Drawing 3 - Machines Hall-Machines Hall

Embed Size (px)

DESCRIPTION

HALL, MACHINE, CENTRAL

Citation preview

  • 3rd Stage

    Shaft excavation down to elevation 152, removing material by access gallery in elevation 152 (T6).Estimated volume: 158 m3

    4th Stage

    Staggering benching from elevation 164.60 down to 158 and 152, removing material by shaft andaccess gallery at elevation 152 (T6).Estimated volume: 23970 m3

    5th Stage

    Shaft excavation down to elevation 132, removing material by draft tube and tailrace tunnel.Estimated volume: 231 m3

    6th Stage

    Staggering benching from elevation 152 down to 145, 138 and 132, removing material by draft tube,shaft and tailrace tunnel.Estimated volume: 21725 m3

    7th Stage

    Benching of the base of the chamber removing material by draft tube and tailrace tunnel.Estimated volume: 1100 m3

    GRAPHIC SCALE