DOS Steel Bridge-2

Embed Size (px)

Citation preview

  • 8/7/2019 DOS Steel Bridge-2

    1/28

    Part 1: BRIDGE STRUCTURES

    Lecture-2

    DESIGN OF STRUCTURES

    STEEL DESIGN

  • 8/7/2019 DOS Steel Bridge-2

    2/28

    DESIGN OF CONCRETE DECK SLAB

    Minimum Slab Thickness

    Absolute Minimum Thickness =

    175 mm (9.7.1.1)

    Traditionally, the minimum

    thickness was specified in

    AASHTO Standard Specification

    for the purpose of deflectioncontrol.

    However, AASHTO LRFD

    removes all the requirements for

    maximum deflection and leaves itto the judgment of the designer.

    Therefore, the thickness of slab

    for deflection control is now

    optional. (2.5.2.6.3)

    S = slab span (mm)

    L = span length (mm)

  • 8/7/2019 DOS Steel Bridge-2

    3/28

    DESIGN OF CONCRETE DECK SLAB

    Slab span (S) is determined from

    1-Face-to-Face distance for slab monolithic with beam (i.e. cast into one piece)

    2-For composite slab on steel or concrete girder, the distance between the face of the

    webs

  • 8/7/2019 DOS Steel Bridge-2

    4/28

  • 8/7/2019 DOS Steel Bridge-2

    5/28

    DESIGN OF CONCRETE DECK SLAB

    Minimum clear cover for reinforcing

    steel and pre-stressing steel (5.12.3)

    Adjustments for Water-Cement Ratio:

    a. For W/C < 0.4, the concrete tends to be

    dense; therefore can use only 80% of the

    value in the table (i.e. multiply by 0.8)

    b. For W/C > 0.5, the concrete tends to be

    porous; the value in the table must be

    increase by 20% (i.e. multiply by 1.2)

    If there is no initial overlay of wearing

    surface, should add another 10 mm to the

    clear cover on the top surface to allows

    for some wear and tear

    Minimum Cover of Reinforcement

  • 8/7/2019 DOS Steel Bridge-2

    6/28

    DESIGN OF CONCRETE DECK SLAB

    Types of Slab Reinforcement

    The deck slab may be designed as One-Way Slab with main reinforcement perpendicular

    or parallel to the traffic direction

    1-Main reinforcement perpendicular to traffic

    Found in girder bridges

    Girder Spacing must not be too large

    2-Main reinforcement parallel to traffic Slab on floor beams (Truss Bridges)

  • 8/7/2019 DOS Steel Bridge-2

    7/28

    DESIGN OF CONCRETE DECK SLAB

    1-Conventional reinforced concrete decks

    supported on girders

    2-Slab superstructures, cast-in-place,

    longitudinally reinforced

    3-Stay-in-place formwork decks

    Types of Deck

  • 8/7/2019 DOS Steel Bridge-2

    8/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    Methods for designing slab are

    1. Empirical Method (9.7.2)

    2. Approximate Method (Strip Method) (4.6.2.1)

    3. Refined Method including

    a. Classical force and displacement methods

    b. Yield Line Method

    c. Finite Element Analysis

  • 8/7/2019 DOS Steel Bridge-2

    9/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    1-Empirical method

    Empirical method is based on the test data (this is why it is called empirical) that the

    primary mechanism of the bridge deck under wheel load is not flexure but rather

    complex arch-action and punching shear.

    Empirical method of design can be only used forconcrete isotropic decks (having two

    identical layers of reinforcement, perpendicular to and in touch with each other)

    supported on longitudinal components.

  • 8/7/2019 DOS Steel Bridge-2

    10/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    1-Empirical method

    Conditions that must be satisfied in order to use the Empirical Method

    1. cross-frames or diaphragms are used throughout the cross-section at lines of

    support

    2. the supporting components (girders) are made of steel and/or concrete3. the deck is fully cast-in-place (no precast!) and water cured

    4. the deck has uniform depth except any local thickening.

    5. core depth of the slab is not less than 100 mm.

    6. the effective length (or slab span S) 4.1 m

    7. the ratio of effective length (S) to design depth is between 6 and 18

    8. the minimum depth of the slab is 175 mm, excluding the wearing surface

    9. the specified 28-day fc

    of the deck concrete is > 28 MPa

  • 8/7/2019 DOS Steel Bridge-2

    11/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    1-Empirical method

    Conditions that must be satisfied in order to use the Empirical Method (Continued)

    10. There should be an overhang beyond the centerline of the exterior girder equal to a

    minimum of 5 times the depth of slab or 3 times depth of slab with vertical barrier.

    11. A minimum of two shear connectors shall be placed at a spacing of 600 mm C/Cbetween the steel girders and the deck slab. For concrete girders, stirrups extending

    into the slab satisfy this requirement.

    Isotropic bottom layer steel should have a minimum area of 0.570 mm2/mm width of slab.

    Isotropic top layer steel should have a minimum area of 0.380 mm2/mm width of slab.

    The outermost layer of steel along the depth of the slab is to be placed in the direction of

    the effective length.Spacing of steel must be 450 mm

    4 layers of isotropic reinforcement (same in all directions) shall be provided

    The minimum depth of the concrete slab to be used as a deck should not be less than 175

    mm. (NHA suggests a minimum value of 220 mm). The wearing surface is separatelyprovided.

    Reinforcement Requirement for Empirical Method

  • 8/7/2019 DOS Steel Bridge-2

    12/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method (Approximate Method)

    Strip method is an approximate analysis method in which the deck is subdivided into

    strips perpendicular to the supporting components (girder)

    The slab strip is now a continuous beam and can be analyzed using classical beam theory

    and designed as a one-way slab

    Slab is modeled as beams and with girders as supports

    Wheel loads are placed (transversely) on this slab to produced the maximum effect

  • 8/7/2019 DOS Steel Bridge-2

    13/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method

    1. The deck is subdivided into strips perpendicular to the supporting components

    (girder)

    2. Determine the maximum moment (M+ and M-) based on classical beam theory(These moments are considered as representative and may be used for all panels.)

    3. Determine the width of strip for each M+ and M- case

    4. Divide the maximum moment by the width of strip to get the moment per 1 unit

    width of slab

    5. Design an RC slab for this moment the reinforcement required will be for 1 unit

    width of slab (this is for the primary direction)

    6. The reinforcement in the secondary direction may be taken as a percentage of those

    in the primary direction

  • 8/7/2019 DOS Steel Bridge-2

    14/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method

    Equivalent Strip Widths for Various

    Parts of the Deck

    S = spacing of supporting components

    X = distance from load to point of support

    +M = positive moment

    -M = negative moment

  • 8/7/2019 DOS Steel Bridge-2

    15/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method

    The previous procedure is quite complex for routine designs (need to consider transverse

    placements of live loads to get the maximum effect). Therefore, AASHTO offers a

    simplified procedure to determine maximum M+ and M- directly!!!

    1. Slab is modeled as beams and with girders as supports

    2. Determine the maximum M+ and M- from table (Table A4-1) based on the slab

    span this is the LL+IM moment per mm.

    3. M+ and M- from DL/DW are relatively small and may be approximated as

    M=wl2/c where c ~ 10-12

    4. Design an RC slab for this moment the reinforcement required will be for 1 mmof slab (this is for the primary direction)

    5. The reinforcement in the secondary direction may be taken as a percentage of

    those in the primary direction

  • 8/7/2019 DOS Steel Bridge-2

    16/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method)

    The design section fornegative

    moments and shear is taken as

    the face of the beam for

    monolithic construction and

    concrete box beams and onequarter the flange width from

    the center line of the support for

    steel beams

  • 8/7/2019 DOS Steel Bridge-2

    17/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method

    Distribution Steel

    Reinforcement in the secondary direction may be determined as a percentage of

    that in theprimary direction.

  • 8/7/2019 DOS Steel Bridge-2

    18/28

    ANALYSIS AND DESIGN METHODS OF CONCRETE DECK SLAB

    2-Strip Method

    Load Combination

    In the case of deck design only one of five strength load combinations needs to be

    investigated:

    STRENGTH I

    This limit state is the basic load combination relating to normal vehicular use of the

    bridge (without wind).

    U = [1.25 DC + 1.75 (LL + IM)]

    Resistance factors for strength limit state:

    0.90 for flexure and tension of reinforced concrete

    1.00 for flexure and tension of prestressed concrete

  • 8/7/2019 DOS Steel Bridge-2

    19/28

    DISTRIBUTION OF LIVE LOAD TO GIRDERS

    A bridge usually have more than one girder so the question arise on how to distributethe lane load to the girders

    The problem is three-dimensional and involves complex behavior of load transfer

    from concrete slab to steel girder.

    The AASHTO bridge specification suggests many methods to analyze bridges, i.e.,

    finite element analysis, grillage analysis, and a load distribution factor (LDF) equation.

    Finite element analysis (FEA) is considered to be an accurate method, but it requiresmuch effort in data preparation, bridge modeling and analysis, and interpretation of

    results.

    The LDF equation is introduced to facilitate in determination of maximum moment in

    the girders.

    With the LDF equation, the maximum moment in the girders is obtained by

    multiplying a moment from a one-dimensional bridge analysis by the value obtained

    from the LDF equation.

  • 8/7/2019 DOS Steel Bridge-2

    20/28

    The wheel load distribution factor from the S/D equation, the AASHTO standard

    equation (AASHTO 1996), for concrete slab on steel girder bridges with two or more

    design lanes loaded is:

    LDF=S/D

    where S is girder spacing in mm and D is the co-efficient depending on the type of

    superstructure, D=1670 for a bridge constructed with a concrete deck on pre-stressed

    concrete or steel girders carrying two or more lanes of traffic.

    .The S/D equation, first introduced in 1930s, involves only one parameter. Although

    the S/D equation is simple to use, it is considered to be unsafe for some bridges and too

    conservative for others.

    The effects of various parameters such as skew, continuity, and deck stiffness were

    ignored in this expression and it was found to be accurate for a few selected bridge

    geometries and was inaccurate once the geometry was changed.

    AASHTO GIRDER DISTRIBUTION FACTORS

  • 8/7/2019 DOS Steel Bridge-2

    21/28

    Development of a formula for a broad range of beam and slab bridges, includingprestressed concrete and steel girder bridges was needed.

    Much research was carried out using finite element analysis, grillage analysis, and field

    tests to arrive at more accurate expressions for DFs.

    The maximum moment at a critical location is determined with an analytical or

    numerical method and is denoted as Mrefined. Next, the same load is applied to a single

    girder and a 1D beam analysis is performed. The resulting maximum moment/shear is

    denoted as Mbeam. The distribution factor (g) is defined as:

    DFs are different for different kinds of superstructure system

    DFs are different for interior and exterior beam

    DFs are available for one design lane and two or more design lanes (the larger one

    controls)

    Must make sure that the bridge is within the range of applicability of the equation.

    AASHTO GIRDER DISTRIBUTION FACTOR

  • 8/7/2019 DOS Steel Bridge-2

    22/28

    Factors affecting the AASHTO LRFD distribution factor includes:

    Span Length (L)

    Girder Spacing (S)

    Modulus of elasticity of beam and deck

    Moment of inertia and Torsional inertia of the section

    Slab Thickness (ts)

    Width (b), Depth (d), and Area of beam (A)

    Number of design lanes (NL)

    Number of girders (Nb)

    Width of bridge (W)

    AASHTO GIRDER DISTRIBUTION FACTORS

  • 8/7/2019 DOS Steel Bridge-2

    23/28

    AASHTO GIRDER DISTRIBUTION FACTORS

    Condition for Applicability of DFs for concrete deck on steel or concrete beams.

    1. Spacing of beams, S, should be between 1.1 and 4.9 m.

    2. Thickness of deck slab, ts, should be between 110 and 300 mm.

    3. Length of beam should be between 6.0 and 73.0 m.4. Number of longitudinal beams in the cross-section, Nb, should be greater than or

    equal to 4.

    5. The width of deck should be constant.

    6. Multiple presence factor is not to be applied when the using the given expressions.

    However, it is always to be considered if the lever rule is used to the find the force

    effects.

    7. If beam spacing exceeds 4.9 m, the live load on each beam shall be the reaction of

    the loaded lanes based on the lever rule.

    8. Beams should be parallel and should have approximately the same stiffness.9. The curvature in plan is less than the specified AASHTO limit.

    10. The roadway part of the overhang, de, does not exceed 910 mm.

  • 8/7/2019 DOS Steel Bridge-2

    24/28

    AASHTO GIRDER DISTRIBUTION FACTORS

  • 8/7/2019 DOS Steel Bridge-2

    25/28

    AASHTO GIRDER DISTRIBUTION FACTORS

    Notation Used

    g = distribution factor

    S = spacing of beams or webs (mm)

    L = span of beam (mm)

    Nb

    = number of beams, stringers or girders

    ts = depth of concrete slab (mm)

    n = modular ratio between beam and deck materials

    I= moment of inertia of beam (mm4)

    eg= distance between the centers of the basic beam and deck (mm), considered zero for

    non-composite beamsA = area of stringer, beam or girder

    Kg =n(I+Aeg2), longitudinal stiffness parameter (moment of inertia of one beam modified

    to equivalent concrete section and transferred to a point at the center of the slab)

    Kg/Lts3

    = a parameter proportional to the ratio of beam stiffness to total slab stiffness intransverse direction at the level of the slab centerline

    de = distance between the center of exterior beam and the interior edge of curb or traffic

    barrier mm). It shall be taken positive if the exterior web is within the roadway inside the

    curb and negative when it is outside the roadway.

  • 8/7/2019 DOS Steel Bridge-2

    26/28

    AASHTO GIRDER DISTRIBUTION FACTORS

    AASHTO GIRDER DISTRIBUTION FACTORS

  • 8/7/2019 DOS Steel Bridge-2

    27/28

    AASHTO GIRDER DISTRIBUTION FACTORS

    AASHTO GIRDER DISTRIBUTION FACTORS

  • 8/7/2019 DOS Steel Bridge-2

    28/28

    AASHTO GIRDER DISTRIBUTION FACTORS

    The lever rule is a method of analysis which involves a statical distribution of load

    based on the assumption that each deck panel is simply supported over the girder,

    except at the exterior girder that is continuous with the cantilever. Because the load

    distribution to any girder other than one directly next to the point of load application isneglected, the lever rule is a conservative method of analysis.

    LEVER RULE

    Multiple presence factor is not to be applied when the using the

    given expressions by the

    specifications (already included in

    the equations). However, it is

    always to be considered if the lever

    rule is used to the find the force

    effects.