Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Our VisionTo be one of the leading
Supreme Audit Institutionsin the world, delivering
professional, excellent, andcost effective auditing
services
REPUBLIC OF GHANA
on the
PERFORMANCE AUDIT REPORT of the
AUDITOR GENERAL
CONSTRUCTION OF ACHIMOTA-OFANKOR ROAD PROJECT
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
TABLE OF CONTENTS
List of Acronyms ……………………………………………………………………….
Transmittal letter …………………………………………………………………. i
Executive summary ………………………………………………………………. iii
CHAPTER ONE ………………………………………………………………….. 1
Introduction ……………………………………………………………………… 1
1.1 Motivation ………………………………………………………………… 1
1.2 Purpose, Scope, Audit Questions and Criteria …………………………….. 2
1.3 Method and implementation ……………………………………………….. 3
CHAPTER TWO ………………………………………………………………….. 4
Description of the audit area ………………………………………………………. 4
2.1 Background of the project ………………………………………………….. 4
2.2 Objectives of the Achimota-Ofankor Road Project ………………………… 4
2.3 Rules and Regulation ………………………………………………………... 5
2.4 Funding for the Achimota Ofankor Road Project ………………………….. 6
2.5 Key players and their responsibilities………………………………………... 6
2.6 Systems Description ………………………………………………………… 9
2.7 Current Development ……………………………………………………….. 13
CHAPTER THREE
Findings, Conclusions and Recommendations …………………………………….. 14
3.1 Introduction …………………………………………………………………. 14
3.2.0 GHA put the Achimota-Ofankor Road project on tender without developing
the feasibility study drawings into detailed engineering drawings …………. 14
3.2.1 GHA did not obtain all the requisite data needed to prepare detailed
drawings and a more accurate BOQ ……………………………………….. 15
3.2.2 GHA tendered the Achimota-Ofankor Road project with insufficient
details …………………………………………………………………… 17
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
3.3 Contractor selection did not meet the full requirements of the Public
Procurement Act …………………………………………………………. 19
3.4 GHA increased the scope of works by 217% over the original contract
sum before seeking approval …………………………………………….. 22
3.5 GHA delayed in providing information for setting out and drawings …… 25
3.6.1 GHA ensured the road project was executed in accordance with the
Specifications …………………………………………………………….. 27
3.7.1 Delays in paying Interim Payment Certificates (IPCs) cost GoG
GH¢4.40 million in interest charges ……………………………………… 29
3.8 Overall conclusion ………………………………………………………… 34
APPENDICES
A Methods and implementation ……………………………………………… 36
B Schematic drawing of Dual Carriage Highway …………………………… 39
C Examples of concerns raised by Tenderers ………………………………. 40
D Instances of delays by contractor in following Resident Engineer’s
Instructions ………………………………………………………………… 42
E Details of total interest paid ……………………………………………….. 44
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
LIST OF ACRONYMS
AfDB African Development Bank
BOQ Bill of Quantities
CEO Chief Executive Officer
CESSM Civil Engineering Standard Method of Measurement
CH Chainage
CRWGC China Railway Wuju Group Corporation
CTRB Central Tender Review Board
DBM Dense Bituminous Macadam
FAA Financial Administration Act
FAR Financial Administration Regulation
FIDIC International Federation of Consulting Engineers
GHA Ghana Highways Authority
GOG Government of Ghana
IPC Interim Payment Certificate
KfW Kreditanstalt Für Wiederaufbau
LHS Left Hand Side
MoFEP Ministry of Finance and Economic Planning
MRH Ministry of Roads and Highways
PPA Public Procurement Act
RCC Regional Coordinating Council
RHS Right Hand Side
RSDP Road Sector Development Programme
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project i
TRANSMITTAL LETTER
AG.01/109/Vol.2/65
Office of the Auditor-General
Ministries Block “O”
P. O. Box MB 96
Accra
Tel. (021) 662493
Fax (021) 662493
15 March 2013
Dear Mr. Speaker,
PERFORMANCE AUDIT REPORT OF THE AUDITOR-GENERAL
ON CONSTRUCTION OF ACHIMOTA-OFANKOR ROAD PROJECT
I have the honour to submit to you a performance audit report on the construction of
the Achimota-Ofankor road project in accordance with my mandate under Section
187(2) of the 1992 Constitution of Ghana and Section 13(e) of the Audit Service Act
which requires me to carry out performance audits.
2. The purpose of the audit was to determine whether or not Ghana Highway
Authority (GHA) ensured that the Achimota-Ofankor road project was designed and
implemented to meet specifications, delivered on time and in accordance with the
cost. The audit covered the period 2006 to 2012.
3. The audit found that the road project was constructed according to the
technical specifications. However, GHA did not plan adequately for the road project
and thus increased the scope of works by 217% before seeking approval. Payments
made to the Contractor delayed leading to extra cost in interest charges. GHA also
made expenditures that were unrelated to the project.
ii Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
4. In this report I have made recommendations to guide GHA in subsequent
projects that they will undertake.
5. I trust that this report will meet the approval of Parliament.
Yours faithfully,
AUDITOR-GENERAL
THE RIGHT HON. SPEAKER
OFFICE OF PARLIAMENT
PARLIAMENT HOUSE
ACCRA
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project iii
PERFORMANCE AUDIT OF THE AUDITOR-GENERAL ON
CONSTRUCTION OF ACHIMOTA-OFANKOR ROAD PROJECT
EXECUTIVE SUMMARY
The road from Achimota to Ofankor forms part of the Accra-Kumasi trunk road and
was a single-lane road prior to November 2006. It could not contain the increased
volume of traffic of about 15,000 vehicles per day. As a result, commuters spent about
three hours in traffic to cover the 5.7 kilometer route. To ease the traffic congestion
and improve transport services for commuters on the road, the Government of Ghana
(GoG), acting through the Ministry of Roads and Highways (MRH) and the Ghana
Highway Authority (GHA), in 2006 undertook a project to upgrade the road from a
single lane to a dual carriageway at an estimated cost of GH¢40.4 million. The project
was expected to be completed in November 2009.
2. As at December 2011, the Achimota-Ofankor road project had exceeded the
expected completion date by 25 months and progress was about 88%. The estimated
cost had shot up to GH¢ 128 million, an increase of about 217%. Commercial drivers
and commuters on the road complained about the extremely long hours spent
commuting between Achimota and Ofankor due to prolonged construction activities
and the diversion of roads.
3. The audit was to determine whether Ghana Highway Authority (GHA)
ensured the Achimota to Ofankor road project was designed and implemented to meet
specifications, delivered on time and in accordance with the cost, with focus on two
lines of enquiry:
developing the road project (planning phase i.e. from feasibility study to
contract award); and
the implementation of the road contract with respect to scope, quality and
cost controls.
iv Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Developing the road project
GHA put the Achimota to Ofankor road project on tender without developing
feasibility study into detailed engineering drawings
4. We found that GHA put the Achimota to Ofankor road project on tender
without detailed engineering drawings and a very accurate Bill of Quantities. This
resulted in a lot of changes to the major components of the project and claims by the
Contractor during implementation.
Recommendation
GHA should ensure that all the right things necessary to ensure that details
needed are obtained for preparing good tender documents before proceeding to
tender. Where time is of essence and GHA cannot go through all the needed
steps to undergo the traditional form of procuring a Contractor, other methods
for procuring a Contractor that do not require detailed tender documents should
be pursued.
Contractor selection did not meet requirements of the Public Procurement Act
5. The selection of the Contractor did not meet the requirements of the Public
Procurement Act. There were a lot of inconsistencies in the tender information
provided by GHA and technical deficiencies in the tendering process which were not
properly addressed by GHA. GHA did not allow tenderers sufficient time to meet the
criteria set for both the prequalification and actual tendering. This led to only one
Contractor being evaluated, thereby reducing the competitiveness of the tender
process.
Recommendation
GHA should allow tenderers sufficient time to prepare and submit tenders to
enhance competition in tendering and also ensure that detailed information are
included in the tender documents.
Implementation of the road project
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project v
GHA increased the scope of works 217% over the original contact sum before
seeking approval
6. We found that GHA increased the scope of works by 217%, over the original
contract sum, before seeking approval from the MRH and the Central Tender Review
Board (CTRB). Due to the increased scope of works without approval, the Ministry of
Finance and Economic Planning (MOFEP) did not know the full extent of the
financial obligation under the contract and was, therefore, unable to pay on time,
which resulted in extra cost from interest payments.
Recommendation
GHA should seek approval from MRH and CTRB before implementing major
changes in design which will result in more than 15% increase in contract sum.
GHA delayed in providing information for setting-out and drawings to the
contractor
7. GHA delayed in providing information for setting-out and drawings to the
Contractor. As a result, the Contractor was inactive on the project for 10 months
which reflected in the extension of the completion time of the project.
Recommendation
GHA should act promptly to request for information to ensure that the Contractor
works diligently on the project. MOFEP should surcharge GHA officers who cause
delays to contract duration with the cost involved in such delays.
GHA ensured the road project was executed in accordance with the
specifications
8. Test reports for concrete at 7 and 28 days exceeded the minimum strength
required by the contract. The test results for the asphalt were mostly satisfactory as
stated by the resident Engineer. GHA ensured that works that did not meet the
specifications were reconstructed to meet specifications.
Recommendation
vi Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
GHA should be vigilant and ensure that only works that meet the specifications are
accepted for payment.
Delays in paying Interim Payment Certificates (IPCs) cost GoG GH¢4.40 million
9. Delays in paying Interim Payment Certificates (IPCs) cost GH¢4.40 million.
The interest on delayed payment from 2007 to 2011 amounted to GH¢3.33 million
and US$1.16 million which have increased the cost of implementing the project.
Recommendations
Government should explore alternative means of funding, for example Public,
Private Partnership (PPP) to spread the burden of project financing;
GHA, MRH, RCC and MOFEP should analyse the tasks involved in the payment
procedure and allot maximum number of days IPCs should spend in each office.
The total period should not exceed the contractual payment period. Officers who
cause the delays should be surcharged with the proportion he/she contributed to the
accruing interest; and
GHA, MRH and MOFEP should review the period for payment inserted in the
contract to what is convenient to forestall the delays and the attendant interest
payments.
GH¢374,000 was spent on items unrelated to the Achimota-Ofankor road project
10. We further found that GHA spent GH¢ 374,000 on items not related to the
Achimota to Ofankor road project. The expenditure was made on items which should
have been paid for from the Administration and Investment vote of GHA.
Recommendation
GHA should desist from including expenditure not related to the project in the
IPCs; and
MRH should check IPCs thoroughly to ensure GHA expenditures that are not
related to road projects are expunged from IPCs before they are forwarded to
MOFEP for payment.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
LIST OF ACRONYMS
AfDB African Development Bank
BOQ Bill of Quantities
CEO Chief Executive Officer
CESSM Civil Engineering Standard Method of Measurement
CH Chainage
CRWGC China Railway Wuju Group Corporation
CTRB Central Tender Review Board
DBM Dense Bituminous Macadam
FAA Financial Administration Act
FAR Financial Administration Regulation
FIDIC International Federation of Consulting Engineers
GHA Ghana Highways Authority
GOG Government of Ghana
IPC Interim Payment Certificate
KfW Kreditanstalt Für Wiederaufbau
LHS Left Hand Side
MoFEP Ministry of Finance and Economic Planning
MRH Ministry of Roads and Highways
PPA Public Procurement Act
RCC Regional Coordinating Council
RHS Right Hand Side
RSDP Road Sector Development Programme
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 1
CHAPTER ONE
INTRODUCTION
1.1 Motivation
The road from Achimota to Ofankor forms part of the Accra-Kumasi trunk road and
was a single-lane road prior to November 2006. It could not contain the increased
volume of traffic of about 15,000 vehicles per day1. As a result, commuters spent
about three hours in traffic to cover the 5.7 kilometre route. To ease the traffic
congestion and improve transport services for commuters on the road, the Government
of Ghana (GoG), acting through the Ministry of Roads and Highways (MRH) and the
Ghana Highway Authority (GHA), in 2006 undertook a project to upgrade the road
from a single lane to a dual carriageway at an estimated cost of GH¢40.4 million. The
project was expected to be completed in November 2009.
2. As at December 2011, the Achimota to Ofankor road project had exceeded
the expected completion date by 25 months and progress was about 88%. The
estimated cost had shot up to GH¢128 million, an increase of about 217%.
Commercial drivers and commuters on the road complained about the extremely long
hours spent commuting between Achimota and Ofankor due to prolonged construction
activities and due to the diversion of roads2.
3. The Auditor-General therefore commissioned a performance audit into the
construction of the Achimota-Ofankor road project to examine the planning and
implementation of the project.
1 Traffic Studies conducted by TABCON LTD in 2002
2 Daily Graphic of 17 September 2010
2 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
1.2 Purpose, Scope, Audit Questions and Criteria
Purpose and scope
4. The purpose of the audit was to determine whether Ghana Highway Authority
(GHA) ensured the Achimota to Ofankor road project was designed and implemented
to meet specifications, delivered on time and at the estimated cost.
5. The audit focused on two lines of enquiry:
developing the road project (planning phase i.e. from feasibility study to
contract award); and
implementing the road contract with respect to scope, quality and cost
controls.
6. The audit period was from May 2004 to December 2011 and was carried out
from June to October 2012.
Limitations
7. The audit was limited to the Achimota to Ofankor road and all observations
are specific to the Achimota to Ofankor road project. However, as the road project
was nearly completed at the time of our audit in 2012, the recommendations included
in this report are for GHA to follow when embarking on future projects.
8. An assessment of the cost of the redesigned road project was beyond the
scope and capabilities of the audit team.
Audit questions and criteria
9. The audit team formulated four main audit questions to determine whether the
Ghana Highway Authority (GHA) ensured that the Achimota to Ofankor road project
was designed and implemented to meet specifications, delivered on time and at the
estimated cost.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 3
Audit question Criteria
1) Were road designs adequately developed prior to
going on tender?
Designs for all major components should be completed prior to
tender.(GHA internal good practice)
2) Did GHA have justification for the differences in the
implemented project and the planned project resulting
in a 217% cost increase?
Project should be executed according to the contract.
(FIDIC)
Major changes should receive approval before being
incorporated into the project (FIDIC)
3) To what extent did GHA ensure the road project was
executed to the agreed quality?
Works should be delivered in accordance with the technical
specifications under Section 6 of the contract.
Approval by the Resident Engineer of each stage of the
works before continuation. (FIDIC)
4) To what extent did GHA avoid unnecessary cost to the
project?
Monies should be used in a manner that secures optimum value
for money. (Regulation 39 (1) of Financial Regulations 2004)
1.3 Method and implementation
10. We reviewed project files kept by GHA, interviewed key staff of GHA, the
Ministry of Roads and Highways (MRH) and the Ministry of Finance and Economic
Planning (MOFEP) on the Achimota to Ofankor road project and visited the project
site for the data required for the audit (Please refer to Appendix A for full details of
method).
4 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
CHAPTER TWO
DESCRIPTION OF THE AUDIT AREA
2.1 Background of the project
11. The Achimota to Ofankor road project forms part of the major development
works component of the Road Sector Development Programme (RSDP)3. It is wholly
funded by the Government of Ghana acting through the Ministry of Roads and
Highways (MRH) and implemented by the Ghana Highway Authority (GHA).
12. The proposed road was a four-lane dual carriageway planned as a two-lane
north and south bound fast access route. These are flanked by two-lane north bound
and south bound service roads for use by local traffic. Traffic management structures
on the road consisted of:
five foot bridges;
four interchanges (two flyovers and two bridges); and
two roundabouts.
13. The schematic drawing of the proposed Achimota to Ofankor dual carriage
road is attached as Appendix B.
14. The contract was awarded to Messrs China Railway Wuju (Group)
Corporation at an initial contract sum of GH¢ 40.4 million. The works started on 15
November 2006 and was to be completed on 14 November 2009, a period of 36
months.
2.2 Objectives of the Achimota to Ofankor road project
15. The objective of the Achimota to Ofankor road project was to reconstruct and
expand the existing single carriageway into a dual carriageway at a cost of GH¢ 40.4
million and to complete it in a period of 36 months.
3 A project aimed at achieving sustainable improvements in the supply and performance of roads and
transport services in Ghana – http://www.worldbank.org/projects/P050623/road-sector-development-project?lang=en – accessed on 3 December 2012
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 5
2.3 Rules and regulations
Ghana Highway Authority Act, 1997 (Act 540)
16. The Ghana Highway Act, 1997 (Act 540) assigns the responsibility of trunk
roads to GHA. GHA classified the Achimota to Ofankor road as a trunk road (a major
highway connecting two or more places) and therefore the Act gives GHA the
mandate to carry out work on it.
Financial Administration Act, 2003 (Act 654) and Financial Administration
Regulation of 2004
17. The Financial Administration Act, 654 regulates the financial management of
public funds, prescribes the responsibilities of persons entrusted with financial
management in government and ensures the effective and efficient management of
state revenue, expenditure, assets, liabilities and resources of government. As the
Achimota to Ofankor road project is wholly financed by the Ghana Government, the
Act places an obligation on all government entities involved, to use public resources
with due regard to economy, efficiency and effectiveness.
Public Procurement Act, 2003 (Act 663)
18. Procuring a competent contractor is important in ensuring the success of the
road project. The Public Procurement Act which has been in force since 2003 sets out
provisions for tendering for contracts.
International Federation of Consulting Engineers’ (FIDIC) Conditions of
Contract for Works of Civil Engineering Construction, 4th
Edition
19. The Achimota to Ofankor road contract was governed by the FIDIC
Conditions of Contract between China Railway Wuju (Group) and the Ministry of
Roads and Highways, on behalf of the Government of Ghana. The FIDIC sets out the
responsibilities of each party to the contract and deals with cost, time and quality
control of the contract.
6 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
2.4 Funding for the Achimota to Ofankor road project
20. The Achimota to Ofankor road project was financed from the Consolidated
Fund. Table 1 shows annual budgetary allocations and expenditures made from
November 2006 to December 2011. Although there was a budget in 2007, no
payments were made in respect of the project for three Interim Payment Certificates
(IPCs) amounting to GH¢5,873,392.49 that were submitted in May, October and
November 2007 for payment. The yearly budget allocations for the project were less
than the yearly invoiced IPCs.
Table 1: Budget and expenditure on the project from 2006 to 2011
Source: MRHMTEF Budget Estimates for 2006 to 2011 and Achimota-Ofankor Project
Progress report No. 33
***No budget was provided in 2009
2.5 Key players and their responsibilities
21. The key players for the Achimota to Ofankor road project are the MRH,
MOFEP, GHA and China Railway (Wuju) Group Corporation (CRWGC). See figure
1 for a system graph showing the relationship between the key players.
Ministry of Roads and Highways (MRH)
22. The MRH is responsible for formulating policies for the road transport sector.
It is the Employer or the Project Owner and acts for and on behalf of the Government
of Ghana. MRH receives monthly progress report from GHA on the Achimota to
Ofankor road project and reports to Cabinet. The Ministry also approves IPCs before
Year Budget amount
(GH¢)
Actual expenditure
(GH¢)
2006 159,600.00 7,187,917
2007 2,805,024 nil
2008 4,055,908 13,133,220
2009 ***- 11,557,368
2010 10,448,011 21,840,735
2011 521,241 34,812,089
Total 17,989,784 88,531,329
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 7
they are submitted to MOFEP for payment. It also reviews major changes made by
GHA before it is forwarded to MOFEP for approval.
Figure 1: Relationship between key players
Ministry of Finance and Economic Planning (MOFEP)
23. MOFEP provided the budget for the project. It disbursed funds to settle
Interim Payment Certificates (IPCs) submitted by GHA on behalf of the Contractor
for the Achimota to Ofankor road project.
Ghana Highway Authority
24. The Ghana Highway Authority is under the Ministry of Roads and Highways
and is responsible for planning, developing and administering the Achimota to
Ofankor road project.
GHA
Pay
men
ts for w
ork
don
e
CEO MOFEP
Planning
Division
Resident
Engineer
Survey &
Design
Division
Contracts
Division
Road
Contract CRWGC
MRH
Issue further
drawings and details
Con
trac
ts A
dm
inis
trat
ion
Seek Clarification
Ap
pro
vals
Pro
gress
Eng
ineer’s in
structio
ns
Submit valuation of
Work done
GHA- Ghana Highway Authority
CEO – GHA Chief Executive
MRH - Ministry of Roads and Highways
MOFEP – Ministry of Finance and Economic
Planning
CRWGC- China Railway (Wuju) Group Corporation
Pla
nn
ing
, desig
n a
nd
selection
of co
ntra
ctor
Imp
lemen
tatio
n
8 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
i) The Chief Executive (CEO)
25. The CEO is the head of GHA who appoints the Resident Engineer and
approves changes suggested by the Resident Engineer. He issues variation orders and
IPCs. He also reports on the status of the Achimota to Ofankor road project to MRH.
ii) The Development Department of GHA
26. The Deputy Chief Executive heads this department comprising: Planning,
Contracts, Materials, Quantity Surveying, Bridges and Survey and Design Divisions.
The Planning Division conducts feasibility studies, identifies right of way and
buildings for demolition to make way for the road as well as assessing properties for
payment of compensation.
27. The Contracts Division prepares tender documents. The Division also handles
tendering and tender evaluation, construction planning (including relocation of
utilities and compensation of affected properties) and the reviewing of IPCs.
28. The Materials Division is responsible for engineering studies and material
investigations. The Division also prospects for materials for construction.
29. The Quantity Surveying Division is involved in the preparation of preliminary
cost estimates for projects. The Division is responsible for the preparation of the Bills
of Quantities (BOQ) (a component of contract documents) and the verification of
quantities on IPCs.
30. The Bridges Division is responsible for identifying locations, designing and
detailing bridges to be constructed.
31. The Survey and Design Division is responsible for gathering site information
through various surveys, designing the road to be constructed and preparing
engineering drawings for construction.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 9
iii) The Resident Engineer
32. The Resident Engineer receives Contractors’ queries, issues instructions to
Contractors, ensures that Contractors follow good practices and approves work done
by Contractors. The Resident Engineer also monitors the progress of works and gives
the CEO regular reports on projects through monthly progress reports. He chairs
monthly site meetings to discuss progress of work.
The Contractor - China Railway (WUJU) Group Corporation (CRWGC)
33. CRWGC is the contractor for the construction of the Achimota to Ofankor
road project. CRWGC is to execute the contract according to the drawings and
specifications. They maintain the project site, receive instructions from the Resident
Engineer and carry them out. They apply for payment of work done from MOFEP
through GHA. CRWGC conducts tests on materials and components, and forwards
test results to the Resident Engineer for approval.
2.6 Systems description
The planning process
34. The planning process for a trunk road project starts after a decision of
Government to undertake the project. GHA conducts a feasibility study as the basis to
develop a scheme for the project. GHA then carries out detailed engineering studies
on the road project in order to come up with a suitable design for the route chosen.
35. After the detailed engineering studies, GHA prepares detailed engineering
drawings, Bills of Quantities and other tender documents that can be used for
tendering for the project. The detailed design and drawings are reviewed by an
independent consultant. After the review, GHA procures a contractor to undertake the
construction of the road project.
10 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Figure 2: Flowchart for planning and implementation of the road project
Tendering
END
Is project
feasible? START
Conduct
feasibility
studies
Prepare detailed
Engineering
Studies, Design &
Drawings
Prepare
detailed Bill
of Quantities
No
Yes
Implementation
Planning
Yes
Select
Contractor
Is Contractor
acceptable?
Sign Contract
Construct road and components
Issue Variations
Clarify drawings/other issues
Approve materials and road components
Approve payments to contractor
Monitor progress of work
No
Prepare
Tender
Documents
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 11
Implementing road projects
36. The implementation phase of road projects deals with constructing the road
according to the contract drawings and specifications. GHA monitors the progress of
the works to ensure timely completion and ensures that cost is within acceptable
limits. The works are carried out according to the agreed schedule in the programme
of works so that the Resident Engineer can monitor the works and make changes as
and when they occur. The Resident Engineer also clarifies any questions/queries the
Contractor may have about the drawings for the project.
37. Where a variation is necessitated, variation orders are issued by GHA to cover
changes to the original design or scope of the project. The Engineer (CEO of GHA)
requires approval from MRH before issuing variation orders above 15% of the
contract sum. Where the value of the change in scope is beyond the approval limit of
MRH, approval will have to be sought from the Central Tender Review Board before
proceeding with the variation.
38. The materials and components for the road project must meet quality
standards set out in the specifications. The Resident Engineer reviews test results of
materials and the road components provided by the Contractor to ascertain whether
they are satisfactory or not.
39. The Contractor submits statements of value of work done on a monthly basis
to the Resident Engineer. The Resident Engineer vets the IPCs and forwards them to
the CEO of GHA for further scrutiny to ensure that only works properly executed are
included in the certificate for payment. The IPCs are then forwarded to MOFEP for
payment.
40. The Resident Engineer monitors the project and provides progress reports to
stakeholders. When the Contractor completes the project, the final valuation is done
for final payment. Final payment implies that the Contractor has discharged all his
duties under the contract.
12 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Process for Payment of Interim Payment Certificates
41. The process of certifying Interim Payment Certificates before paying the
Contractor for work carried out is shown in Figure 3.
Figure 3: Process for paying Interim Payment Certificates
2. Deputy
Chief Executive (Dev’t)
receives IPC and
forwards to Directors for
Contracts and Quantity
Survey
1. Chief
Director receives
IPC from GHA and
checks and validates
the IPC
Project Site
Greater Accra Regional
Coordinating Council
Ghana Highway
Authority Head Office
Ministry of Roads and
Highways
Ministry of Finance &
Economic Planning
1) Resident
Engineer
prepares the IPC
on site with input
from the
contractor
2) Regional
Highways
Director checks
and validates IPC
3) Regional
Economic
Planning Officer
checks and
validates IPC
4) Regional
Minister checks
and validates IPC
and forwards to
GHA
6) Director Contracts
checks IPC for errors and
contractual issues and
forwards to Quantity
Survey
7) Director Quantity
Survey checks for
accuracy of measurements
for payment requested and
forwards to Dir. Contracts
8) Accounts Department
receives IPC from
Contracts Division,
checks for accuracy of
amount to be paid and
process request for
payment of IPC.
5) Deputy Chief
Executive (Dev’t) receives
IPC and forwards to
Directors for Contracts and
Quantity Survey
10) Chief Director
receives IPC from
GHA and checks
and validates the
IPC
11) Minister of MRH
checks and validates
IPC Forwards IPC to
MOFEP for payment
12. Minister MOFEP
receives IPC from
MRH and forwards to
Budget Division
14) Controller &
Accountant General
pays contractor on
receipt of warrant
from MOFEP
Contractor receives
cheque from Controller
and Accountant General
when IPC is paid
9) Chief Executive
reviews IPC and forwards
to MRH for validation
13) Budget Officer
prepares warrant
Controller to
Accountant General
based on availability
of funds in MRH
account
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 13
2.7 Current development
42. As at 29 February 2012, all outstanding IPCs due to the Contractor had been
settled, reducing the delay by the Contractor. The project has been substantially
completed and the defects liability period began on 20 September 2012 and will end
on 20 September 2013.
14 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
CHAPTER THREE
FINDINGS, CONCLUSIONS AND RECOMMENDATIONS
3.1 Introduction
43. We present our findings of the audit on the developing the road project in the
areas of the development of the scheme, detailed design and the selection of the
Contractor. With the implementation of the road project the audit team made
observations on the revision in scope, payment of IPCs and the use of monies
allocated for A900 in the contract.
Developing the road project
3.2.0 GHA put the Achimota to Ofankor road project on tender without
developing the feasibility study drawings into detailed engineering drawings
44. GHA’s normal practice for tendering for road projects is to develop
preliminary drawings into detailed engineering drawings and prepare Bills of
Quantities (BOQ) out of the detailed drawings. These documents then form the basis
for interested tenderers to compete on a common understanding of the requirements of
the project.
45. The audit team expected GHA to complete the design and drawings for the
major components of the road project comprising the roadway, flyovers, underpass
and pedestrian footbridges and streetlights before going on to tender.
46. Our review of the tender documents and the tender process showed that the
BOQ used for tendering were prepared using preliminary designs and drawings
prepared by TABCON Limited (a consultant commissioned by MRH to conduct the
feasibility study) in 2004. GHA reviewed TABCON’s feasibility study designs and
drawings and passed them to be used for the tender documents and subsequent
tendering.
47. Our review of tender documents and correspondences between GHA and the
tenderers showed that no drawings were available for the retaining walls, interchanges
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 15
and pedestrian bridges. When tenderers questioned GHA during the pre-tender
meeting about outstanding drawings, GHA responded that the detailed drawings were
in progress and that tenderers were to price their tenders according to the provisions
made in the BOQ. We examined the contract document and found that the part for
drawings used for tendering were the preliminary designs submitted by TABCON
Limited.
48. We also found that the BOQ that GHA had prepared made references to
drawings of concrete kerbs, retaining walls, reflective road signs, galvanised steel
beam guard rails and pedestrian hand rails which were not provided with the tender
documents.
49. Our examination of project documentation and interviews on why GHA could
not provide detailed drawings before going on tender showed that:
i. GHA did not obtain the requisite data needed to prepare detailed drawings
and a more accurate BOQ; and
ii. MRH rushed GHA to take the Achimota to Ofankor road project to tender
with little details.
3.2.1 GHA did not obtain all the requisite data needed to prepare detailed
drawings and a more accurate BOQ
50. According to the Director of Survey and Design Division of GHA, detailed
road drawings should be based on detailed engineering studies. Detailed engineering
studies provide information on soil and subsurface conditions, location of sites for
gravel and sand for the project, utility lines, right of way and properties to be affected
by the road construction. This information informs the design of the road and also
allows for a more accurate costing of the project.
51. We found through interviews and review of project correspondences that, the
soil and sub-surface condition report needed for the detailed road and bridge designs
16 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
were not ready at the time of tender. As indicated in paragraph 44, there were no
drawings for the bridges and retaining walls. GHA needed these details to prepare a
comprehensive BOQ and a more accurate cost of the project. The tenderers needed
this information to determine the actual roadway, location of existing buildings and
utility lines, and an appreciation of the actual scope of work.
52. We found that there were no drawings on items such as retaining walls,
girders, concrete u-drains and kerbs which were mentioned in the BOQ. These
drawings were to accompany the BOQ to help tenderers prepare their tenders. Our
review of project correspondences indicated that tenderers complained that some of
the drawings GHA submitted to them after the pre-tender meeting were not readable
and also lacked cross-sectional details.
53. A priced BOQ based on inadequate information in a contract renders the
contract susceptible to a lot of changes and claims by the Contractor during
implementation.
Conclusion
54. The CESMM54as well as the FIDIC indicates that quantities in the BOQ are
estimates. Value for money is achieved when the variance between completed cost of
the project and the contract sum is minimal. Therefore, the BOQ which is the basis for
the costing of the tender should be prepared based on detailed information. Since there
were no drawings for bridges, retaining walls, kerbs, etc., the quantities provided in
the BOQ were unreliable and led to huge changes in the project during
implementation. For example, the whole of the concrete works for the two flyovers
were redesigned during the implementation, increasing the scope of concrete works by
about 375%.
55. GHA did not have enough time to gather the requisite data to prepare detailed
drawings and a more accurate BOQ.
4 This is the fifth edition of the standard method of measurement used to measure civil engineering works.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 17
Recommendation
56. GHA should obtain all necessary data needed to develop detailed drawings
and accurate BOQ for road projects.
GHA’s response
57. GHA responded that time constraints accounted for the delay observed by the
Auditor-General. However, the information provided was reasonably sufficient to go
for tender.
3.2.2 GHA tendered the Achimota to Ofankor road project with insufficient
details
58. It is the practice of GHA to use about four years to conduct feasibility studies,
develop road schemes, detailed engineering studies, preliminary designs, design
reviews and preparation of detailed drawings and estimates, sourcing of funds,
preparation of tender documents and tendering.
59. The Ministry of Finance and Economic Planning (MOFEP) initially sought
funding for the project from KfW and AfDB in 2005. The process of sourcing funds
put the estimated start date of the project at 2008 which was not favourable to the
Government. MOFEP curtailed the process with KfW and AfDB on 15 May 2006
because Government decided to finance the project from the Consolidated Fund.
MRH gave GHA a three-month non-negotiable period from 19 May 2006 to 21 July
2006 to prepare the project for tendering and award of contract.
60. At the time of the directive, only the feasibility study report and cost estimate
prepared by TABCON in 2004 were available. The feasibility study report included
initial surveys and investigations and preliminary road designs. GHA needed to
conduct the engineering studies, review designs, prepare detailed drawings and Bill of
Quantities and other documents for tendering.
18 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
61. A set of tender documents comprised the following:
Tender and Appendix to Tender;
Conditions of Contract, Part II;
Conditions of Contract, Part I;
The special and general technical specifications;
Blank BOQ; and
Drawings.
62. The first four components listed above are standard documents which GHA
need not spend time to customise for the project. The BOQ is prepared from the
drawings. GHA was not able to carry out the detailed engineering studies and detailed
drawings for the preparation of the BOQ so GHA used the preliminary drawings to
prepare the BOQ used for tendering.
63. The tenderers sought a lot of clarifications from GHA during tendering
because the information in the tender documents was not clear. As a result, two of the
tenderers lost interest in the project and pulled out. The whole project was completely
redesigned when the details that GHA should have obtained and used in preparing
detailed drawings before going on tender became available after award of the contract.
Conclusion
64. The preliminary drawings issued for tendering were not detailed. The
drawings did not include the details on flyovers, retaining walls and pedestrian
bridges. GHA did not carry out proper design review, detailed engineering studies and
detailed drawings on the road within the three-month period. The tender documents
were, therefore, deficient in important information to allow tenderers submit
competitive tenders.
Recommendation
65. We recommend that GHA should ensure that all the right things necessary to
ensure that details needed are obtained to prepare good tender documents before
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 19
proceeding to tender. Where time is of essence and GHA cannot go through all the
needed steps to undergo the traditional form of procuring a Contractor, other methods
for procuring a Contractor that do not require detailed tender documents should be
pursued.
GHA’s response
66. Recommendation accepted.
3.3 Contractor selection did not meet the full requirements of the Public
Procurement Act
67. Section 45 of the Public Procurement Act, 2003 (Act 663) governs effective
international competitive tendering. It deals with pre-qualification and tendering.
Section 45 (2c) of the Act specifies that tenderers should be allowed at least six weeks
for the submission of their tenders (either pre-qualification or the actual tender). This
is to allow sufficient time for the invitation to reach the tenderers and for them to
prepare their tenders based on information that is clear and understandable.
68. Our review of the tender process (through documents and interviews) showed
that GHA conducted the tender by first inviting interested tenderers for pre-
qualification. Subsequently tenderers who passed the pre-qualification were invited to
the actual tender. GHA advertised the sale of pre-qualification dossiers for the
construction of the Achimota to Ofankor road project in the two national dailies
(Ghanaian Times on 22 April 2006 and Daily Graphic on 26 April 2006). Eleven
international firms purchased the pre-qualification dossiers, but seven submitted their
applications to GHA on 5 May 2006. Out of the seven, three were pre-qualified to
submit tenders. GHA’s reasons for not pre-qualifying the other four loosing tenderers
were:
key technical staff of tenderer did not meet the pre-qualification criteria; and
tenderer did not submit equipment holding, financial statements and curriculum
vitae of all personnel in line with the format in the pre-qualification dossier.
20 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
69. M/s Daewoo E&C Company Limited, China Railway Wuju Group
Corporation and Bilfinger Berger were the three tenderers invited to submit tenders on
16 July 2006. The tender documents were forwarded to the three tenderers without all
the drawings. The quantities in the BOQ were based on preliminary drawings. The
tenderers together sent 57 queries about the tender documents for GHA to clarify.
Some of the queries for which the tenderers wanted answers included:
i. inconsistencies between the drawings and BOQ ;
ii. request for outstanding drawings;
iii. title of project stated 3-lane and 3 interchanges whereas drawings
showed 2-lane and 4 interchanges;
iv. some of the available drawings were not readable;
v. errors in drawings;
vi. inconsistencies in BOQ, unclear description of items; and
vii. request for soil report.
70. To answer the queries, GHA organised a pre-tender meeting on 30 June 2006
(two weeks to the submission date) where they discussed the queries and also issued
an Addendum to the tender documents. According to the tenderers, the addendum bill
created considerable increases in the original quantities in the BOQ and also
introduced a lot of new items.
71. The minutes of the pre-tender meeting got to the tenderers on 18 July 2006.
Based on this, GHA extended the tender submission date by 12 days from 16 July to
28 July 2006. China Railway Wuju Group Corporation was the only pre-qualified firm
which submitted its tender by 28 July 2006.
72. Our analysis of the tender process showed that GHA allowed two weeks for
the pre-qualification (from 22 April to 5 May 2006) and initially gave the pre-
qualified tenderers five weeks to submit their tenders (9June to 16 July 2006). GHA
upon request from tenderers extended the period by two weeks. These times were not
sufficient to allow tenderers to meet the criteria set in the Instructions to Tenderers for
both the pre-qualification and actual tendering. In the case of the pre-qualification,
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 21
four interested tenderers could not submit tenders. Out of the seven who submitted,
four namely: Taysec Limited, P. W. Civils, Sonitra Limited and Parsons Brinkerhoff
could not provide detailed pre-qualification documents although they are known to be
competent contractors in civil engineering works. Two of the tenderers (Taysec
Limited and Sonitra Limited) were working for the Government of Ghana at the time
of the pre-qualification.
Conclusion
73. An effective competitive tendering thrives on the basis that all tenderers are
provided sufficient, clear and understandable information to tender. The audit team
was of the opinion that the time given for the pre-qualification and tendering were
short (two weeks for pre-qualification and, seven weeks for tendering) and that not all
the information needed to enable competitive tendering was provided by GHA. The
tender documents were not clear and specific to allow qualified contractors to prepare
accurate cost estimates.
74. As there were a lot of inconsistencies in the tender information provided by
GHA and queries were not fully answered at the pre-tender meeting, tenderers did not
have the same understanding to deliver competitive tenders. The two week extension
was not sufficient for two of the tenderers to submit tenders and their request for
extension of time was turned down. Only one tenderer was evaluated and declared the
winner of the tender for the Achimota to Ofankor road project.
75. The technical deficiencies in the tendering process were not addressed to
make the tender information clearer. Competition thrives on more contestants
participating in the tender so that in order to win, a contestant has to provide the best
price under the circumstances. The conditions that existed allowed only one contractor
to be evaluated, thereby reducing the competitiveness of the tender process.
22 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Recommendation
76. We recommend that GHA should allow tenderers sufficient time to prepare
and submit tenders to enhance competition in tendering and also ensure that detailed
drawings are included in the tender documents.
GHA’s response
77. GHA responded that the requisite time would be allotted for the procurement
process.
The implementation of the road project
3.4 GHA increased the scope of works by 217% over the original contract
sum before seeking approval
78. The original scope of works for the contract for the Achimota to Ofankor road
project was the construction of a three-lane dual carriageway from Achimota to
Ofankor spanning a length of 5.7 kilometers with three interchanges and service roads.
The interchanges were to be two 80 metre four-span bridges (flyovers) at Mile 7 and
Ofankor and an underpass at Tantra Hill. In addition to these were four cable-stayed
pedestrian footbridges at various locations between Neoplan Junction and Ofankor.
79. Clause 51.1 of the Conditions of Contract Part I gives the Engineer the power
to vary the scope of the project. Sub-Clause 2.1 (d) and (e) of the Conditions of
Contract Part II stipulate that the Engineer shall obtain specific approval of the
Employer before issuing a variation under Clause 51, except where the variation
would increase the contract price by less than the amount stated in the Appendix to
Tender or less than 15 % of the contract price. In the Appendix to Tender, the
Engineer’s authority to issue variations is 15% of the contract price. This means that
any change in scope of work which will lead to an increase in cost of 15% or more of
the contract sum cannot be issued by the Engineer unless he obtains approval from
MRH. Schedule 3 of the threshold for Procurement Entities in the Procurement Act
requires that procurement of works above GH¢15 million is to be approved by the
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 23
Central Tender Review Board. In this case, the revision in scope can only be effected
after approval has been given by the Board.
80. The audit team found that the Achimota to Ofankor road project went on
tender with drawings from preliminary designs. We found through review of
correspondence that drawings for the project submitted to the Contractor could not be
implemented and a new set of drawings were submitted by the Resident Engineer to
the Contractor in August 2007 which changed the original concept. The revised design
concept was for four lanes for the highway, with two breakdown lanes and two service
lanes from Neoplan to Ofankor. Other major changes were:
a. Mile 7 and Ofankor bridges were redesigned from 4-span to 19-span;
b. the Tantra Hill bridge was changed from 3-span bridge of
1,495m3reinforced concrete to 2,674m
3 reinforced concrete box
underpass;
c. retaining walls were also increased from a length of 750m to 12,000m;
and
d. the footbridges were changed from cable-stayed bridge to simply
supported reinforced concrete deck slab on cylindrical columns.
81. We expected GHA to have costed the new designs and determined whether or
not they needed to seek approval from the Central Tender Review Board (CTRB) but
instead they went ahead and implemented the new designs. GHA only sought
approval from CTRB for the changes on 26 November 2009. The CTRB
appropriately queried GHA for not seeking prior approval before implementing the
new designs and asked GHA to provide justification for the redesign. The CTRB gave
approval of the revision in the scope of the project on 6 April 2010 when the project
was estimated at GH¢128 million. Table 2 shows a comparison of the cost of
components of original scope and revised scope of works.
24 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Table 2: Cost comparison of the original scope and revised scope of works.
No. Major components
Original cost
as per BOQ
(GH¢
Component)
Original cost as
per BOQ (US$
Component)
Original cost as per
BOQ (GH¢ Equivalent)
Revised cost
per Re-design
(GH¢)
%
increase
1 General Items 3,552,090 1,919,979.22 5,319,977.68 15,027,738.04 183
2 Roads and Pavings 2,913,031 16,221,562.46 17,849,602.63 19,007,654.31 8
3 Mile 7 Flyover
731,580 3,735,938.07 4,171,575.33
14,491,953.19
4 Ofankor Flyover 17,223,224.24 735
5 Tantra Hill Underpass 3,128,751.17
6 6 No. Foot Bridges 527,836 2,654,668.56 2,972,215.42 4,617,016.62 55
7 Drainage 619,851 2,776,950.73 3,176,825.92 7,298,378.28 230
8 Retaining wall 281,840.91 281,840.91 16,840,392.62 5875
Subtotal (A) 8,344,388 27,309,099.04 33,490,196.98 85,604,608.17
Specified provisional sums
included in bill items (B) 3,402,803 1,599,300.00 4,875,414.34
Subtotal of bills less
provisional sums (A)-(B) =
(C)
4,941,585 25,709,799 28,614,782.60
Add physical contingency
(D) 494,159 2,570,979.90 2,861,478.26 10% of Sub-Total (C)
Add physical contingency
4,280,230.41
5 % of (A)
Add price contingency (E ) 1,482,476 2,570,979.90 3,849,795.33
Add price contingency
(10%) of (A) 8,560,460.82
Total Dayworks (F) 48,732 95,735.42 136,884.21
Net Bid price
(A)+(B)+(E)+(F) 10,369,755 32,546,794 40,338,354.54
Total Cost of variation 98,445,299.39
Bill of omissions -10,622,889.50
Net Variation 87,822,409.89
Revised Cost 128,160,764.43
Source: GAS Analysis of GHA “Revised scope and estimated cost to complete” document dated 30 October 2009
Note: Exchange rate is US$1=GH¢0.92
82. Due to the increased scope of works without approval, the Ministry of
Finance and Economic Planning did not know the full extent of the financial
obligation under the contract. Therefore, Ghana Government was saddled with
unplanned cost and was unable to pay on time, which resulted in extra cost from
interest payments.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 25
Conclusion
83. It is important for clients to be informed of major cost implications on
projects for the client to plan and find additional resources to meet the added burden.
The contract required GHA to follow good practice of seeking approval prior to
implementing major changes exceeding 15% of the contract sum. GHA failed in this
regard although they had the capacity to assess the cost implication of the redesign.
Though the CTRB was unhappy about the actions of GHA, they had no option than to
grant approval.
Recommendation
84. The MRH should engage an independent cost consultant to assess the cost of
the completed project to determine the reasonableness of the total cost of the project.
85. GHA should seek approval from MRH and Central Tender Review Board
before implementing major changes in design which will result in more than 15%
increase in the contract sum.
GHA’s Response
86. GHA responded that they needed time to have the reviewed scope fully
identified. Also the desire not to have the Contractor idling while the re-scoping was
on-going brought about the delay in seeking the appropriate approvals. On completion
of the re-scoping, GHA sought the necessary approval of MRH and notified the CTRB
as required under the Public Procurement Act 663.
3.5 GHA delayed in providing information for setting-out and drawings
87. As in all contracts, information needed for the smooth start of a project should
be ready prior to the commencement of a project. This is to enable the Contractor to
commence work and complete within the agreed period or any extended time properly
given by the Engineer under the contract.
88. We found through a review of correspondence between GHA and the
Contractor and interviews with the Resident Engineer that GHA delayed in providing
26 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
setting- out information to the Contractor which delayed the start of the works by six
months. Within this six months period, the Contractor set up his campsite and was
ready to work but could not proceed. He was idle due to the non-availability of
information to proceed. GHA was to have provided the setting-out information to the
Contractor in November 2006 to enable him to start work.
89. GHA contracted HAG Consult (a civil engineering consultancy firm) to
conduct a new survey to collect the setting- out information required for the works to
start. CRWGC began setting out for the project after they received the information
from GHA in May 2007.
90. GHA also delayed in issuing drawings for the major components of the
project. They issued the drawings to CRWGC in September 2007 instead of
November 2006. Within the period that drawings for the new designs for major works
such as the four pedestrian footbridges, retaining walls, drainage, the main
carriageway and flyovers were not ready, the Engineer instructed the Contractor to
carry out minor works.
91. The setting -out information and drawings were delayed because GHA did not
conduct the detailed engineering study to collect the setting-out information and
prepare detailed drawings. The information and drawings issued initially were those
from preliminary designs which the Contractor could not work with.
92. As a result, the actual start of the project was delayed by 10 months due to the
absence of setting- out information and detailed drawings. The Contractor made a
claim for unproductive labour time and equipment on site for the 10 month period but
GHA did not pay any compensation because the Contractor did not formally inform
GHA that it had begun to count the days that labour and equipment were idle.
Conclusion
93. The delay in providing the Contractor information needed to set out the
project caused a delay of 10 months that reflected in the extension of time granted the
Contractor.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 27
Recommendation
94. We recommend that GHA should act promptly to request for information to
ensure that the Contractor works diligently on the project. MOFEP should surcharge
GHA officers who cause delays to contract duration with the cost involved in such
delays.
GHA’s response
95. GHA responded that given the complexity of the project, the 10 months it
took in providing the setting out data was considered reasonable, in view of the
processes involved. The 10 months were used not only for detailed designs but also to
resolve issues regarding relocation of services, demolishing of structures, payment of
compensation to property affected persons, road diversions, etc.
Ensuring the road works meet quality specifications of the contract
3.6.1 GHA ensured the road project was executed in accordance with the
specifications
96. According to the General Conditions of Contract Sub-clause 36.1(a) all
materials, plant and workmanship shall be of the respective kinds described in the
contract and in accordance with the Engineer’s instructions.
97. Under the General Conditions of Contract Part I, Sub-clause 37.2 (Inspection
and testing), the materials used for construction should be inspected and tested by the
Engineer to ensure they meet quality specifications. The General Conditions of
Contract Sub-clause 38.1 (Examination of work before Covering up) and Sub-clause
39.1 (Removal of improper work, materials or plant) no part of the works shall be
covered up or put out of view without the approval of the Engineer and the Engineer
shall have the authority to remove from site any materials or plant which are not in
accordance with the contract.
98. Interviews with the Resident Engineer indicated that GHA had 12 Engineers
and other staff who help him do daily supervision of the works on site. The team was
28 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
made up of a Materials Engineer, a Quantity Surveyor, a Surveyor, five Works
Inspectors, two Survey Assistants and two Laboratory Technicians. We also noted that
there was a materials laboratory on site to test the quality of materials and
components.
99. There were cube test results for all major concrete works done on site. These
were: concrete test results for retaining walls, bridge foundations and piers, suspended
concrete and kerb foundations. There were test reports for 7 and 28 days old concrete.
These results were reviewed by the Resident Engineer who gave his consent to the
results achieved. We reviewed a sample of 20 concrete test reports for concrete at 7
and 28 days and found that they all exceeded the minimum strength for what they
were to be used for as stated in the Specifications.
100. We reviewed test results on compaction tests for gravel base and found they
were consistently done and also exceeded the minimum of 96% density allowable in
the Specifications.
101. We took measurement of the thickness of the asphalt bitumen laid on the road
surface for verification and noted that it conformed to the thickness of 60 mm for
service road and 80 mm for main carriageway as stated in the drawings. The test
results for the asphalt were mostly satisfactory as stated by the resident Engineer.
Where the test result was not satisfactory, we found that the Resident Engineer
instructed the Contractor to remove 1.77 kilometre of asphalt which had been laid
without quality control reports. Again the Resident Engineer instructed the Contractor
to remove asphalt on Mile 7 Overpass which did not meet the specifications when
tested.
102. We found through review of documents and interviews with the Resident
Engineer that he made sure the Contractor demolished substandard concrete works
and reconstructed them to meet specifications.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 29
Conclusion
103. GHA ensured works delivered were of the required specifications in the
contract. GHA’s site supervisors reported breaches of the quality control measures to
the Resident Engineer for rectification. Consequently, works below specification
brought to the attention of the RE were rejected and reconstructed according to
specification.
Recommendation
104. We recommend that GHA should be vigilant and ensure that only work that
meets the specifications are accepted for payment.
GHA’s response
105. GHA responded that they would continue to be vigilant on all projects, as
they have done on the Achimota to Ofankor road project, to ensure work is done to
specification.
Managing the cost of the road project
3.7.1 Delays in paying Interim Payment Certificates (IPCs) cost GoG GH¢4.40
million in interest charges
106. According to Sub-clause 60.8 of the Conditions of Particular Application of
the contract, IPCs are to be paid within 56 days after certification by the Engineer.
The Contractor is entitled to interest on the unpaid debt at the rate of the Bank of
Ghana prime rate plus 2% and a London Inter-Bank on-lending rate plus 1% for cedi
and dollar components respectively each day the debt remains unpaid.
107. The IPC is prepared on site by the Resident Engineer with input from the
Contractor. The process for preparing and paying IPCs to the Contractor under the
Achimota to Ofankor road project is shown in Figure 3 (page 15).This procedure has
14 steps before the IPC is finally paid.
30 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
108. We examined all IPCs issued and the dates IPCs were paid by MOFEP. As at
31 December 2011, 36 IPCs had been issued and certified by the Engineer and 35 had
been paid during the time of our audit in 2012. The audit team found that apart from
IPC No.1 (mobilization) which was exempt from interest payment, the remaining 35
IPCs were paid beyond the 56 days payment period. The average delay period was
224 days for Ghana cedi component and 231 days for US dollar component. See
Appendix 5 for details of all 35 IPCs issued as at 31 December 2011, the periods of
delay for each certificate and the corresponding interest accruing from the delay.
109. We examined the trail of 23 IPCs (IPC No 12 to 36)5 from the project site to
the point where MOFEP instructs the Controller and Accountant General to pay the
Contractor. Averagely, the IPC spends 35 days at the Greater Accra Regional
Coordinating Council, 39 days at GHA, 28 days at MRH, 89 days at MOFEP and 33
days at the Controller and Accountant-Generals Department. The total days exceeds
the 56 days period within which the Contractor should be paid.
110. The interest on delayed payment from 2007 to 2011 amounted to GH¢3.33
million and US$ 1.16 million (GH¢4.4 million equivalent). This amount has also
increased the cost of implementing the project.
111. The Contractor used the delay in paying IPCs as an excuse to delay the rate of
progress of work. As a consequence of this, the Contractor did not follow his
programme of work and always fell short of his monthly planned progress throughout
the period covered by the audit.
5 Information on IPC No 2 to 11 was not provided by GHA
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 31
Table 4: Payment Trail for IPCs 12 to 36
Number of Days at
G.A.R.C.C. G.H.A. MRH MOFEP IPC No. Regional
highway
director
Regional
economic
planning
officer
Chief
director
gar
Regional
minister
gar
Dir.
Quantity
surveying
Dir.
Contracts
Dy. Chief
executive
dev't
Chief
executive
officer
Chief
director
Minister
MRH
MOFEP Controller
and
accountant
general
12 5 7 0 2 9 3 1 7 30 4 1 n/a
13 8 5 0 14 23 4 n/a 8 8 25 3 n/a
14 12 3 0 5 17 4 n/a 7 9 25 2 n/a
15 15 6 0 14 17 1 3 8 8 5 1 n/a
16 13 5 2 n/a 20 1 0 6 n/a 21 6 n/a
17 20 4 1 20 23 6 1 6 n/a 22 0 36
18 n/a 11 0 24 46 2 0 5 n/a 11 3 52
19 10 11 0 10 46 2 0 5 n/a 9 2 77
20 19 8 0 16 32 2 0 7 11 7 2 107
21 6 10 0 n/a 50 3 1 6 11 4 1 163
29 7 7 1 28 12 1 0 18 14 9 1 221
30 8 25 1 31 17 2 1 7 n/a 32 3 179
31 12 9 1 13 20 5 1 3 27 8 3 152
32 31 7 1 8 18 37 0 7 16 2 3 84
33 11 3 0 10 14 5 1 7 13 2 4 28
33A 11 3 0 0 32 41 1 12 50 0 99
34 13 2 0 14 n/a 4 0 4 9 12 1 44
35 9 7 0 9 20 1 3 17 12 14 1 21
36A n/a 16 0 20 20 1 1 13 8 5 2 19
36 10 6 0 20 13 1 0 8 21 5 2 19
Average 12.2 7.8 0.4 14.3 23.6 6.3 0.8 8.1 14.1 13.6 2.1 86.7
34.7 38.8 27.7 88.8
n/a – not enough information to compute
Source: GAS analysis of IPCs
Conclusion
112. It is an obligation on both parties to a contract to abide by the terms of the
contract. China Railway Wuju Group Corporation was to execute the works in
accordance with the conditions of the contract. Ghana government’s obligation was to
pay the Contractor amounts legitimately due him and at the times specified in the
contract. The many steps and long periods officers take to process the IPCs before
payment led to the Government incurring additional cost of GH¢4.40 million that
could have been avoided.
32 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Recommendation
113. We recommend that:
i. Government should explore alternative means of funding, for example
Public, Private Partnership (PPP) to spread the burden of project
financing;
ii. GHA, MRH, RCC and MOFEP should analyse the tasks involved in the
payment procedure and allot maximum number of days the IPC should
spend at each office. The total period should not exceed the contractual
payment period. Officers who cause delays should be surcharged with the
proportion he/she contributed to the accruing interest;
iii. GHA, MRH and MOFEP should review the period for payment inserted
in the contract to what is convenient to forestall the delays and the
attendant interest payments. Such periods may preferably be discussed
with the prospective tenderers.
GHA’s response
114. GHA accepted the recommendation. GHA and other stakeholders will work
together towards timely processing and payment of IPCs.
3.7.2 GH¢374,000 was spent on items unrelated to the Achimota to Ofankor
road project
115. Regulation 39 (1) of the Financial Administration Regulations, 2004
stipulates that monies should be utilized in a manner that secures both optimum value
for money and the intention of Parliament. BOQ Item A900 is a provisional sum
(GH¢957,457.20 and US$ 450,000.00) included in the BOQ to settle payments for
incidental consultancy services regarding designs, reviews and supervision that
become necessary under the project. It is also for paying expenditures incurred by the
GHA supervisory staff in their day to day supervisory work.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 33
116. We sampled 240 expenditures that GHA had made and categorised under
Item A900 of the BOQ. We selected expenditure samples of GH¢ 2,000.00 and above.
Table 6 shows expenditures that in our opinion were not related to the project.
Table 6: Expenditures made not related to the Achimota to Ofankor road project
Item Date Details Amount
A 09/12/08 Head office backstopping GH¢ 50,000
B 01/12/2010 Participation fees in favour of four (4) GHA
officers who participated in a short course in Urban
Transportation Systems Planning organised by the
Department of Civil Engineering KNUST.
GH¢ 2400.00
C 25/01/2011 Purchase of saloon car (BMW 740Li – 2010
MODEL)
One year comprehensive insurance
$ 160,305.76
$ 6,672.71
(GH¢242118.78
)equivalent
D 08/04/2011 Training of four GHA staff at GIMPA GH¢11,264.00
E 20/04/2011 Posting allowance for 13 GHA staff transferred to
the head office
GH¢34,764.73
F 01/06/2011 Conversion of GHA’s Archive Basement into
offices and renovation of the office of Deputy Chief
Executive (Dev.)
GH¢33,225.62
G Total GH¢374,000.00
Source: GAS review of General Correspondence file
117. Each year, GHA is allocated funds in their budget to fund their operations
under Investments and Administration. Our analysis of the expenditures in Table 6
shows that two of the expenditures, items B and D, were for training which falls under
Administration. The training for which the expenditures were made was not related to
the Achimota to Ofankor road project.
118. The procurement of assets, items C and F in Table 6, i.e. the purchase of a
BMW saloon car and the conversion of the basement of GHA head office into
archives, fall under Investment. Although GHA had used funds under Item A900 to
purchase and maintain vehicles, those vehicles were directly used by the GHA
Engineers to conduct supervision.
34 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
119. According to the CEO, funds allocated to GHA for its operations are
inadequate to support its internal operations so the practice has been to use funds from
GoG funded projects to support internal activities. Payment for expenditure items not
related to the Achimota to Ofankor road project increased the contract sum by
GH¢374,000 as at 31 December 2011.
Conclusion
120. The amount of GH¢374,000.00 was misapplied by incorporating expenditures
that were not directly related to the road project under audit. Such practices have the
effect of increasing project cost unnecessarily. It also has the tendency of distorting
cost information on the project. The real cost of the project cannot be correctly
determined and unit cost comparison will make Government construction look very
expensive.
Recommendation
121. GHA should desist from including expenditure not related to the project in
IPCs. MRH should check IPCs thoroughly to ensure GHA expenditures that are not
related to road projects are expunged from IPCs before they are forwarded to MOFEP
for payment.
GHA’s response
122. Inadequate budgetary allocation for training of staff partly accounted for this
situation. Contract administration goes beyond those technical staff at the site. It
involves key staff from Contracts, Survey and Design, Materials, Bridges, Safety and
Environment Divisions providing Head Office technical backstopping to the resident
project supervision teams. GHA makes provision on all its projects for Head Office
backstopping and continuing educational programmes, etc., for deserving staff.
3.8 Overall conclusion
123. The Achimota to Ofankor road project was completely redesigned after the
contract had been awarded because according to GHA the preliminary design used for
tendering was not implementable. GHA did not conduct detailed engineering studies
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 35
to develop a detailed design, drawings and an accurate BOQ. GHA increased the
scope of the project without prior approval from Government and this caused
Government to delay in paying the Contractor. This slowed the pace of construction
and cost an avoidable GH¢4.40 million extra. GHA delivered the project to the
required specification in 72 months instead of the 36 months initially envisaged. The
redesign has cost Government GH¢88 million more than initially estimated as at 31
December 2011.
36 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
APPENDICES
Appendix A
Methods and implementation
i) List of Documents reviewed
Document Information required
Contract document
Specifications and project description on road works.
General and specific conditions.
Enabling Act Legally mandated role of GHA on the project
Progress report
(monthly)
Activities carried out on the project from inception/commencement
to date
Trends, date, and cost of the project
Quality review, quality assurance and quality checks conducted by
GHA on the project
Information on the site visits
Reports of progress of actual works
Inception
report/documents
Background of the project, project activities, justification of project.
Phases of project, project outputs, project partners and their roles.
Road map of project with time frame
Feasibility study
report
Economic analysis, source of funding for the project, project
schedule with lay milestone, objectives of the project.
Project budget
Risk evaluation
Interim Payment
certificates
Payments that have been made to the contractor over the period
Project
correspondence
Project issues discussed between partners on the project, letters,
resolutions, negotiations, authorisations
Programme of works Details of activities to be done, time lines, proposed budgets,
milestones
Minutes of project
meetings
Issues discussed during meetings between the partners on the project
Approval, requests and actions
Operational reports
Project scope The extent of the project requested by the client and agreed to by the
contractor
Project variations Changes that were made to the project, who requested for the
changes, authorisations, costs of the changes approved
Project initial
estimates
Initial costs of components of the project
Organisational
structure
Accountability relationship at GHA
Project expenditure All amounts spent on the project (expenses made so far on the
project)
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 37
ii) List of Officials interviewed and subjects for interviews
Interviewee Subject
CEO and
Deputy Chief
Executive
Officer
(Development)
i) Roles and responsibilities,
ii) Coordination of the divisions under Development
department.
iii) Feasibility studies
iv) Planning for the Achimota-Ofankor Road Project.
v) Preliminary estimate
vi) Selection of contractor
vii) Human resource for the project.
viii) Challenges and the way forward
Director
Planning
i) Roles and responsibilities,
ii) Role in the planning and implementation of the
Achimota-Ofankor Road Project,
iii) Planning for Achimota-Ofankor Road Project.
iv) Identification of properties and payment of
compensation.
v) Challenges and the way forward
Director Survey
and Design
i) Roles and responsibilities,
ii) Role in the planning and implementation of the
Achimota-Ofankor Road Project.
iii) Initial road profile
iv) Design of components of the project
v) Change in design.
vi) Challenges and the way forward
Director Bridges i) Roles and responsibilities,
ii) Design of the footbridges and flyovers.
iii) Change in design of the flyovers and footbridges
iv) Challenges and the way forward
Director
Quantity
Surveying
i) Roles and responsibilities,
ii) Cost Planning.
iii) Tender documentation
iv) IPCs
v) Challenges and the way forward
Director i) Roles and responsibilities,
38 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Interviewee Subject
Contracts ii) Tendering
iii) Selection of contractor
iv) Contract Administration
v) IPCs
vi) Challenges and the way forward
Director
materials
i) Roles and responsibilities,
ii) Quality control
iii) Quality assurance
iv) Challenges and the way forward
Resident
Engineer
i) Role in the implementation of the Achimota-Ofankor
Road Project.
ii) IPCs
iii) Quality assurance
iv) Monitoring of the project.
v) Progress of work on the project
vi) Challenges and the way forward
Project Manager
(CRWG)
i) Interim Payment Certificates.
ii) Progress of work on the project.
iii) Quality of works
iv) Challenges and the way forward
Chief Executive i) Roles and responsibility in planning and
implementation of the project
ii) Approval processes
iii) Relationship with MRH and MOFEP
iv) Role of MRH on the project
v) Relationship with Resident Engineer
vi) Tendering
vii) IPCs
viii) Challenges and the way forward
Budget Officer –
MOFEP
i) Roles and responsibility in planning and
implementation of the project
ii) Approval processes
iii) Relationship with MRH and GHA
iv) Role of MOFEP on the project
v) Payment of IPCs
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 39
Appendix B
Schematic Drawing of Dual Carriage Highway
40 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Appendix C
Examples of concerns raised by Tenderers
The audit team gathered from review of project files that tender documents were
forwarded without drawings, and quantities were based on conceptual sketches.
(Correspondence between CEO-GHA and Minister of Transport dated 22 May 2006).
Tenderers also complained of incomplete tender documents and errors in tender
documents and sought for clarifications. Examples are:
i. On the 19th
of June 2006, P. W. Civils requested for tender drawings, Bills
of Quantities and rates.
ii. On the 22nd
of June 2006 Bilfinger Berger and Daewoo E & C Co. Ltd
requested for clarification of tender document.
iii. On 26th
June 2006 Daewoo E & C Co. Ltd requested for drawings since
they were not included in the tender documents. Bilfinger Berger requested
for clarification on drawings showing 2-lane carriageway with four
interchanges instead of 3-lane carriageway with three interchanges as per
the project name.
iv. On 28th
June 2006 CRWG requested for clarification on nine errors detected
in tender documents, one of the errors being incomplete design drawing.
v. On 29th
June 2006 Bilfinger Berger sought clarification on the bill of
quantities. Also, tender documents did not have contract identification
numbers.
vi. On 30th
June 2006 Bilfinger Berger requested for outstanding drawings in
order to formulate responsive bid since the drawings were not included in
the tender documents. Also the BOQ referred to drawings which were not
provided within the tender documents such as concrete kerb details,
reflective road sign details, retaining wall details, galvanised steel beam
guardrail details, and pedestrian handrail details.
vii. On the 4th
of July 2006, Bilfinger Berger drew the attention of GHA to the
errors in drawings and sought clarification.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 41
viii. 14th
July, Bilfinger Berger queried GHA for not furnishing them with the
minutes of the Pre-Bid meeting of 30th
June 2006.
Request for extension of deadline to submit tenders
i. On the 12th
of July 2006 Bilfinger Berger requested for extension of
deadline because they had not received the revised contract documentation
as of 7th
July 2006. The estimation process was suspended as a result.
ii. Daewoo wrote for extension of submission date from 28th
July 2006 to 25th
August 2006 due to changes in quantities in the Bill of Quantities received
from GHA on 18th
July 2006.
Request for extension of time denied
On 21st July 2006, GHA wrote to deny Daewoo E & C Co. Ltd the request for
extension of time.
Withdrawal of Bid
On 28th
July 2006 Daewoo informed GHA of their decision to withdraw their bid due
to lack of bid preparation time.
42 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Appendix D
Instances of delays by contractor in following Resident Engineer’s instructions
i. On 9th
April 2009, the Resident Engineer instructed the Contractor to
construct Tapering End Post for the New Jersey barriers but as at 13th
May2011, the Contractor had not constructed the Tapering End Posts
ii. Laying of Asphalt Wearing Course in the RHS main carriageway without
first submitting the quality control reports for the DBM and binder courses
laid for the section between ch.2 + 290 ~ 4 + 060 without seeking approval
to proceed as required. (sub-clause 38.1 “Examination of work before
covering)
iii. Dumping of 19mm chippings in swamp to stabilise sub-grade contrary to
the RE’s instruction for sub-grade stabilisation prior to casting of the
required concrete binding for the base of 1.5m x 1.5m box culvert.
iv. The RE instructed the contracted on the 28/04/2009 to reverse slopes in the
kerb inlets and to change the pre-cast moulds to ensure regular slopes for
drainage from the road to the side drains. The works was not done
according to specification. All the kerb inlets had to be removed and
replaced.
v. Poor concrete finish for New Jersey Barrier within Ch 4 +816 ~ 4 + 828, Ch
4 +865 ~ 4 + 877.
a. According to the RE, the expatriate supervisor was never present during
concrete pour except for the operatives and although the RE drew his
attention to it, no action was taken.
b. (sub clause 15.1 Contractor’s superintendence at site at all times)
vi. Random jointing and corrugations on DBM placed within Ch. 3 +370 ~ 4 +
050 LHS main carriageway resulting in bumpy riding surface contrary to
specification to place asphalt layer within specified surface tolerances to
ensure smooth riding quality.
Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project 43
vii. Irregular sizes of pre-cast u-drain cover slabs placed on u-drains at several
locations along the main carriageways and service roads, and poor finish of
the in-situ concrete deck slabs contrary to specifications.
viii. Defective work for wearing course on Mile 7 overpass Ch. 2 + 116 ~ 2 +
133 LHS
a. The wearing course was manually finished instead of paver finish and
covered in a coat of bitumen to conceal the resultant undulations contrary
to specifications.
ix. Laying of either deformed or broken kerb stones along Ch.1 + 460 ~3 +060
LHS service road.
44 Performance audit report of the Auditor-General on construction of Achimota-Ofankor Road Project
Appendix E
Details of total interest paid as at 31 December 2012
PC No. Amount Total days of delay in
payment Interest paid
% increase over IPC
amount
GH¢ component
US$ component GH¢ part US$ part
GH¢ part US$ part GH¢ part US$ part
1 7,187,917.00
0 0 0 0 0 0
2 489,589.98 1,117,010.63 241 245 48,961.00 54,395.00 10.00% 4.87%
3 522,305.91 1,452,690.80 307 279 69,014.00 76,182.83 13.21% 5.24%
4 1,569,485.61 1,005,520.79 144 150 92,210.97 27,690.85 5.88% 2.75%
5 1,228,444.28 1,053,793.79 211 219 115,959.11 41,582.62 9.44% 3.95%
6 924,500.71 1,642,855.47 146 154 61,231.39 45,557.18 6.62% 2.77%
7 627,079.44 2,165,292.02 187 188 57,936.00 73,606.24 9.24% 3.40%
8 1,141,990.26 2,895,863.13 187 265 91,049.42 100,934.21 7.97% 3.49%
9 2,551,401.49 2,791,886.27 269 291 375,519.14 87,341.42 14.72% 3.13%
10 617,896.06 1,562,262.41 377 323 138,058.02 40,188.24 22.34% 2.57%
11 181,616.44 422,206.24 347 347 36,664.89 10,799.61 20.19% 2.56%
12 976,449.85 1,021,790.98 379 384 183,459.42 27,133.72 18.79% 2.66%
13 554,971.74 87,828.78 249 254 89,874.21 1,608.31 16.19% 1.83%
14 797,666.93 1,620,846.56 241 246 109,318.16 24,577.53 13.70% 1.52%
15 1,041,173.82 534,870.95 226 231 133,896.42 7,545.13 12.86% 1.41%
16 2,072,303.44 3,203,329.16 104 109 122,565.02 19,559.04 5.91% 0.61%
17 935,419.27 1,974,619.32 121 136 48,632.76 14,087.13 5.20% 0.71%
18 762,321.72 1,804,898.06 116 118 67,183.78 20,790.51 8.81% 1.15%
19 640,033.83 1,342,776.27 133 136 57,452.12 12,970.65 8.98% 0.97%
20 1,261,515.65 912,304.68 175 175 111,029.99 9,229.40 8.80% 1.01%
21 382,493.39 881,021.98 233 252 41,492.90 11,863.43 10.85% 1.35%
22 313,429.44 1,047,650.36 320 327 46,238.82 17,790.68 14.75% 1.70%
23 1,753,172.41 1,080,304.32 293 300 234,427.03 16,774.01 13.37% 1.55%
24 754,317.83 2,001,347.83 261 268 89,067.43 27,414.43 11.81% 1.37%
25 766,710.80 1,847,766.18 397 421 89,252.39 34,236.97 11.64% 1.85%
26 2,421,399.94 12,404,880.05 378 402 390,624.62 232,488.33 16.13% 1.87%
27 470,497.61 1,346,618.48 183 190 35,978.34 11,922.07 7.65% 0.89%
28 612,824.05 1,277,474.12 135 142 34,229.65 8,456.18 5.59% 0.66%
29 692,255.54 1,785,410.78 320 327 92,447.39 27,272.46 13.35% 1.53%
30 553,078.83 1,551,642.48 281 288 64,120.27 20,856.76 11.59% 1.34%
31 656,080.43 1,668,263.10 231 238 62,566.03 18,515.44 9.54% 1.11%
32 488,276.63 1,493,934.79 137 144 38,429.81 9,930.26 7.87% 0.66%
33 504,780.54 813,371.69 83 90 15,687.21 4,521.59 3.11% 0.56%
34 752,340.24 1,985,151.26 113 127 32,266.64 12,897.34 4.29% 0.65%
35 1,584,204.43 1,460,032.48 88 87 50,130.64 8,500.64 3.16% 0.58%
Total 31,602,028.54 61,257,516.21 3,326,974.99 1,159,220.21
Total GH¢
Equivalent 88,439,814.96
4,394,367.57
Average 223.9 231.0
Source: GAS analysis of IPCs. Note: IPC No1 was mobilization payment and did not attract interest payment
Mission
Statement
The Ghana Audit Service exists
To promote
good governance in the areas of transparency,
accountability and probity in the public financial
management system of Ghana
By auditing
to recognized international auditing standards the
management of public resources
And
reporting to Parliament
Printed by The Advent Press, Tel: + 233 (0) 302 781044/777861Email: [email protected]