Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
rpsgroup.com
DUBLIN PORT MAINTENANCE DREDGING 2022 - 2029 APPLICATION FOR FORESHORE LICENCE Stakeholder Consultation
Dublin Port Maintenance Dredging 2022-2029
Stakeholder ConsultationFinal
8 February 2021
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation
rpsgroup.com Page ii
Document status
Version Purpose of document Authored by Reviewed by Approved by Review date
Final Statutory Authorisation 08/02/2021
Approval for issue
8 February 2021
Prepared by: Prepared for:
RPS Dublin Port Company
Senior Associate - Water Environment and Flood
Risk Management
Port Engineer
Elmwood House
74 Boucher Road, Belfast
Co. Antrim BT12 6RZ
Dublin Port Centre
Alexandra Road
Dublin 1, D01 H4C6
T +44 2890 667 914
E
T 01 8876000
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation
rpsgroup.com Page iii
Contents 1 PRE-APPLICATION CONSULTATION ............................................................................................. 1
1.1 Pre-application consultation with relevant statutory stakeholders ........................................... 1 1.2 Pre-application consultation with Marine Institute .................................................................... 4 1.3 Consultation with other relevant stakeholders ......................................................................... 4
2 CONSULTATION DURING FORESHORE CONSENTING PROCESS ............................................ 5 2.1 Public Consultation Phase ....................................................................................................... 5 2.2 Consultation with Prescribed Bodies ....................................................................................... 5
3 CONSULTATION DURING MAINTENANCE DREDGING CAMPAIGNS ........................................ 6
Appendices
Appendix A Consultation Letter issued to relevant Stakeholders ................................................................ 7 Appendix B Consultee Responses ............................................................................................................... 8
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 1
rpsgroup.com
1 PRE-APPLICATION CONSULTATION
Prior to making the foreshore licence application to Department of Housing, Local Government and Heritage (DHLGH), RPS (on behalf of Dublin Port Company) consulted with a number of relevant stakeholders to inform them of the proposed maintenance dredging campaigns to take place from 2022 – 2029. This application provides a summary of the pre-application consultation which took place.
1.1 Pre-application consultation with relevant statutory stakeholders
A letter and information pack (including drawings) was issued to relevant statutory stakeholders as part of the pre-application consultation phase. The following consultees received the information pack:
Development Applications Unit of Department of Culture, Heritage and the Gaeltacht*
Inland Fisheries Ireland
Marine Survey Office
The Sea Fisheries Protection Authority
Dublin City Council
*The Development Applications Unit (DAU) is the co-ordination unit for consultations with National Parks and Wildlife Service and National Monuments Service.
An example letter is provided in Appendix A of this report.
Responses were received from the following organisations:
Underwater Archaeological Unit and National Parks and Wildlife Service of Department of Culture, Heritage and the Gaeltacht (letter received by email on 18th March 2020 via the DAU)
Marine Survey Office (email received from MSO on 11th May 2020)
A copy of the replies from the consultees is provided in Appendix B of this report and a short summary is provided below:
Underwater Archaeological Unit, Department of Culture, Heritage and the Gaeltacht
It is recommended that all known wreck sites located within the proposed dredged zone are subject to 30m exclusion zones.
No dredging should take place within the exclusion zones.
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 2
rpsgroup.com
Should new wreck sites be discovered during future ABR dredge campaigns then these should be subject to exclusion zones.
A chart showing the location of the exclusion zones in relation to the dredge areas should be forwarded to this Department in advance of dredging proceeding.
Explanation of how Advice from Underwater Archaeological Unit has been taken on-board in the Foreshore Application:
A standalone report on the impact of the proposed maintenance dredging 2022-2029 on underwater archaeology accompanies this application. In this report mitigation measures are specified to take into account the potential impact of dredging on known and unknown wreck sites including the exclusion zones mentioned by Underwater Archaeology Unit in their submission.
The report was prepared by ADCO Ltd who are an experience underwater archaeology assessment company and have been working on Dublin Port projects since the inception of the ABR Project. They are currently the consultants involved in archaeological monitoring of all dredging and landside construction activities taking place in the port.
National Parks and Wildlife Service, Department of Culture, Heritage and the Gaeltacht
The proposed activity would occur within and adjacent to the following Natura 2000 site:
- Rockabill to Dalkey Island Special Area of Conservation (Site Code: IE002137)
- Article 6(3) of Council Directive 92/43/EC (the Habitats Directive) states that “Any plan of project not directly connected with or necessary to the management of the (Natura) site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site’s conservation objectives”. The proposed development would require such an assessment as the works would occur within or adjacent to designated Natura sites.
- Guidance on this process can be found within “Assessment of plans and projects significantly affecting Natura 2000 sites: Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive 92/43/EEC” published by the European Commission in 2001.
In order to fulfil the Article 6 legal requirements the following information should be supplied with the application:
A. Full description of the proposed operation/activity
- A full description of the proposed construction and operational methodology including the likely time-scale of works.
- Are there similar operations/activities already in the locality? If existing operations/activities occur adjacently then a justification for additional facilities should be included. Would the proposed works act in conjunction with any existing developments?
- The facilities or licensing arrangements to be put in place to cope with both biological and industrial waste (e.g. construction materials, dredge spoil etc) generated during construction of the proposed facility should be detailed.
- Detailed contingency plans sufficient to address potential negative interactions with the marine environment eg. oil spills.
B. Baseline Description of relevant environment
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 3
rpsgroup.com
- If there is construction proposed over the designated area then a description of the biological environment over which the activity will impact including the marine flora and fauna must be included.
- Consideration should be given to whether the likely construction/operation would result in disturbance or loss to Annex I habitats (Reefs). Any loss or interruption of normal processes must be quantified relative to the entire designated area not just within the direct footprint of development. The evaluation should also reference the biological communities identified within the proximity of the proposed development.
- A baseline description of the presence of marine mammals listed on Annex II and IV of Council Directive 92/43/EEC must be completed prior to supplement the Article 6(3) Assessment (harbour porpoise is a qualifying interest for this site). This must be of sufficient resolution to predict the likely interaction with these species over both a spatial and temporal scale. It is likely that existing data sources will be useful in formulating this assessment, however, additional data collection should be considered. It is recommended that suitably qualified marine mammal ecologists should be involved in undertaking relevant assessments. This document will inform on decisions related to Article 12 of the Habitats Directive and Regulation 51 of the European Communities (Birds and Natural Habitats) Regulations of 2011.
Explanation of how Advice from National Parks and Wildlife Service has been taken on-board in the Foreshore Application:
In response to the advice and requests made by National Parks and Wildlife Service in their submission, the following standalone reports were produced which address their concerns and requirements:
Natural Impact Statement, RPS, 2020.
Marine Mammal Risk Assessment of Proposed Dublin Port Company Maintenance Dredging and Disposal at Sea. IWDG Consulting, 2020.
Benthic Ecology and Fisheries Assessment. Aquatic Services Unit, UCC, 2020.
The above reports have all been prepared by experts competent and experienced in their specialist fields.
Marine Survey Office (MSO)
The MSO advised that this (application) will only be considered on receipt of a foreshore application which should be forwarded in full to the Department of Housing, Planning and Local Government (now DHLGH).
It would appear that this is a standard maintenance dredge application which should follow the same procedure as previous dredge applications received by this department.
Explanation of how Advice from Marine Survey Office has been taken on-board in the Foreshore Application:
RPS followed the DHLGH guidance when preparing the foreshore consent application. This ensures that the submission is complying with their requirements and also those of the prescribed bodies such as MSO who will be commenting on the application.
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 4
rpsgroup.com
No further responses were received up until the date of submission of the foreshore license application.
1.2 Pre-application consultation with Marine Institute
Dublin Port Company (DPC) consulted with the Marine Institute regarding their plans to submit both Foreshore Licence and Dumping at Sea Permit applications for an eight year maintenance dredging programme (2022-2029). DPC also discussed their plans to undertake further capital dredging works within Dublin Harbour as set out in the Dublin Port Masterplan 2040, reviewed 20118.
Further to this consultation, the Marine Institute issued a Sampling & Analysis Plan (SAP) to DPC on 27th March 2020 designed to cover both the proposed eight year maintenance dredging programme (2022-2029) and DPC’s capital dredging requirements in Dublin Harbour.
The details of the sediment volumes and sediment chemistry are presented under separate cover.
.
1.3 Consultation with other relevant stakeholders
Regular communication takes place between DPC Harbour Master’s Office and the users of the Port. Regular maintenance dredging is essential for the viability and safety of the users of Dublin Port’s facilities.
Regular communication also takes place between DPC and the Winter Swimming Group who regularly swim either side of the North Bull Wall. At the request of the Winter Swimming Group, DPC has deployed a water quality monitoring buoy as close as possible to the area used for swimming within the Tolka Estuary. The buoy measures turbidity and it will be present throughout the proposed maintenance dredging campaigns between 2022 and 2029.
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 5
rpsgroup.com
2 CONSULTATION DURING FORESHORE CONSENTING PROCESS
2.1 Public Consultation Phase
Following review of the Foreshore Licence application by DHLGH, DPC will advertise the foreshore licence application in both the National Press and Local Press and offer the public the opportunity to view the proposals and to make submissions directly to the Department. The period of public consultation will extend to 30 working days. The application material will be made available on the Departments’ website and DPC will also upload the material onto their website at a dedicated page for “Dredging Activities”. If people don’t have access to the internet, the material will also be made available in hard copy format at Garda Stations (providing Covid 19 regulations allow at the time) in close proximity to Dublin Port.
Any submissions that are made by the public during this phase of the process are compiled by DHLGH and will be provided to DPC for comment and response if necessary when the public consultation phase concludes.
2.2 Consultation with Prescribed Bodies
DHLGH will provide copies of the application material to a number of prescribed bodies as set out in the Foreshore Legislation to seek their views on the proposal. Following this consultation, DHLGH will provide DPC with a summary of the responses from the prescribed bodies. There will be an opportunity for DPC to respond on any issues raised by the prescribed bodies and provide further information or clarification on any points that they might raise.
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 6
rpsgroup.com
3 CONSULTATION DURING MAINTENANCE DREDGING CAMPAIGNS
Subject to DHLGH granting foreshore consent, DPC will undertake to inform relevant stakeholders in advance of maintenance dredging taking place:
DHLGH will be informed of the commencement date, two weeks in advance
A Marine Notice will be issued by DPC.
DPC will insert a Public Notice in the local press to inform the general public in advance of maintenance dredging commencing.
DPC will display key information with respect to the maintenance dredging campaigns on their website.
DPC has a dedicated community liaison team to deal with any issues or concerns which may arise from the public during the maintenance dredging campaign. DPC are happy to meet and discuss with any stakeholders that may wish to discuss the maintenance dredging before, during or after the campaigns.
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 7
rpsgroup.com
Appendix A
Consultation Letter issued to relevant Stakeholders
Our ref: IBE1618/ltr1
Date: 6th May 2020
rpsgroup.com
Elmwood House
74 Boucher Road, Belfast
Co. Antrim BT12 6RZ
T +44 2890 667 914
Page 1
The Manager
Development Applications Unit
Department of Culture, Heritage and the Gaeltacht
Dear Sir/Madam
Dublin Port Company – Proposed Maintenance Dredging 2022 - 2029
Dublin Port Company (DPC) need to carry out regular maintenance dredging of the navigation channel,
basins and berthing pockets in order to maintain their advertised charted depths and hence provide safe
navigation for vessels to and from the Port.
DPC is seeking permissions to undertake an eight year maintenance dredging programme between 2022
and 2029. It is proposed to undertake the maintenance dredging and disposal at sea operations within the
period April to September each year. The dredging campaign within each of these periods is expected to
last approximately 4-6 weeks, depending on weather conditions.
In order to carry out maintenance dredging, it is necessary to have the following statutory permits in place:
Foreshore Licence issued by the Department of Housing, Planning and Local Government
Dumping at Sea Permit issued by the EPA
RPS are currently preparing the applications for the above two consents on behalf of Dublin Port Company.
It is anticipated that the applications for Foreshore Consent and Dumping at Sea Permit will be lodged
during October 2020.
Please find attached a short project description outlining the proposed maintenance dredging operations
and drawings showing the location of the loading areas and licenced offshore disposal site.
Our ref: IBE1389/ltr5
rpsgroup.com
. No.. . Page 2
We welcome your comments on the proposed eight year maintenance dredging programme and if there is
any specific issues you wish to see in the applications, please let us know. We would greatly appreciate a
response by 31st May 2020.
Yours sincerely,
for RPS
Senior Associate - Water Environment and Flood Risk Management
Enc: Project Information
Maintenance dredging drawings
Dublin Port Company
Proposed Eight Year Maintenance Dredging Programme 2022 to 2029
Project Information
Summary of proposed maintenance dredging works
Dublin Port Company (DPC) need to carry out regular maintenance dredging of the navigation channel, basins and berthing pockets in order to maintain their advertised charted depths and hence provide safe navigation for vessels to and from the Port. The loading of dredged material will be restricted to those areas of the navigation channel, basins and berthing pockets which contain sediments which are suitable for disposal at sea (Class 1 : uncontaminated, no biological effects likely). Confirmation of the suitability of the dredged sediments for disposal at sea is made through a programme of sediment chemistry sampling and analysis and eco-toxicological testing. It is proposed to dispose of the dredged sediments at the existing licensed offshore disposal site located at the entrance to Dublin Bay to the west of the Burford Bank, (6.75 km from the lighthouse at the end of the Great South Wall). The approximate amount of material to be dredged is 300,000 cubic metres per annum and it consists mostly of silt and sand with elements of clay, gravel and cobbles. Dredging will be carried out by a trailer suction hopper dredger and support vessels. It is proposed to undertake the maintenance dredging and disposal at sea operations within the period April to September each year between 2022 and 2029. The dredging campaign within each of these periods is expected to last approximately 4-6 weeks, depending on weather conditions.
Consent Requirements
DPC propose to submit an application to the Environmental Protection Agency for a permit under Section 5 of the Dumping at Sea Acts 1996 to 2010. The application is for the loading and dumping of dredged material arising from the proposed maintenance dredging programme.
DPC also propose to submit an application to the Department of Housing, Planning & Local Government (DHPLG) for a Foreshore Licence under the Foreshore Act 1933 (as amended).
Dredging Operations
The location of the proposed areas to be dredged (loading areas) and the existing licenced offshore dump
site are presented on the following drawings:
IBE1618/2022-2029/01/ RevA Location of Loading Activity
IBE16188/2022 - 29/02/ RevA Location of Loading and Disposal Activity
It is proposed that the following annual quantities of material will be dredged from the Inner Liffey Channel
and Dublin Bay during the proposed maintenance dredging campaigns.
Inner Liffey Channel (Dublin Harbour, area within the Bull Walls)
The Annual Average quantity of siltation within the inner Liffey channel based on previous maintenance
dredging campaigns is circa 120,000 cubic metres
The proposed maximum annual volume is 150,000 cubic metres. The material to be dredged is mostly silt.
Dublin Bay (area of navigation channel outside the Bull Walls)
The navigation channel has been dredged from -7.8m Chart Datum to -10.0m CD under the Alexandra
Basin Redevelopment (ABR) Project. Siltation is likely during storm activity.
The proposed maximum annual volume is 150,000 cubic metres. The material to be dredged is mostly fine
sand.
Total Volume and Tonnage over the eight year maintenance dredging programme
The total volume over the eight year maintenance dredging programme is 2,400,000 cubic metres
A conversion factor of 1.65 will be used to convert ‘volume’ to ‘wet tonnes’ (as per ABR Project Capital
Dredging, Dumping at Sea Permit S0024-01)
The total tonnage to be requested under the proposed consents is therefore 3,960,000 wet tonnes
Dredging Windows
The proposed maintenance dredging will be restricted to the summer period (April – September). Capital
dredging works will be restricted to the winter period (October – March). This separation provides the clarity
required by the EPA to enforce separate permits for maintenance and capital dredging programmes.
Environmental Considerations
DPC’s current practice is to dispose of the dredge material at the licensed offshore disposal site located to
the west of the Burford Bank in compliance with the conditions of a Dumping at Sea Permit from the EPA.
The licenced offshore disposal site lies within the Rockabill to Dalkey Island candidate Special Area of
Conservation (site code: 003000). The qualifying interests for the site are Harbour Porpoise and reefs. As
there are no reefs near to the site, the key qualifying interest is Harbour Porpoise.
In order to safeguard the Harbour Porpoise, DPC confirms that it shall be fully compliant with the
requirements set out in National Parks & Wildlife Service’s “Guidance to Manage the risk to Marine
Mammals from Man-made Sound Sources in Irish Waters” (January 2014) in respect of both the
maintenance dredging activity on the foreshore and the disposal activity at the licensed offshore disposal
site. As part of this commitment, an independent, suitably qualified, Marine Mammal Observer will be
present during the dredging and dumping activities to ensure full compliance with the Guidance. This will
ensure that the maintenance dredging will have no measureable impact on the welfare of Harbour Porpoise
in Dublin Bay and the Irish Sea.
Additional Proposed Maintenance Dredging Restrictions
DPC propose the additional maintenance dredging restrictions
No overspill from dredger will be allowed within the inner Liffey channel;
The filled hopper volume within the inner Liffey channel will be limited to 4,100 cubic metres (in line
with the ABR Project) to control concentrations of suspended solids at the dump site;
Overspill from dredger will however be allowed within Dublin Bay. Furthermore there will be no restriction
on hopper capacity within Dublin Bay because the fine sand does not give rise to a significant sediment
plume at the dump site
Pier Head to be removed under the MP2 Project (ABP-304888-19) Zone 1 - Navigation Channel
Zone 4Oil Berths
Zone 3 Alexandra Basin East
Zone 2 - South Quays
Zone 5 - LoLo Container & Ferry Terminals
Zone 6 - Sludge/Oil Jetty
Rev Amendments Drawn by Date
Client
Project
Title
Drawing Status Sheet Size Drawing Scale
Drawing Number
Project Leader Drawn By Date Initial Review
¯
Dublin Port CompanyMaintenance Dredging Campaign 2022-2029
2022 -2029 Maintenance DredgingLocation of loading activity
Elmwood House74 Boucher Road BelfastBT12 6RZ
T +44 (0) 28 90 667914F +44 (0) 28 90 668286W www.rpsgroup.com/irelandE [email protected]
DRAFT A3 1:12,000
27/04/2020
IBE1618/ 2022-2029 / 01 A1:20,000
0 0.75 1.5 2.25 30.375Km
0 375 750 1,125 1,500187.5Metres
NOTES: 1. Verifying Dimensions.
The contractor shall verify dimensions against such other drawings or site conditions as pertain to this part of the work.
2. Existing Services. Any information concerning the location of existing services indicated on this drawing is intended for general guidance only. It shall be the responsibility of the contractor to determine and verify the exact horizontal and vertical alignment of all cables, pipes, etc. (both underground and overhead) before work commences.
3. Issue of Drawings. Hard copies, dwf and pdf will form a controlled issue of the drawing. All other formats (dwg, dxf etc.) are deemed to be an uncontrolled issue and any work carried out based on these files is at the recipients own risk. RPS will not accept any re sponsibility for any errors arising from the use of these files, either by human error by the recipient, listing of un -dimensioned measurements, compatibility issues with the recipient's software, and any errors arising when these files are used to aid th e recipients drawing production, or setting out on site.
4. Datum. 5. © Ordnance Survey Ireland of Ireland /
Government of Ireland. Ordnance Survey Ireland Licence No. EN0001618
Maintenance Dredging Area 2022 - 2029Zone 1 - Navigation ChannelZone 2 - South QuaysZone 3 - Alexandra Basin EastZone 4 - Oil BerthsZone 5 - LoLo Container & Ferry TerminalsZone 6 - Sludge/Oil Jetty
Rev
Rev Amendments Drawn by Date
Client
Project
Title
Drawing Status Sheet Size Drawing Scale
Drawing Number
Project Leader Drawn By Date Initial Review
¯
Dublin Port CompanyMaintenance Dredging Campaign 2022-2029
2022 -2029 Maintenance DredgingLocation of loading and disposal activity
Elmwood House74 Boucher Road BelfastBT12 6RZ
T +44 (0) 28 90 667914F +44 (0) 28 90 668286W www.rpsgroup.com/irelandE [email protected]
DRAFT A3 1:40,000
27/04/2020
IBE1618/ 2022-2029 / 02 A0 1.5 3 4.5 60.75Km
NOTES: 1. Verifying Dimensions.
The contractor shall verify dimensions against such other drawings or site conditions as pertain to this part of the work.
2. Existing Services. Any information concerning the location of existing services indicated on this drawing is intended for general guidance only. It shall be the responsibility of the contractor to determine and verify the exact horizontal and vertical alignment of all cables, pipes, etc. (both underground and overhead) before work commences.
3. Issue of Drawings. Hard copies, dwf and pdf will form a controlled issue of the drawing. All other formats (dwg, dxf etc.) are deemed to be an uncontrolled issue and any work carried out based on these files is at the recipients own risk. RPS will not accept any re sponsibility for any errors arising from the use of these files, either by human error by the recipient, listing of un -dimensioned measurements, compatibility issues with the recipient's software, and any errors arising when these files are used to aid th e recipients drawing production, or setting out on site.
4. Datum. 5. © Ordnance Survey Ireland of Ireland /
Government of Ireland. Ordnance Survey Ireland Licence No. EN0001618
Maintenance Dredging Area 2022 - 2029Maintenance Dredging Disposal Area 2022 -2029
Rev
STAKEHOLDER CONSULTATION
Dublin Port Maintenance Dredging 2022-2029 | Stakeholder Consultation 8
rpsgroup.com
Appendix B
Consultee Responses
Aonad na nIarratas ar Fhorbairt, Bóthar an Bhaile Nua, Loch Garman, Y35 AP90
Development Applications Unit, Newtown Road, Wexford, Y35 AP90
www.chg.gov.ie
Your Ref: Dublin Port Dredging
Our Ref: G Pre00072/2020
(Please quote in all related correspondence)
18 August 2020
Elmwood House
74 Boucher Road
Belfast BT12 6RZ
Northern Ireland
Via email
Re: Proposed Maintenance Dredging at Dublin Port during 2022-2029
A chara
On behalf of the Department of Culture, Heritage and the Gaeltacht, I refer to
correspondence received in connection with the above.
Outlined below are heritage-related observations/recommendations of the Department
under the stated heading(s).
Underwater Archaeology
Recent dredging operations carried in Dublin Port connected with the Alexander Basin
redevelopment project has resulted in the discovery of a number of artefacts and a new
wreck site in areas where the proposed maintenance dredging is to be carried out.
Given the archaeological potential of the dredging area and in light of these recent
discoveries it is recommended that all known wreck sites located within the proposed
dredged zone are subject to 30m exclusion zones. No dredging should take place within
the exclusion zones. Should new wreck sites be discovered during future ABR dredge
campaigns then these too should be subject to exclusion zones. A chart showing the
location of the exclusion zones in relation to the dredge areas should be forward to this
Department in advance of dredging proceeding.
Nature Conservation
EU Habitats Directive- Article 6(3) assessment
The proposed activity would occur within and adjacent to inter alia the following Natura
2000 sites:
Rockabill to Dalkey Island Special Area of Conservation (Site code: IE002137).
Details of the site synopses and qualifying interests of Natura sites are available on
http://www.npws.ie/protected-sites. Further information related to site specific conservation
rpsgroup.com LinkedIn | Facebook | Instagram | YouTube
In response to COVID-19, RPS has adapted the way we work to ensure we remain connected
with you and our colleagues, and continue to deliver good work.
We recognise that the months ahead will pose challenges for many of our clients and
partners. We’re here to help in any way we can. While COVID-19 might separate us physically
in the short term, please know that we’re here, we’re with you and we’re stronger together.
If you need support or would like to discuss your forward looking priorities, please get in
touch. You can continue to contact me in the usual ways via phone and email, or we can set
up a virtual meeting.
This e-mail message and any attached file is the property of the sender and is sent in confidence to the addressee only.
Internet communications are not secure and RPS is not responsible for their abuse by third parties, any alteration or corruption intransmission or for any loss or damage caused by a virus or by any other means.
RPS Group Plc, company number: 208 7786 (England). Registered office: 20 Western Avenue Milton Park Abingdon OxfordshireOX14 4SH.
RPS Group Plc web link: http://www.rpsgroup.com
************************************************************Tá eolas sa teachtaireacht leictreonach seo a d'fhéadfadh bheith príobháideach nó faoi rúnagus b'fhéidir go mbeadh ábhar rúnda nó pribhléideach ann. Is le h-aghaidh an duine/nandaoine nó le h-aghaidh an aonáin atá ainmnithe thuas agus le haghaidh an duine/nandaoine sin amháin atá an t-eolas. Tá cosc ar rochtain don teachtaireacht leictreonach seodo aon duine eile. Murab ionann tusa agus an té a bhfuil an teachtaireacht ceaptha dóbíodh a fhios agat nach gceadaítear nochtadh, cóipeáil, scaipeadh nó úsáid an eolaisagus/nó an chomhaid seo agus b'fhéidir d'fhéadfadh bheith mídhleathach.
Tá ár Ráiteas Príobháideachta le fáil ar www.dttas.gov.ie
The information in this email is confidential and may be legally privileged. It is intendedsolely for the addressee. Access to this email by anyone else is unauthorised. If you arenot the intended recipient, any disclosure, copying, distribution or any action taken oromitted to be taken in reliance on it is prohibited and may be unlawful.
Our Privacy Statement is available on www.dttas.gov.ie
***********************************************************
…..
2
objectives are also available at this location by interrogating the Site Code. Additional
supporting information and referenced publications are also available to download from this
resource. Site boundaries and mapped habitat resources are available to download from
http://www.npws.ie/maps-and-data.
Article 6(3) of Council Directive 92/43/EC (the Habitats Directive) states that “Any plan or
project not directly connected with or necessary to the management of the [Natura] site but
likely to have a significant effect thereon, either individually or in combination with other
plans or projects, shall be subject to appropriate assessment of its implications for the site
in view of the site's conservation objectives”. This is transposed into national legislation by
Regulation 42 of the European Communities (Birds and Natural Habitats) Regulations
2011. The proposed development would require such an assessment as the works would
occur within or adjacent to designated Natura sites.
Guidance on this process can be found within “Assessment of plans and projects
significantly affecting Natura 2000 sites: Methodological guidance on the provisions of
Article 6(3) and (4) of the Habitats Directive 92/43/EEC” published by the European
Commission in 2001. A document entitled “Appropriate Assessment of Plans and Projects
in Ireland: Guidance for Planning Authorities” published by the Department of the
Environment, Heritage & Local Government is available to download on
http://www.npws.ie/protected-sites/guidance-appropriate-assessment-planning-authorities.
Additional information is also available at http://www.npws.ie/guidance-appropriate-
assessment-planning-authorities.
In order to fulfil the Article 6 legal requirements the following information should be supplied
within the application:
A. Full description of proposed operation/activity
A full description of the proposed construction and operational methodology
including the likely time-scale of works.
Are there similar operations/activities already in the locality? If existing
operations/activities occur adjacently then a justification for additional facilities
should be included. Would the proposed works act in conjunction with any
existing developments?
The facilities or licensing arrangements to be put in place to cope with both
biological and industrial waste (e.g. construction materials, dredge spoil etc.)
generated during construction of the proposed facility should be detailed.
Detailed contingency plans sufficient to address potential negative interactions
with the marine environment e.g. oil spills.
B. Baseline description of relevant environment
…..
3
If there is construction proposed over the designated area then a description of
the biological environment over which the activity will impact including the
marine flora and fauna (infauna, epifauna etc) must be included. Some
information will already exist through the conservation objective setting process.
However, this may need to be supplemented by collecting intertidal or subtidal
data as appropriate. The data collection exercise should be sufficiently
intensive to adequately predict the expected habitat interaction.
Consideration should be given to whether the likely construction/operation
would result in disturbance or loss to Annex I habitats (Reefs). Any loss or
interruption of normal processes must be quantified relative to the entire
designated area not just within the direct footprint of development. The
evaluation should also reference the biological communities identified within the
proximity of the proposed development.
A baseline description of the presence of marine mammals listed on Annex II
and IV of Council Directive 92/43/EEC must be completed prior to supplement
the Article 6(3) Assessment (harbour porpoise is a qualifying interests for this
site). This must be of sufficient resolution to predict the likely interaction with
these species over both a spatial and temporal scale. It is likely that existing
data sources will be useful in formulating this assessment, however, additional
data collection should be considered. It is recommended that suitably qualified
marine mammal ecologists should be involved in undertaking relevant
assessments. This document will inform on decisions related to Article 12 of the
Habitats Directive and Regulation 51 of the European Communities (Birds and
Natural Habitats) Regulations of 2011.
You are requested to send further communications to this Department’s Development
Applications Unit (DAU) at [email protected] (team monitored); if this is not
possible, correspondence may alternatively be sent to:
The Manager
Development Applications Unit (DAU)
Department of Culture, Heritage and the Gaeltacht
Newtown Road
Wexford
Y35 AP90
Is mise, le meas
__
…..
4
Development Applications Unit
From:To:Cc:Subject: RE: Proposed Maintenance Dredging at Dublin Port during 2022-2029Date: 11 May 2020 14:43:35Attachments: image002.png
CAUTION: This email originated from outside of RPS.Good afternoon I refer to the above and wish to advise that this will only be considered on receipt of a foreshoreapplication which should be forwarded in full to the Department of Housing, Planning and LocalGovernment.It would appear that this is a standard maintenance dredge application which should follow thesame procedure as previous dredge applications received by this department. Kind regards.
Marine Survey Office__An Roinn Iompair, Turasóireachta agus Spóirt
Department of Transport, Tourism and Sport An Tsráid Mhór Uachtarach, Béal Átha Seanaidh, Co. Dhún Na Ngall, F94 C44W
Upper Main Street, Ballyshannon, Co Donegal, F94 C44W
__T
[email protected] www.dttas.gov.ie
From: @rpsgroup.com] Sent: 06 May 2020 11:28To: Subject: Proposed Maintenance Dredging at Dublin Port during 2022-2029 Dear We wish to consult with the Marine Survey Office regarding the above proposed project. Pleasefind attached relevant information. If you require any further detail please let me know. Yours sincerelyFor RPS
Senior Associate - Water Environment and Flood Risk ManagementRPS | Consulting UK & Ireland Elmwood House74 Boucher Road, BelfastCo. Antrim BT12 6RZ, United KingdomT +44 2890 667 914
rpsgroup.com LinkedIn | Facebook | Instagram | YouTube
In response to COVID-19, RPS has adapted the way we work to ensure we remain connected
with you and our colleagues, and continue to deliver good work.
We recognise that the months ahead will pose challenges for many of our clients and
partners. We’re here to help in any way we can. While COVID-19 might separate us physically
in the short term, please know that we’re here, we’re with you and we’re stronger together.
If you need support or would like to discuss your forward looking priorities, please get in
touch. You can continue to contact me in the usual ways via phone and email, or we can set
up a virtual meeting.
This e-mail message and any attached file is the property of the sender and is sent in confidence to the addressee only.
Internet communications are not secure and RPS is not responsible for their abuse by third parties, any alteration or corruption intransmission or for any loss or damage caused by a virus or by any other means.
RPS Group Plc, company number: 208 7786 (England). Registered office: 20 Western Avenue Milton Park Abingdon OxfordshireOX14 4SH.
RPS Group Plc web link: http://www.rpsgroup.com
************************************************************Tá eolas sa teachtaireacht leictreonach seo a d'fhéadfadh bheith príobháideach nó faoi rúnagus b'fhéidir go mbeadh ábhar rúnda nó pribhléideach ann. Is le h-aghaidh an duine/nandaoine nó le h-aghaidh an aonáin atá ainmnithe thuas agus le haghaidh an duine/nandaoine sin amháin atá an t-eolas. Tá cosc ar rochtain don teachtaireacht leictreonach seodo aon duine eile. Murab ionann tusa agus an té a bhfuil an teachtaireacht ceaptha dóbíodh a fhios agat nach gceadaítear nochtadh, cóipeáil, scaipeadh nó úsáid an eolaisagus/nó an chomhaid seo agus b'fhéidir d'fhéadfadh bheith mídhleathach.
Tá ár Ráiteas Príobháideachta le fáil ar www.dttas.gov.ie
The information in this email is confidential and may be legally privileged. It is intendedsolely for the addressee. Access to this email by anyone else is unauthorised. If you arenot the intended recipient, any disclosure, copying, distribution or any action taken oromitted to be taken in reliance on it is prohibited and may be unlawful.
Our Privacy Statement is available on www.dttas.gov.ie
***********************************************************