DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014

DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR

MISSION Meera Fickling ECODIT, LLC June 26, 2014

Page 2: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

INDIA’S SOLAR PROGRAM

•  JNNSM: launched in 2010 under National Action Plan on Climate Change. •  1.1 GW of grid connected

PV, 0.2 GW of off grid by 2013.

•  20 GW of grid connected PV, 2 GW of off grid by 2022.

Page 3: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

INDIA’S SOLAR PROGRAM

•  Phase I: Reverse auction mechanism •  Solar developers submit bids to

government •  Government selects lowest

bids •  Government purchases power

•  Two auctions under Phase I: •  Batch I: PPAs signed in 2011 •  Batch II: PPAs signed in 2012

•  One auction so far under Phase II: •  PPAs signed in 2014

Page 4: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

THE SOLAR PV MANUFACTURING CHAIN

Page 5: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

THE PHASE I LCR

•  Crystalline silicon panels required to be sourced domestically.

•  Thin film panels exempt from the requirement.

Page 6: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

0.5

0.7

0.9

1.1

1.3

1.5

1.7

1.9

2.1

1/2

010

3/2

010

5/2

010

7/2

010

9/2

010

11/

2010

1/2

011

3/2

011

5/2

011

7/2

011

9/2

011

11/

2011

1/2

012

3/2

012

5/2

012

7/2

012

9/2

012

11/

2012

CSi vs Thin Film Module Spot Prices, Adjusted for BOS Penalty, 2010-2012

Pvinsights CSi Multi Module Spot $/watt - Average

PVinsights Thin Film Module Spot $/watt + BOS Penalty

Globally, only 11 percent of PV deployment is in thin film; 89 percent is in Csi.

Under the JNNSM, over 60 percent of capacity subsidized under Phase I was in thin film.

Page 7: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

Gujarat vs. Rajasthan

    Projects  Financed  2011-­‐2012       JNNSM  

Projects  Non-­‐JNNSM  Projects  >  

5  MW  Gujarat   0   59            North  Gujarat   0   2  

Rajasthan   52   2  

Page 8: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

PERCENT MARKET SHARE: FOREIGN CSI, FOREIGN THIN FILM, DOMESTIC

   

Rajasthan   Gujarat  

Foreign  CSi   0   30  

Foreign  Thin  Film   62   38  

Domes?c  CSi   38   33  

Page 9: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

PHASE II: POLICY ADJUSTMENTS

•  Viability Gap Funding (VGF) •  Total 750 MW in Batch I •  Two separate auctions: •  375 MW is open; no LCR •  375 MW has technology-

neutral LCR

•  Imported thin film now at a disadvantage •  US has requested a

dispute settlement panel in WTO

Page 10: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

PHASE II LCR’S IMPACT ON THE COST OF SUBSIDIZING SOLAR GENERATION

0

5

10

15

20

25

30

10

60

110

160

210

260

310

360

410

460

510

560

610

660

710

Via

bili

ty G

ap

Fun

din

g (

VG

F),

Mill

ions

of R

upe

es

MW

True Supply

Supply with LCR

Page 11: DOMESTIC CONTENT REQUIREMENTS AND INDIA’S NATIONAL SOLAR … · AND INDIA’S NATIONAL SOLAR MISSION Meera Fickling ECODIT, LLC June 26, 2014 . INDIA’S SOLAR PROGRAM • JNNSM:

SUMMARY

•  Phase I LCR: •  A failure for Indian

manufacturing: No significant additional domestic market share.

•  A win for foreign thin film manufacturers: mean estimate of 24% increase in thin film market share.

•  Phase II LCR: •  50% increase in subsidy at the

margin relative to a non-LCR scenario.