DUE PROCESS PROJECT MONITORING BUREAU OFFICE OF THE EXECUTIVE GOVERNOR JIGAWA STATE MAY-DECEMBER, 2007 - END OF YEAR PROJECT REPORT DUE PROCESS AND PROJECT MONITORING BUREAU JIGAWA STATE 1 EXECUTIVE SUMMARY The Due Process and Project Monitoring Bureau was established in may, 2007 by His Excellency the Executive Governor, Alhaji Sule Lamido in line with the Federal Government request that all state governments create such offices. Among its mandate is the preparation of quarterly/annual report on government activities/contracts to give a clear view of its achievements within the period. The report covers a period of eight month (May-December 2007) and includes list of capital projects awarded and duly notified to the Bureau by the Council Affairs Directorate, progress on same as certified by it, and those proposals sent for vetting. The report consist mainly of 5 major sections, vide; 1. COMPLETED PROJECTS – Projects that were certified completed (100%) as per contract agreement by the Bureau. 2. ONGOING PROJECTS – Projects that are in progress and the Bureau is involved in issuance of certification of readinessfor payment.

DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

Embed Size (px)

Citation preview

Page 1: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

DUE PROCESS PROJECT MONITORING BUREAU OFFICE OF THE EXECUTIVE GOVERNOR JIGAWA STATE MAY-DECEMBER, 2007 - END OF YEAR PROJECT REPORT

DUE PROCESS AND PROJECT MONITORING BUREAU JIGAWA STATE

1

EXECUTIVE SUMMARY

The Due Process and Project Monitoring Bureau was established in may, 2007 by His Excellency the Executive Governor, Alhaji Sule Lamido in line with the Federal Government request that all state governments create such offices. Among its mandate is the preparation of quarterly/annual report on government activities/contracts to give a clear view of its achievements within the period. The report covers a period of eight month (May-December 2007) and includes list of capital projects awarded and duly notified to the Bureau by the Council Affairs Directorate, progress on same as certified by it, and those proposals sent for vetting. The report consist mainly of 5 major sections, vide;

1. COMPLETED PROJECTS – Projects that were certified completed (100%) as per contract agreement by the Bureau.

2. ONGOING PROJECTS – Projects that are in progress and the Bureau is involved in issuance of

certification of readinessfor payment.

Page 2: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

DUE PROCESS PROJECT MONITORING BUREAU OFFICE OF THE EXECUTIVE GOVERNOR JIGAWA STATE MAY-DECEMBER, 2007 - END OF YEAR PROJECT REPORT

DUE PROCESS AND PROJECT MONITORING BUREAU JIGAWA STATE

2

3. SUPPLIES / PROCUREMENT CONTRACTS – Procument/Supplies contracts awarded and their delivery confirmed by the Bureau.

4. PRE-CONTRACT EVALUATION – Projects proposed estimates sent to the Bureau for vetting

prior to tender process. Occasionally the sum may be increased or decreased based on the Bureau’s perceived right price.

5. LIST OF CONTRACTS AWARDED - List of all contracts awarded, within the reporting period,

with their values and the names of client organization as reported to the Bureau by Directorate of Council Affairs/Executing Agencies.

Note: Ideally there should be a section for statement on Liabilities owed contracts by government, but the Committee on Management of Contractual liabilities was assigned this responsibility. After the committees report was presented this report will capture them as they were cleared for payment. However, the committee’s report presented to the government clearly stated that the sum of N3.03 Billion is owed contractors. ANALYSIS: i. COMPLETED PROJECTS: At the end of this reporting period, the total number of completed

projects (3No.) amounted to N62.9m which represents only (0.5%) of the total awarded. This is basically due to late take up of most projects and completion period agreed upon as per complexity.

Page 3: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

DUE PROCESS PROJECT MONITORING BUREAU OFFICE OF THE EXECUTIVE GOVERNOR JIGAWA STATE MAY-DECEMBER, 2007 - END OF YEAR PROJECT REPORT

DUE PROCESS AND PROJECT MONITORING BUREAU JIGAWA STATE

3

ii. ON-GOING PROJECT: The report indicated that most of the projects are at the initial stage i.e. just mobilized. While other have reached advanced stage of completion, most of the contractors have received advanced payments and will be completed accordingly. The total cost of the on-going projects amount to N11.84Billions.

iii. SUPPLIES/PROCUMENT CONTRACTS: Though lots of contracts were awarded especially

for the supply of vehicles non of them were confirmed supplied by the Bureau. The award are yet to be communicated.

iv. PRE-CONTRACT EVALUATION: For the reporting period a total of 86No. proposals worth

N11,612,538,865.05 were submitted to the Bureau for vetting, whereas the sum of N10,460,667,869.40 was recommended. These represent a saving of N1,151,870,995.65 for government.

v. CONTRACTS AWARDED: At the end of reporting period total contracts awarded in all

sectors (84No.) amount to N11.81bilion only. The allocation as per sector is; a. Education N2.545billion ( 21.5%)

b. Housing N7.420billion ( 62.8%)

c. Health N0.251billion ( 2.1%)

d. Electrification N0.403billion (3.4%)

e. Water Supply N- (0%)

Page 4: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

DUE PROCESS PROJECT MONITORING BUREAU OFFICE OF THE EXECUTIVE GOVERNOR JIGAWA STATE MAY-DECEMBER, 2007 - END OF YEAR PROJECT REPORT

DUE PROCESS AND PROJECT MONITORING BUREAU JIGAWA STATE

4

f. Roads N1.170billion (9.9%)

g. Others N0.021billion (0.3%)

Total N11.81billion (100%)

The total amount for contracts awarded (N11.81represent 101% of the revised Budget (N11.750 billion) for the year ending as such projects are expected to perform accordingly. CONCLUSSION: The Bureau commended the government for budget discipline and adherence to Due Process within the reporting period and hope compliance will be maintained in subsequent years to come. Furthermore, it is hoped that adequate funds will be apportioned for settlement of all verified liabilities and all viable projects will be completed accordingly within the time frame allotted for their completion. The Bureau is equally requesting for Government’s support in the provision of effective transportation to enable it carry out the supervision/inspection of projects without hitch across the state.

Ado Hussaini Director General Due Process & Project & Monitoring Bureau

Lawan Yunusa D/Zomo Special Adviser to the Governor

Due Process & Project & Monitoring Bureau

Page 5: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007 Pre-contract Evaluation

S/N PROJECT IN PROCESS QUOTED SUM DPPM RECOMMENDED SAVING/ REMARKS

(N) COST (N) INCREASE

1 RE-CONSTRUCTION AND REHABILITATION OF OLD SECRETARIAT 2KM ROADS 11,716,950.00 8,767,500.00 2,949,450.00 DIRECT LABOUR

2 PROPOSED RESIDENTIAL CHARLET FOR MARAFAN RINGIM 8,121,005.00 8,121,005.00 - L.G. DIR. APPROVED COST

3 REQUEST FOR THE RELEASE OF FUNDS IN RESPECT OF FANISAU 5,133,652.15 4,082,895.00 1,050,757.15

4 CONSTRUCTION OF 15M FALLEN WALL & EROSION CONTROL AT KANDAHAR 2,985,400.00 2,378,145.00 607,255.00 CONTRACTUALLY

5 EROSION CONTROL AT BYE-PASS HOUSE AND OLD GOVERNMENT HOUSE DUTSE 12,217,905.00 7,243,700.63 4,974,204.37 CONTRACTUALLY

6 FURNISHING OF ADVISER'S AND ASSISTANT'S OFFICES (31NO.) 42,662,580.05 42,662,580.05 - CONTRACTUALLY

7 REHABILITATION OF ARMCO AND BOX CULVERTS AT KOFAR YAMMA KAZAURE 3,036,800.00 3,157,800.00 (121,000.00) DIRECT LABOUR

8 REHABILITATION OF EMBANKMENT AT KANTI KAZAURE 2,821,000.00 2,821,000.00 -

9 MATERIALS AND LABOUR FOR 2NO. TOILET AT RELIGIOUS CHIEFTANINCY AFFAIRS 342,200.00 319,540.00 22,660.00 DIRECT LABOUR

10 RE-RENOV. AND FURNITURE SUPPLY FOR THE JIGAWA STATE HOUSE OF ASSEMBLY 164,531,324.80 164,531,324.80 - CONTRACTUALLY (SELECTION)

11 RE-RENOVATION AND FURNISHING OF OFFICE BLOCKS (MINISTRY OF COMMERCE) 2,361,376.50 2,277,430.02 83,946.48 DIRECT LABOUR

12 INSTALLATION OF COMMUNICATION GADGETS AT GOVT. HOUSE 10,114,500.00 8,630,490.00 1,484,010.00 CONTRACTUALLY

13 RE-COMPLETION OF TRASMITTER HOUSE AT RADIO JIGAWA 21,117,750.30 16,548,737.30 4,569,013.00

14 RE-PROPOSAL FOR RE-ESTABLISHMENT OF ZONAL EDUCATION OFFICES (9NO.) 68,435,100.00 72,485,100.00 (4,050,000.00) DIRECT LABOUR

15 RE-INSTALLATION OF 200 KVA 33/0.415KV SUBSTATIONS AT JIGAWA STATE FM ANDAZA 3,589,929.13 3,441,101.00 148,828.13 DIRECT LABOUR

16 RE-RENOVATION AND FURNISHING OF GOVERNOR'S LODGE ABUJA 26,555,165.00 26,697,665.00 (142,500.00)

17 RE-SETTING UP OF STATE EDUCATION INSTITUTIONS INSPECTORATE AND MONITORING 18,726,180.00 18,347,490.00 378,690.00

18 RE-RENOVATION OF DUTSE MULTI PURPOSE CENTRE 2,244,110.00 2,050,350.00 193,760.00

19 RE-COMPLETION OF ABANDONED OFFICE BLOCK AND OFFICE FURNITURE AT (MOLG) 3,274,782.00 4,129,111.35 (854,329.35)

20 WALL FENCING OF RAWMATERIALS DISPLAY CENTRE DUTSE 2,340,122.80 2,216,412.00 123,710.80

21 INVITATION TO INSPECT TWO 3BEDROOM BUNGALOWS AT JIGAP HQTR. M/MADORI 1,025,000.00 1,154,863.00 (129,863.00)

22 RE-RENOV. OF COMM'S, P.S.'S HOUSES AT BYE PASS HOUSE ESTATE 33,983,790.00 43,019,150.00 (9,035,360.00) CONTRACTUALLY

23 RE-COMPLETION OF MAIGATARI JUMA'AT MOSQUE 23,811,142.86 21,047,917.70 2,763,225.16 CONTRACTUALLY

24 RE-COMPLETION OF ON-GOING ELECTRIFICATION PROJECTS IN THE STATE 388,709,054.00 423,729,773.40 (35,020,719.40) CONTRACTUALLY

25 RE-PURCHASE OF WORKING MATERIALS FOR DISTRIBUTION TO SELF HELP GOUPS 24,197,500.00 20,074,500.00 4,123,000.00 CONTRACTUALLY

BAL. C/F 884,054,319.59 909,935,581.25 (25,881,261.66)

1

May-December 2007

Page 6: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007 Pre-contract Evaluation

S/N PROJECT IN PROCESS QUOTED SUM DPPM RECOMMENDED SAVING/ REMARKS

(N) COST (N) INCREASE

BAL. B/F 884,054,319.59 909,935,581.25 (25,881,261.66)

26 RE-CONSTRUCTION AND SUPPLY OF EQUIPMENTS AT COLLEGES -

a HUSSAINI ADAMU POLYTECHNIC (CBMS) DUTSE 52,299,439.58 52,299,439.58 -

b COLLEGE OF AGRICULTURE HADEJIA 16,893,149.75 13,541,163.75 3,351,986.00

c COLLEGE OF EDUCATION GUMEL 43,305,979.60 43,305,979.60 -

d COLLEGE OF ISLAMIC STUDIES RINGIM 17,501,723.00 17,501,723.00 -

27 RE-FACIA CLADDING TO FACTORY BLOCKS AT MAIGATARI BORDER FREE ZONE 1,748,880.00 1,562,120.00 186,760.00 CONTRACTUALLY

28 DAMAGE ASSESMENT AT MBFZ MAIGATARI (WALL FENCE) 3,556,405.00 3,838,712.50 (282,307.50) CONTRACTUALLY

29 RE-PEOPOSED HON. SPEAKER AND DEPUTY SPEAKER RES. AND ROADS AT LEGISLATORS QTRS. 228,523,170.25 157,954,654.00 70,568,516.25

30 RE-RENOV. OF L.G. SECRETARIATS AND STAFF QUARTERS IN THE STATE 471,313,980.69 482,039,558.83 (10,725,578.14) CONTRACTUALLY

31 RE-REHAB. OF B/KUDU WATER SUPPLY SCHEME & PROCUREMENT OF 2NO. 250KVA GEN. SET 18,500,000.00 18,500,000.00 - CONTRACTUALLY

32 RE-IMPROVEMENT OF HEALTH FACILITIES/REHAB. CENTRES 196,248,006.49 204,276,795.74 (8,028,789.25) CONTRACTUALLY

33 RE-RENOVATION AND FURNISHING OF OFFICES AT MIN. OF AGRICULTURE 4,177,610.00 5,429,418.76 (1,251,808.76) CONTRACTUALLY

34 RE-RENOV. OF OFFICE BLOCK, SUPPLY OF FURNITURE & CONSTR. OF SEATER LATRINE -

AT JIGAWA STATE SPORT COUNCIL 2,276,999.00 2,377,668.08 (100,669.08) CONTRACTUALLY

35 RE-CONSTR. OF DUPLEX CLASS ROOM AT COLLAGE OF AGRICULTURE, HADEJIA 7,000,000.00 5,567,508.50 1,432,491.50

36 RE-QUOTATION FOR DRILLING OF MOTORIZED BOREHOLE 950,000.00 950,000.00 - CONTRACTUALLY

37 CONSTRUCTION OF ROADS AND DRAINAGES AT MAIGATARI BORDER FREE ZONE 98,950,232.33 82,909,168.65 16,041,063.68 CONTRACTUALLY

38 RENOVATION OF OFFICE BLOCK AT CHIEFTAINCY AFFAIRS 2,224,490.00 2,974,190.03 (749,700.03)

39 CONSTRUCTION OF DUTSE TOWNSHIP ROADS 1,200,923,539.34 1,200,923,539.34 - CONTRACTUALLY

40 RE-BILL OF ENGR. MEASUREMENT AND EVALUATION FOR 2007 REVISED BUDGET ESTIMATES FOR OCT. 07 43,000,000.00 37,479,715.00 5,520,285.00 CONTRACTUALLY

41 REPAIRS OF PROJECTS VEHICLES BELONGING TO RURAL ELECTRIFICATION BOARD 4,174,500.00 4,342,485.00 (167,985.00) DIRECT LABOUR

42 FAILURE OF DAMS IN JIGAWA STATE 4,062,246.70 3,446,329.43 615,917.27

43 FLOOD CONTROL AT MAI ALKAMA, GABARI & AGUMAU IN HADEJIA AND ZARENAWA -

IN BIRNIN KUDU 94,993,632.00 34,617,036.93 60,376,595.07 CONTRACTUALLY

44 FLOOD CONTROL PROJECT AT MAIKAINUWA AREA BEHIND EMIR PALACE, HADEJIA 50,312,400.00 24,104,508.75 26,207,891.25 CONTRACTUALLY

BAL. C/F 3,446,990,703.32 3,309,877,296.72 137,113,406.60

2

May-December 2007

Page 7: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007 Pre-contract Evaluation

S/N PROJECT IN PROCESS QUOTED SUM DPPM RECOMMENDED SAVING/ REMARKS

(N) COST (N) INCREASE

BAL. B/F 3,446,990,703.32 3,309,877,296.72 137,113,406.60

45 REHABILITATION OF KIYAWA-JAHUN ROAD (ASPHALT OVERLAY) 997,519,950.00 997,519,950.00 - CONTRACTUALLY

46 REHABILITATION OF WALL FENCING FOR THE NEW SECRETARIAT DUTSE 47,000,000.00 47,000,000.00 -

47 EROSION CONTROL AT BY-PASS HOUSES AND WALL FENCE 65,335,524.70 54,205,326.63 11,130,198.07 CONTRACTUALLY

48 PURCHASE OF 2NO. INFORMATION VANS 39,000,000.00 35,200,000.00 3,800,000.00

49 RENOVATION/FURNISHING OF GOVERNOR'S LODGE FAMILY WING AND DRILLING OF 2NO. -

BOREHOLE AT OUR 2NO. GUEST HOUSES AT KADUNA LIASON OFFICE 4,536,850.00 4,083,030.00 453,820.00 DIRECT LABOUR

50 CONSTRUCTION OF WALL FENCE AT RURAL INFRASTRUCTURE & COMMUNITY DEV. 4,924,320.00 5,211,612.00 (287,292.00) CONTRACTUALLY

51 EXPANSION OF OFFICE ACCOMMODATION AT DEPUTY GOVERNOR'S OFFICE DUTSE 4,219,339.50 4,743,475.75 (524,136.25)

52 RE-CONSTR. OF TOWNSHIP ROADS IN BIRNIWA. GANTSA AND GARKI TOWNS. 1,087,363,893.00 1,087,363,893.00 - CONTRACTUALLY

53 RE-TAKE OFF GRANT DIRECTORATE OF LOCAL GOVERNMENT AUDIT 11,500,000.00 10,479,374.07 1,020,625.93

54 ASPHALT OVERLAY OF GIRIMBO-GANTSA-SARA ROAD (48KM) 1,279,880,497.50 1,279,880,437.50 60.00 CONTRACTUALLY

55 LANDSCAPING OF THE MINISTRY FOR LOCAL GOVT. 6,692,268.00 6,095,793.00 596,475.00 CONTRACTUALLY

56 REHAB. OF KWANAR KAUGAMA-K/MADANA ROAD (37KM) 304,961,036.63 289,146,192.30 15,814,844.33 CONTRACTUALLY

57 REVISED ESTIMATE FOR THE CONSTR. OF -

a K/FULANI-TSANGARWA-MARUTA-ZANDAM TA GABAS ROAD (36KM) 1,403,764,362.00 726,173,752.50 677,590,609.50 CONTRACTUALLY

b AND DINGAYA-KALASU ROAD (17KM) SURFACE DRESSING 601,329,729.00 345,575,317.50 255,754,411.50 CONTRACTUALLY

58 REPAIR OF FLY GT 2151 PUMP AT BIRNIN KUDU AND KAZAURE WATER WORKS 919,272.00 919,272.00 -

59 REVISED BUDGET ESTIMATE FOR THE MONTH OF NOV. 2007, HEAD 462, SUB-HEADS 101,102 & 106 32,008,090.00 26,544,761.63 5,463,328.37 CONTRACTUALLY

60 CAPITAL PROJECT ON WOMEN DEVELOPMENT PROGRAMME 23,726,590.00 23,301,872.30 424,717.70

61 PURCHASE OF FORD RANGER PICH-UP VAN, REPAIRS OF VEHICLE AND POWER CONNECTION -

TO 9NO. WATER SCHEMES. 9,910,000.00 9,910,000.00 - DIRECT LABOUR

62 PREPARATION FOR THE TAKE-OFF TRAINING AT THE FOUR SKILLS CENTRES 16,490,000.00 16,184,528.00 305,472.00

63 SUPPLY OF RADIO COMMUNICATION AND SECURITY EQUIPMENT, AND 2NO. TOYOTA

HILLUX DOUBLE CABIN (4X4 & A/C) 18,920,920.00 15,533,000.00 3,387,920.00 CONTRACTUALLY

64 REPLACEMENT OF 200MM DIAMETRE PVC PIPE 6BAR WITH 10 BAR FROM AJAWA TO RAGU (1.752KM) 10,000,000.00 9,601,200.00 398,800.00 CONTRACTUALLY

65 PURCHASE OF VEHICLE AND COMMUNICATION GADGETS FOR PATROL (15NO.) 97,762,500.00 97,762,500.00 -

66 CONSTRUCTION OF 200MM API BOREHOLES 20NO. 91,070,000.00 91,070,000.00 - CONTRACTUALLY

67 STREETLIGHT REPAIRS IN DUTSE 21,346,160.00 19,634,720.00 1,711,440.00 CONTRACTUALLY

68 ESTIMATE FOR VARIOUS CAPITAL PROJECTS BY RUWASA 10,000,000.00 10,000,000.00 -

69 SUPPLY OF FURNITURE AND EQUIPMENT FOR HEADQUATER AND 9NO. GUNDUMA COUNCIL 21,000,000.00 21,000,000.00 -

70 PURCHASE OF GENERATOR AND OTHER ELECTRICAL MATERIALS (MIN. OF INFORMATION) 15,249,587.75 15,219,371.25 30,216.50

71 CONSTRUCTION OF WALL FENCE (1520M) TO F.M. STATION ANDAZA 17,169,000.00 15,738,250.00 1,430,750.00

72 SUPLLY OF 60KVA GENERATOR 2,690,000.00 2,690,000.00 -

73 PURCHASE OF TOYOTA HILLUX (2WD) AND REPAIRS OF 7NO VEHICLES 4,909,750.00 4,909,750.00 -

74 CONSTRUCTION OF ESTATE ROADS AT DANMASARA 500 HOUSING ESTATE (9.7KM) 652,259,985.00 652,259,985.00 - CONTRACTUALLY

BAL. C/F 10,350,450,328.40 9,234,834,661.15 1,115,615,667.25

3

May-December 2007

Page 8: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007 Pre-contract Evaluation

S/N PROJECT IN PROCESS QUOTED SUM DPPM RECOMMENDED SAVING/ REMARKS

(N) COST (N) INCREASE

BAL. B/F 10,350,450,328.40 9,234,834,661.15 1,115,615,667.25

75 REHAB. OF ROAD (0.7KM) TO DEPUTY GOVERNOR'S RESIDENCE, DUTSE 33,743,488.13 33,743,488.13 -

76 CONSTRUCTION OF WALL FENCE (4KM) TO NEW SECRETARIAT DUTSE 64,778,137.20 64,778,137.20 -

77 CONSTRUCTION OF 400 HOUSING ROAD NET WORKS (10KM) DUTSE -SHUWARIN ROAD 787,085,775.00 787,085,775.00 -

78 POWER SUPPLY TO MECHANIC VILLAGE 12,489,036.51 12,254,348.61 234,687.90

79 POWER SUPPLY TO DAMASARA 500 HOUSING UNIT 53,798,239.20 21,531,408.99 32,266,830.21

80 POWER SUPPLY TO TIMBER MARKET 9,037,714.29 8,906,156.51 131,557.78

81 PIPELINE AND WATER RETICULATION AT TIMBER MARKET, DUTSE 3,176,558.00 3,176,558.00 -

82 WATER SUPPLY RETICULATION TO MECHANIC VILLAGE DUTSE. 12,391,330.00 12,391,330.00 -

83 CONSTR. OF TIMBER VILLAGE (1.7KM) AND MECHANIC VILLAGE (2.3KM) ROAD NET WORK (LATERITE) 32,033,474.50 32,033,474.50 -

84 CONSTRUCTION OF PUBLIC PARK ETC 11,083,155.92 9,303,961.24 1,779,194.68

85 REHABILITATION OF PHC'S COTTAGE HOSPITAL, GENERAL HOSPITAL AND CENTRES 238,135,627.90 236,292,570.07 1,843,057.83

86 STATE PROFESSIONAL/TECHNICAL RETREAT ON ADEQUATE WATER SUPPLY 4,336,000.00 4,336,000.00 -

-

-

-

-

-

-

-

-

-

TOTAL 11,612,538,865.05 10,460,667,869.40 1,151,870,995.65

4

May-December 2007

Page 9: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRA CT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

NO. (N)

1 17/5/2007 Renovation of H.E.'s Office and Residence GH/ADM/12/S.3/VV Ringim Galadanci 20,478,965.23 Government House

2 2007.12.09 Partitioning and Landscaping in the New Govt. House FGPC/12/07/V.I/14 GTESC Limited 371,889,000.00 D. C.D.A.

3 2007.12.09 Furnishing and Renov. Of Jigawa State House of Assembly FGPC/13/07/V.I/18 Rana Tahir Furniture Nig. Ltd. 164,531,324.00 D. C.D.A.

4 19/9/07 Commissioning as Consultant on Environmental

Degradation in Jigawa State. FGPC/11/07/V.I/13 Woodhill Engineering Nig. Ltd. 3,500,000.00 Ministry of Environment

5 25/9/07 Construction of 100 blocks of two bedroom houses in

Dutse. FGPC/14/07/V.I/4 Crane Builders and Eng. Ltd. 881,154,960.00 D. C. D. A.

6 25/9/07 Construction of 100 blocks of three bedroom houses in

Dutse. FGPC/15/07/V.I/5 JP Sigma Nigeria Limited 725,473,327.10 D. C. D. A.

7 25/9/07 Construction of 50 blocks of one bedroom houses in

Dutse. FGPC/16/07/V.I/6 RG. Construction Co. Ltd. 377,855,809.00 D. C. D. A.

8 25/9/07 Construction of 50 blocks of one bedroom houses in

Dutse. FGPC/17/07/V.I/7 Edil Belmoate 377,855,809.00 D. C. D. A.

9 2007.12.11 Electrification of Malamawar Gangara FGPC/25/2007/v.1/5 Muteco Nigeria Limited 5,048,874.75 Ministry of Rural Infrastructure

10 2007.12.11 Electrification Projects in the state FGPC/21/2007/v.1/5 Disscom Limited Ministry of Rural Infrastructure

a Shugurin (B/Kudu) 20,968,089.50

b Rabadi (Gwaram) 9,361,893.75

c Danbazau (Buji) 6,504,710.37

d Dumus (B/Kudu) 17,457,846.25

e Kukuma (Buji) 19,107,215.00

f Nahuce (Gwaram) 11,851,512.50

g Lelan kudu (Buji) 5,064,606.48

11 2007.12.11 Electrification Projects in the state FGPC/20/2007/v.1/5 Prestige Integrated Services Ltd. Ministry of Rural Infrastructure

a Agufa (Miga) 21,993,133.75

b Katuka (Kiyawa) 7,761,417.25

c Nahucen Harbo (Jahun) 10,983,826.75

d Kadawawa (Jahun) 8,943,836.25

Bal. C/F 3,067,786,156.93

1

Awarded May 07 -December 07

Page 10: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 3,067,786,156.93

12 20/11/07 Electrification Projects in the state FGPC?16/07/V.1/5 Firdausi Elect. & Computer Ltd. Rural Infrastructure

a Kwalam-Majia ITC (Taura LGA) 4,096,073.00

b Ajaura town (Taura LGA) 4,758,215.50

c Kandi-Wariya town (Birniwa LGA) 7,359,210.80

d Kiri town (Taura LGA) 2,811,971.50

e Gujungu town (taura LGA) 18,234,982.50

13 20/11/07 Electrification Projects in the state FGPC?17/07/V.1/5 ITTASS Nigeria Limited Rural Infrastructure

a Insha Ruwa village (Babura LGA) 20,444,635.75

b Galadi town (Maigatari LGA) 19,911,543.00

14 21/11/2007 Electrification Projects in the state FGPC/19/2007/v.1/5 HYGEO Nigeria Limited Ministry of Rural Infrastructure

a Chai-Chai Sintilmawa ITC Ringim) 26,706,190.00

b Kargo (Garki) 32,496,289.00

c Amaguwa (Ringim) 9,716,848.00

d Gujaba (Ringim) 3,004,130.00

e Shafar (Ringim) 3,004,130.00

f Sintilmawa (Ringim) 1,119,130.00

15 21/11/2007 Electrification of Koren Garki FGPC/22/2007/v.1/5 Kano Traders Multi purpose 10,302,139.00 Ministry of Rural Infrastructure

16 23/11/2007 Electrification of Ayama in Auyo Local Govt. Area FGPC/23/2007/v.1/5 AYUT Nigeria Limited 19,266,532.00 Ministry of Rural Infrastructure

17 23/11/2007 Constr.and Renov.works at Government Girls Secondary School Roni FGPC/30/2007/v.1/4 Main Structures Nigeria Ltd. 19,909,947.00 Min of Education, Science & Tech.

18 23/11/2007 Constr.and Renov.works at Government Secondary School Roni FGPC/29/2007/v.1/4 Amasmar Nigeria Ltd. 24,897,899.00 Min of Education, Science & Tech.

19 24/11/2007 Construction works at GDSS Andaza FGPC729/2007/v.1/4 Main Land Limited 14,460,945.00 Min of Education, Science & Tech.

20 27/11/2007 Constr.and Renov.works at Day Secondary School Garin Gabas FGPC/30/2007/v.1/4 Risan Nigeria Ltd. 6,480,545.00 Min of Education, Science & Tech.

21 27/11/2007 Construction works at Governmen Secondary School in state FGPC/49/2007/v.1/4 Beefar Construction Nig. Ltd. Min of Education, Science & Tech.

i GDASS Katanga 13,659,095.00

ii GDSS Danladi 14,462,945.00

iii GDSS K/Kasamma 6,631,890.00

iv GDSS Turabu 6,631,890.00

Bal. C/F 3,358,153,332.98

2

Awarded May 07 -December 07

Page 11: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 3,358,153,332.98

22 27/11/2007 Construction works at GDSS Firji FGPC/50/2007/v.1/4 Dunguza Nigeria Ltd. 10,100,945.00 Min of Education, Science & Tech.

23 27/11/2007 Construction works at GDASS A.M. Ringim FGPC/52/2007/v.1/4 Imam Ahmed Nig. Ltd. 5,740,945.00 Min of Education, Science & Tech.

24 27/11/2007 Constr.and Renov.works at GDSS S/Tankarkar FGPC/63/2007/v.1/4 Unique Marketing Co. Ltd. 8,188,695.00 Min of Education, Science & Tech.

25 27/11/2007 Construction & Renov. works at Governmen Secondary School in state FGPC/54/2007/v.1/4 Polyspec Nig. Ltd. Min of Education, Science & Tech.

i GGSS Kazaure 11,936,830.00

ii GDSS D/Zomo 35,706,472.00

iii GDSS Maje 8,584,665.00

26 27/11/2007 Water supply (Solar system) for all boarding Senior Sec. Sch. in state FGPC/46/2007/v.1/4 Garwai Ventures Ltd/ 191,500,000.00 Min of Education, Science & Tech.

27 27/11/2007 Constr. of Motorized Borholes at GDSS in the state FGPC/45B/2007/v.1/4 Loyalty Ltd. Min of Education, Science & Tech.

GDSS Gumel 2,000,000.00

GDASS Danmanomi 2,000,000.00

GDSS Guri 2,000,000.00

GDSS T/Gwaram 2,000,000.00

GDSS Fagam 2,000,000.00

GDSS Galambi 2,000,000.00

GDSS Maruta 2,000,000.00

GDSS Koreyel 2,000,000.00

GDSS Gwiwa 2,000,000.00

GDSS Wunti 2,000,000.00

GDASS A Yusuf 2,000,000.00

GDSS F10 Hadejia 2,000,000.00

GDASS Jahun 2,000,000.00

GDSS Harbo 2,000,000.00

GDSS Kale 2,000,000.00

GDSS Gunka 2,000,000.00

GDSS K/Kasamma 2,000,000.00

GDSS Turabu 2,000,000.00

GDSS K/Hausa 2,000,000.00

GDASS I H K/Hausa 2,000,000.00

Bal. C/F 3,669,911,884.98

3

Awarded May 07 -December 07

Page 12: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 3,669,911,884.98

GDSS Bulangu 2,000,000.00

GDSS Sarawa 2,000,000.00

GDSS Sabon Gida 2,000,000.00

GDSS Kaugama 2,000,000.00

GDSS Dakaiyawa 2,000,000.00

GDSS Marke 2,000,000.00

GDSS M/Yelleman 2,000,000.00

GDSS Kazaure 2,000,000.00

GDSS Kiyawa 2,000,000.00

28 27/11/2007 Constr. of Motorized Borholes at GDSS in the state FGPC/45A/2007/v.1/4 Loyalty Ltd. Min of Education, Science & Tech.

a GDSS Auyo 2,000,000.00

b GDSS Auyokayi 2,000,000.00

c GDSS Babura 2,000,000.00

d GDSS Jigawa 2,000,000.00

e GDSS Garin Gudinya 2,000,000.00

f GDSS K/Babba 2,000,000.00

g GDSS Wurno 2,000,000.00

h GDSS Sundimina 2,000,000.00

i GDSS Y/Damai 2,000,000.00

j GDSS Sara 2,000,000.00

k GDSS Birniwa 2,000,000.00

l GDSS Diginsa 2,000,000.00

m GDSS Y/Tukur 2,000,000.00

n GDSS G/Dutse 2,000,000.00

o GDSS Madobi 2,000,000.00

p GDSS Galamawa 2,000,000.00

q GDASS Gagarawa 2,000,000.00

r GGSS Garki 2,000,000.00

s GDSS Garki 2,000,000.00

t GDSS Doko 2,000,000.00

Bal. C/F 3,727,911,884.98

4

Awarded May 07 -December 07

Page 13: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 3,727,911,884.98

29 27/11/2007 Construction & Renov. works at Governmen Secondary School in state FGPC/60/2007/v.1/4 M.A. Tuggar & Sons Ltd. Min of Education, Science & Tech.

i GGSS Taura 11,511,316.60

ii GDSS Kwalam 10,310,912.60

30 27/11/2007 Construction & Renov. works at GSS Basirka FGPC/48/2007/v.1/4 Ringim Galadanchi Nig. Ltd. 105,355,293.00 Min of Education, Science & Tech.

31 27/11/2007 Construction & Renov. works at Governmen Secondary School in state FGPC/57/2007/v.1/4 Khanadi General Enterprises Min of Education, Science & Tech.

i GDSS Garki 9,290,945.00

ii GDSS Gumel 23,250,145.00

32 27/11/2007 Construction & Renov. works at GGSS S/Tankarkar FGPC/79/2007/v.1/4 Ishi Niheria Limited 39,892,466.00 Min of Education, Science & Tech.

33 27/11/2007 Construction works at GC Birnin Kudu FGPC/62/2007/v.1/4 Northians General Enterprises 77,196,635.00 Min of Education, Science & Tech.

34 27/11/2007 Construction & Renov. works at Government Secondary School in state FGPC/69/2007/v.1/4 Bakabo Nigeria Ltd. Min of Education, Science & Tech.

i GDSS Auyo 8,275,856.00

ii GDSS Auyakayi 10,100,945.00

iii GDSS Babura 9,352,198.00

iv GGASS Babura 83,556,685.00

v GDSS Jigawa 13,618,217.00

vi GDSS G/Gudinya 7,522,855.00

vii GDSS K/Babba 14,465,899.00

35 27/11/2007 Construction & Renov. works at GDASS IH K/Hausa & GDSS Sarawa FGPC/77/2007/v.1/4 Tropical Builders Nig. Ltd. 19,885,643.00 Min of Education, Science & Tech.

36 28/11/2007 Construction & Renov. works at Science Secondary School K/Hausa FGPC/51/2007/v.1/2 Maso Tech. Nig. Ltd. 71,161,668.00 Min of Education, Science & Tech.

37 28/11/2007 Construction & Renov. works at GDSS Koreyal FGPC/61/2007/v.1/2 Salisu Ali Nigeria Ltd. 11,408,540.00 Min of Education, Science & Tech.

38 28/11/2007 Construction & Renov. works at Government Day Sec School in state FGPC/56/2007/v.1/3 Beams & Columns Nig. Ltd. Min of Education, Science & Tech.

i GDSS Garki 9,670,780.00

ii GDSS Guri 8,434,680.00

iii GDSS Doko 1,781,890.00

iv GDSS Dantanoma 13,472,731.00

v GDSS T/Gwaram 14,650,908.00

vi GDSS Fagam 7,506,986.00

vii GDSS Galambi 6,050,194.00

viii GDSS Maruta 5,740,945.00

39 28/11/2007 Construction & Renov. works at Government Day Sec School in state FGPC/59/2007/v.1/2 Magadawa Nig. Ltd. Min of Education, Science & Tech.

i GDSS Bulangu 9,488,147.00

ii GDSS K/Hausa 12,332,894.00

40 28/11/2007 Construction & Renov. works at Science Secondary School Lautai FGPC/64/2007/v.1/2 Land & Water Partnership 59,408,039.00 Min of Education, Science & Tech.

41 28/11/2007 Construction & Renov. works at GDSS Kazaure FGPC/53/2007/v.1/2 Babandoki Gen. Enterprises 34,122,952.00 Min of Education, Science & Tech.

Bal. C/F 4,436,729,250.18

5

Awarded May 07 -December 07

Page 14: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 4,436,729,250.18

42 28/11/2007 Construction works at GGASS Z/Kazaure & GDSS Kiyawa FGPC/47/2007/v.1/4 Maurice Project Centre Ltd. Min of Education, Science & Tech.

i GGASS Z/Kazaure 5,740,945.00

ii GDSS Kiyawa 13,695,095.00

43 28/11/2007 Supply of Furnitures in the State FGPC/44/2007/v.1/3 Fawaz Steelwood & Chem. 10,040,000.00 Min of Education, Science & Tech.

44 28/11/2007 Construction & Renov. works at Government Day Sec School in state FGPC/55/2007/v.1/2 Turabu Constr. Limited Min of Education, Science & Tech.

i GDSS Dutse 85,610,415.00

ii GDSS Gagarawa 9,160,624.00

45 29/11/2007 Electrification of Sabon Garin Danmasara & Iggi towns JGCA/19/v.1/35 Direct Labour 11,498,542.50 Ministry of Rural Infrastructure

46 29/11/2007 Construction of township roads in Dutse state capital 67FGPC/55/2007/v.1/10 Dantata & Sawoe Constr. Co. 1,170,900,450.60 DCDA

47 29/11/2007 Constr. of Motorized water supply in the state FGPC/58/2007/v.1/2 Spider Engeering & Tech. Ltd. 40,000,000.00 Min of Education, Science & Tech.

48 29/11/2007 Construction & Renov. Works at GSS M/Madori FGPC/66/2007/v.1/2 BM Investment Limited 58,343,414.00 Min of Education, Science & Tech.

49 29/11/2007 Electrification of Korayel town in Gwiwa LGA FGPC/18/2007/v.1/14 Ashalt Nigeria Ltd. 16,170,428.00 Ministry of Rural Infrastructure

50 29/11/2007 Construction & Renov. Works at GDSS Y/Tukuri FGPC/68/2007/v.1/4 Idi Aliko & Sons Enterprises 6,770,039.00 Min of Education, Science & Tech.

51 29/11/2007 Construction & Renov. Works at Govt. Secondary Sch. In the state FGPC/65/2007/v.1/2 Anhas Nigeria Limited Min of Education, Science & Tech.

i GDSS F10 Hadejia 26,621,740.00

ii SIAS Hadejia 132,944,392.00

iii GDSS A. Yusuf 16,945,699.00

iv GSSS Jahun 24,382,421.00

v GSS Aujara 60,382,449.00

vi GDSS Harbo 16,329,389.00

vii GDSS Kale 12,100,945.00

52 30/11/2007 Construction Works at GDSS Kaugama FGPC/78/2007/v.1/4 Modang Investments Ltd. 6,631,890.00 Min of Education, Science & Tech.

53 30/11/2007 Construction Works at GDSSS Dakaiyawa & GDSS Marke FGPC/75/2007/v.1/4 KUL DWELL Min of Education, Science & Tech.

i GDSS Dakaiyawa 3,152,839.00

ii GDSS Marke 5,740,945.00

Bal. C/F 6,169,891,912.28

6

Awarded May 07 -December 07

Page 15: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 6,169,891,912.28

54 30/11/2007 Construction & Renov. Works at GASS Kaugama FGPC/70/2007/v.1/4 Trust Engineering Services 36,526,263.00 Min of Education, Science & Tech.

55 30/11/2007 Construction & Renov. Works at Govt. Secondary Sch. In the state FGPC/76/2007/v.1/4 Homelux Constr. & Equipment Min of Education, Science & Tech.

i GDSS Wuron 7,312,295.00

ii GDSS Sundumina 1,821,579.00

iii GDSS Y/Damai 10,100,945.00

iv GDASS Sara 7,279,845.00

v GGASS Birniwa 51,522,072.00

vi GDSS Birniwa 10,100,945.00

vii GDSS Diginsa 8,868,833.00

56 30/11/2007 Construction & Renov. Works at GDASS S/G Yaya FGPC/74/2007/v.1/4 Beverly Nigeria Ltd. 6,722,420.00 Min of Education, Science & Tech.

57 30/11/2007 Constr. of 20 No. (2) Bed room Houses at Dutse-Kiyawa road FGPC/71A/2007/v.1/6 MAX Quinis Nig. Ltd. 169,043,595.00 DCDA

58 30/11/2007 Constr. of 20 No. (2) Bed room Houses at Dutse-Kiyawa road FGPC/71B/2007/v.1/6 Hemkay Nig. Ltd. 169,043,595.00 DCDA

59 30/11/2007 Constr. of 10 No. (2) Bed room Houses at Dutse-Kiyawa road FGPC/71C/2007/v.1/6 AL-USABS Constr. Ltd. 84,521,797.00 DCDA

60 30/11/2007 Constr. of 50 No. (4) B/room & 100No. (2) B/roomHouses at Dutse-Kiyawa road FGPC/71D/2007/v.1/6 Crane Builders & Eng. Ltd. 1,578,910,830.00 DCDA

61 30/11/2007 Constr. of 40 No. (2) Bed room Houses at Dutse-Kiyawa road FGPC/71E/2007/v.1/6 Salam Starts Enterprises 338,087,190.00 DCDA

62 30/11/2007 Constr. of 10 No. (2) Bed room Houses at Dutse-Kiyawa road FGPC/71F/2007/v.1/6 MOAK Nigeria Limited 84,521,797.50 DCDA

63 30/11/2007 Constr. of 50 No. (3) Bed room Houses at Dutse-Kiyawa road FGPC/71G/2007/v.1/6 Inter world I&E Nig. Ltd. 671,064,187.50 DCDA

64 30/11/2007 Constr. of 50 No. (3) Bed room Houses at Dutse-Kiyawa road FGPC/71H/2007/v.1/6 G.S.M. Nigeria Ltd. 671,064,187.50 DCDA

65 30/11/2007 Constr. of 50 No. (4) Bed room Houses at Dutse-Kiyawa road FGPC/71I/2007/v.1/6 RG Construction Ltd. 733,692,855.00 DCDA

66 2007.03.12 Supplies of Furnitures at Govt. Sec. Sch. In the state FGPC/80/2007/v.1/3 Aybee Furnishing Min of Education, Science & Tech.

i GSS (U) Ringim 4,800,000.00

ii GDSS Ringim 1,472,000.00

iii GDSS Dabi 480,000.00

iv GDASS A.M. Ringim 360,000.00

v GDASS Y/Dutse 496,000.00

vi GDSS Sankara 160,000.00

vii GSS Roni 2,216,000.00

viii GDSS Amaryawa 120,000.00

Bal. C/F 10,820,201,143.78

7

Awarded May 07 -December 07

Page 16: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 10,820,201,143.78

67 2007.03.12 Construction Works at Govt. Secondary Sch. In the state FGPC/73/2007/v.1/4 Basic Four Nig. Ltd. Min of Education, Science & Tech.

i GDSS G/Dutse 10,145,747.00

ii GGDASS Dutse 15,351,890.00

iii GDSS Madobi 9,290,945.00

68 2007.03.12 Construction Works at Govt. Secondary Sch. In the state FGPC/81/2007/v.1/4 Yayari Tukur Nigeria Ltd. Min of Education, Science & Tech.

i GDASS Y/Dutse 5,740,945.00

ii GDSS Amaryawa 6,631,890.00

69 2007.04.12 Construction & Renov. works at GDSS Sabon Gida FGPC/84/2007/v.1/4 KASBIT & Sons Nig. Ltd. 8,821,597.00 Min of Education, Science & Tech.

70 2007.04.12 Construction & Renov. works at GDSS GGSS M/Madori FGPC/83/2007/v.1/4 TASNEE Nigeria Ltd. 32,051,627.00 Min of Education, Science & Tech.

71 2007.04.12 Construction & Renov. works at GDSS GGASS M/Madori FGPC/82/2007/v.1/4 Habije General Service Ltd. 8,297,714.00 Min of Education, Science & Tech.

72 2007.04.12 Construction & Renov. works at Govt. Secondary Sch. In the state FGPC/38/2007/v.1/4 HAJAIG Nigeria Ltd. Min of Education, Science & Tech.

i GGSS (U) Gwaram 127,253,437.00

ii GDSS Gunka 11,669,073.00

iii GDSS Gwiwa 12,448,127.00

iv GSS Fantai Hadejia 71,626,792.00

v GDSS Wunti 18,188,172.00

vi GSTC Hadejia 65,402,555.00

72 2007.04.12 Construction & Renov. works at GDSS Shuwarin FGPC/86/2007/v.1/4 EXODUS Nigeria Ltd. 10,100,945.00 Min of Education, Science & Tech.

73 2007.04.12 Construction & Renov. works at Govt. Day Sec. Sch. Ringim FGPC/87/2007/v.1/2 Tauraco Nigerai Ltd. 7,882,835.00 Min of Education, Science & Tech.

74 2007.06.12 Construction works at Govt. Day Sec. Sch. M/Yelleman FGPC/87/2007/v.1/2 TAWALI'U Biz. Entreprises 6,631,890.00 Min of Education, Science & Tech.

75 2007.06.12 Construction works at Govt. Day Sec. Sch. Kiri FGPC/88/2007/v.1/2 HERITAGE Circle Nig. Ltd. 7,512,835.00 Min of Education, Science & Tech.

76 2007.06.12 Construction & Renov. works at Govt. Secondary Sch. In the state FGPC/41/2007/v.1/5 AIMS Constr. Ltd. Min of Education, Science & Tech.

i GDSS Jahun 8,631,890.00

ii GSS Maigatari 36,177,754.00

77 2007.06.12 Construction & Renov. works at Govt. Secondary Sch. (Unity) Ringim FGPC/43/2007/v.1/4 AJAWA Invest. Nig. Ltd. 67,349,980.00 Min of Education, Science & Tech.

78 2007.06.12 Construction & Renov. works at Govt. Secondary Tech. Sch. Karkarna FGPC/42/2007/v.1/4 ALFA Sigma Nig. Ltd. 80,126,530.00 Min of Education, Science & Tech.

79 2007.06.12 Construction works at Govt. Day Sec. Sch. Galamawa FGPC/91/2007/v.1/4 3C International Nig. Ltd. 9,290,945.00 Min of Education, Science & Tech.

80 2007.07.12 Construction & Renov. works at Govt. Secondary Sch. In the state FGPC/34/2007/v.1/4 CEKJANI Nig. Ltd. Min of Education, Science & Tech.

i GDSS Sakara 6,376,366.00

ii GDSS Taura 11,395,950.00

Bal. C/F 11,474,599,574.78

8

Awarded May 07 -December 07

Page 17: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,CONTRACT AWARDED MAY 2007 - DECEMBER 2007

S/N DATE PROJECT CONTRACTOR AMOUNT EXECUTING MINISTRIES REMARKS

(N)

Bal. B/F 11,474,599,574.78

81 2007.11.12 Re-Electr. Project of Jigawa-Kanya Babba (28km ITC line) FGPC/107/2005/T.1/7 Gerawa Global 46,786,323.00 Ministry of Rural Infrastructure

82 24/12/2007 Supply of Furniture in the state FGPC/94/2007/v.1/3 Rana Tahir Furniture 20,007,500.00 Min of Education, Science & Tech.

83 Construction of Model Houses at Danmasara Direct Labour 21,348,360.93 DCDA

84 24/12/2007 Completion of Danmasara Specialist FGPC/92/2007/V.I/5 Datum Constr. Nig. Ltd. 251,490,120.51 Ministry of Health

Hospital

TOTAL 11,814,231,879.22

9

Awarded May 07 -December 07

Page 18: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

S/N PROJECT EXECUTOR LOCATION EXECUTING CONTRACT COMMENCEMENT STATUS REMARKS

MINISTRY AMOUNT DATE IN %

1 Construction of Primary Health Center A. Mohd Maidaji & Co. Kwatalo Health 16,692,535.13 May, 2003 52 Delayed

2 Upgrading of Water Supply Schemes Monarch Drillers Nig.Ltd. Gumel Water 46,213,500.00 September, 2004 60 Delayed

3 Construction of Drainage Kano Traders Marke (Kaugama LGA) Environment 15,666,000.00 August, 2002 83 Stalled

4 Rehab. of Fandai & Akama Burrow Pits Gerawa Global Jahun Environment 44,295,561.00 April, 2005 5 Stalled

5 Construction of Road CGC Nigeria Limited Gwiwa-Korayal-Unguwar mani E.I.A. 758,177,271.34 July, 2002 12 Delayed

6 Highway Road Construction Afdin Ventures Karkarna-Yanduna-Maibara E.I.A. 170,975,610.00 June, 2004 56 Delayed

7 Highway Road Construction Triacta Nig. Ltd. Babaldu-Jangari-Buji E.I.A. 875,208,082.50 August, 2004 20 Delayed

8 Feeder Road Construction Gonaco Nig. Ltd. Dingaya-Galambi-Kalasu E.I.A. 153,314,590.00 October, 2004 20 Awaiting Mob.

9 Feeder Road Construction Gonaco Nig. Ltd. K/Fulani-Tsangarwa-Zandam E.I.A. 341,739,720.00 October, 2004 5 Awaiting Mob.

10 Highway Road Construction Triacta Nig. Ltd. Babaldu-Jangari-Buji E.I.A. 875,208,082.50 Aug. 2004 10 Delayed

11 Feeder road construction Gonaco Nig. Ltd. Dingaya-Galambi-Kalasu E.I.A. 153,314,590.00 Oct. 2004 5 Awaiting Mob.

12 Feeder road construction Gonaco Nig. Ltd. K/Fulani-Tsangarwa-Zandam E.I.A. 341,739,720.00 Oct. 2004 5 Delayed

13 Construction of Road Afdin Nigeria Limited Karkarna-Gwarta E.I.A. 131,513,077.30 September, 2005 22 Delayed

14 Construction of Road Gerawa Global Majia-Kore E.I.A. 134,442,708.75 Oct.05 5 Delayed

15 Construction of Road Gerawa Global Sarawa Junction-Sara E.I.A. 171,125,640.00 Sep.05 5 Delayed

16 Construction of Road Gerawa Global Garki-Taura E.I.A. 487,011,845.25 Aug.05 2 Delayed

17 Construction of Road Triacta Nig. Ltd. Babaldu-Wurno-Buji E.I.A. 991,731,082.00 May, 2005 30 Delayed

18 Dutse Township Road Wallong Camco Nig. Dutse Township E.I.A. 5,068,131,311.30 Decmeber, 2004 No Information

19 Rural Electrification (ITC) Kano TMP Ltd. Koren Garki S.E.B. 14,654,097.05 March, 2002 29 Delayed

20 Supply of 100 Megawatts Power Gen. Plant. Gen. Plant Service Ltd. Independent Power Project S.E.B. 14,000,000,000.00 July, 2005 Nil Not supplied

21 Electrification of Kanya Babba 28km ITC Gerawa Global Ltd. Jigawa-Kanya S.E.B. 54,549,093.69 0 Not Executed

22 Supply of 2No. 550KVA, Denyo sound proof diedel generators Modi Investement Co. Ltd. Basic Educ. 43,018,640.00 Supplied

23 Supply of 1No. 1000KVA, Denyo sound proof diesel generator Modi Investement Co. Ltd. Informatic Institute Kazaure Basic Educ. 45,885,000.00 Supplied

24 Supply of Institutional Furniture and Computers Betrust Nigeria Limited Informatic Institute Kazaure Basic Educ. 105,524,472.40 68 In Progress

25 Electrification of newly constructed staff quarters Polepee Nigeria Limited Informatic Institute Kazaure Basic Educ. 9,701,760.50 60 In Progress

26 Supply of assorted science labs equipment, chemicals & reagents Harasam Internation Ltd. Basic Educ. 114,137,890.00 0 Not Executed

to Secondary Schools

27 Gumel Township Road Abduljalil Hajaig Ltd. Gumel Township Land Admin. 282,183,472.62 March, 2003 80 On-going

28 Kazaure Township Road NRC Ltd. Kazaure Township Land Admin. 227,419,500.00 September, 2002 On-going

29 Hadejia Township Road Dantata & Sawoe Hadejia Township Land Admin. 460,223,552.69 October, 2002 75 On-going

30 Mallam Madori Township Road Philko Nig. Ltd. Mallam Madori Township Land Admin. 235,711,688.63 May, 2004 50 On-going

31 Gwaram Township Road Gonaco Nig. Ltd. Gwaram Township Land Admin. 354,305,261.75 May, 2004 70 On-going

32 Township Road Construction Dantata & Sawoe Hadejia Land Admin. 460,223,552.69 Sept. 2002 75 On-going

33 Township Road Construction phase II Abdul Jalil Hajaig & Sons Gumel Land Admin. 248,246,536.44 March, 2006 Nil Yet to Mobilize

Page 19: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

34 Township Road Construction Borini Prono Nig. Ltd. Garki Land Admin. 313,430,536.44 May, 2006 Just Mob. Surveying works in progress

35 Dualization of K/yamma-K/Gabas Standard West Africa Hadejia Land Admin. 342,740,406.80 Dec., 2006 Yet to Mobilize

36 Township Road Construction Gerawa Global Eng. Kiyawa Land Admin. 284,693,077.94 May, 2006 Yet to Mobilize

37 Construction of Prototype factory Dalsa Nig. Ltd. Maigatari (EPZ) Commerce 20,000,000.00 December, 2000 92 Stalled

38 Construction of Protoytype factory Graphic Arch Maigatari (EPZ) Commerce 20,000,000.00 December,2002 95 Stalled

39 Construction of Towers, Custom & Police post Triple Trade Maigatari (EPZ) Commerce 17,326,120.30 March, 2003 86 Stalled

40 Construction of (2No) Model Ware House Ali Maina Maigatari (EPZ) Commerce 46,365,971.34 October, 2003 45 Stalled

41 Construction of Cattle Yard Musa O' % Sons Kumsa Market Commerce 9,104,635.00 0 Not started

42 Construction of Cattle Yard Alh. Ubali Gizago & Co. Kumsa Market Commerce 9,104,635.00 0 "

43 Construction of Motor Park Makama Shehu Nigeria Ltd. Kumsa Market Commerce 6,052,636.45 0 "

44 Constr. of Police Station & 6No. Hand Operated Boreholes Dan Kundi Nigeria Limited Kumsa Market Commerce 6,936,029.00 0 "

45 Construction of Mosque Namalam Zangi Kumsa Market Commerce 5,676,000.00 0 "

46 2No. Blocks of 10 open shops S & M Nigeria Limited Kumsa Market Commerce 8,780,552.84 0 "

47 1No. Block of 9 lockable shops Mabudi Kumsa Market Commerce 7,353,865.00 0 "

48 1No. Block of 9 lockable shops A & Z Nigeria Limited Kumsa Market Commerce 7,353,865.00 0 "

49 4No. Blocks of 5 cubicles Muhalli Consultants Kumsa Market Commerce 4,810,000.00 0 "

50 1No. Block of 9 lockable & 1No. Block of 10 open shops Turabu Construction Kumsa Market Commerce 11,744,091.40 0 "

51 Development of Hadejia Market Lazer Tech Nigeria Limited Hadejia Market Commerce 90,302,681.96 0 "

52 5No. Blocks of 10 open shops, Warehouse & Fire Service Station Ajawa Investment Nig. Ltd. Sara Market Commerce 33,339,616.88 0 "

53 Public Convenience Gaimads Engineering Sara Market Commerce 46,965,366.00 0 Not stated

54 Consultants for Development of 8No. Markets Stirling Development Agency Maigatari,Gujungu, Hadejia, Commerce 14,547,597.67 0 Not stated

Kazaure, Firji, Sara, Kumsa & Shuwarin Commerce

55 Construction of Central Mosque Nafsa Gen. Enterprises Amaryawa Commerce 10,344,654.80 0 "

56 Cattle Yard Isya Garba Shuwarin Shuwarin Market Commerce 3,641,853.05 0 "

57 Construction of Ware house & Mosque Isya Garba Shuwarin Shuwarin Market Commerce 19,468,356.99 0 "

58 Craft ultra model shop & Public convenience Isya Garba Shuwarin Commerce 14,641,307.74 0 "

59 Construction of Admin. Block & Clinic Isya Garba Shuwarin Commerce 8,669,933.65 0 "

60 Construction of Juma'at Moque Garba Barde Kwatalo Religious Affairs 7,547,523.20 May, 2003 30 Abondaoned

61 Construction of Juma'at Moque Gerawa Global Danladin Gumel Religious Affairs 5,285,041.00 May, 2005 40 Abondaoned

62 Constr. of Multi-purpose hall Zanikon Govt. House DCDA 322,975,132.70 0 Not Started

63 Constr. of Presidential Lodge A.B. Alhassan Nigeria Ltd. Govt. House DCDA 320,037,869.00 0 "

64 Constr. of Filling station, Parking space & Office A.B. Alhassan Nigeria Ltd. Old Fire Service secretariat (3) DCDA 12,966,661.83 0 "

Page 20: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007

Dutse Capital Development Authority

POST CONTRACT PROJECT EVALUATION

S/N Head PROJECT LOCATION CONTRACT STATUS REMARKS

AMOUNT IN %

1 Construction of Model Houses at Danmasara (3No.) Danmasara Dutse LGA 21,348,360.93 100 Completed

Total 21,348,360.93

1 May-December 2007

Page 21: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007

Ministry of Information

POST CONTRACT PROJECT EVALUATION

S/N Head PROJECT LOCATION CONTRACT AMOUNT STATUS REMARKS

(N) IN %

1 Construction of Trasmitter House Radio Jigawa, Dutse. 21,117,750.30 100 Completed

Total 21,117,750.30

2 May-December 2007

Page 22: DUE PROCESS PROJECT MONITORING BUREAU€¦ · due process project monitoring bureau ... 38 renovation of office block at chieftaincy affairs ... guest houses at kaduna liason office

JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,

END OF YEAR PROJECTS REPORT, MAY - DECEMBER, 2007

Government House

POST CONTRACT PROJECT EVALUATION

S/N Head PROJECT LOCATION CONTRACT AMOUNT STATUS REMARKS

(N) IN %

1 Rehabilitation of H.E.'S Office & Residence New Govt. House 20,478,965.28 100 Completed

Total 20,478,965.28

3

May-December 2007