Dr. Morgan CIS 480

MS Project Concepts

CIS 480

Systems Analysis and Design

1

Page 2: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Outline• Project Configuration

– Setting the project start date

– Setting the calendar

• Creating tasks– Task

– Summary task

– Milestone task

• Creating dependencies– Type of dependency

– Calculation of slack time

• Gantt Chart• Pert Network

Dr. Morgan CIS 480 2

Page 3: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Setting Up the Project

Dr. Morgan CIS 480

Project->Project Information…

ProjectStart date

A Standard calendar

has weekends

off

3

Page 4: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Creating a Task

Dr. Morgan CIS 480

Type inthe task name

Adjustthe taskduration

The start andfinish are

calculated basedon the project start

Date and dependencies

4

Page 5: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Creating a Summary Task

Dr. Morgan CIS 480

Use pointer torearrange

tasks

Use doubleended arrow

to subordinate tasks

Note summary task

shownin black

5

Page 6: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Creating a Milestone

Dr. Morgan CIS 480

Makemilestone

Milestones have zero duration

6

Page 7: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Task Dependencies

• Finish-to-Start (FS)– Task B cannot start until task A finishes (most

common)

• Start-to-Start (SS)– Task B cannot start until task A starts (both start the

same time)

• Finish-to-Finish (FF)– Task B cannot finish until task A finishes (both finish

at the same time)

• Start-to-Finish (SF)– Task B cannot finish until task A starts

7

Page 8: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Dependency Gantt Examples

FinishStart(FS)

StartStart(SS)

FinishFinish(FF)

StartFinish(SF)

8

Page 9: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Lead and Lag Dependencies

1 day Lag

1 dayLead

9

Page 10: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Adding Dependencies

Dr. Morgan CIS 480 10

Page 11: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Detail Dependency Information

Dr. Morgan CIS 480

Setting for dependency type and lag

11

Page 12: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Adding Display Columns

• Right click on a column heading to add a new column of data before it

• Select the column you want to add to the display and click OK

Dr. Morgan CIS 480 12

Page 13: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Understanding Calculations

Dr. Morgan CIS 480

Take the following project with the predecessors (dependencies) listed

13

Page 14: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

How are Calculations Performed?

• Early Start times are determined by a forward pass analyzing the predecessor. The calendar is used to skip the weekends.

• Late Start is determine by looking at the end finish date and making a backward pass to calculate when the latest time the task can start without effecting the project timeline.

• Slack Time is the difference between early start and late start

Dr. Morgan CIS 480 14

Page 15: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Task List

EarlyStart

LateStart

SlackDifferenceEarly-Late

CriticalPath

A difference betweenEarly-start and late-startIndicates slack time

15

Page 16: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Gantt Chart

1,2 & 3 all start at

beginning

Note the predecessors

3

7

9

16

Page 17: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Calculation of EarlyStart,LateStart,Slack• Task Three (3 days)

– EarlyStart (Project Start on 6/1/06)– LateStart = Task 7 LateStart – Task 3 duration: 6/2/06

• Task Seven (6 days)– Task 7 StartFinish predecessor of Task 3– EarlyStart =Task 3 Finish 6/5/06 + 1 day: 6/6/06– LateStart = Task 9 LateStart – Task 7 duration: 6/7/06

• Task Nine (3 days)– Task 9 StartFinish predecessor of Task 7– EarlyStart = Task 7 Finish 6/13/06 + 1 day: 6/14/06– LateStart = Task 10 Start – 3 days: 6/15/06

Forward Calculation

Backward Calculation

Slack1 day

Task 9 has predecessor of 7

and 7 has predecessor of 3

17

Page 18: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480

Pert NetworkView->Network Diagram

Red task boxes

represent the critical path

18

Page 19: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Working Backward from a Completion Date

Dr. Morgan CIS 480

from Project Menu select - Project Information

In dialog box pick schedule from Project Finish Date Enter the target finish date

19

Page 20: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Highlighting the Critical Path

Dr. Morgan CIS 480

From the Format Menu select the Check the Critical Tasks Check box

20

Page 21: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Creating and Assigning Resources

• Select the Resources main menu choice and click on the Assign Resources Tab

• Double click on new resource on the dialog box that appears.

Dr. Morgan CIS 480 21

Page 22: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Creating and Assigning Resources (Continued)

• Add your resources name and any other appropriate information on the general tab,

• Move to the costs tab and enter at least a standard rate and look at the other options

• The Notes tab is used for any descriptive info needed,: about skill sets, etc.

• When finished click OK to save

• Repeat for as many resources as you will be using for the project.

Dr. Morgan CIS 480 22

Page 23: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Creating and Assigning Resources (Continued)

• With the assign resources dialog displayed• Click on a task on the Gantt chart• You are now ready to assign resources to the selected

task.• The R/D column stands for Request/Demand and those

are the 2 choices• The Units column allows you to specify the percentage

of effort of the resource that will be allocated to the task• You do not fill in the cost column that value is calculated• Click on assign when you have specified the units you

want. Dr. Morgan CIS 480 23

Page 24: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Dr. Morgan CIS 480 24

Page 25: Dr. Morgan CIS 480 MS Project Concepts CIS 480 Systems Analysis and Design 1

Adjusting Duration by Adding Resources

• If more than 100% of person’s time is assigned to a task, an icon appears in the task mode allowing you options for adjusting the schedule

• Pick reduce duration if workers were added to speed up a task on the critical path.

Dr. Morgan CIS 480 25