and hence not to charge a shiplock fee

along the entire Xijiang River section in Guangxi;. the sale price of electricity (sold by the

power plant to state grid) has been fixed by the government currently at RMB0.29 per

KWh (six cents lower than the price anticipated at project appraisal). The project

implementing entity, which is 100% owned by the provincial government, faces a lower

than expected financial return, as shown in the table below. The FIRR has decreased from

3.4% to 0.74% , but is still positive.

2004 2005 2006 2007 2008 2009 2010 2015 2020 2029

I. Cash Inflow 1.28 46.57 61.71 79.34 87.48 91.85 106.33

1.28 46.57 61.71 79.34 87.48 91.85 106.33

4.38 157.00 212.80 273.60 273.60 273.60 273.60

0.29 0.29 0.29 0.29 0.32 0.34 0.39

II.Cash Outflow (million Yuan) 92.91 86.00 100.00 153.53 43.22 81.56 78.50 80.48 81.35 36.91

92.91 86.00 100.00 148.00 21.19 0.00 0.00 0.00 0.00 0.00

0.23 8.23 10.91 14.03 15.47 16.24 18.80

5.30 9.47 9.56 9.66 10.15 10.67 11.67

12.14 2.90 1.86 0.83 0.00

0.00 0.00 48.94 48.94 48.94 48.94 0.00

Include: Domestic loan 0.00 0.00 20.71 20.71 20.71 20.71 0.00

World Bank loan 0.00 0.00 28.23 28.23 28.23 28.23 0.00

0.00 4.33 0.00 2.97 4.06 4.67 6.44

(92.91) (86.00) (100.00) (152.25) 3.35 (19.84) 0.84 7.00 10.50 69.42

IV. FIRR 0.74%

Construction Period Operation Period

Item\Year

1. Electricity Sales Revenue (million Yuan)

Electricity sold to grid systems (Gwh)

6.Income Tax (million Yuan)

III. Net Cashflow

Electricity Sale Price (yuan/Kwh)

1.Capital Investment (own source)

2.Sales Tax and Associate Charge

3.Operating Cost(excluding depreciation)

4.Financial Cost(interest deducted)

5.Principal Payment (million Yuan)

In Guangdong, the PAD estimated a negative FIRR. The recalculation at completion still

shows a net financial loss to the operator of the Xiniu Complex. As the government has

agreed to cover the losses of the complex from its annual budget, the negative FIRR does

not affect the financial viability of the Project.

In summary, since the ultimate objective of the Project is to provide public goods, both

local and global, low financial returns (or even a loss) of the government-owned project

implementing entity is acceptable.

Page 39: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

26

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Graham Smith Consultant SASDT Task Team Leader

John Carter Scales Lead Transport Specialist EASCS Alternative Task Team Leader

Xin Chen Senior Program Assistant EACCF Team Assistance

Emmanuel Py Infrastructure Specialist EASIN Project Assistance

Wenlai Zhang Senior Transport Specialist EASCS Civil Engineering

Xiaowei Guo Senior Procurement Specialist EAPPR Procurement

Emmanuel Py Infrastructure Specialist EASIN Project Assistance

Naoya Tsukamoto Senior Environmental Engineer EASEN Environmental Assessment

Han-Kang Yen Research Analyst EASIN Financial Analysis

Chaohua Zhang Senior Social Sector Specialist SASDS Social Assessment

Kek Choo Chung Consultant EASCS Navigation

Hongyun Liu Consultant EASIN Hydropower

Richard Y. Scheiner Consultant AFTTR Civil Engineering

Supervision/ICR

Wenlai Zhang Senior Transport Specialist EASCS Task Team Leader (2008-2011)

John Carter Scales Lead Transport Specialist EASCS Task Team Leader (2006-2008)

Graham Smith Consultant SASDT Task Team Leader (2004-2005)

Xin Chen Senior Program Assistant EACCF Team Assistance

Teresita Ortega Program Assistant EASIN Team Assistance

Xuan Peng Program Assistant EACCF Team Assistance

Yunqing Tian Team Assistant EACCF Team Assistance

Hong Chen Operations Officer EASSD Project Assistance

Yi Geng Senior Financial Management

Specialist EAPFM Financial Management

Jianjun Guo Procurement Specialist EAPPR Procurement

Haiyan Wang Senior Finance Officer CTRDM Disbursement

Songling Yao Senior Social Development

Specialist EASCS Social Assessment

Yiren Feng Environmental Specialist EASCS Environment

Jian Xie Senior Environmental Specialist EASER Environmental Economics

Peishen Wang Consultant EASCS Environment

Jianming Zhao Consultant EASCS Geotechnical

Kek Choo Chung Consultant EASCS Navigation

Jiang Dai Consultant EASCS Hydropower

Page 40: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

27

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY02 4.7 32.95

FY03 37.03 268.33

FY04 29.77 248.81

FY05 0 -1.06

FY06 0 0.00

FY07 0 0.00

FY08 0 0.00

Total: 71.50 549.03

Supervision/ICR

FY02 0 0.00

FY03 0 0.00

FY04 1.25 15.71

FY05 19.37 103.98

FY06 14.05 67.70

FY07 14.67 65.21

FY08 14.84 91.92

FY09 13.56 79.44

FY10 8.99 68.99

FY11 10.50 74.52

Total: 97.23 567.47

Page 41: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

28

Annex 5. Summary of Borrower's ICR and/or Comments

Part A: Guangxi

According to the Comprehensive Utilization Plan of Yujiang River of the Xijiang River

System of the Pearl River Basin approved by the State Council, Guangxi Youjiang Naji

Navigation Complex Project is the fourth of ten cascade dams on the whole length of the

Youjiang and Yujiang Rivers. As a navigation complex and one of the key construction

projects in the State‟s “11th

Five-year Plan”, the Naji Project is an integral component of

the overall Xijiang River water management system, with supplementary functions of

power generation, irrigation and other benefits. The Project mainly includes the

construction of a power plant, a ship lock, a dam and channel improvement from Baise to

Nanning. After completion, the Project is expected to generate 253 GWh of electricity per

year and annual taxes amounting to RMB 16million. The navigation standard is improved

to 500 DWT vessels of Class IV navigation standard from the previous Class VI for 120

DWT vessels. The channelized Youjiang River will be able to accommodate 1,000 DWT

capacity of Class III Navigation Standard after the completion of the Yuliang, Jinji and

Laokou Complexes. The improvement of navigation on Youjiang River is significant in

contributing towards the ongoing course of improving the social and economic

development in the poorer areas in Baise as well as in the development of the Xijiang

Economic Corridor and the Pan-Pearl River Delta Economic Zone.

The total investment of the Project is estimated at RMB 1.18billion, including the USD

45million loan from the World Bank and the rest from the central and Guangxi government

grants, contribution by the implementing entity and domestic loans. Since the

commencement of the Project, with the support and assistance from the GTD, and under

World Bank‟s guidance and supervision as well as the joint efforts from and close

cooperation between contractors, consultants, engineers and the employer, the second

phase closure was completed and navigation opened in Oct. 2007; the first generator started

operation in Dec. 2007 followed by the second in Mar. 2008 and the third in Jun. 2008

respectively. Despite all difficulties, the Project has been implemented as planned and on

schedule. We have gained many useful experiences and learned certain lessons on the

project implementation as follows.

The cooperation with the World Bank has brought great positive changes in the philosophy

and concepts of our practice, operation and management, which helped us to realize that

equal attention should be paid to both economic and social benefits. As a result, more

efforts have been made and effective actions taken in practice to improve efficiency in

environmental protection and resettlement.

Adequate attention was given to resettlement to ensure that affected persons could improve

and maintain livelihoods not lower than those before resettlement so as to create harmony

and stability in the reservoir area where these people could live and work in contentment.

For the purpose of smooth implementation of the resettlement program, the Employer,

together with local governments and the task team of the World Bank Beijing Office has

undertaken a series of studies and consultations for the most appropriate mode. Measures

taken included: (1) affected persons were resettled in their own villages or nearby in the

reservoir area without moving to other villages or towns; (2) dumped soil was used in

Page 42: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

29

raising/filling lands for cultivation and such farmlands were returned to the villagers. Lands

were reallocated by local governments to ensure basic life security; where possible, unified

resettlement was arranged and implemented so as to have it included into the Plan of

Building New Socialism Countryside; some of the compensation for lands was used in the

production development and planning in the resettled villagers for the purpose of

increasing farmers‟ income. The implementation of such measures reflected the policy and

the practice of building a resource-saving and environmental friendly society and the

advocating of showing more concerns for the people, which has improved our relation with

the local population. There was no obstruction to construction or complaint to the higher

authorities during construction and after operation of the Project. Such measures have been

proven to be effective in maintaining stability and harmony in both the reservoir and local

areas. The Baise Municipal Government is in the process of inspecting and evaluating the

outcome of the resettlement for categorizing it as having met the standards for a

demonstration project.

Issues concerning environmental protection have been given considerable attention during

the construction period. Under the guidance and supervision of the World Bank review

missions, environmental monitoring was carried out throughout the construction period.

Effective measures and actions were taken to mitigate adverse impacts on the environment

and the ecology. Such measures included: (1) urging all concerned parties to build

domestic sewage treatment stations in the living quarters of the work site so that waste

water met relevant standards before being discharged; (2) building the two-stage

sedimentation basin in the sand yard of the contractor so as to ensure the waste water from

the sand yard met relevant standards; (3) frequent spraying to relieve dust emissions that

caused adverse environmental impacts during construction; (4) timely cladding on the

slopes of the dumping sites to mitigate washout of the slopes by rain water; (5) regular fry

releases were conducted to protect the fishery ecology. (The first fry release was completed

on Aug. 27, 2009); (6) greening and landscaping were carried out during the later period of

construction in the entire dam site with local mango, peach and kapok trees planted along

the banks at upstream and downstream of the dam. There is no doubt that a beautiful

landscape of trees, green grass and flowers will eventually materialize. We consider this an

important contribution to the enhancement of the local environment.

The Bank‟s supervision was important and necessary for improving proper and

standardized project management. The implementing entity, GXWCDC, acquired

advanced management methods and benefited from the experiences of the implementation

of similar overseas and domestic projects, which could be used as references, in the

preparation and development of relevant rules and regulations to ensure proper day-to-day

operation and management.

Careful planning and strict management in the procurement and financial management

(bidding, contract negotiation, contract execution, funds utilization, financial management,

payment and claim for disbursements etc.) have greatly improved our level of management.

Compliance with the Bank‟s procurement guidelines has positive influences on the

designers, consultants and engineers whose work has been recognized and appreciated by

the senior management.

Page 43: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

30

The World Bank loan was vital to the implementation and progress of the Project. The

loan was sufficient and disbursed in time, which was a great help to the implementing

entity.

The semi-annual missions allowed the World Bank to review, analyze and put forward

recommendations to address issues and problems occurred during construction and project

implementation. Besides, the World Bank‟s unique coordination capacity and position also

made it easier to request immediate attention of the contractor‟s management to solve the

problems such as negligence in work, insufficient resources and breaches of contract with

continuous follow-up checks and inspections. Such measures and actions were of great

importance to the smooth implementation of the Project.

A dam safety panel (DSP) was established as requested according to World Bank policy to

provide necessary technical assistances. The DSP consisted of experts and specialists of

whom more than half were professors or senior engineers in the fields of hydro-engineering,

geology, construction and metal structure with specific expertise and experiences in both

theory and practice and strong sense of responsibility. The DSP provided regular as well as

non-scheduled consultations, supervisions, comments and recommendations as necessary

for the smooth implementation of the Project. Their work, achievements and efforts were

highly appreciated by the World Bank. Such successful experience is worthy of being

duplicated.

The selection of an appropriate contractor is very important for the success of project

implementation, as the contractor is the key performer of the construction works. In an

immature market lacking of sound enforcement on social credibility, awarding contract to

the lowest bidder may not always be cost-effective to the employer but rather may cost

more in manpower and financial resources to make up for delay and poor quality of works.

In the case of our project, the winner for the contract of the civil works was not good at

hydraulic construction. Lots of deficiencies were exposed in work safety, quality, progress

and management during the preliminary phase of construction. Despite all the efforts and

assistances extended to the project site management office of the contractor, progress was

still slow. The Employer had to request replacement of the inefficient site management of

the contractor. Though the situation was improved gradually and finally, it was a painful

experience and a costly lesson for the Employer and the senior management, and the

engineers responsible for supervising civil works.

Construction safety is the first priority and safe work practices must be followed in

accordance with relevant laws and safety codes. The contractor should be held liable for

construction safety. The qualification and capacity of work safety management of the

contractor must be carefully checked. All concerned parties, especially the contractor were

required to take necessary precautions and fulfill their responsibility for site safety

supervision. In case of non-conformity, the contractor would be ordered to take effective

actions to improve or stop work as necessary. Termination of contract would be the last

means if no improvement is made. An accident that caused the death of four laborers

happened at the work site of the lower lock gate due to landslide in the slopes before dawn

on July 30, 2006. Though the accident was caused by a unpredictable geological collapse;

and the failure of the contractor to organize an efficient and effective emergency

evacuation indirectly contributed to the damage and fatalities. Learning lesson from the

Page 44: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

31

accident which included efficient and proper measures for backfilling in the slope toes and

slope surface, and wire-netting sprayed concrete for slope protection were taken.

Necessary measures were also taken against potential safety hazards. Since then, no

casualty accident has happened. It was a painful experience and a costly lesson. Safety

should always be placed in the first place in comparison with work progress.

The quality of project relies greatly on the project management level of the employer. The

Employer aimed for the efficient management of investments, quality control and

implementation progress. In this case, the employer attached great importance to the

overall coordination and planning so as to solve problems which occurred during

construction. Such unified planning has been proven to be important for the completion of

works ahead of schedule.

Attention must be paid to proper and efficient procurement of works, goods and services.

The process concerning invitation for bids must be treated seriously. Preparation for

invitation for bids for the Bank-financed procurement required a series of standard

procedures and time for approval, therefore, sufficient time had to be allowed for the

invitation for bids and bid award to avoid missing the planned schedule for implementation.

Proper and timely communication with the Bank team was important for the Employer to

better understand the Bank‟s rules and regulations and likewise for the World Bank to

know more about the real situations in China so as to mitigate potential risks and adverse

impacts to the employer through following the principle of awarding contract to the lowest

evaluated bidder.

As the local construction market is immature, the possibility of potential risks caused by

the adoption of the principle of awarding contract to the lowest bidder may not be ruled out.

In view of this, it is recommended that the employer be granted certain rights on decision-

making where the Bank‟s rules and regulations allow.

The aforesaid are the experiences and lessons we learned through utilizing foreign funds in

the implementation of the Project which we would like to share and hope they may be

helpful to other similar projects. Our summary may not cover every aspect of project

implementation. We welcome comments and appreciate any kind of suggestions.

Page 45: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

32

Part B: Guangdong

1. Project Introduction

1.1 General

The Guangdong Component of the Project has three sub-components: regulation works on

the middle reaches of Beijiang River (from Shaoguan to Qingyuan, 184 km), upgrading of

Lao-long-hu Waterway (16km) and the construction of Xiniu Dam on the Lianjiang River.

Guangdong Provincial Development and Planning Commission approved the Feasibility

Study Reports (FSR) of the three sub-projects respectively through three official documents.

The project was appraised in March, 2004; a loan of USD 46 million from the World Bank

was negotiated; and the Loan Agreement was signed in May, 2004, with the effective date

of January 9, 2005. The original closing date of the loan was January 31, 2010, and then

extended to June 30, 2011.

Channel regulation works on the middle reaches of Beijiang River upgraded the channel to

national Class V standard to accommodate vessels up to 300 dwt. The depth of the

waterway is 1.3 m, the width is 40 m, and the bending radius is 330m. As for regulation

works on the Lao-long-hu Waterway, the channel was upgraded to national Class III

standard to accommodate vessels of 1,000 dwt, with a depth of 4m, a width of 50m and a

bending radius of 330m. For the construction of Xiniu Complex on Lianjiang River, the

ship lock was designed to accommodate 100 dwt motor barges, with the annual tonnage

capacity of 2.57 million tons. The installed capacity of the power station is 3×3,340kw.

The total investment of this Project was estimated at RMB 930 million with an estimated

construction period of 4 years. The EIRR at the time of appraisal was estimated at 16.58%

and the ENPV was RMB 264.04 million.

The project was aimed to reduce the cost of waterway transport from the impoverished

rural and mountain areas in the west and northern part of Guangdong to the Pearl River

Delta. It plays an important role in improving the comprehensive transport network,

forming the Pearl River Delta waterway network of “Three-vertical-and-three-horizontal”

waterways and promotes the development of the export-oriented economy.

1.2 Investment Estimate and Funds Source

The total investment of the Project was estimated at RMB 930.34 million, equivalent to

US$ 112.36 million (USD1=RMB8.28). The funding sources of this project included the

World Bank loan, and the funds from MOT and the provincial government.

Table 1. Project Funding Sources:

Funding Sources Amount

(in USD million)

Amount

(in RMB million)

Ministry of Transport 35.11 290.74

Guangdong Province 31.25 258.72

World Bank 46.00 380.88

Total 112.36 930.34

1.3 Procurement Plan

The project was undertaken through 21 contracts involving civil works, equipment

Page 46: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

33

procurement and consulting services. In terms of the procurement method, 8 contracts

were procured by ICB, 4 contracts by NCB, 4 contracts by QCBS, 2 contracts by CQ, 1

contract by NS, and 2 contracts being non-Bank financed. The disbursement percentages

of the Bank loan for the civil works, goods, consulting services and training were 50%,

100%, 91% and 100% respectively.

2. Performance of Project Implementation

2.1 Progress of Implementation

The Guangdong Component started in March, 2005. The Bank-financed part of the project

was completed by June 30, 2011 but the non-World Bank financed contracts are scheduled

to be completed by May 2012. The implementation progress lagged behind the schedule

due mainly to complicated geological conditions, excessive floods, large contract variations,

difficulties in land acquisition, and the contractors‟ poor performance.

2.2 Quality of Construction

The 4-grade quality guarantee system of “Government inspecting, Client managing,

Engineer supervision and Contractor back-check” was adopted for the quality control of the

Project. The contractors and the supervising engineers installed laboratories at the

construction sites. The contractors did the sample inspection of the materials, semi-finished

products and finished products while the supervising engineers did the parallel tests.

Moreover, the client entrusted a third party to spot-check the materials, semi-finished

products and finished products of the important component of the project, which effectively

controlled the quality of these parts. The site supervision engineers and the management

staff of the Client urged the contractor to inspect, site-supervise and examine the

construction procedures, methods and techniques so as to monitor and ensure the

construction quality.

The qualifying rate of the quality of Contract W2 is 100% and the excellent rate reaches

70%. The quality of Contract W4 is rated as “qualified”. It has been awarded the Excellent

Building Structure Project 2007 in Qingyuan, presented by Qingyuan Construction Quality

Supervision Station, as well as the Excellent Sample Project 2009 in Qingyuan, issued by

the Qingyuan Construction Bureau. Other civil works are predicted to be rated as

“qualified” based on the present quality. As for the goods contracts, except Contract G5

being still on-going, other contracts are rated as “qualified”. Contract T2 (Electronic

waterway mapping system) and Contract T4 (Shiplock Management System) are qualified.

2.3 Financial Management

The actual total investment will be estimated at RMB 843.97 million. Up to June 30, 2011,

the percentage of total actual disbursement to estimated amount is 89.75%, with

counterpart funds 87.27% and the Bank loan 100%. To fully use the Bank loan and reduce

financing cost, the disbursement percentage for civil works was increased from 50% to

80%. The financial management has been under appropriate control. All the annual audit

reports during the project implementation were unqualified (clean).

2.4 Technical Assistance and Training

The technical assistance comprised Contract T2 (Electronic Waterway Mapping System)

and Contract T4 (Shiplock Management System). The Waterway Electronic Mapping

System is a tool to analyze and process the waterway geographic data and support the

Page 47: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

34

decision-making. Contract T2 has designed and developed a waterway electronic mapping

system which boosted the transformation of the waterway information managing mode and

improved modern management level of the waterway. The Shiplock Management System

has developed a shiplock management center, facilitating the collection, transmission,

tabulation, analyzing, querying, comparison and statement printing of the data which

showed the status, water level and vessels of the twelve shiplocks on the Lianjiang River.

Meanwhile the shiplock management system realized the control of monitoring and

warning as well as the water level regulating gate in the shiplock area. This system

enhanced the information sharing and management between the shiplock managing

departments at all levels, increased the management efficiency of the twelve shiplocks and

promoted the management level and capability of the waterway shiplocks.

Training programs of the Project include: study on inland waterway development planning,

inland waterway management and vessel operation, environment protection; study on

waterway polices and regulations, waterway construction and maintenance; research on

waterway design optimization, navigation junction management and maintenance,

procurement and contract, development and utilization of navigational aids, maintenance

and monitoring of channel markers, advanced financial management, human resource

management, project management, MIS, economic analysis and evaluation,

informationization of waterway construction, software application, English language, etc.

During 2005 and 2010, there were totally 19 overseas training groups, involving 127

persons. The overseas training planned to involve about 84 man-months. Actually there

were accumulatively 64.52 man-months. Although the actual man-months were lower than

the planned ones due to the government‟s restriction on the numbers of participants and the

days of overseas training, the planned training topics and tasks have been mostly

implemented. From 2004 to 2010, totally there were 17 domestic training groups,

involving 293 persons. The domestic training was planned to involve about 130 man-

months. But actually there were 97.37 man-months for domestic training.

3. Land Requisition and Resettlement

3.1 Land Requisition

The total land requisition area of the Project is 1,236.371 mu, which is 386.051 mu more

than the planned area figure (849.32 mu, not including the flood lands) in the resettlement

action plan, increasing by 45.57%.

3.2 Infrastructure Removal and Restoration

There was no removal of residences and enterprise housing. The buildings removed have

been compensated.

3.3 Resettlement Fee

The total cost of the resettlement was about RMB 129.49 million, which was more than the

estimated cost in the resettlement plan. The increased cost mainly involved three aspects:

(1) Zhangwu Village and Hetou Village whose cultivated lands per capita were less than

0.5 mu have been compensated by RMB 11.655 million; (2) the changed national policies

for land requisition have increased the compensation rates for land requisition; (3) the

removal fee for the Longma and Lianyao Bridges was RMB 10 million. The fees

mentioned above were not listed in the resettlement plan. The land requisition

Page 48: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

35

compensation standard of this Project was apparently higher than the stipulated standard in

the resettlement plan. The compensation standard of paddy fields for the Xiniu project

have been increased by 36% and the standard of dry lands have been increased by 6%. As

for the regulation work of Lao-long-hu River, the Xinhui Transport Bureau has basically

reached the compensation standard according to the land types and use of lands (quarry and

discarded lands in the brick yards). The comprehensive unit price of the land requisition

compensation of the two bridges was 45% higher than that of the Lao-long-hu project.

3.4 Residents’ Living Standard

As for the residents‟ living standard, the net income per household has increased by 23.7%

and the net income per capita has increased by 28.5%, compared to that before the land

requisition, which is not a significant increase compared with the households that are

unaffected by the land requisition.

Generally, the resettlement of the project has been carried out based on the requirements set

in the resettlement action plan in terms of land requisition, compensation, information

disclosure, economy recovery and complaints processing. It has achieved the goal of

improving the living standard of the affected people.

4. Environment Protection and Monitoring

During the project implementation, relevant environment management agencies were set up

to make the management system for environment protection. The environment

management agencies at all levels have taken measures in respect of the acoustic

environment, water environment and ecological environment based on the requirements in

the Environmental Impact Assessment Report and the Environment Protection Actions

Plan. The measures included the effective noise-reducing and dust-controlling measures,

reducing the influence of the suspended solids; the ecological restoration measures on the

mud dumping area and temporary construction area; the compensation to the fishery

resources; construction of the fish ladder. Meanwhile, the environment management system

was improved by the Client and the supervising engineers. We insisted that the

construction should be implemented together with the protection of environment. Therefore,

we strictly carried out the project based on the environment monitoring plan during

construction.

4.1 Protection of Fishery Resources

With the objective of ecological and environmental protection and based on the

requirements of ecological and environmental protective measures in the EIA and EMP, the

protection of fishery resources in Lianjiang River has been carried out. For example, during

the construction, the rubbish and harmful chemical hazards were forbidden to be discarded

into the river. Meanwhile, no-fishing zones of 200 meters each was set in the upstream and

downstream of the river. To effectively protect the fishery resources, the Qingyuan Branch

of the Guangdong Fishery Corps took remedy measures of fishery resource enhancement

and releasing to improve the situation of fishery decreasing. The fishery resource

enhancement and releasing measures will last 15 years, with the total investment of RMB

1.5 million. By now, 4 fishery resource enhancement and releasing activities have been

carried out, releasing about 2.16 million fishes such as black carp, dace, grass carp, crucian,

carp and so on.

Page 49: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

36

To minimize the damage of the construction to the environment of the fishery and to solve

the fish ladder issues, the GPWB entrusted the Environment Protection Center of the MOT

and the Pearl River Fishery Research Institute to research the measures of protecting the

fishery in Lianjiang River and design the scheme of the fish ladder. Meanwhile the GPWB

also invited the experts from the Ministry of Water Resources, the Ministry of Agriculture,

the Ministry of Transport and Guangdong Province to evaluate the fish ladder scheme. The

construction of the fish ladder was completed and operational in February 2011.

4.2 Environment Monitoring

According to the requirements of the environmental monitoring plan in the EIA and the

EMP, the Pearl River Basin Water Environment Monitoring Center was selected through

the public bidding to undertake the environmental monitoring during the construction.

During Dec., 2004 and the end of the construction, the Pearl River Basin Water

Environment Monitoring Center carried out the environmental monitoring on the

construction area and made comprehensive analysis on the influence of the construction to

the water environment based on the progress and environment. Meanwhile, the

environmental monitoring materials as well as 13 semiannual monitoring reports have been

periodically sent to the World Bank and relevant departments.

In the water quality monitoring of middle reaches of Beijiang River and the Xiniu

construction on Lianjiang River, the average value of the cross sections of each project has

reached the Grade I-III water standard. There was no over proof and no big influence on

the water quality. For some reaches of the river, there were more suspended matters during

the flood period and the cofferdam dismantled period than usual, but the influence lasts not

long. Since some reaches of Beijiang River was polluted by the industrial effluents

containing the cadmium and the arsenic, whose heavy metals were over standard and the

quantity of arsenic exceed the standard in the Controlling Standard for Pollutants in Farm-

oriented Sludge (GB4284-84), the contractors paid great attention to the management of the

dredged materials and did not discard them arbitrarily or apply them to the farm.

According to the monitoring results during construction, the air quality of the urban

residences around the constructed waterway was fine, and its TSP and PM10 were much

lower than the Grade II limit in the Environment Air Quality Standard. This showed that

the contractor had effectively reduced the dust from the dredging, excavation and

transportation, and controlled the air pollution caused by the construction within a small

range around the construction area, which did not influenced the air quality of the residents

around the waterway.

The measuring results of the noise gauging points in the monitoring plan were all within

the limit of Grade II standard set in the Environment Noise Standard in Urban Area

(GB3096-93), which met the requirements of acoustic environmental protection objective.

It means that the construction did not brought significant noise on the area.

5. Experience, Lessons and Suggestions

5.1 Experience

(1) The Guangdong province has introduced the World Bank loan twice to improve the

waterway and its management level. This Project is the second World Bank loan project in

Guangdong. By implementing the Project, we have studied the essential refined and

scientific element in the management of World Bank loan project and improved the

Page 50: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

37

management mode, which upgraded the waterway comprehensive management level and

advanced the sustainable development of waterway.

(2) We expected that the application of Reno Gabion, a new material for environment

protection, will bring a demonstration effect. Reno Gabion is a new material for

environment protection, which can be applied to the construction such as bank protection,

revetment and foot protection. The features of this material include good integrity, great

erosion-resisting ability, flexible structure, good flexibility in adapting to the deformation

of foundation. If the sludge fills in Reno Gabions, it is easy for the vegetation grow.

Meanwhile, it is environmentally friendly and not expensive if there are available materials

in the local area. It is the first time for us to apply the Reno Gabion to bank protection in

terms of hydraulic engineering and waterway projects in Guangdong. Since there were a

great amount of pebbles in Xiniu construction site, we decided to apply the Reno Gabion to

bank protection of approach channels along the upstream and downstream around the ship

lock, with the application area of about 50,000 ㎡. In July, 2006, the worst flood in 50

years took place, but the Reno Gabion was not affected. After the work completed, the

Reno Gabion was basically covered with vegetation. Based on the effect of the application

of Reno Gabion for the moment, we concluded that it is a success in applying this new

material in the construction of Xiniu Dam. Meanwhile, the demonstration effect emerged.

The Reno Gabion has been applied in the other waterway projects such as Reinforcement

of Canalization Complexes and Waterway Improvement on Lianjiang River, as well as the

Improvements of Meijiang River and Tingjiang River.

(3) We have attached great importance to the environment protection and the compatibility

of construction and environment protection. Based on the requirements of ecological and

environmental protection in the EIA and EMP, we carried out monitoring on the water

quality, air and noise of the regulation work of middle reaches of Beijiang River, the

regulation work of Lao-long-hu River and the construction of Xiniu Dam on Lianjiang

River. The results showed that the monitoring data met the national criteria. In order to

protect the fishery resources in Lianjiang River and minimize the blocking loss brought by

the construction of Xiniu Dam, the Project made a 15-year plan of fishery resource

enhancement and releasing and built the first fish ladder in Guangdong Province. We can

expect that the blocking loss brought by the construction of Xiniu Dam will be minimized

in respect of the fishery protecting technology for the moment.

5.2 Lessons

(1) The World Bank‟s procurement guidelines cannot be applied rigidly in China.

Since the market economy started late in China, the market competition system is still

incomplete and the credit system is still inadequate. Though the management experience

of World Bank projects has been proven to be advanced and scientific, it is still difficult to

promote the principle of low-quoted price bidding in project procurement. For most of the

domestic bidders, the first thing they are considering is to win the bid instead of gaining

profit because they need to sustain their business. Therefore, the World Bank projects low-

bidding phenomenon is prevailing in China. However, in the project implementation, the

contractor who won the bid with a low price would make up the margin by contract

variation, claiming or even delaying the construction, which made it difficult to carry out

the project.

Page 51: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

38

(2) Some local governments lack enough understanding and support to the waterway,

which makes the coordination more difficult. The construction of waterways possesses the

features of great public benefit, long investing period and low return, which means that a

period of time is needed to show its social and economy effect. However, due to the slow

economy effect of the waterway, some local governments take no account of the waterways.

Instead, they attach importance to the construction of roads and highways, which caused

difficulties in the coordination during project implementation.

5.3 Suggestions

(1) We suggest that the World Bank take the actual situation of China into account and

apply the World Bank policies to the project management flexibly and systematically, with

the economy and efficiency as the first principles, while the Bank is promoting its

normative procurement and project management system.

(2) We suggest that relevant governmental departments make greater efforts to promote

the waterways and the local government attach more importance to the waterways.

Meanwhile, the fund raising channel for the waterway construction should be broadened

and more capital should be invested. Through the improvements of waterways, the local

economy can be boosted, forming a good economy cycle.

Page 52: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

39

Annex 6. List of Supporting Documents

1. The World Bank, Project Appraisal Document, Fourth Inland Waterways Project,

March 1, 2004Guangdong Project Management office, “Project Cost Estimates and

Financing Plan”, received on May 13, 2011.

3. The World Bank, Fourth Inland Waterways Project, Aide-Memoires, Management

Letters, 2004-2011.

4. Guangdong Project Management office, “Semi-annual Project Progress Report”,

2004-2010.

5. Guangdong Project Management office, Social Assessment Report, July 2002.

6. Guangdong Project Management office, Environment Assessment Report, May

2005.

7. Guangdong Project Management office, Resettlement Action Plan, August 2008.

8. Guangdong Project Management office, Audit Reports, 2006-2010.

Page 53: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

Grand Canal

Huang H

o

Chang Jiang

Bo Hai

E a s t

C h i n a

S e a

Y e l l o w

S e a

S e a

o f

J a p a n

S o u t h

C h i n a S e a

Left

Hongshui HeRightRiver

(Youjiang)

River

(Zuojiang) Yujia

ng

Xijiang

For detail seeIBRD 32888

NajiDam

For detail seeIBRD 32890

For detail seeIBRD 32889

XiniuDam

H E B E I

SHANDONGS H A N X I

BEIJING

TIANJIN

L IAONING

J I L I N

H E I L O N G J I A N G

NE

I M

ON

GO

L

S H A A N X I

NINGXIA

G A N S U

QINGHAI

S I C H U A N

XIZ

AN

G

YUNNAN

G U I Z H O U

G U A N G X I

HUNANJ IANGXI

G U A N G D O N G

FUJ IAN

HAINAN

TAIWAN

ZHEJ IANG

JIANGSU

A N H U I

H E N A N

H U B E I

HONG KONGMACAO

Qiqihar

Anda

Hegang

Shuangyashan

Jixi

Jilin

Fushun

Benxi

Dandong

AnshanLiaoyang

YingkouJinzhou

Fuxin

Baotou

Shizuishan

Tongchuan

Baoji

Kaifeng

Pingdingshan

Luoyang

ZaozhuangLianyungang

Xuzhou

Huaibei

BengbuHuainan

NantongZhangjiagang

WuxiWuhu

Ningbo

Tongling

Jingdezhen

Wenzhou

Xiamen

Macao

Hong Kong

Wuzhou

Guilin

Liuzhou

Beihai

PingziangZhuzhou

Huangshi

ZigongChongqing

Panzhihua

Dongchuan

Zibo

Qingdao

Xichang

Yangpingguan

Ankang

Da Xian

Xiaonanhai

Luohuang

Jiuchang ZhijiangHuaihua

Hengyang

Shenzhen

Le An

Maoming

Shantou

Meixian

Longchuan

Jiujiang

Yingtan

Shaowu

Laizhou

Yong’an

Zhangping

Xingtanbian

BailutangZhicheng

Shimun

Xiangfan

Pixian

HezeHandan

Yanzhou

Shangqiu

Shijiusuo

Fuyang

Mengmiao

Tianshui

Houma

Yan’an

ZhongweiWuwei

Yumen

Shenmu

Jining

Datong

Zhangjiakou

Erenhot

Huade

Tongliao

Yuanbaoshan

Qinhuangdao

Yueshan

Jiaozuo

Changzhi

DezhouHengshuiShengli

Yantai

Siping

Jiamusi

Mudanjiang

Wuyiling

Hulin

Tongjiang

Suihua

Baicheng

Yirshi

Songling

HailarManzhouli

Mordaga

Mangui

Gulian

Bei’an

Tumen

Songjianghe

Dalian

Shanjiang

Tangu

To Urumqi

Suifenhe

Heihe

Zhenjiang

Anqing

Chenglingji

Yibin

GuipingGuigang

Xiangtan

JiaxingHuzhou

Harbin

Changchun

Shenyang

Tianjin

BEIJING

Shijiazhuang

Taiyuan

Hohhot

Yinchuan

Lanzhou

Xining

Xi’anZhengzhou

Hefei

Nanjing

Shanghai

Hangzhou

Nanchang

Fuzhou

Guangzhou

Nanning

Changsha

WuhanChengdu

Guiyang

Kunming

Haikou

Jinan

REP. OFKOREA

DEM. PEOPLE’SREP. OF KOREA

M O N G O L I A

PHIL IPP INESTHAILAND

LAO PEOPLE’S

DEM. REP.

VIETNAMMYA

NM

AR

MYA

NM

AR

0 100 200 300 400 500 MILES

0 200 400 600 800 KILOMETERS

MAJOR NAVIGABLE WATERWAYS

RIVER PORTS

PREVIOUS BANK FINANCED RIVER PORTS

SEA PORTS

PREVIOUS BANK FINANCED SEA PORTS

PREVIOUS BANK FINANCED SHIPLOCKS

PREVIOUS CHANNEL IMPROVEMENTS

MAJOR ROADS

EXISTING RAILWAYS

SELECTED CITIES

PROVINCE CAPITALS

NATIONAL CAPITAL

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARIES

CHINA

FOURTH INLAND WATERWAYSPROJECT

IBRD 3

28

87

MA

RCH

20

04

20°

100° 110° 120°

20°

30°

40°

50°

110°100°

30°

130°120°

BaiseDam(BMP)

ChannelImprovements

(IWW1)

Guigang Dam (IWW1)

Channel Improvements (IWW2)

ChannelImprovements

(IWW1)Dayuandu Dam (IWW1)

Zhuzhou Dam/Shiplock (IWW3)

ChannelImprovements

(IWW1)

Suqian No.3 (IWW2)

Xeitai No.2(IWW2)

Huanyin No.3 (IWW2)Huanian No.3 (IWW2)

Jianbi No.2 (IWW2)

Channel Imp.(IWW3)

ChannelImprovements

(IWW4)Channel Improvements (IWW4)

BEIJING

HEILONGJIANG

JILIN

LIAONING

NEI MONGOL

HEBEI

BEIJING

TIANJIN

SHANXI

SHAANXIGANSU

QINGHAI

XINJIANG

XIZANG

NIN

GXI

A

SHANDONG

HENANANHUI

JIANGSU

ZHEJIANG

SHANGHAI

SICHUAN

CHO

NGQIN

G HUBEI

GUIZHOU

HUNANJIANGXI

FUJIAN

GUANGXIGUANGDONG

TAIWAN

HAINAN

YUNNAN

HONG KONGMACAO

RUSSIAN FEDERATION

MONGOL IA

JAPAN

PHILIPPINES

VIETNAMMYANMAR

LAO

REP. OFKOREA

D.P.R. OFKOREA

P.D.R.

Sea ofJapan

YellowSea

EastChinaSea

P A C I F I C

O C E A N

National Capital

Province BoundariesInternational Boundaries

For detail see IBRD32889 and 32890

For detail seeIBRD 32888

Page 54: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

This map was produced by the Map Design Unit of The World Bank.The boundaries, colors, denominations and any other informationshown on this map do not imply, on the part of The World BankGroup, any judgment on the legal status of any territory, or anyendorsement or acceptance of such boundaries.

Baise

Wuzhou

Yulin

Guilin

Liuzhou

NANNING

FangchengGezu

Qinzhou

Beihai

Yulin

NANNING

FangchengGezu

V I E T N A M

V I E T N A M

Y U N N A N

G U I Z H O U

H U N A N

GUANGDONG

G U A N G X I

Beibu Gulf

Rong

Jiang

Hongshui

(Youjiang)

Hongshui He

Nanpan Jiang

Gui Jiang

He Jiang

Xijiang

South China Sea

He

Be ibu Gu l f

(Zuojiang)

Yujia

ng

Righ

t Riv

er

(You

jiang

)

Right R.

Left R. (Zuojiang)

105° 106° 107° 108° 109° 110° 111°

105° 106° 107° 108° 109° 110° 111° 112°

26°

25°

24°

23°

25°

24°

23°

22°

112°

26°

NajiDam channel

improvements

See detail below

PROVINCE CAPITALS

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARIES

0 100

KILOMETERS

0 10 20 30

KILOMETERS

40 50 60

PROVINCE CAPITALS

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARIES

Guiping

Wuxuan

Bobai

Hepu

Pubei

Lingshan

ShangsiNingmingPingxiang

Longzhou

Daxin

Tiandeng

Fusui

Yongning

WumingLong'an

Pingguo

Tianyang

BamaYaozu

LingyunTianlin

DahuaYaozu Mashan

Shanglin

Binyang

Guigang

Hengxian

Laibin

Debao

Jingxi

Chongzuo

Qinzhou

Luchuan

IBRD 32888

MARCH 2004

NAJI NAVIGATION COMPLEX DETAIL

0 50 100 m.

Dam Section PowerhouseSection

ShiplockSection

Ups

tream

App

roac

h

Emba

nkm

ent

Emba

nkm

ent

Xijing

Laokou

Jingji

Yuliang

Naji DamTiandong

Dongshun

BaiseChengbihe

Wacun

Chengbi

Baidong R.Boyi R.

Gul

a R.

Right R. (Youjiang)

Yujia

ng

WATER SYSTEM OF YUJIANG VALLEY

For detail seemap at right

CHANNEL IMPROVEMENTS

HYDROLOGIC STATIONS

WATER LEVEL STATIONS

EXISTING DAMS

FUTURE DAMS

OBSERVATORIES

BASIN BOUNDARY

RIVER PORTS

NATIONAL ROADS

RAILROADS

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARY

Dow

nstre

am A

ppro

ach

Access Bridge

New BridgeLe

ft R.

CHINA

FOURTHINLAND WATERWAYS

PROJECTGUANGXI PROVINCE

NAJI NAVIGATION COMPLEXAND

CHANNEL IMPROVEMENTS

SURFACE PROFILE OFSTEPPED DAMS DEVELOPMENTIN RIGHT RIVER (YOUJIANG)

VALLEY

1000

500

1100 1000 900 800 700

Naj

i

Bais

eD

ongs

un

Wac

un

350.

0

228.

0

115.

012

1.0

DISTANCE IN KILOMETERS

ELEV

ATIO

N IN

MET

ERS

0

Riverbed Line

Page 55: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

G U A N G D O N G

Gua

nyin

g-ke

ng

S o u t h C h i n a S e a

Nanshui

Zhenshui

(Nor

th R.

)

Zhut

ian

Huan

gdon

g

Bolu

o

Qin

glia

n

Quanshui

NanshuiReservoir

Jiangwan

Nanshui

Beiji

ang

Lianjiang

Lianjiang

Binjiang Pajia

ng

Lianjiang

Bei J

iang

Boloukeng

Wengjiang

Xiashui

Binj

iang

Longxudai

(Nor

th R

.)

L i a n j i a n g

0 40 80 120

KILOMETERS

111°

25°

23°

22°

21°

24°

25°

23°

22°

21°

110° 112° 115° 117°

111°110° 112° 113° 114° 115° 117°116°

24°

XiniuDam Midd

leRe

ach

Beiji

ang

Lianjiang

Xijiang

PROVINCE CAPITAL

PROVINCE BOUNDARIES

Wangbu

Hangguang ShihuipuJiaqiaoshi Dam

Baisha

Dawan

Zhangpo

ShigutangHengshitang Yunling

Shakou

Luokeng

Jiangwan

Dabu

Gumushui

Luoyan

Longnan

LuyuanyaozhuHougongdu

Yiliu

Fengtian

Longgui

BaituQujiang

Xilian Toucun

HexiShaoguan

Xinshao

Baisha

Wushi

Zhanshi

Dakengkou

Qingkeng

BoluoFengtian

Pingjia

Huangpen

XijiangLianxian

Longtang

Xiaojiang

Litou

YangshanGaofeng

Daliang

Shanlian Shuikou

Dongshan

Jiangying

HuamingzuiDam

JiaojianboDam

QinglianDam

QingshuanDam

ShuoyitanDam

HuangmaoxiaDam

Huilian

Qingyuan

Qingxin

Zhouxin

Jiangkou

Gaoqiao

Longshan

Minan

Shenping

Gaotian

Longnan

Fogang

SanbaShuitou

Gaogang

Huanggang

Dazhan

Yingde

Lianjiangkou

Shuibian

Xiniu

Shaba

Lixi

Dadong

Xinzhou

Shahe

Heyun

Longjing Yuba

Zhukeng

Jiulong

Mingjing

Huangshi

Jingtou

Shitang

Chentang

Tankou Dam

Ma’antou Dam

Jingkou Dam

Qixinggang

IBRD 32889

MARCH 2004

GENERAL PLAN LAYOUT OFXINIU NAVIGATION COMPLEX

SectionD

For detail seemap at right

0 100 200 m.

For detail seeIBRD 32890

This map was produced by the Map Design Unit of The World Bank.The boundaries, colors, denominations and any other information shownon this map do not imply, on the part of The World Bank Group, anyjudgment on the legal status of any territory, or any endorsement oracceptance of such boundaries.

CHANNEL IMPROVEMENTS

EXISTING DAMS

RIVER PORTS

NATIONAL ROADS

RAILROADS

Baishiyao Dam

Mengzhouba Dam

LongchuangchangDam

JietanDam

HuangniutanDam

HuangyantanDam

SectionC

SectionA

SectionB

Feilaixia Dam

Xiniu DamFor detail seemap at right

SectionE

0 10 205 15 30

KILOMETERS

4025 35

Dam Section

Pow

erho

use

Sect

ion

Ship

lock

Sect

ion

CHINA

FOURTH INLAND WATERWAYS PROJECTGUANGDONG PROVINCE

XINIU NAVIGATION COMPLEX AND BEIJIANG CHANNEL IMPROVEMENTS

HONG KONG

H U N A NJ I A N G X I

F U J I A N

G U A N G X I

MACAO

Zhanjiang

Maoming

Zhaoqing

Qingyuan

Shaoguan

Shantou

ShanweiShenzhen

HongKong

HuizhouDongguanFoshan

GUANGZHOU

Heyuan

Meixian

Yangjiang

Jaingmen

SURFACE PROFILEOF STEPPED DAMS

DEVELOPMENTIN LIANJIANG VALLEY

90

80

70

60

50

40

30

20

10

50 100 150 181

Long

chua

ngch

ang

Jieta

n

Hua

ngni

utan

Hua

ngya

ntan

Hua

min

gzui

Jiaoj

ianb

o

Qin

glia

n

Qin

gshu

an

Shuo

yita

n

Huan

gmao

xia

Jiaqi

aosh

i

Xini

u

Lian

jian

DISTANCE IN KILOMETERS

ELEV

ATIO

N IN

MET

ERS

0

Riverbed Line

58.5

53.3

49.6

44.3

38.5

33.1

24.0

86.0

81.0

73.5

70.0

62.7

29.0

Page 56: Document of The World Bankdocuments1.worldbank.org/curated/en/...the waterways and the local government attach more importance to the waterways. Meanwhile, the fund raising channel

This map was produced by the Map Design Unit of The World Bank.The boundaries, colors, denominations and any other information shownon this map do not imply, on the part of The World Bank Group, anyjudgment on the legal status of any territory, or any endorsement oracceptance of such boundaries.

LAO LONG HU WATERWAY AND PROJECT BRIDGES

CHANNEL IMPROVEMENTS

PROJECT BRIDGES

EXISTING BRIDGE

ROADS

RIVER REACH TO BE WIDENED

SHORT-CUTTING REACH

G U A N G D O N G

S o u t h C h i n a S e a0 40 80 120

KILOMETERS

111°

25°

23°

22°

21°

24°

25°

23°

22°

21°

110° 112° 115° 117°

111°110° 112° 113° 114° 115° 117°116°

24°

XiniuDam

Beiji

ang

Lianjiang

Xijiang

PROVINCE CAPITAL

PROVINCE BOUNDARIES

IBRD 32890

MARCH 2004

For detail seeIBRD 32889

For detail seemap at right

0 1 2 3 4 5

KILOMETERS

SanjiangTown

LongquanVillage

MuzhouTown

SanjiaweiVillage

DongchengVillage

Longquan (Longma)Bridge replacement

HukengBridge

Gouwei Bridgereplacement

Hukeng

Waterway BabaoWaterway

Longquanhai River

Xiezhousha

Waterw

ay

Laolaoxi

Hem

axiW

aterway

Waterway

Laol

aoxi

wayMuzhou Water

Baba

oW

ater

way

Huk

eng

Wat

erw

ay

River reach tobe widened

short-cuttingreach

YinzhouhuW

aterway

APPROXIMATE SCALE

CHINA

FOURTHINLAND WATERWAYS

PROJECTGUANGDONG PROVINCE

LAO-LONG-HUCHANNEL IMPROVEMENTS AND

BRIDGE REPLACEMENT

HONG KONG

H U N A NJ I A N G X I

F U J I A N

G U A N G X I

MACAO

Zhanjiang

Maoming

Zhaoqing

Qingyuang

Shaoguan

Shantou

ShanweiShenzhen

HongKong

HuizhouDongguanFoshan

GUANGZHOU

Heyuan

Meixian

Yangjiang

Jaingmen